CN109831029A - The method that intelligent substation protects equipment high efficiency to make an inspection tour - Google Patents
The method that intelligent substation protects equipment high efficiency to make an inspection tour Download PDFInfo
- Publication number
- CN109831029A CN109831029A CN201910024487.XA CN201910024487A CN109831029A CN 109831029 A CN109831029 A CN 109831029A CN 201910024487 A CN201910024487 A CN 201910024487A CN 109831029 A CN109831029 A CN 109831029A
- Authority
- CN
- China
- Prior art keywords
- tour
- maked
- inspection tour
- project
- inspection
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S10/00—Systems supporting electrical power generation, transmission or distribution
- Y04S10/16—Electric power substations
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses the method that a kind of intelligent substation protection equipment high efficiency is maked an inspection tour, technical problems to be solved are to improve the tour efficiency of secondary equipment of intelligent converting station.The invention adopts the following technical scheme: a kind of method that intelligent substation protection equipment high efficiency is maked an inspection tour; the following steps are included: establishing inspection tour system; initial configuration; timing match trigger condition starts to make an inspection tour, and reloads configuration; make an inspection tour configuration content; analysis is maked an inspection tour and makes an inspection tour result as a result, generating and making an inspection tour as a result, issuing by messaging bus to user.The present invention is compared with prior art, by the way of the processing of distributed multimode block, the time that response signal is handled during making an inspection tour is effectively reduced, by configuration file, fixed cycle, timed patrol is by tour secondary device by tour project, analyze to by tour project, generates to make an inspection tour as a result, issuing to user and make an inspection tour result, the tour efficiency of secondary equipment of intelligent converting station is improved, and then improves the efficiency of entire intelligent substation O&M.
Description
Technical field
The present invention relates to a kind of guard method of intelligent substation, especially a kind of in-service monitoring intelligence intelligent substation two
The method of secondary device.
Technical background
Safe and reliable, the stable operation of secondary equipment of intelligent converting station has pole to the normal operation of entire electric system
Its important role.Timing checks each operating parameter of the secondary device of intelligent substation, provides announcement to abnormal signal
Alert prompt, helps to improve the operational safety degree of intelligent substation.How abnormal letter is obtained from a large amount of, complicated signal
Number, and it is quickly reflected to operation maintenance personnel, become and improves intelligent substation operational safety and its an important ring.By artificial
Check item by item, seriously affect the efficiency of intelligent substation O&M, by secondary equipment of intelligent converting station intelligent patrol program into
Row is automatic to be maked an inspection tour, and intelligent substation O&M efficiency can be greatly improved, based in current tour project comprising being similar to protection
This kind of response type signal for requiring user to wait of definite value, during the tour of secondary equipment of intelligent converting station, the prior art is patrolled
All it is to traverse item by item depending on the way taken, calls order to send user, then waits secondary device response user's calling
Order, the process take a long time, and greatly reduce the efficiency of tour.
Summary of the invention
The object of the present invention is to provide the method that a kind of intelligent substation protection equipment high efficiency is maked an inspection tour, the technology to be solved is asked
Topic is to improve the tour efficiency of secondary equipment of intelligent converting station.
The invention adopts the following technical scheme: a kind of method that intelligent substation protection equipment high efficiency is maked an inspection tour, including it is following
Step:
One, inspection tour system is established
Intelligent patrol module is set, and intelligent patrol module is connected with real-time database, database, and the connection of intelligent patrol module is actively
Module and passive module, active module and passive module and real-time data base, which are established, to be communicated to connect;
Two, initial configuration
Intelligent patrol module obtains the secondary device and its permit that tour vacuum phase, tour time and permission are maked an inspection tour from database
Perhaps by tour project, secondary device model information is obtained from real-time database, is categorized into tour project, obtain a reference value from database
Information data;
Three, timing match trigger condition
Intelligent patrol module judges whether the tour time in tour vacuum phase, if so, judgement reaches trigger condition;
Four, start to make an inspection tour
Secondary device that the permission obtained when intelligent patrol module is according to initial configuration is maked an inspection tour and its by tour project,
Traversal is allowed to the tour project of the secondary device maked an inspection tour being allowed to, and obtains respective value real time data from real-time database one by one,
It after the completion of traversal, is formed and makes an inspection tour destination file, destination file will be maked an inspection tour by messaging bus and be sent to user;
Five, configuration is reloaded
Intelligent patrol module again from database obtain tour vacuum phase, the secondary device that tour time and permission are maked an inspection tour and
It allows by tour project, obtains secondary device model information from real-time database, is categorized into tour project, obtains base from database
Quasi- value information data;
Six, configuration content is maked an inspection tour
Intelligent patrol module walks allow the secondary device maked an inspection tour by tour project, obtained from real-time database and make an inspection tour item
Mesh corresponds to live data values, obtains making an inspection tour result;
Seven, result is maked an inspection tour in analysis
Intelligent patrol module is according to tour as a result, being analyzed;
Eight, it generates to make an inspection tour as a result, issuing by messaging bus to user and makes an inspection tour result.
Step two of the invention is by tour project are as follows: hard pressing plate is maked an inspection tour, soft pressing plate is maked an inspection tour, is opened and is maked an inspection tour, converts into quantity of state
Switch is maked an inspection tour, clock is maked an inspection tour, communications status is maked an inspection tour, secondary circuit is maked an inspection tour, self-checking alarming is maked an inspection tour, GPS alarm is maked an inspection tour, recording is patrolled
It is maked an inspection tour depending on, analog quantity, Current Voltage circuit is maked an inspection tour, channel is maked an inspection tour, definite value area is maked an inspection tour, definite value is maked an inspection tour, software version is maked an inspection tour.
Step three intelligent patrol module of the invention judges whether the tour time in tour vacuum phase, if it is not, after
Continue this step timing match trigger condition.
Step four tour process of the invention is divided into two classes, and one kind is that intelligent patrol module is arranged according to configuration file is maked an inspection tour
It is maked an inspection tour in the tour time of tour vacuum phase, the another kind of tour order for receiving user for intelligent patrol module passes through the life
It enables so that the enabled triggering of intelligent patrol module is maked an inspection tour.
Step seven analysis of the invention is maked an inspection tour as a result, the same by tour project of same secondary device is analyzed, if by patrolling
Depending on the project real time data it is without exception, it is consistent with a reference value, it is believed that the tour project of the secondary device " it is normal, be not necessarily to
Maintenance ".
Of the invention analyzes the same by tour project of same secondary device, if the real time data for the project maked an inspection tour
There are exception, real time data and a reference value are different extremely, and the number of abnormal real time data is less than entire project and makes an inspection tour number in real time
According to 10%, it is believed that the tour project " abnormal, to need to pay close attention to ".
Of the invention analyzes the same by tour project of same secondary device, if the project maked an inspection tour is abnormal real-time
Data number has reached 50% or more of entire tour project real time data, it is believed that the tour project " serious, to need to overhaul ".
Same secondary device of analysis of the invention, all tour projects all " normal, without maintenance ", it is believed that this is secondary to set
It is standby " normal, without maintenance ".
If there are tour projects non-" normally, without maintenance " and non-" normally, being not necessarily to overhaul " for the present invention secondary device
Project be less than and entire make an inspection tour the 10% of project, it is believed that the secondary device " abnormal, to need to pay close attention to ".
If non-" normal, without the maintenance " project of the secondary device of the invention be more than it is entire make an inspection tour project 50% and with
On, it is believed that the secondary device " serious, to need to overhaul ".
Compared with prior art, the present invention establishing inspection tour system, by the way of the processing of distributed multimode block, it is effectively reduced
The time of response signal is handled during making an inspection tour, by configuration file, fixed cycle, timed patrol is maked an inspection tour by tour secondary device
Project analyze to by tour project, generates to make an inspection tour and make an inspection tour as a result, issuing to user as a result, improving intelligent substation
The tour efficiency of secondary device, and then improve the efficiency of entire intelligent substation O&M.
Detailed description of the invention
Fig. 1 is the inspection tour system structural schematic diagram of the embodiment of the present invention.
Fig. 2 is the flow chart of the embodiment of the present invention.
Fig. 3 is the mutually matched flow chart of each module of inspection tour system of the embodiment of the present invention.
Specific embodiment
Invention is further described in detail with reference to the accompanying drawings and examples.
As shown in Figure 1, the method that intelligent substation protection equipment high efficiency of the invention is maked an inspection tour, establishes inspection tour system, makes an inspection tour
System is equipped with secondary equipment of intelligent converting station intelligent patrol module (intelligent patrol module), and intelligent patrol module is connected with real-time number
According to library (real-time database), database, intelligent patrol module connects the module that data are sent in processing secondary device active through messaging bus
The modules (passive module) of data, active module and passive module and in real time are sent on (active module) and processing secondary device are passive
Database communication connection.
As shown in figure 3, inspection tour system is also understood that as by data processing module, infrastructure service module and intelligent patrol mould
Block is constituted.Data processing module is obtained in fact to 16 tour projects required for secondary equipment of intelligent converting station intelligent patrol
When value information after handled to obtain the module of real time data, slave secondary device actively or passively obtains real value, will be real-time
Value is written to real-time database storage, while being sent to user to the information of variation in the form alerted.Data processing module includes master
Modules in dynamic model block and passive module.The system that infrastructure service module refers to the underlying services of intelligent patrol module, packet
It includes and establishes database, establish real-time database, data are loaded into the execution process of real-time database from database.The work of intelligent patrol module
Make to depend on data processing module and infrastructure service module, the work of data processing module equally also relies on infrastructure service mould
Block.
In the present embodiment, it includes 16 that intelligent patrol module, which presses " south electric network intelligence oscillograph technical specification " annex H,
Tour project: hard pressing plate is maked an inspection tour, soft pressing plate is maked an inspection tour, is opened into quantity of state tour, change-over switch tour, clock tour, communications status
It makes an inspection tour, secondary circuit is maked an inspection tour, self-checking alarming is maked an inspection tour, GPS alarm is maked an inspection tour, recording is maked an inspection tour, analog quantity is maked an inspection tour, Current Voltage circuit is patrolled
It is maked an inspection tour depending on, channel, definite value area is maked an inspection tour, definite value is maked an inspection tour, software version is maked an inspection tour.
Before tour starts, the period, from secondary device acquisition real time data, real time data was written each data processing module
Real-time database.
When making an inspection tour beginning, intelligent patrol module loads the tour configuration file of secondary device from database, and setting is maked an inspection tour
Period and tour time are arranged by a reference value of tour secondary device project, 16 tour projects are then read from real-time database
The live data values of write-in, finally comprehensive formed make an inspection tour destination file, and by messaging bus, will make an inspection tour result with the side of message
Formula is sent to user, and will make an inspection tour result and be stored in database.
A reference value is reference value given by man, and as the foundation judged extremely, real value is not identical with a reference value, then recognizes
It is identical for exception, think normal.
Real time data is stored in memory bank by real-time data base, that is, memory bank, to improve the speed of reading and writing data.Real time data
Library receives to handle the write-in of later real time data from 16 different data processing modules, real-time database to real time data without
Any processing, the interim memory storage for being intended only as a data exist, for providing corresponding real-time number to tour module
According to.When tour module triggering, which is maked an inspection tour, to be started, module is maked an inspection tour from live data values needed for each tour project of real-time database acquisition.
The tour configuration file (configuration file) and benchmark text of secondary device needed for database is used to store tour module
Number of packages is according to (secondary device reference file), and during tour, database provides configuration file, intelligent patrol to intelligent patrol module
After module obtains the configuration file, new tour vacuum phase, tour time, the tour project of permission and each base for making an inspection tour project are set
Quasi- value information, during entire make an inspection tour, database exists with being only used as the hard-disc storage of configuration file, to data without appointing
What processing after tour, will make an inspection tour result and be stored in database in a manner of file.
Messaging bus is to transmit letter during secondary equipment of intelligent converting station intelligent patrol between each different function module
The common communication link of breath.
The different tour project of 16 of secondary equipment of intelligent converting station intelligent patrol is corresponding at 16 different data
Module is managed, information obtained is divided into two classes, and one kind is the information sent in secondary device active, and corresponding data processing module is passive
Receive the information sent on secondary device, it is another kind of to answer data processing module to issue calling order after, send on secondary device is passive
Information.Therefore, two classes are also classified into for the data processing module of two types of processing:
1. the module (active module) of data is sent in processing secondary device active, for receiving the information sent on secondary device
After processing, the real time data is written to real-time database, the real time data of early warning is reached to variation, is sent by messaging bus to user
Warning information.
Active module includes: hard pressing plate processing module, soft pressing plate processing are maked an inspection tour, are opened into quantity of state processing module, conversion
Switch process module, clock processing module, communications status processing module, secondary circuit processing module, self-checking alarming processing module,
Global position system GPS warning processing module, recording processing module, analog quantity processing module, Current Voltage circuit processing module,
Channel processing module.
Hard pressing plate processing module: hard pressing plate signal is extracted according to classification from the model information of secondary device, receives two
The hard pressing plate real value sent on secondary device, if hard pressing plate real value changes, the form which is alerted is sent out
User is given, real time data is written to real-time database.
The model information of secondary device is secondary device attribute and secondary device accurate description behavior in intelligent substation
The set of a series of signal.
Soft pressing plate processing is maked an inspection tour: being extracted soft pressing plate signal according to classification from the model information of secondary device, is received two
After the real value information processing for the soft pressing plate sent on secondary device, it is written to real-time database.
It opens quantity of state processing module: being extracted and opened into state quantity signal according to classification from the model information of secondary device,
After receiving the real value processing for opening quantity of state sent on secondary device, it is written to real-time data base;
Change-over switch processing module: extracting change-over switch signal according to classification from the model information of secondary device, receives
After the real value information processing of the change-over switch sent on to secondary device, it is written to real-time database.
Clock processing module: clock signal is extracted according to classification from the model information of secondary device, receives secondary set
After the real value information processing of the standby clock above sent, it is written to real-time database.
Communications status processing module: extracting communications status signal according to classification from the model information of secondary device, receives
After the real value information processing of the communications status sent on to secondary device, it is written to real-time database.
Secondary circuit processing module: extracting secondary circuit signal according to classification from the model information of secondary device, receives
After the real value information processing of the secondary circuit sent on to secondary device, it is written to real-time database.
Self-checking alarming processing module: extracting self-test alarm signal according to classification from the model information of secondary device, receives
After the real value information processing of the self-checking alarming sent on to secondary device, it is written to real-time database.
GPS warning processing module: GPS alarm signal is extracted according to classification from the model information of secondary device, is received
After the real value information processing for the GPS alarm sent on secondary device, it is written to real-time database.
Recording processing module: recording signal is extracted according to classification from the model information of secondary device, receives secondary set
After the real value information processing of the standby recording above sent, it is written to real-time database;
Analog quantity processing module: analog signals are extracted according to classification from the model information of secondary device, receive two
After the real value information processing for the analog quantity sent on secondary device, it is written to real-time database.
Current Voltage circuit processing module: Current Voltage circuit letter is extracted according to classification from the model information of secondary device
Number, after the real value information processing for receiving the Current Voltage circuit sent on secondary device, it is written to real-time database;
Channel processing module: channel signal is extracted according to classification from the model information of secondary device, receives secondary set
After the real value information processing in the standby channel above sent, it is written to real-time database.
2. send the modules (passive module) of data on processing secondary device is passive, for the period by messaging bus to secondary
Equipment sends calling order, when secondary device response command, after information is returned to passive resume module, real time data is written real
Shi Ku reaches the real time data of early warning to variation, is sent a warning message by messaging bus to user.
Passive module is definite value area processing module, definite value processing module, software version processing module.
Definite value area processing module: definite value area signal is extracted according to classification from the model information of secondary device, is set to secondary
Preparation send calling definite value area order, after the real value information processing for receiving the definite value area sent on secondary device, be written in real time
Library.
Definite value processing module: extracting set value signal according to classification from the model information of secondary device, sends out to secondary device
Calling definite value order is sent to be written to real-time database after the real value information processing for receiving the definite value sent on secondary device.
Software version processing module: software version signal is extracted according to classification from the model information of secondary device, to two
Secondary device sends calling software version order and writes after the real value information processing for receiving the software version sent on secondary device
Enter to real-time database.
The overall logic of each data processing module is all identical, breath of either delivering letters in reception secondary device active, or
Passive receive send real-time value information on secondary device, real-time database is written in real time data after all handling, and variation record is passed through
Messaging bus is sent to user.
Infrastructure service module is the underlying services system of inspection tour system, constitutes entire secondary equipment of intelligent converting station intelligence
The basis of tour, all real-time value informations all derive from the service of infrastructure service module offer, the model including secondary device
Information, the configuration file of intelligent patrol make an inspection tour destination file.Infrastructure service module is actively created by user, in all basis clothes
Be engaged in it is complete in the case where, just secondary equipment of intelligent converting station intelligent patrol module and data processing module is allowed to run, also could
Guarantee the normal correct operation of all modules.
In the present embodiment, intelligent patrol module, real-time data base, database, active module, passive module, infrastructure service
Module is all disposed in the Centos7.3 operating system of dawn 1210-G30 server, and inspection tour system uses C++11 program language
It realizes.Each module is an independent application system (program), can be deployed in simultaneously on a server, can also be more
A server dispersion deployment, modules are communicated with each other by messaging bus realization.
As shown in Figure 1, the method that intelligent substation protection equipment high efficiency of the invention is maked an inspection tour, comprising the following steps:
One, initial configuration
When intelligent patrol module starts on the server, initial configuration first reads from database and makes an inspection tour configuration file,
The secondary device and its allow by tour project that tour vacuum phase, tour time and permission are maked an inspection tour are obtained, obtains two from real-time database
Secondary device model information is categorized into different tour projects, is read reference file data from database, is obtained reference value information
Data.
It is initially configured as the preparation process maked an inspection tour to secondary equipment of intelligent converting station, which includes loading from database
Configuration file is maked an inspection tour to intelligent patrol module, reads and makes an inspection tour configuration file, extracting tour parameter, (tour vacuum phase, is patrolled at tour time
Depending on secondary device and make an inspection tour project).
Tour vacuum phase is the time interval maked an inspection tour, and in the present embodiment, is maked an inspection tour for 1 day primary.
Tour time is the triggered time maked an inspection tour, and is 8 points of morning in the present embodiment.
The secondary device of tour is that intelligent substation whole station is allowed to the secondary device maked an inspection tour.
Tour project is the tour project being allowed to, and the tour project of each secondary device is not quite similar, can freely match
Set, project of making an inspection tour includes 16: hard pressing plate is maked an inspection tour, soft pressing plate is maked an inspection tour, is opened into quantity of state tour, change-over switch are maked an inspection tour, clock patrols
It is maked an inspection tour depending on, communications status, secondary circuit is maked an inspection tour, self-checking alarming is maked an inspection tour, GPS alarm is maked an inspection tour, recording is maked an inspection tour, analog quantity is maked an inspection tour, electricity
Flow voltage circuit tour, channel is maked an inspection tour, definite value area is maked an inspection tour, definite value is maked an inspection tour, software version is maked an inspection tour.
Two, timing match trigger condition
The tour vacuum phase and tour time that intelligent patrol module is obtained according to initial configuration first compare last time and make an inspection tour completion
Whether the time meets the requirement of tour vacuum phase to current date, if meeting the requirement of tour vacuum phase, then compares tour time, such as
Fruit tour time is identical with the current time, then triggers tour.I.e. intelligent patrol module judges whether patrolling in tour vacuum phase
Between apparent time, if so, judgement reaches trigger condition;If it is not, continuing this step timing match trigger condition.
Trigger condition is to be greater than to current date more than or equal to tour vacuum phase with current time tour target date last time
Or it is equal to tour time.
Three, start to make an inspection tour
Secondary device that the permission obtained when intelligent patrol module is according to initial configuration is maked an inspection tour and its by tour project,
Traversal is allowed to the tour project of the secondary device maked an inspection tour being allowed to, and obtains respective value real time data from real-time database one by one,
It after the completion of traversal, is formed and makes an inspection tour destination file, destination file will be maked an inspection tour and be sent to user by way of messaging bus.
Tour process is divided into two classes, and patrolling for tour vacuum phase is arranged according to configuration file is maked an inspection tour for intelligent patrol module in one kind
It is maked an inspection tour between apparent time, the another kind of tour order for receiving user for intelligent patrol module, by the order so that intelligent power transformation
The enabled triggering of secondary device intelligent patrol module of standing is maked an inspection tour.
Four, configuration is reloaded
When intelligent patrol module starts to execute tour process every time, it can be read again from database and make an inspection tour configuration file and base
Quasi- file data obtains reference value information data (parsing reference file, the result of parsing is loaded into intelligent patrol module).
I.e. intelligent patrol module obtains the secondary device and its permission that tour vacuum phase, tour time and permission are maked an inspection tour from database again
By tour project, secondary device model information is obtained from real-time database again, is categorized into tour project, obtained again from database
Reference value information data.
Initial configuration exists only in intelligent patrol module and runs on the server for the first time, and reloads configuration and parse
Then can afterwards every time start make an inspection tour when.
Since configuration file is stored in database in a manner of file, theoretically there is the possibility artificially changed manually, because
Configuration file is reloaded in tour every time for this, and the tour project to guarantee the practical secondary device maked an inspection tour of intelligent patrol module is same to match
It sets file setting secondary device and makes an inspection tour the tour week that the consistent of project, practical tour vacuum phase and tour time are arranged with configuration file
Phase is consistent with tour time, so that it is consistent with configuration file to reach tour result.
Five, configuration content is maked an inspection tour
When intelligent patrol module starts to make an inspection tour, according to the setting of configuration file, traverse what permission in configuration file was maked an inspection tour
Secondary device by tour project, obtained from real-time database and live data values correspond to by tour project, that is, maked an inspection tour and configure content, root
According to configuration, the project for being allowed to make an inspection tour for the secondary device for being allowed to make an inspection tour is maked an inspection tour, obtains making an inspection tour result.
Tour project is 16: hard pressing plate is maked an inspection tour, soft pressing plate is maked an inspection tour, is opened into quantity of state tour, change-over switch tour, clock
Tour, communications status are maked an inspection tour, secondary circuit is maked an inspection tour, self-checking alarming is maked an inspection tour, GPS alarm tour, recording is maked an inspection tour, analog quantity is maked an inspection tour,
Current Voltage circuit is maked an inspection tour, the tour of definite value area is maked an inspection tour in channel, definite value is maked an inspection tour, software version is maked an inspection tour.The secondary of tour is allowed to set
Project that is standby and being allowed to tour is embodied according to the needs of the on-site actual situations of user by making an inspection tour configuration file.
Six, result is maked an inspection tour in analysis
Intelligent patrol module is according to tour as a result, being analyzed.
The same by tour project of same secondary device is analyzed, the tour project of each secondary device is by least one
Real value composition, if the real time data for the project maked an inspection tour is without exception, consistent with a reference value, (a reference value passes through secondary device
Reference file obtains), it is believed that the tour project " normal, without maintenance " of the secondary device.
If there are exceptions for the real time data for the project maked an inspection tour, real time data and a reference value are different extremely, and abnormal real
When data number be less than entire project makes an inspection tour real time data 10%, it is believed that the tour project " abnormal, to need to pay close attention to ".
If the abnormal real time data number for the project maked an inspection tour reached entire tour project real time data 50% and
More than, it is believed that the tour project " serious, to need to overhaul ".
Analyze same secondary device, all tour projects all " normal, without maintenance ", it is believed that the secondary device is " normally,
Without maintenance ".
If there are non-" normal, without maintenance " and non-" normal, without the maintenance " projects of the project of tour for the secondary device
The 10% of project is maked an inspection tour less than entire, it is believed that the secondary device " abnormal, to need to pay close attention to ".
If non-" normal, without the maintenance " project of the secondary device is more than entirely to make an inspection tour 50% or more of project, it is believed that
The secondary device " serious, to need to overhaul ".
The operating status for finally obtaining current secondary equipment provides maintenance, concern or the treatment advice without maintenance.
Seven, it generates and makes an inspection tour result
Intelligent patrol module generates xml format according to the requirement of " south electric network intelligence oscillograph technical specification " annex H
Document.
Eight, the tour result of generation is issued by messaging bus to user in a manner of message and is maked an inspection tour by intelligent patrol module
As a result.
As shown in figure 3, being maked an inspection tour to the project for being allowed to make an inspection tour for the secondary device that permission is maked an inspection tour, data processing mould
The workflow of block, infrastructure service module and intelligent patrol module is respectively as follows:
(1) basis of the infrastructure service module as entire intelligent patrol, it is secondary from database load before tour starts
The model information data of equipment are intelligently patrolled to real-time data base with guaranteeing that each data processing module can get corresponding data
It is available to corresponding data depending on module, to guarantee the normal correct operation entirely maked an inspection tour.
Model information data are the basic data of secondary device, for describing secondary device in intelligent substation operational process
The set of middle action behavior.
(2) data processing module, after model information data are imported database and real-time database by infrastructure service module, and
Before intelligent patrol module starts tour, from real-time database stress model information data, to guarantee that each data processing module can be from
Model data is obtained in real-time data base to be handled and real-time data base is written again, while guaranteeing that intelligent patrol module starts
When tour, processed real time data can be obtained from real-time database, to support each tour project of intelligent patrol.
(3) data processing module starts to load configuration data after real-time database load completion model data, from when being spaced
Between, access evidence is called together from secondary device at what time, i.e., obtains trigger data from configuration and recruit the condition taken.
Configuration data: period, time.
Trigger data trick takes: starting to recruit access evidence.
(4) data processing module presses regular check trigger condition.
(5) data processing module takes period and trick to take the time according to the trick obtained from configuration, is accomplished to when last time recruits to take
Interval number of days today, which is more than or equal to recruit, takes the period, while the current time is more than or equal to trick and the time is taken to start to recruit access
According to different data processing module tricks takes different types of data, it may be assumed that
Hard pressing plate processing module: hard pressing plate data;
Soft pressing plate processing is maked an inspection tour: soft pressing plate data;
It opens into quantity of state processing module: opening into state quantity data;
Change-over switch processing module: change-over switch data;
Clock processing module: clock data;
Communications status processing module: communications state data;
Secondary circuit processing module: secondary circuit data;
Self-checking alarming processing module: self-checking alarming data;
GPS warning processing module: GPS alarm data;
Recording processing module: recorder data;
Analog quantity processing module: analog data;
Current Voltage circuit processing module: Current Voltage loop data;
Channel processing module: channel data.
(6) data processing module will recruit the data taken to be stored in real-time data base.
(7) intelligent patrol module reads corresponding data from real-time data base, intelligent patrol 16 different tour projects,
Therefore the corresponding data of different tour projects are read from real-time database, complete the tour of corresponding tour project.
Hard pressing plate project: hard pressing plate data;
Soft pressing plate project: soft pressing plate data;
It opens into quantity of state project: opening into state quantity data;
Change-over switch project: change-over switch data;
Clock project: clock data;
Communications status project: communications state data;
Secondary circuit project: secondary circuit data;
Self-checking alarming project: self-checking alarming data;
GPS alerts project: GPS alarm data;
Recording project: recorder data;
Analog quantity project: analog data;
Current Voltage circuit project: Current Voltage loop data;
Channel Projects: channel data
The present invention using distributed multimode block processing by the way of, by be effectively reduced make an inspection tour during processing response signal when
Between, improve the efficiency of entire O&M.
Claims (10)
1. a kind of method that intelligent substation protection equipment high efficiency is maked an inspection tour, comprising the following steps:
One, inspection tour system is established
Intelligent patrol module is set, and intelligent patrol module is connected with real-time database, database, and intelligent patrol module connects active module
With passive module, active module and passive module and real-time data base, which are established, to be communicated to connect;
Two, initial configuration
Intelligent patrol module obtains the secondary device and its allow quilt that tour vacuum phase, tour time and permission are maked an inspection tour from database
Tour project, obtains secondary device model information from real-time database, is categorized into tour project, obtains reference value information from database
Data;
Three, timing match trigger condition
Intelligent patrol module judges whether the tour time in tour vacuum phase, if so, judgement reaches trigger condition;
Four, start to make an inspection tour
Secondary device that the permission obtained when intelligent patrol module is according to initial configuration is maked an inspection tour and its by tour project, traversal
It is allowed to the tour project of the secondary device maked an inspection tour being allowed to, obtains respective value real time data, traversal from real-time database one by one
After the completion, it is formed and makes an inspection tour destination file, destination file will be maked an inspection tour by messaging bus and be sent to user;
Five, configuration is reloaded
Intelligent patrol module obtains the secondary device and its permit that tour vacuum phase, tour time and permission are maked an inspection tour from database again
Perhaps by tour project, secondary device model information is obtained from real-time database, is categorized into tour project, obtain a reference value from database
Information data;
Six, configuration content is maked an inspection tour
Intelligent patrol module walks allow the secondary device maked an inspection tour by tour project, tour project pair is obtained from real-time database
Live data values are answered, obtain making an inspection tour result;
Seven, result is maked an inspection tour in analysis
Intelligent patrol module is according to tour as a result, being analyzed;
Eight, it generates to make an inspection tour as a result, issuing by messaging bus to user and makes an inspection tour result.
2. the method that intelligent substation protection equipment high efficiency according to claim 1 is maked an inspection tour, it is characterised in that: the step
Two by tour project are as follows: hard pressing plate is maked an inspection tour, soft pressing plate is maked an inspection tour, is opened and is maked an inspection tour into quantity of state tour, change-over switch tour, clock, is logical
Letter state is maked an inspection tour, secondary circuit is maked an inspection tour, self-checking alarming is maked an inspection tour, GPS alarm is maked an inspection tour, recording is maked an inspection tour, analog quantity is maked an inspection tour, Current Voltage
Circuit is maked an inspection tour, channel is maked an inspection tour, definite value area is maked an inspection tour, definite value is maked an inspection tour, software version is maked an inspection tour.
3. the method that intelligent substation protection equipment high efficiency according to claim 1 is maked an inspection tour, it is characterised in that: the step
Three intelligent patrol modules judge whether the tour time in tour vacuum phase, if it is not, continuing the triggering of this step timing match
Condition.
4. the method that intelligent substation protection equipment high efficiency according to claim 1 is maked an inspection tour, it is characterised in that: the step
Four tour processes are divided into two classes, and one kind is the tour time that tour vacuum phase is arranged according to configuration file is maked an inspection tour in intelligent patrol module
It is maked an inspection tour, the another kind of tour order for receiving user for intelligent patrol module, by the order so that intelligent patrol module makes
It can triggering tour.
5. the method that intelligent substation protection equipment high efficiency according to claim 1 is maked an inspection tour, it is characterised in that: the step
Seven analyses are maked an inspection tour as a result, the same by tour project of same secondary device is analyzed, if the real time data for the project maked an inspection tour
It is without exception, it is consistent with a reference value, it is believed that the tour project " normal, without maintenance " of the secondary device.
6. the method that intelligent substation protection equipment high efficiency according to claim 5 is maked an inspection tour, it is characterised in that: the analysis
Same secondary device it is same by tour project, if there are exception, real time datas for the real time data for the project maked an inspection tour
It is different extremely with a reference value, and the number of abnormal real time data is less than entire project makes an inspection tour real time data 10%, it is believed that the tour
Project " abnormal, to need to pay close attention to ".
7. the method that intelligent substation protection equipment high efficiency according to claim 6 is maked an inspection tour, it is characterised in that: the analysis
Same secondary device it is same by tour project, entirely patrolled if the abnormal real time data number for the project maked an inspection tour has reached
Depending on 50% or more of project real time data, it is believed that the tour project " serious, to need to overhaul ".
8. the method that intelligent substation protection equipment high efficiency according to claim 7 is maked an inspection tour, it is characterised in that: the analysis
Same secondary device, all tour projects all " normal, without maintenance ", it is believed that the secondary device " normal, without maintenance ".
9. the method that intelligent substation protection equipment high efficiency according to claim 8 is maked an inspection tour, it is characterised in that: if this is secondary
Equipment is less than there are non-" normal, without overhauling " and non-" normal, without the maintenance " project of the project of tour entirely makes an inspection tour project
10%, it is believed that the secondary device " abnormal, to need to pay close attention to ".
10. the method that intelligent substation according to claim 9 protection equipment high efficiency is maked an inspection tour, it is characterised in that: if this two
Non- " normal, without the maintenance " project of secondary device is more than entirely to make an inspection tour 50% or more of project, it is believed that the secondary device is " tight
Weight, needs to overhaul ".
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910024487.XA CN109831029B (en) | 2019-01-10 | 2019-01-10 | Efficient inspection method for intelligent substation protection equipment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910024487.XA CN109831029B (en) | 2019-01-10 | 2019-01-10 | Efficient inspection method for intelligent substation protection equipment |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109831029A true CN109831029A (en) | 2019-05-31 |
CN109831029B CN109831029B (en) | 2022-09-20 |
Family
ID=66860933
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910024487.XA Active CN109831029B (en) | 2019-01-10 | 2019-01-10 | Efficient inspection method for intelligent substation protection equipment |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109831029B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114296427A (en) * | 2021-12-13 | 2022-04-08 | 国网山东省电力公司电力科学研究院 | Remote secondary equipment analog quantity intelligent diagnosis method based on scheduling master station |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2013140418A (en) * | 2011-12-28 | 2013-07-18 | Toshiba Syst Technol Corp | Patrol inspection system and management server for power facility apparatus |
CN103699075A (en) * | 2013-12-11 | 2014-04-02 | 国家电网公司 | Video-monitoring-based transformer substation tour-inspection intelligent-scheduling and control system |
CN105790441A (en) * | 2016-05-02 | 2016-07-20 | 国家电网公司 | Intelligent transformer substation relay protection inspection system |
CN106558917A (en) * | 2016-11-30 | 2017-04-05 | 国家电网公司 | A kind of secondary operational system protective relaying device inspection method |
CN107390604A (en) * | 2017-07-10 | 2017-11-24 | 国网浙江省电力公司温州供电公司 | The inspection method and system of unattended operation transformer station electrical secondary system novel maintenance |
CN107862395A (en) * | 2017-11-20 | 2018-03-30 | 国网山西省电力公司检修分公司 | Alarm method is checked and accepted and maked an inspection tour to intelligent substation |
CN107995051A (en) * | 2017-12-29 | 2018-05-04 | 国网安徽省电力有限公司 | Secondary equipment of intelligent converting station visualized O&M module information interactive system and method |
-
2019
- 2019-01-10 CN CN201910024487.XA patent/CN109831029B/en active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2013140418A (en) * | 2011-12-28 | 2013-07-18 | Toshiba Syst Technol Corp | Patrol inspection system and management server for power facility apparatus |
CN103699075A (en) * | 2013-12-11 | 2014-04-02 | 国家电网公司 | Video-monitoring-based transformer substation tour-inspection intelligent-scheduling and control system |
CN105790441A (en) * | 2016-05-02 | 2016-07-20 | 国家电网公司 | Intelligent transformer substation relay protection inspection system |
CN106558917A (en) * | 2016-11-30 | 2017-04-05 | 国家电网公司 | A kind of secondary operational system protective relaying device inspection method |
CN107390604A (en) * | 2017-07-10 | 2017-11-24 | 国网浙江省电力公司温州供电公司 | The inspection method and system of unattended operation transformer station electrical secondary system novel maintenance |
CN107862395A (en) * | 2017-11-20 | 2018-03-30 | 国网山西省电力公司检修分公司 | Alarm method is checked and accepted and maked an inspection tour to intelligent substation |
CN107995051A (en) * | 2017-12-29 | 2018-05-04 | 国网安徽省电力有限公司 | Secondary equipment of intelligent converting station visualized O&M module information interactive system and method |
Non-Patent Citations (2)
Title |
---|
梁建来等: "变电智能巡视功能的拓展研究――GPS、3G和GIS在无人值守变电站巡视维护及日常管理中的应用", 《自动化应用》 * |
赵学会等: "智能变电站继电保护巡检系统的研究", 《安徽电气工程职业技术学院学报》 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114296427A (en) * | 2021-12-13 | 2022-04-08 | 国网山东省电力公司电力科学研究院 | Remote secondary equipment analog quantity intelligent diagnosis method based on scheduling master station |
CN114296427B (en) * | 2021-12-13 | 2024-03-26 | 国网山东省电力公司电力科学研究院 | Remote secondary equipment analog intelligent diagnosis method based on dispatching master station |
Also Published As
Publication number | Publication date |
---|---|
CN109831029B (en) | 2022-09-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105790441B (en) | A kind of intelligent substation relay protection cruising inspection system | |
CN111521911B (en) | Intelligent monitoring method and equipment for power transmission line | |
CN108366067B (en) | System and method for testing consistency of universal service protocol of power system | |
CN102122431B (en) | Method and system for intelligently diagnosing faults of electricity information collection terminal | |
CN112910089A (en) | Transformer substation secondary equipment fault logic visualization method and system | |
CN108767818B (en) | A kind of Commissioning of Relay Protection system and adjustment method based on virtual Prudential Master | |
CN103631921A (en) | Method and device for detecting configuration information of transformer substation | |
CN109450094A (en) | A kind of substation relay protection method for inspecting and system | |
CN106789406A (en) | A kind of IEC61850 communication protocol standards consistency testing system | |
CN206313530U (en) | A kind of telecontrol system with on-line monitoring function | |
CN109561155B (en) | Remote centralized monitoring and operation and maintenance method for substation equipment | |
CN109831029A (en) | The method that intelligent substation protects equipment high efficiency to make an inspection tour | |
CN110596485A (en) | Digital-analog integrated tester and digital-analog synchronous output method thereof | |
CN111786463A (en) | Electric power energy-saving monitoring control system | |
CN103633736B (en) | From the on-line monitoring communication means of power transformation substation to main website | |
CN112947364A (en) | System and method for early warning of equipment faults of power distribution station based on big data | |
CN209072155U (en) | A kind of power distribution network anti-error lock-in control management system | |
CN115393118A (en) | Secondary system fault positioning method and system based on monitoring data analysis | |
CN109961376A (en) | A kind of distributed energy storage apparatus management/control system and method | |
CN116738815A (en) | Electric power emergency plan deduction method, system, electronic equipment and storage medium | |
CN108320078A (en) | A kind of power plant monitoring device timeliness index Test analysis method based on big data | |
CN212460601U (en) | Network security situation perception system based on wind power plant monitoring | |
CN114202718A (en) | Safety monitoring method and device based on artificial intelligence | |
CN110989988A (en) | Micro-grid edge layer software platform based on edge calculation | |
CN110781162A (en) | Database modeling method based on SCD |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |