CN109826653B - Synchronous construction formwork trolley and construction method thereof - Google Patents
Synchronous construction formwork trolley and construction method thereof Download PDFInfo
- Publication number
- CN109826653B CN109826653B CN201910234500.4A CN201910234500A CN109826653B CN 109826653 B CN109826653 B CN 109826653B CN 201910234500 A CN201910234500 A CN 201910234500A CN 109826653 B CN109826653 B CN 109826653B
- Authority
- CN
- China
- Prior art keywords
- template
- construction
- platform
- formwork
- steel frame
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
本发明公开了一种同步施工模板台车及其施工方法,模板台车前段位于衬砌钢筋施工区域、中段位于衬砌砼施工区域、后段位于已施工完的衬砌区域,包括钢架系统、模板系统和通车系统,钢架系统包括钢框架、中部撑靴、框架升降油缸和行走轮,模板系统包括顶模、侧模、底模、前端顶撑支座和后端顶撑支座,通车系统包括通道平台、平台升降油缸和平台拉紧丝杆。本发明用于隧道混凝土衬砌整圆浇筑施工,内部可通行服务车,可实现整圆现浇二衬与管片一衬同步施工,大幅提高隧道施工效率,节约施工工期,并避免了通车对模板区域砼的影响,保障了砼施工质量,模板台车整体一次移动一个施工段,换步效率高。
The invention discloses a synchronous construction formwork trolley and a construction method thereof. The front section of the formwork trolley is located in the lining steel bar construction area, the middle section is located in the lining concrete construction area, and the rear section is located in the completed lining area, including a steel frame system and a formwork system. and opening system, the steel frame system includes steel frame, middle support shoes, frame lifting cylinders and walking wheels, the formwork system includes top mold, side mold, bottom mold, front top support support and rear top support support, the traffic system includes Channel platform, platform lift cylinder and platform tensioning screw. The invention is used for the full-circle pouring construction of the tunnel concrete lining, and the service vehicle can pass through the interior, which can realize the synchronous construction of the full-circle cast-in-place second lining and the first lining of the segment, greatly improve the tunnel construction efficiency, save the construction period, and avoid the opening of the traffic to the template. The influence of the regional concrete ensures the quality of the concrete construction. The formwork trolley moves one construction section at a time, and the step change efficiency is high.
Description
技术领域technical field
本发明属于隧道衬砌施工技术领域,具体涉及一种同步施工模板台车及其施工方法。The invention belongs to the technical field of tunnel lining construction, and particularly relates to a synchronous construction formwork trolley and a construction method thereof.
背景技术Background technique
需要整圆一次浇筑成型的隧道二衬施工,一般选用针梁式或穿行式模板台车,此类传统模板台车内部无法通行服务车,而盾构机在隧道前方掘进时,后方需通行服务车,运输渣土及材料等,故传统模板台车必须等隧道洞通后才可投入施工,总体施工工期长。另外,一段隧道区间洞通后,一般只能最多投入2台传统模板台车进行施工,额外增加工作面难度大,材料及人员运输困难,故二衬施工效率受限,施工工期长。For the construction of the secondary lining of the tunnel that needs to be cast in one round, the needle beam or walk-through formwork trolleys are generally used. Such traditional formwork trolleys cannot pass service vehicles, and when the shield machine is excavating in front of the tunnel, the rear needs to pass for service. Therefore, the traditional formwork trolley can only be put into construction after the tunnel is opened, and the overall construction period is long. In addition, after a section of the tunnel is opened, generally only two traditional formwork trolleys can be put into construction. It is difficult to increase the working face, and the transportation of materials and personnel is difficult. Therefore, the construction efficiency of the secondary lining is limited and the construction period is long.
发明内容SUMMARY OF THE INVENTION
本发明的目的是提供一种同步施工模板台车及其施工方法,用于隧道混凝土衬砌整圆浇筑施工,内部可通行服务车,可实现整圆现浇二衬与管片一衬同步施工,大幅提高隧道施工效率,节约施工工期,并避免了通车对模板区域砼的影响,保障了砼施工质量,模板台车整体一次移动一个施工段,换步效率高。The purpose of the present invention is to provide a synchronous construction formwork trolley and a construction method thereof, which are used for the full-circle pouring construction of tunnel concrete lining, and the service car can pass through the interior, which can realize the synchronous construction of the full-circle cast-in-place second lining and the segment first lining, It greatly improves the tunnel construction efficiency, saves the construction period, avoids the impact of opening to traffic on the concrete in the formwork area, and ensures the quality of the concrete construction. The formwork trolley moves one construction section at a time, and the step change efficiency is high.
本发明所采用的技术方案是:The technical scheme adopted in the present invention is:
一种同步施工模板台车,整体分为前、中、后3段,前段位于衬砌钢筋施工区域、中段位于衬砌砼施工区域、后段位于已施工完的衬砌区域,包括钢架系统、模板系统和通车系统;A synchronous construction formwork trolley is divided into front, middle and rear sections as a whole. The front section is located in the lining steel bar construction area, the middle section is located in the lining concrete construction area, and the rear section is located in the completed lining area, including a steel frame system and a formwork system. and traffic systems;
钢架系统沿隧道纵向布置,包括钢框架、中部撑靴、框架升降油缸和行走轮,中部撑靴支撑在钢框架中部且通过撑靴升降油缸升降,框架升降油缸安装在钢框架前、后端底部两侧,行走轮安装在框架升降油缸底部,钢架系统通过框架升降油缸实现整体升降且通过行走轮实现整体平移;The steel frame system is arranged longitudinally along the tunnel, including the steel frame, the middle support shoe, the frame lifting cylinder and the walking wheel. The middle support shoe is supported in the middle of the steel frame and is lifted and lowered by the support shoe lifting cylinder, and the frame lifting cylinder is installed on the front and rear ends of the steel frame. On both sides of the bottom, the walking wheels are installed at the bottom of the frame lifting cylinder, and the steel frame system realizes the overall lifting through the frame lifting cylinder and the overall translation through the walking wheels;
模板系统位于钢架系统中段,整体套在钢架系统及通车系统外围并与两者脱离开,包括顶模、侧模、底模、前端顶撑支座和后端顶撑支座,顶模、侧模和底模之间通过铰接节点、模板油缸和模板丝杆连接且能实现模板系统支模、脱模动作;支模状态下,模板系统伸出形成整环模板,整体通过前端顶撑支座和后端顶撑支座支撑,与钢架系统及通车系统均脱开;脱模状态下,模板系统收回脱离衬砌内壁,模板系统与钢架系统临时连接,随钢架系统整体移动;The formwork system is located in the middle section of the steel frame system, and is integrally wrapped around the steel frame system and the traffic opening system and separated from the two, including the top form, side form, bottom form, front end top support support and rear top support support, top mold , The side die and the bottom die are connected by hinge joints, formwork cylinders and formwork screw rods, and the formwork system can support and demold the formwork; in the formwork support state, the formwork system extends to form a whole ring formwork, which is supported by the front end as a whole. The support and the rear top support support are separated from the steel frame system and the traffic opening system; in the demolding state, the formwork system is retracted and separated from the inner wall of the lining, the formwork system is temporarily connected with the steel frame system, and moves with the steel frame system as a whole;
通车系统连接在钢架系统下部,包括通道平台、平台升降油缸和平台拉紧丝杆,通道平台上表面设置有供服务车通行的轨道,平台升降油缸及平台拉紧丝杆安装在通道平台上部两侧,平台升降油缸伸缩时,平台拉紧丝杆松开,平台升降油缸伸缩到位时,平台拉紧丝杆拉紧固定。The traffic opening system is connected to the lower part of the steel frame system, including the channel platform, the platform lifting cylinder and the platform tensioning screw. The upper surface of the channel platform is provided with a track for the passage of the service vehicle, and the platform lifting cylinder and the platform tensioning screw are installed on the upper part of the channel platform. On both sides, when the platform lifting cylinder is telescopic, the platform tightening screw is loosened, and when the platform lifting cylinder is telescopic in place, the platform tightening screw is tightened and fixed.
进一步地,钢框架由2道沿隧道方向并行的纵向钢梁或钢桁架和若干道顶部横向钢梁或钢桁架连接形成,横断面为“门”字型,钢框架分为前、中、后3段,每段之间通过可水平弯折的节点连接,当隧道为直线时,钢框架整体呈直线,当隧道为曲线时,调节相邻段之间的连接节点,能使钢框架整体沿隧道弯折。Further, the steel frame is formed by connecting two longitudinal steel beams or steel trusses in parallel along the tunnel direction and several top transverse steel beams or steel trusses. 3 sections, each section is connected by horizontally bendable nodes, when the tunnel is a straight line, the steel frame as a whole is a straight line, when the tunnel is a curve, adjust the connecting nodes between adjacent sections, so that the overall steel frame can be Tunnel bends.
进一步地,框架升降油缸和撑靴升降油缸均为机械自锁式油缸。Further, both the frame lifting cylinder and the support shoe lifting cylinder are mechanical self-locking cylinders.
进一步地,中部撑靴整体呈“U”型。Further, the middle support shoe has a "U" shape as a whole.
进一步地,侧模上端与顶模底端铰接且通过模板油缸伸缩,侧模绕顶模底边转动至支模状态时,连接模板丝杆固定,底模通过模板油缸连接在顶模下部且通过模板油缸伸缩,调整底模与顶模上下相对距离至支模状态时,连接模板丝杆固定。Further, the upper end of the side mold is hinged with the bottom end of the top mold and is extended and retracted by the template cylinder. When the side mold rotates around the bottom edge of the top mold to the state of supporting the mold, the connecting template screw is fixed, and the bottom mold is connected to the lower part of the top mold through the template cylinder and passes through. The template oil cylinder is telescopic, and when the relative distance between the bottom mold and the top mold is adjusted to the state of supporting the mold, the connecting template screw is fixed.
进一步地,侧模有2组,对称连接在顶模底端。Further, there are two sets of side molds, which are symmetrically connected to the bottom end of the top mold.
进一步地,通道平台有2段,一段位于钢筋施工区域,一段位于砼施工区域,每段由纵横相交的钢梁或桁架构成。Further, the passage platform has two sections, one is located in the steel bar construction area, and the other is located in the concrete construction area, and each section is composed of steel beams or trusses that intersect vertically and horizontally.
进一步地,通车系统横断面呈“U”型。Further, the cross-section of the open system is in a "U" shape.
上述同步施工模板台车的施工方法,包括步骤:The construction method of the above-mentioned synchronous construction formwork trolley comprises the steps:
1)模板台车前段区域的二衬钢筋绑扎完毕,模板台车中段区域的二衬现浇砼浇筑完毕并养护至具备脱模条件;1) The secondary lining steel bars in the front section of the formwork trolley have been bound, and the secondary lining cast-in-situ concrete in the middle section of the formwork trolley has been poured and maintained until the demoulding conditions are met;
2)解除平台拉紧丝杆,收回平台升降油缸提升通车系统,收回撑靴升降油缸提升中部撑靴;2) Release the platform tensioning screw, retract the platform lift cylinder to lift the traffic opening system, and retract the support shoe lift cylinder to lift the middle support shoe;
3)解除所有的模板丝杆,依次收回侧模及底模;收回模板系统的前端顶撑支座和后端顶撑支座,模板系统与钢架系统临时连接固定;3) Remove all formwork screw rods, take back the side formwork and the bottom formwork in turn; retract the front-end top support support and the rear-end top support support of the formwork system, and the formwork system and the steel frame system are temporarily connected and fixed;
4)缩回框架升降油缸,钢架系统下降,模板台车整体通过前、后端行走轮移动一个施工段,模板台车整体移动过程中,内部不通行服务车;4) The frame lifting cylinder is retracted, the steel frame system is lowered, and the formwork trolley moves a construction section through the front and rear traveling wheels. During the overall movement of the formwork trolley, there is no service vehicle inside;
5)模板台车行车换步结束后,框架升降油缸伸出,钢架系统上升至预定高度,伸出平台升降油缸,下落通车系统,连接平台拉紧丝杆,下落中部撑靴,恢复模板台车内部通行服务车;5) After the step change of the formwork trolley, the frame lifting cylinder is extended, the steel frame system is raised to the predetermined height, the platform lifting cylinder is extended, the opening system is dropped, the platform is connected to tighten the screw rod, the middle support shoe is dropped, and the formwork table is restored. Internal access service vehicle;
6)伸出模板系统的前端顶撑支座和后端顶撑支座,调整顶模至预定位置,伸出模板油缸调整底模至预定位置,伸出模板油缸转动侧模至预定位置,连接模板丝杆,将顶模、侧模、底模固定为一个整体,模板系统由前端顶撑支座和后端顶撑支座支撑,模板系统与钢架系统及通车系统脱离开;6) Extend the front-end top support and rear-end top support of the formwork system, adjust the top die to the predetermined position, extend the formwork cylinder to adjust the bottom die to the predetermined position, extend the formwork cylinder to rotate the side die to the predetermined position, connect The formwork screw fixes the top die, side die and bottom die as a whole, the formwork system is supported by the front end top support support and the rear end support support, and the formwork system is separated from the steel frame system and the traffic system;
7)浇筑模板台车中段区域的二衬砼,绑扎模板台车前段区域的二衬钢筋;7) Pour the secondary lining concrete in the middle section of the formwork trolley, and bind the secondary lining steel bars in the front section of the formwork trolley;
8)重复步骤1)至7)直至施工完毕。8) Repeat steps 1) to 7) until the construction is completed.
本发明产生的有益效果是:The beneficial effects that the present invention produces are:
该模板台车含通车系统,可实现二衬整圆浇筑施工的同时,内部通行服务车,不阻碍生产物资及渣土运输,从而实现模板台车在隧道洞通前即投入使用,且一个区间可同时投入多台模板台车,大幅提高二衬施工效率,节约施工工期。The formwork trolley includes a traffic opening system, which can realize the full circle pouring of the second lining and at the same time, the service vehicle can pass through the interior without hindering the transportation of production materials and muck, so that the formwork trolley can be put into use before the tunnel is opened, and an interval Multiple formwork trolleys can be put in at the same time, which greatly improves the construction efficiency of the secondary lining and saves the construction period.
该模板台车内部通车时,模板系统整体套在钢架系统及通车系统外围,并与两者脱离开。服务车通行荷载始终传递给通车系统,再传递至钢架系统,再传递至管片及已施工完的二衬结构上,模板系统始终只承受砼荷载,并直接传递至管片及已施工完的二衬结构上,从而避免了通车对模板区域砼的影响,保障了砼施工质量。When the formwork trolley is opened to traffic, the formwork system is integrally wrapped around the steel frame system and the periphery of the opening system, and is separated from the two. The traffic load of the service vehicle is always transmitted to the traffic system, and then to the steel frame system, and then to the segment and the completed secondary lining structure. The formwork system always only bears the concrete load, and is directly transmitted to the segment and the completed secondary lining structure. On the secondary lining structure, the impact of opening to traffic on the concrete in the formwork area is avoided, and the quality of the concrete construction is guaranteed.
该模板台车行车换步时,模板系统脱开二衬内壁,并与钢架系统临时连接,随钢架系统整体前移,模板台车整体一次移动一个施工段,换步效率高。When the formwork trolley moves to change steps, the formwork system is separated from the inner wall of the secondary lining and temporarily connected with the steel frame system. With the overall movement of the steel frame system, the formwork trolley moves one construction section at a time, and the step change efficiency is high.
附图说明Description of drawings
下面结合附图及实施例对本发明作进一步说明。The present invention will be further described below with reference to the accompanying drawings and embodiments.
图1是本发明实施例的侧面总示意图。FIG. 1 is a general schematic side view of an embodiment of the present invention.
图2是本发明实施例的横断面总示意图。FIG. 2 is a general schematic cross-sectional view of an embodiment of the present invention.
图3是本发明实施例的侧面组成示意图。FIG. 3 is a schematic diagram of a side composition of an embodiment of the present invention.
图4是本发明实施例中钢架系统侧面及横断面示意图。FIG. 4 is a schematic side view and a cross-sectional view of the steel frame system in the embodiment of the present invention.
图5是本发明实施例中模板系统侧面及横断面示意图。5 is a schematic side view and a cross-sectional view of a formwork system in an embodiment of the present invention.
图6是本发明实施例中通车系统侧面及横断面示意图。FIG. 6 is a schematic side view and a cross-sectional view of the open-to-vehicle system in the embodiment of the present invention.
图中:1-一衬管片、2-二衬、2.1-二衬钢筋、2.2-二衬现浇砼、3-模板台车、3.1-钢架系统、3.1.1-钢框架、3.1.2-中部撑靴、3.1.3-框架升降油缸、3.1.4-行走轮、3.2-模板系统、3.2.1-顶模、3.2.2-侧模、3.2.3-底模3.2.4-前端顶撑支座、3.2.5-后端顶撑支座、3.2.6-模板油缸、3.2.7-模板丝杆、3.3-通车系统、3.3.1-通道平台、3.3.2-平台升降油缸、3.3.3-平台拉紧丝杆、4-台车轨道、5-服务车。In the picture: 1- one lining pipe piece, 2- two lining, 2.1- two lining steel bar, 2.2- two lining cast-in-place concrete, 3- formwork trolley, 3.1- steel frame system, 3.1.1- steel frame, 3.1. 2-Middle support shoe, 3.1.3-Frame lifting cylinder, 3.1.4-Walking wheel, 3.2-Template system, 3.2.1-Top die, 3.2.2-Side die, 3.2.3-Bottom die 3.2.4- Front-end top support, 3.2.5-rear top support, 3.2.6-formwork cylinder, 3.2.7-formwork screw, 3.3-opening system, 3.3.1-channel platform, 3.3.2-platform lift Oil cylinder, 3.3.3-platform tensioning screw, 4-trolley track, 5-service car.
具体实施方式Detailed ways
为了使本发明的目的、技术方案及优点更加清楚明白,以下结合附图及实施例,对本发明进行进一步详细说明。应当理解,此处所描述的具体实施例仅用以解释本发明,并不用于限定本发明。In order to make the objectives, technical solutions and advantages of the present invention clearer, the present invention will be further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention, but not to limit the present invention.
如图1、图2、图3所示,模板台车3位于隧道一衬管片1内部,整体分为前、中、后3段,前段位于衬砌钢筋2.1施工区域,中段位于衬砌现浇砼2.2施工区域,后段位于已施工完的衬砌2区域,模板台车3包括钢架系统3.1、模板系统3.2和通车系统3.3。As shown in Figure 1, Figure 2 and Figure 3, the
如图3、图4所示,钢架系统3.1沿隧道纵向布置,由钢框架3.1.1、中部撑靴3.1.2、框架升降油缸3.1.3及行走轮3.1.4组成,2个中部撑靴3.1.2支撑在钢框架3.1.1中部,靠近模板系统3.2两端,框架升降油缸3.1.3安装在钢框架3.1.1前、后端底部两侧,行走轮3.1.4安装在框架升降油缸3.1.3底部,钢架系统3.1通过前、后端共至少4个框架升降油缸3.1.3实现整体升降,通过前、后端共至少4个行走轮3.1.4实现整体平移。As shown in Figure 3 and Figure 4, the steel frame system 3.1 is arranged longitudinally along the tunnel, consisting of a steel frame 3.1.1, a middle support shoe 3.1.2, a frame lifting cylinder 3.1.3 and a walking wheel 3.1.4, and two middle support The shoe 3.1.2 is supported in the middle of the steel frame 3.1.1, close to both ends of the formwork system 3.2, the frame lifting cylinder 3.1.3 is installed on both sides of the bottom of the front and rear ends of the steel frame 3.1.1, and the walking wheel 3.1.4 is installed on the frame lifting At the bottom of the oil cylinder 3.1.3, the steel frame system 3.1 realizes the overall lifting through at least 4 frame lifting cylinders 3.1.3 at the front and rear ends, and realizes overall translation through at least 4 walking wheels 3.1.4 at the front and rear ends.
如图2、图5所示,模板系统3.2位于钢架系统3.1中段,整体套在钢架系统3.1及通车系统3.3外围,并与两者脱离开,模板系统3.2由顶模3.2.1、侧模3.2.2、底模3.2.3、前端顶撑支座3.2.4、后端顶撑支座3.2.5组成,顶模3.2.1、侧模3.2.2、底模3.2.3之间通过铰接节点、模板油缸3.2.6、模板丝杆3.2.7连接,实现模板系统3.2支模、脱模动作;支模状态下,模板系统3.2伸出形成整环模板,整体通过前端顶撑支座3.2.4及后端顶撑支座3.2.5支撑,与钢架系统3.1及通车系统3.3均脱开;脱模状态下,模板系统3.2收回脱离衬砌内壁,模板系统3.2与钢架系统3.1临时连接,随钢架系统3.1整体移动。As shown in Figure 2 and Figure 5, the formwork system 3.2 is located in the middle section of the steel frame system 3.1, and is integrally wrapped around the steel frame system 3.1 and the traffic opening system 3.3, and is separated from the two. The formwork system 3.2 consists of the top form 3.2.1, side Die 3.2.2, bottom die 3.2.3, front end top support 3.2.4, rear end top support 3.2.5, between top die 3.2.1, side die 3.2.2 and bottom die 3.2.3 The formwork system 3.2 is supported and demolded through the connection of hinged nodes, formwork cylinder 3.2.6 and formwork screw 3.2.7; in the formwork support state, formwork system 3.2 extends to form a complete ring formwork, which is supported by the front end top support as a whole Supported by seat 3.2.4 and rear end top support support 3.2.5, they are disengaged from steel frame system 3.1 and traffic opening system 3.3; in demolding state, formwork system 3.2 is retracted from the inner wall of the lining, formwork system 3.2 and steel frame system 3.1 Temporary connection, moving as a whole with the steel frame system 3.1.
如图2、图6所示,通车系统3.3连接在钢架系统3.1下部,由通道平台3.3.1、平台升降油缸3.3.2及平台拉紧丝杆3.3.3组成,平台升降油缸3.3.2及平台拉紧丝杆3.3.3安装在通道平台3.3.1上部两侧,通车系统3.3横断面呈“U”型。As shown in Figure 2 and Figure 6, the traffic opening system 3.3 is connected to the lower part of the steel frame system 3.1, and is composed of the channel platform 3.3.1, the platform lifting cylinder 3.3.2 and the platform tensioning screw 3.3.3. The platform lifting cylinder 3.3.2 And the platform tensioning screw 3.3.3 is installed on both sides of the upper part of the channel platform 3.3.1, and the cross section of the opening system 3.3 is "U" shape.
在本发明的优选实施例中,如图4所示,钢框架3.1.1由2道沿隧道方向并行的纵向钢梁(或钢桁架)、若干道顶部横向钢梁(或钢桁架)连接形成,横断面为“门”字型,所述钢框架3.1.1分为前、中、后共3段,每段之间通过可水平弯折的节点连接,当隧道为直线时,所述钢框架3.1.1整体呈直线型,当隧道为曲线时,调节每段之间的连接节点,使所述钢框架3.1.1整体沿隧道曲线弯折。In a preferred embodiment of the present invention, as shown in Figure 4, the steel frame 3.1.1 is formed by connecting two longitudinal steel beams (or steel trusses) parallel to the tunnel direction and several top transverse steel beams (or steel trusses) , the cross section is a "door" shape, the steel frame 3.1.1 is divided into three sections: front, middle and rear, and each section is connected by horizontally bendable nodes. When the tunnel is a straight line, the steel frame The frame 3.1.1 is linear as a whole. When the tunnel is curved, the connection nodes between each section are adjusted so that the steel frame 3.1.1 is bent along the tunnel curve as a whole.
在本发明的优选实施例中,如图4所示,中部撑靴3.1.2整体呈“U”型,通过机械自锁式油缸升降。In a preferred embodiment of the present invention, as shown in FIG. 4 , the middle support shoe 3.1.2 has a “U” shape as a whole, and is lifted and lowered by a mechanical self-locking oil cylinder.
在本发明的优选实施例中,如图4所示,框架升降油缸3.1.3为机械自锁式油缸。In a preferred embodiment of the present invention, as shown in FIG. 4 , the frame lifting oil cylinder 3.1.3 is a mechanical self-locking oil cylinder.
在本发明的优选实施例中,如图5所示,侧模3.2.2上端与顶模3.2.1底端铰接,侧模3.2.2通过模板油缸3.2.6伸缩,可绕顶模3.2.1底边转动,转动至支模状态时,连接模板丝杆3.2.7固定。In a preferred embodiment of the present invention, as shown in Figure 5, the upper end of the side mold 3.2.2 is hinged with the bottom end of the top mold 3.2.1, and the side mold 3.2.2 is extended and retracted through the template oil cylinder 3.2.6, and can wrap around the top mold 3.2.2. 1. When the bottom edge is rotated, when it is rotated to the state of supporting the die, the screw rod 3.2.7 of the connecting template is fixed.
在本发明的优选实施例中,如图5所示,侧模3.2.2有2组,对称连接在顶模3.2.1底端。In a preferred embodiment of the present invention, as shown in Figure 5, there are two sets of side molds 3.2.2, which are symmetrically connected to the bottom end of the top mold 3.2.1.
在本发明的优选实施例中,如图5所示,底模3.2.3通过模板油缸3.2.6连接在顶模3.2.1下部,通过模板油缸3.2.6伸缩,调整底模3.2.3与顶模3.2.1上下相对距离,调整至支模状态时,连接模板丝杆3.2.7固定。In the preferred embodiment of the present invention, as shown in Figure 5, the bottom mold 3.2.3 is connected to the lower part of the top mold 3.2.1 through the template oil cylinder 3.2.6, and the template oil cylinder 3.2.6 expands and contracts to adjust the bottom mold 3.2.3 and the bottom mold. The top mold 3.2.1 is the relative distance up and down. When it is adjusted to the mold support state, the connection template screw 3.2.7 is fixed.
在本发明的优选实施例中,如图6所示,通道平台3.3.1有2段,一段位于钢筋2.1施工区域,一段位于砼2.2施工区域,每段由纵横相交的钢梁或桁架构成,其上表面设置有供服务车5通行的轨道。In a preferred embodiment of the present invention, as shown in Figure 6, the channel platform 3.3.1 has two sections, one is located in the construction area of the steel bar 2.1, and the other is located in the construction area of the concrete 2.2, each section is composed of steel beams or trusses that intersect vertically and horizontally, The upper surface is provided with a track for the
在本发明的优选实施例中,如图6所示,平台升降油缸3.3.2为机械自锁式油缸。In a preferred embodiment of the present invention, as shown in FIG. 6 , the platform lifting oil cylinder 3.3.2 is a mechanical self-locking oil cylinder.
在本发明的优选实施例中,如图6所示,平台升降油缸3.3.2伸缩时,所述平台拉紧丝杆3.3.3松开,所述平台升降油缸3.3.2伸缩到位时,所述平台拉紧丝杆3.3.3拉紧固定。In a preferred embodiment of the present invention, as shown in FIG. 6, when the platform lifting cylinder 3.3.2 is telescopic, the platform tensioning screw 3.3.3 is loosened, and when the platform lifting cylinder 3.3.2 is telescopic in place, all the The platform tightening screw 3.3.3 is tightened and fixed.
上述模板台车3的施工方法,包括步骤:The construction method of above-mentioned
1)模板台车3行车换步前,通过收回平台升降油缸3.3.2,提升通车系统3.3,并提升中部撑靴3.1.2;解除模板系统3.2所有模板丝杆3.2.7,通过收回模板油缸3.2.6,依次收回侧模3.2.2及底模3.2.3;收回模板系统3.2的前端顶撑支座3.2.4和后端顶撑支座3.2.5,模板系统3.2与钢架系统3.1临时连接固定,框架升降油缸3.1.3缩回,钢架系统3.1下降,模板台车3整体通过前、后端行走轮3.1.4移动一个施工段;模板台车3整体移动过程中,内部不通行服务车5。1) Before the
2)模板台车3行车换步结束后,通过框架升降油缸3.1.3伸出,钢架系统3.1上升至预定高度,通过伸出平台升降油缸3.3.2,下落通车系统3.3,并连接平台拉紧丝杆3.3.3,下落中部撑靴3.1.2,恢复模板台车3内部通行服务车5。通过伸出模板系统3.2的前端顶撑支座3.2.4和后端顶撑支座3.2.5,调整顶模3.2.1至预定位置,通过伸出模板油缸3.2.6,调整底模3.2.3至预定位置,连接顶模3.2.1、底模3.2.3间的拉紧丝杆,通过伸出模板油缸3.2.6,转动侧模3.2.2至预定位置,连接顶模3.2.1、侧模3.2.2间及侧模3.2.2、底模3.2.3间的拉紧丝杆,将顶模3.2.1、侧模3.2.2、底模3.2.3固定为一个整体,整体由前端顶撑支座3.2.4和后端顶撑支座3.2.5支撑,与钢架系统3.1及通车系统3.3脱离开,再进行砼2.2浇筑。2) After the
如图1-图6所示,模板台车3施工如下:As shown in Figures 1-6, the construction of the
1)模板台车3前段区域的二衬钢筋2.2绑扎完毕,模板台车3中段区域的二衬现浇砼2.1浇筑完毕并养护至具备脱模条件;1) The secondary lining steel bar 2.2 in the front section of the
2)解除平台拉紧丝杆3.3.3,通过收回平台升降油缸3.3.2,提升通车系统3.3,并提升中部撑靴3.1.2;2) Release the platform tensioning screw 3.3.3, by retracting the platform lifting cylinder 3.3.2, lift the traffic opening system 3.3, and lift the middle support shoe 3.1.2;
3)解除所有模板丝杆3.2.7,依次收回侧模3.2.2及底模3.2.3;收回模板系统3.2的前端顶撑支座3.2.4和后端顶撑支座3.2.5,模板系统3.2与钢架系统3.1临时连接固定;3) Release all formwork screw 3.2.7, retract side form 3.2.2 and bottom form 3.2.3 in turn; retract front-end top support 3.2.4 and rear-end top support 3.2.5 of formwork system 3.2, formwork System 3.2 is temporarily connected and fixed with steel frame system 3.1;
4)钢架系统3.1下降,模板台车3整体通过前、后端行走轮3.1.4移动一个施工段。4) The steel frame system 3.1 is lowered, and the
5)钢架系统3.1上升至预定高度,下落通车系统3.3,连接平台拉紧丝杆3.3.3,下落中部撑靴3.1.2,恢复模板台车3内部通车。5) The steel frame system 3.1 rises to the predetermined height, drops the open-to-vehicle system 3.3, connects the platform to tighten the screw 3.3.3, drops the middle support shoe 3.1.2, and restores the
6)通过伸出模板系统3.2的前端顶撑支座3.2.4和后端顶撑支座3.2.5,调整顶模3.2.1至预定位置,再调整底模3.2.3至预定位置,转动侧模3.2.2至预定位置,连接模板丝杆3.2.7,将顶模3.2.1、侧模3.2.2、底模3.2.3固定为一个整体,整体由前端顶撑支座3.2.4和后端顶撑支座3.2.5支撑,与钢架系统3.1及通车系统3.3脱离开;6) Adjust the top die 3.2.1 to the predetermined position by extending the front end top support support 3.2.4 and the rear end top support support 3.2.5 of the formwork system 3.2, and then adjust the bottom mold 3.2.3 to the predetermined position, rotate The side mold 3.2.2 is moved to the predetermined position, and the template screw 3.2.7 is connected, and the top mold 3.2.1, side mold 3.2.2, and bottom mold 3.2.3 are fixed as a whole, and the whole is supported by the front end support 3.2.4 It is supported by the rear end top support support 3.2.5, and is separated from the steel frame system 3.1 and the traffic opening system 3.3;
7)浇筑模板台车3中段区域的二衬砼2.1,绑扎模板台车3前段区域的二衬钢筋2.2。7) The secondary lining concrete 2.1 in the middle area of the
8)上述步骤1)至步骤7)依次循环施工。8) The above steps 1) to 7) are cycled and constructed in turn.
应当理解的是,对本领域普通技术人员来说,可以根据上述说明加以改进或变换,而所有这些改进和变换都应属于本发明所附权利要求的保护范围。It should be understood that for those skilled in the art, improvements or changes can be made according to the above description, and all these improvements and changes should fall within the protection scope of the appended claims of the present invention.
Claims (9)
Applications Claiming Priority (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2018102587371 | 2018-03-27 | ||
| CN201810258737 | 2018-03-27 |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN109826653A CN109826653A (en) | 2019-05-31 |
| CN109826653B true CN109826653B (en) | 2020-10-27 |
Family
ID=66872460
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201910234500.4A Active CN109826653B (en) | 2018-03-27 | 2019-03-26 | Synchronous construction formwork trolley and construction method thereof |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN109826653B (en) |
Families Citing this family (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110130937B (en) * | 2019-06-06 | 2024-02-20 | 涪特智能装备(重庆)有限公司 | Tunnel construction trolley |
| CN110374632A (en) * | 2019-07-15 | 2019-10-25 | 中铁工程装备集团隧道设备制造有限公司 | Shield tunnel synchronization lining wholecircle formwork jumbo and construction method |
| CN110454177B (en) * | 2019-09-04 | 2025-08-05 | 中交天和机械设备制造有限公司 | A multi-mode hard rock tunnel boring machine |
| CN111365035B (en) * | 2020-05-14 | 2025-01-24 | 中铁四局集团第二工程有限公司 | A kind of pipe gallery diaphragm fast linkage construction trolley and pipe gallery diaphragm construction method |
| CN112814702B (en) * | 2021-01-06 | 2022-06-07 | 中国铁建重工集团股份有限公司 | Shield constructs machine and synchronous translation mechanism of whole circular ware of section of jurisdiction thereof |
| WO2022193200A1 (en) * | 2021-03-18 | 2022-09-22 | 中建三局基础设施建设投资有限公司 | Rapid construction method for secondary lining of small-section tunnel |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101403305A (en) * | 2008-09-08 | 2009-04-08 | 中铁隧道集团有限公司 | Construction method for tunnel continuous mucking, lining and excavation synchronization |
| CN202417530U (en) * | 2012-01-17 | 2012-09-05 | 张新泉 | Bottom-positioned traversing synchronous tunnel lining trolley for continuous conveyor construction of tunnel |
| CN204754941U (en) * | 2015-06-17 | 2015-11-11 | 安徽奥发建筑制品有限公司 | All -hydraulic self -propelled tunnel lining platform truck |
| CN105401525A (en) * | 2015-10-23 | 2016-03-16 | 中铁六局集团有限公司 | Cast-in-situ construction method of beam flange plates of acoustic barriers through movable mold base vehicles |
| EP3112585A1 (en) * | 2015-07-01 | 2017-01-04 | Great Ocean Constructions Ltd | A tunneling machinery and a method of providing a concrete tunnel base |
| CN206874289U (en) * | 2017-05-23 | 2018-01-12 | 中交第一公路工程局有限公司 | Just lining construction hydraulic template trolley |
-
2019
- 2019-03-26 CN CN201910234500.4A patent/CN109826653B/en active Active
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101403305A (en) * | 2008-09-08 | 2009-04-08 | 中铁隧道集团有限公司 | Construction method for tunnel continuous mucking, lining and excavation synchronization |
| CN202417530U (en) * | 2012-01-17 | 2012-09-05 | 张新泉 | Bottom-positioned traversing synchronous tunnel lining trolley for continuous conveyor construction of tunnel |
| CN204754941U (en) * | 2015-06-17 | 2015-11-11 | 安徽奥发建筑制品有限公司 | All -hydraulic self -propelled tunnel lining platform truck |
| EP3112585A1 (en) * | 2015-07-01 | 2017-01-04 | Great Ocean Constructions Ltd | A tunneling machinery and a method of providing a concrete tunnel base |
| CN105401525A (en) * | 2015-10-23 | 2016-03-16 | 中铁六局集团有限公司 | Cast-in-situ construction method of beam flange plates of acoustic barriers through movable mold base vehicles |
| CN206874289U (en) * | 2017-05-23 | 2018-01-12 | 中交第一公路工程局有限公司 | Just lining construction hydraulic template trolley |
Also Published As
| Publication number | Publication date |
|---|---|
| CN109826653A (en) | 2019-05-31 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN106089253B (en) | A kind of all-hydraulic template system poured for culvert | |
| CN207109856U (en) | Piping lane, culvert construction hydraulic steel formwork jumbo | |
| CN113417219B (en) | Hydraulic internal mold asynchronous traveling system and method for bridge suspension casting basket box chamber | |
| CN211762304U (en) | A self-propelled hydraulic integral T beam formwork device | |
| CN109826653A (en) | Synchronous construction formwork trolley and construction method thereof | |
| CN109968499B (en) | Special die for pouring T-shaped beam and application method thereof | |
| CN108442255A (en) | A mobile formwork bridge-building machine and a construction method for a cast-in-place bridge | |
| CN105649654A (en) | Automatic hydraulic inverted arch trestle trolley and construction method thereof | |
| CN112647436B (en) | Porous cast-in-place box culvert floor and construction method | |
| CN114575892B (en) | Off-wall vault lining trolley and construction method thereof | |
| CN102660925B (en) | Moveable formwork for variable-width curved bridge | |
| CN202658533U (en) | Movable formwork of curved bridge with variable width | |
| CN209144661U (en) | Mould bases for bridge construction | |
| CN107100648B (en) | Auxiliary facility and method for tunnel plain concrete lining construction | |
| CN205277439U (en) | Rectangle tunnel lining platform truck | |
| CN107060831A (en) | One kind is used for tunnel groove constructing device | |
| CN202416190U (en) | Formwork for prefabricated box girder of rear poured flange slab | |
| CN112746857A (en) | Full-hydraulic highway tunnel cable trench lining construction device and construction method | |
| CN101205702A (en) | Beam and mold combined mobile formwork | |
| CN217813509U (en) | Non-portal trolley | |
| CN214464241U (en) | Full-hydraulic lining construction device for cable trench of highway tunnel | |
| CN111022078A (en) | Trestle type upper opening full-section synchronous construction equipment and construction method thereof | |
| CN207825160U (en) | Large-span Precast box beam hydraulic deploying and retracting internal mold | |
| CN206359897U (en) | A kind of radial type steel core form unit | |
| CN117967353A (en) | An inverted arch sliding formwork trestle trolley and an inverted arch casting method thereof |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |
