CN109816940A - The fault alarm method and device of sewage treatment plant - Google Patents

The fault alarm method and device of sewage treatment plant Download PDF

Info

Publication number
CN109816940A
CN109816940A CN201910217416.1A CN201910217416A CN109816940A CN 109816940 A CN109816940 A CN 109816940A CN 201910217416 A CN201910217416 A CN 201910217416A CN 109816940 A CN109816940 A CN 109816940A
Authority
CN
China
Prior art keywords
node
warning message
zero
causality
degree
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910217416.1A
Other languages
Chinese (zh)
Other versions
CN109816940B (en
Inventor
王达
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
DASMART ENVIRONMENTAL TECHNOLOGIES (BEIJING) CO LTD
Original Assignee
Beijing Etechwin Electric Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Etechwin Electric Co Ltd filed Critical Beijing Etechwin Electric Co Ltd
Priority to CN201910217416.1A priority Critical patent/CN109816940B/en
Publication of CN109816940A publication Critical patent/CN109816940A/en
Application granted granted Critical
Publication of CN109816940B publication Critical patent/CN109816940B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Testing And Monitoring For Control Systems (AREA)

Abstract

The fault alarm method and device of a kind of sewage treatment plant are provided, which includes: the system topology figure for constructing sewage treatment plant, and the system topology figure describes the association between the component part that each system includes in sewage treatment plant;Obtain current multiple warning messages;System topology figure based on building determines the possibility causality figure between the multiple warning message;According to determining possibility causality figure, the alert process sequence for being directed to the multiple warning message is generated.Using the fault alarm method and device of the sewage treatment plant of exemplary embodiment of the present, the association between multiple warning messages can be embodied, and the processing sequence of multiple warning messages is provided, helps to improve the treatment effeciency to sewage treatment plant's alarm.

Description

The fault alarm method and device of sewage treatment plant
Technical field
All things considered of the present invention is related to technical field of sewage, more particularly, is related to a kind of event of sewage treatment plant Hinder alarm method and device.
Background technique
Sewage treatment is to make sewage purification using the method for physics, chemistry and biology, can recycle, be multiplexed, to reach To protection environment and the purpose for making full use of water resource.The basic principle of sewage treatment is by filtering, absorption, precipitating, oxidation With reduction etc. processes, realize sewage in a variety of inorganic pollutions and organic pollutant removal and conversion.In order to guarantee at sewage Reason process can be gone on smoothly, and the process flow of multistage close association will be not only arranged in sewage treatment plant, there is provision of a variety of Auxiliary system and auxiliary facility.
Large and medium-sized sewage treatment plant's land occupation is in large scale, and on-site further includes other than complicated process flow system Power supply-distribution system, blast aeration system, automatic medicament feeding system, monitoring system, heating ventilation air-conditioning system and fire protection alarm system etc..This A little systems can be further divided into the smaller subsystem of range again, as process flow system can be analyzed to sewage disposal system with Sludge treating system.It is more inside the multiple systems and same system of sewage treatment plant due to the complexity of sewage disposal process The characteristics of close-coupled is all shown between a subsystem.
With being gradually increased for sewage treatment plant's automatization level, each process section device therefor, instrument and meter type and Quantity is more and more.The monitoring system of most of sewage treatment plants has passed through integration networks mechanics of communication, software technology and control Technology processed realizes the decentralised control and centralized management to these equipment, instrument and meter.The architecture of monitoring system is generally divided into Two layers, lower layer is read the data of each equipment and instrument and meter by PLC (programmable logic controller (PLC)), and is issued real-time control and referred to It enables, realizes the local control of equipment;Upper layer, as server, engineer station and operator station, is led to using industrial personal computer or business PC The communication with PLC is crossed, realizes data acquisition and status display, history data store and trend analysis, the long-range start and stop of equipment and ginseng Number setting, alarm and alert process generate report and with the communication of other systems etc..
In general, PLC is placed near equipment or power distribution station, and server, engineer station and operator station are placed in central control Room (abbreviation Central Control Room).In Central Control Room, operation maintenance personnel should check equipment, the operation data of instrument and meter in time, grasp comprehensively The condition of production, pays close attention to various warning messages again, all harm for production of eliminating the effects of the act rapidly.Generally, warning message It is divided into two kinds, one is the alarm that processing parameter is more than threshold value, another kind is that device parameter is more than itself threshold value or failure The alarm of damage.The characteristics of former is alarmed is that equipment self-condition is good, but exceeded situation occur in certain productions, need to life Production adjusts.The characteristics of latter is alarmed is equipment due to longtime running, aging or operation maintenance personnel misoperation etc., is made There is performance decline or damage in equipment, leads to its partial failure or is unable to run, but relevant production run is normal.At this moment, it needs Want operation maintenance personnel on-call maintenance or more exchange device.Sometimes, two kinds of alarms may occur simultaneously, and operation maintenance personnel needs basis Actual conditions take neatly counter-measure, so that loss is preferably minimized level.
Although the monitoring screen in present sewage treatment plant Central Control Room has been able to show various alarms, and there are also special Device guarantees that warning message can be received by the operation maintenance personnel outside Central Control Room and be handled in time, but existing sewage treatment plant reports Police's formula does not consider the incidence relation between multiple warning messages, does not consider the processing priority of multiple warning messages yet, causes Alert process is not prompt enough.
Summary of the invention
The fault alarm method and device for being designed to provide a kind of sewage treatment plant of exemplary embodiment of the present invention, To overcome at least one above-mentioned defect.
One side according to an exemplary embodiment of the present invention provides a kind of fault alarm method of sewage treatment plant, comprising: The system topology figure of sewage treatment plant is constructed, the system topology figure describes each system in sewage treatment plant and includes Component part between association;Obtain current multiple warning messages;System topology figure based on building, determine described in Possibility causality figure between multiple warning messages;According to determining possibility causality figure, generates and be directed to the multiple report The alert process sequence of alert information.
Optionally, the system topology figure may include the property set and Bian Ji of node collection, node, wherein node collection In each node component part that can include for each system in sewage treatment plant, by side will be present associated two nodes into Row connection, indicates there is connection between two component parts connected by side, and each attribute in the property set of node can be Component part corresponding with node prestores warning message.
Optionally, the system topology figure can be stored in the form of adjacency matrix, and the property set of node can be with chain The form of table stores.
Optionally, the system topology figure based on building determines that the possibility cause and effect between the multiple warning message is closed The step of system's figure can include: searched from the property set of node and the multiple warning message is matched respectively multiple prestores alarm Information;Determine with matched the multiple prestore the corresponding multiple component parts of warning message;According to the multiple composition portion Divide the incidence relation present in the system topology figure, generates the possible causality figure.
Optionally, it according to the multiple component part incidence relation present in the system topology figure, generates The step of possibility causality figure can include: traverse all warning messages, obtain multiple warning message combinations, any alarm It include two warning messages in information combination;For any warning message combine, determine in the system topology figure with With the presence or absence of the side being connected between corresponding two component parts of two warning messages in any warning message combination Perhaps access is if there is the side or access being connected, then according to two component parts in the system topology figure Existing incidence relation determines the cause and effect points relationship between two warning messages;According to all warning messages and it is corresponding because Fruit points relationship generates the possible causality figure.
Optionally, the possible causality figure may include node collection and side collection, wherein each node that node is concentrated can For the warning message of acquisition, associated two nodes will be present by side and be attached, indicates two connected by side alarms Exist between information may causality, and by while direction indicate while terminal node warning message dependent on side The warning message of start node generates.
Optionally, according to determining possibility causality figure, the alert process sequence for being directed to the multiple warning message is generated The step of column can include: the node that search in-degree is zero from possible causality figure;If the section that the in-degree searched is zero The quantity of point is not more than 1, then by be zero with the in-degree searched node corresponding warning message deposit alert process sequence in; It is determining according to history partial ordering relation to be with the in-degree searched if the quantity for the node that the in-degree searched is zero is greater than 1 The processing priority of the corresponding warning message of zero node, and will be zero with the in-degree searched according to determining processing priority Node corresponding warning message deposit alert process sequence in;From may delete in causality figure the node that in-degree is zero with And with the associated side of node that in-degree is zero, obtain beta pruning after possibility causality figure, and return execution from may cause and effect close The step of being the node that search in-degree is zero in figure.
Optionally, the history partial ordering relation may include the history alarm treatment sequence between different warning messages, wherein According to the determination of history partial ordering relation be zero with the in-degree searched the corresponding warning message of node processing priority the step of If can include: there is the report for the corresponding each warning message of node for being zero with the in-degree searched in history alarm treatment sequence Alert disposition sequence phase situation first each other, then sequentially exist according to the alarm treatment of each warning message in history alert process sequence The frequency that first situation occurs, to determine the processing priority of the corresponding warning message of the node for being zero with the in-degree searched.
Optionally, the place of the corresponding warning message of the node for being zero with the in-degree searched according to the determination of history partial ordering relation The step of managing priority can further include: if there is no the nodes pair for being zero with the in-degree searched in history alarm treatment sequence The alarm treatment sequence for the warning message answered, then according to the search time for the node that search in-degree is zero from possible causality figure The processing priority of the corresponding warning message of the node that sequence determination is zero with the in-degree searched.
Optionally, the fault alarm method can further include: shows the alert process sequence of generation, and shows the multiple The warning reason of warning message and alarm treatment method for each warning message.
In another general aspect, a kind of accident warning device of sewage treatment plant is provided, comprising: topological diagram construction unit, The system topology figure of sewage treatment plant is constructed, the system topology figure describes each system in sewage treatment plant and includes Component part between association;Warning message acquiring unit obtains current multiple warning messages;Causality figure is established single Member, the system topology figure based on building determine the possibility causality figure between the multiple warning message;Alert process Sequence generating unit generates the alert process sequence for being directed to the multiple warning message according to determining possibility causality figure.
Optionally, the system topology figure may include the property set and Bian Ji of node collection, node, wherein node collection In each node component part that can include for each system in sewage treatment plant, by side will be present associated two nodes into Row connection, indicates there is connection between two component parts connected by side, and each attribute in the property set of node can be Component part corresponding with node prestores warning message.
Optionally, the system topology figure can be stored in the form of adjacency matrix, and the property set of node can be with chain The form of table stores.
Optionally, causality figure establishes unit can include: information matches subelement, from the property set of node search with The multiple warning message is matched respectively multiple to prestore warning message;Component part determines subelement, determines matched with institute It is the multiple to prestore the corresponding multiple component parts of warning message;Relational graph generates subelement, according to the multiple component part The incidence relation present in the system topology figure generates the possible causality figure.
Optionally, relational graph, which generates subelement, can traverse all warning messages, obtain multiple warning message combinations, Ren Yibao Include two warning messages in alert information combination, combines, determined in the system topology figure for any warning message With the presence or absence of being connected between corresponding two component parts of two warning messages in being combined with any warning message Perhaps access is if there is the side or access being connected on side, then according to two component parts in the system topology figure Present in incidence relation determine the cause and effect points relationship between two warning messages, according to all warning messages and corresponding Cause and effect points relationship generates the possible causality figure.
Optionally, the possible causality figure may include node collection and side collection, wherein each node that node is concentrated can For the warning message of acquisition, associated two nodes will be present by side and be attached, indicates two connected by side alarms Exist between information may causality, and by while direction indicate while terminal node warning message dependent on side The warning message of start node generates.
Optionally, alert process sequence generating unit can include: search subelement, from may search in causality figure into The node that degree is zero;Storing sub-units, if the quantity for the node that the in-degree searched is zero is not more than 1, storing sub-units By be zero with the in-degree searched node corresponding warning message deposit alert process sequence in, if the in-degree searched is The quantity of zero node is greater than 1, then the node that it is zero with the in-degree searched that storing sub-units are determined according to history partial ordering relation The processing priority of corresponding warning message, and according to determining processing priority by be zero with the in-degree searched node pair In the warning message deposit alert process sequence answered;Beta pruning subelement deletes the section that in-degree is zero from possible causality figure Point and the associated side of node for being zero with in-degree, the possibility causality figure after obtaining beta pruning, search subelement continue from can The node that in-degree is zero can be searched in causality figure.
Optionally, the history partial ordering relation may include the history alarm treatment sequence between different warning messages, wherein If there is the alarm treatment for the corresponding each warning message of node for being zero with the in-degree searched in history alarm treatment sequence Sequence phase situation first each other, then storing sub-units can be suitable according to the alarm treatment of each warning message in history alert process sequence The frequency that the first situation of sequence occurs, to determine the processing priority of the corresponding warning message of the node for being zero with the in-degree searched.
Optionally, if there is no the corresponding alarms of node for being zero with the in-degree searched in history alarm treatment sequence The alarm treatment sequence of information, then storing sub-units can searching according to the node that search in-degree is zero from possible causality figure The processing priority of the corresponding warning message of the node that Suo Cixu determination is zero with the in-degree searched.
Optionally, the accident warning device can further include: display unit shows the alert process sequence of generation, and shows Show the warning reason of the multiple warning message and the alarm treatment method for each warning message.
In another general aspect, a kind of computer readable storage medium for being stored with computer program is provided, feature exists In when the computer program realizes the fault alarm method of above-mentioned sewage treatment plant when being executed by processor.
In another general aspect, a kind of computing device is provided, the computing device includes: processor;Memory is stored with Computer program realizes the fault alarm method of above-mentioned sewage treatment plant when the computer program is executed by processor.
Using the fault alarm method and device of the sewage treatment plant of exemplary embodiment of the present, multiple reports can be embodied Association between alert information, and the processing sequence of multiple warning messages is provided, help to improve the place to sewage treatment plant's alarm Manage efficiency.
Detailed description of the invention
Pass through the detailed description carried out below with reference to the attached drawing for being exemplarily illustrated embodiment, exemplary embodiment of the present Above and other objects, features and advantages will become apparent, in which:
Fig. 1 shows the flow chart of the fault alarm method of sewage treatment plant according to an exemplary embodiment of the present invention;
Fig. 2 shows the possibility causes and effects between the multiple warning messages of determination in Fig. 1 according to an exemplary embodiment of the present invention The flow chart of the step of relational graph;
Fig. 3 show in Fig. 2 according to an exemplary embodiment of the present invention according to multiple component parts in system topology Incidence relation present in figure generates the flow chart of the step of possible causality figure;
Fig. 4 shows the alert process that the generation in Fig. 1 according to an exemplary embodiment of the present invention is directed to multiple warning messages The flow chart of the step of sequence;
Fig. 5 shows sewage disposal system, sludge treating system and blast aeration system according to an exemplary embodiment of the present invention The schematic diagram of system;
Fig. 6 shows the corresponding system topology figure of three systems shown in fig. 5 according to an exemplary embodiment of the present invention;
Fig. 7 shows the exemplary diagram of possible causality figure according to an exemplary embodiment of the present invention;
Fig. 8 shows the block diagram of the accident warning device of sewage treatment plant according to an exemplary embodiment of the present invention;
Fig. 9 shows the block diagram that causality figure according to an exemplary embodiment of the present invention establishes unit;
Figure 10 shows the block diagram of alert process sequence generating unit according to an exemplary embodiment of the present invention.
Specific embodiment
Now, different example embodiments is more fully described with reference to the accompanying drawings, wherein some exemplary embodiments are attached It is shown in figure.
Fig. 1 shows the flow chart of the fault alarm method of sewage treatment plant according to an exemplary embodiment of the present invention.
Referring to Fig.1, in step slo, the system topology figure of sewage treatment plant is constructed.Here, the system topological knot Composition describes the association between the component part that each system includes in sewage treatment plant.
As an example, the component part that each system includes in sewage treatment plant may include but be not limited to it is multiple for realizing control Unit is managed everywhere in system and/or the equipment and sewage treatment process of monitoring function.
In a preferred embodiment, system topology figure may include the property set and Bian Ji of node collection, node.Namely It says, it is the figure of system topology figure that constructed system topology figure, which is the system topology of extension, in step S10 Shape indicates and the combination of the property set of node.
For example, the component part that each node that node is concentrated can include for each system in sewage treatment plant, it will by side There are associated two nodes to be attached, and indicates there is connection, the category of node between two component parts connected by side Property each attribute for concentrating can prestore warning message for component part corresponding with node, that is, may by each component part Attribute of the warning message of generation as node.
Based on system topology figure constructed by aforesaid way, each component part in sewage treatment plant can be indicated simultaneously Between topological structure relationship and component part prestore warning message.
For example, system topology figure ESG, ESG=(V, E) are a digraph, wherein V is node collection, V= {v1,...,vm, indicate that the m component part that each system includes in sewage treatment plant, E are side collection, E={ e1,...,eq, packet Containing q side, the oriented relationship between two component parts, { v are indicateda_1,...,va_pIndicate a-th of node vaProperty set, Altogether include p attribute, prestores warning message for describe component part.
As an example, system topology figure can be stored in the form of adjacency matrix, node on computer disposal Property set can be stored in the form of chained list.However, the present invention is not limited thereto, can also be using other modes come storage system topology The property set of structure chart and node.
In step S20, current multiple warning messages are obtained.
Here, multiple warning messages of acquisition can be what each component part in sewage treatment plant generated at current time Warning message.As an example, the type of multiple warning messages may include equipment alarm information (for example, the relevant parameter of equipment is super The warning message crossing itself threshold value or equipment fault damage and generating) and/or Process Alarm information (for example, sewage treatment The warning message that technological parameter is generated more than threshold value).
In step s 30, the system topology figure based on building determines that the possibility cause and effect between multiple warning messages is closed System's figure.
Here, identified possible causality figure is alternatively referred to as causality figure, to indicate multiple warning messages it Between causality that may be present.Here, it can be determined according to sewage treatment process sequence, it can between multiple warning messages Causality existing for energy.
In exemplary embodiments of the present invention, the absolute causality between the multiple warning messages of searching has been avoided, and has changed To find the possibility causality between multiple warning messages, alert process sequence is determined based on this, alarm can be reduced and close The difficulty and complexity of connection problem and alert process issue of priority, for seeking alert process sequence provides possibility automatically.
The step of determining the possibility causality figure between multiple warning messages is introduced referring to Fig. 2.It should be understood that figure Determined shown in 2 may causality figure mode it is merely illustrative, other be used to determine the possibility between multiple warning messages because The method of fruit relational graph is also feasible.
Fig. 2 shows the possibility causes and effects between the multiple warning messages of determination in Fig. 1 according to an exemplary embodiment of the present invention The flow chart of the step of relational graph.
Referring to Fig. 2, in step S301, searched from the property set of node matched multiple with multiple warning messages difference Prestore warning message.
For example, being directed to any warning message, can come to search and any report from the property set of node in the following manner What alert information matched prestores warning message: the component part alarmed is determined based on any warning message, from it is identified It is searched in the property set of the corresponding node of the component part alarmed, prestores warning message with what any warning message matched.
In a preferred embodiment, alarm is prestored to guarantee to find match multiple from the property set of node Information need to detect the content integrity of multiple warning messages of acquisition after getting multiple warning messages.Example Such as, by taking any warning message of acquisition as an example, judge obtain any warning message in whether comprising component part title and Alarm content, if in any warning message obtained including the title and alarm content of component part, it is determined that any report The content of alert information is complete, if do not included in the title and/or alarm of component part in any warning message obtained Hold, it is determined that the content of any warning message is incomplete, at this point, need to be by inputting come content (such as group of completion missing At title of part and/or alarm content), to execute subsequent step based on complete warning message.
In step s 302, determine with matched multiple prestore the corresponding multiple component parts of warning message.
In step S303, according to multiple component parts incidence relation present in system topology figure, generation can It can causality figure.
The incidence relation next life present in system topology figure according to multiple component parts is introduced referring to Fig. 3 The step of at possible causality figure.It should be understood that the mode of the possible causality figure of generation shown in Fig. 3 is merely illustrative, other Method for generating possible causality figure is also feasible.
Fig. 3 show in Fig. 2 according to an exemplary embodiment of the present invention according to multiple component parts in system topology Incidence relation present in figure generates the flow chart of the step of possible causality figure.
All warning messages are traversed in step s310 referring to Fig. 3, obtain multiple warning message combinations.Here, any It include two warning messages in warning message combination.
In one embodiment, n warning message A of dual traversal can be passed through1,A2,…,AnMode, obtain alarm combination Ai With Aj(1≤i, j≤n and i ≠ j).
In step S311, two alarm signals in combining in system topology figure with k-th of warning message are determined It ceases between corresponding two component parts with the presence or absence of the side or access being connected.
Here, there is the side being connected between two component parts can refer to two component parts in system topology figure Between be directly connected to by a directed edge.There are accesses can refer to two compositions in system topology figure between two component parts It is connected between part by two or two or more sides.
For example, by taking above-mentioned cited embodiment as an example A alarm can be combinediWith AjCorresponding two component parts mapping For the node collection { V on ESGb,Vc, it is searched on ESG from V using DFS (depth-first search) algorithmbTo VcSide or access.
If phase is not present between corresponding two component parts of two warning messages in combining with k-th of warning message The side of connection or access, then follow the steps S312: so that k=k+1, and return to step S311.
It is connected if existed between corresponding two component parts of two warning messages in being combined with k-th of warning message The side connect or access, then follow the steps S313: being associated with pass present in system topology figure according to two component parts It is the cause and effect points relationship determined between two warning messages.
In step S314, judge whether k is equal to M.
As an example, the initial value of k can be 1, at this point, 1≤k≤M, M are the number of warning message combination, M is greater than zero Natural number.However, the present invention is not limited thereto, the initial value for being also possible to k is M, judges whether k is equal to 1 in step S314, herein In the case of, k=k-1 should be made in step S312 and S315 to realize circulation.
If k is not equal to M, S315 is thened follow the steps: so that k=k+1, and return to step S311.
If k is equal to M, S316 is thened follow the steps: according to all warning messages and corresponding cause and effect points relationship, generating The possibility causality figure.
By taking above-mentioned cited embodiment as an example, if there is from VbTo VcThe side being connected or access, then store report Warning message A in alert combinationiAnd AjAnd cause and effect points relationship between the two.It is above-mentioned having been executed to all alarms combination After circular treatment, using the warning message stored as node, the cause and effect points relationship between warning message is side, more to establish Possibility causality figure PCRG between a warning message.
In a preferred embodiment, possible causality figure may include node collection and side collection.
For example, each node that node is concentrated can be the warning message obtained, associated two nodes will be present by side It is attached, indicates there is possible causality between two warning messages connected by side, and the Compass for passing through side Show while terminal node warning message dependent on while the warning message of start node generate.
Fig. 1 is returned, in step s 40, according to determining possibility causality figure, generates the report for being directed to multiple warning messages Alert processing sequence.
It in a preferred embodiment, can be by carrying out beta pruning processing to possible causality figure, to obtain alert process sequence.
It is introduced referring to Fig. 4 according to determining possibility causality figure and generates the alarm for multiple warning messages The step of processing sequence.It should be understood that the mode shown in Fig. 4 for generating alert process sequence is merely illustrative, other are used for basis can The method that energy causality figure generates alert process sequence is also feasible.
Fig. 4 shows the alert process that the generation in Fig. 1 according to an exemplary embodiment of the present invention is directed to multiple warning messages The flow chart of the step of sequence.
Referring to Fig. 4, in step S401, judge whether possible causality figure is empty graph.
If possible causality figure is empty graph, then does not generate the alert process sequence for multiple warning messages.
If possible causality figure is not empty graph, thens follow the steps S402: search for in-degree from possible causality figure The node for being zero.
Here, the node that in-degree is zero can refer to be directed toward oneself there is no cause and effect points relationship in possible causality figure The node on side.
In step S403, judge whether the quantity for the node that the in-degree searched is zero is greater than 1.
If the quantity for the node that the in-degree searched is zero is greater than 1, S404 is thened follow the steps: according to history partial ordering relation The processing priority of the corresponding warning message of the node that determination is zero with the in-degree searched, and according to determining processing priority By be zero with the in-degree searched node corresponding warning message deposit alert process sequence in.
As an example, history partial ordering relation may include the history alarm treatment sequence between different warning messages, to be based on History alarm treatment between different warning messages sequentially determines the processing priority of warning message.In alert process sequence Multiple warning messages are ranked up according to the processing priority of warning message.
For example, if the corresponding warning message of a node in the node that each in-degree is zero is in history alarm treatment sequence In disposition sequence prior to other nodes for searching, it is determined that the processing priority of the corresponding warning message of a node Also formerly.
In addition to the above, corresponding if there is the node for being zero with the in-degree searched in history alarm treatment sequence Each warning message alarm treatment sequence mutually first each other situation, then according to each warning message in history alert process sequence The alarm treatment sequence frequency that formerly situation occurs, to determine the corresponding warning message of the node for being zero with the in-degree searched Processing priority.
In addition, according to the processing of the corresponding warning message of node that the determination of history partial ordering relation is zero with the in-degree searched The step of priority, can further include: if there is no the node for being zero with the in-degree searched is corresponding in history alarm treatment sequence Warning message alarm treatment sequence, then according to from may search in-degree is zero in causality figure node search-order The processing priority of the corresponding warning message of the node that determination is zero with the in-degree searched.For example, the section formerly scanned for The processing priority of the corresponding warning message of point is also first.
Here, history alarm treatment sequence between different warning messages can expert by sewage treatment field or scene Alarm treatment sequence between multiple warning messages that operation maintenance personnel rule of thumb provides, for example, two air blowers are shut down simultaneously The processing priority of alarm is higher than influent COD upper limit alarm.As an example, putting into operation a period of time to system, one is had The alert process sequence that series is generated, at this point, warning message A1Prior to A2Processed and warning message A2Prior to A1It is processed Situation may occur simultaneously, in the case, can be according to warning message A1Prior to A2Processed and warning message A2Prior to A1Quilt The frequency occurred in history alarm treatment sequence is handled, determines the A in current alerts processing sequence1And A2First post-processing time Sequence.If warning message A1Prior to A2Processed number is greater than warning message A2Prior to A1Processed number, then report currently A in alert processing sequence1Processing priority be higher than A2Processing priority.
That is, sequentially or the search-order for the node that in-degree be zero can be searched for determine using history alarm treatment The processing priority of multiple warning messages.
If the quantity for the node that the in-degree searched is zero is not more than (that is, being less than or equal to) 1, then follow the steps S405: by be zero with the in-degree searched node corresponding warning message deposit alert process sequence in.
Here, in cause and effect points relationship while start node warning message processing priority be higher than while terminal node The processing priority of the warning message of point.In alert process sequence multiple warning messages according to warning message processing priority It is ranked up, the processing priority for the warning message being first stored in alert process sequence is stored in alert process sequence after being higher than The processing priority of warning message.
In step S406, the node that in-degree is zero and the node for being zero with in-degree are deleted from possible causality figure Associated side, the possibility causality figure after obtaining beta pruning, and return to step S401.
In a preferred embodiment, the fault alarm method of sewage treatment plant according to an exemplary embodiment of the present invention can be also It include: the alert process sequence that display generates.
For example, multiple warning messages can be shown according to processing priority carry out sequence in alert process sequence, with for Operation maintenance personnel processing warning message offer assists help, this had both facilitated new operation maintenance personnel and has adapted to new working environment as early as possible, mentioned High its ability for handling emergency problem, it helps reduce post threshold, allow other staff also can interim part-time operation maintenance personnel Post helps sewage treatment plant to reduce cost of human resources.
In addition, the fault alarm method of sewage treatment plant according to an exemplary embodiment of the present invention can further include: display is more The warning reason of a warning message and alarm treatment method for each warning message.
For example, can be stored in advance in the database multiple warning messages warning reason and corresponding alarm treatment method, After getting multiple warning messages, warning reason corresponding with multiple warning messages and alarm treatment are searched for from database Method, to be shown.
That is, shown report of the fault alarm method of exemplary embodiment of the present in most of monitoring systems On the basis of alert record (such as alarm date, time of fire alarming, alert locations, monitored variable and alarm trigger condition), increase to report The display of alert reason and alarm treatment method, enable operation maintenance personnel quickly know alert consitions triggering possibility warning reason and Countermeasure.
The example of a sewage treatment plant will be passed through below, it is next using the fault alarm method of above-mentioned sewage treatment plant to introduce Generate the process of alert process sequence.
Sewage treatment is to make sewage purification using the method for physics, chemistry and biology, can recycle, be multiplexed, to reach To protection environment and the purpose for making full use of water resource.The basic principle is that passing through filtering, absorption, precipitating, oxidation and reduction etc. Process realizes the removal and conversion of a variety of inorganic pollutions and organic pollutant in sewage.In order to guarantee sewage disposal process energy It enough goes on smoothly, the process flow of multistage close association will be not only arranged in sewage treatment plant, there is provision of a variety of auxiliary systems With auxiliary facility.Large and medium-sized sewage treatment plant's land occupation is in large scale, and on-site also wraps other than complicated process flow system Include power supply-distribution system, blast aeration system, automatic medicament feeding system, monitoring system, heating ventilation air-conditioning system and fire protection alarm system etc.. These systems can be further divided into the smaller subsystem of range again, as process flow system can be analyzed to sewage disposal system And sludge treating system.Due to the complexity of sewage disposal process, inside the multiple systems and same system of sewage treatment plant The characteristics of close-coupled is all shown between multiple subsystems.
Fig. 5 shows sewage disposal system, sludge treating system and blast aeration system according to an exemplary embodiment of the present invention The schematic diagram of system.It should be understood that Fig. 5 is with sewage disposal system, sludge treating system and the blast aeration system in sewage treatment plant It is introduced for the equipment component that system includes, the other equipment in sewage treatment plant can also be shown using the present invention Fault alarm method described in example property embodiment is handled, and the present invention is to this without enumerating.
Fig. 5 gives sewage disposal system, sludge treating system and blast aeration system and its pass of certain sewage treatment plant System.As shown in figure 5, the sewage into sewage treatment plant first flows through coarse rack, the impurity of larger particles in the water that shuts off.Elevator pump The water pump in room, which is taken out, rises sewage to certain altitude, guarantees that sewage can flow through subsequent each processing unit by gravity.Next, Sewage further removes the impurity of smaller particle by fine fack.Sewage turns under the drive of the motor in rotation setting pot It is dynamic, to realize girt-water separation.The effect of hydrolysis acidification pool is to retain the non-dissolved organic matter in sewage and be gradually changed into Dissolved organic matter, it is difficult to which biodegradable macromolecular substances are converted into the small-molecule substance for being easy to degrade, to improve sewage Biodegradability and degradation speed.Integrated oxidation ditch uses inversion A2O technique (anoxic-anaerobic-aerobic), activated sludge benefit Biochemical reaction is carried out with the pollutant in the air and sewage entered by exposure, to realize denitrogenation dephosphorizing.The air entered by exposure is by air blast Air blower in computer room generates, and is delivered in oxidation ditch via pipeline and valve.Air blower in air blast computer room receives power distribution station drop The control signal of 380V industrial electro and PLC (programmable logic controller (PLC)) after pressure realizes energy control for need.In integrated oxidation ditch Activated sludge, a part persistent loop, another part then flow to secondary settling tank together with sewage.The effect of secondary settling tank is to make to mix Liquid clarification is concentrated to realize that sludge separates, and the sludge being separated temporarily is stored in sludge pump sump.The water outlet of secondary settling tank enters Efficient sedimentation tank makes the further flocculation sedimentation of the particulate matter in sewage by adding PAC and PAM medicament.Add after efficient sedimentation tank Filtering cloth filtering pool is in order to stop the suspended matter after flocculation sedimentation in sewage, to remove total solid suspended matter, total phosphorus and heavy metal. Disinfecting tank is gone out by chlorination removes the viral germ of influence environment in sewage, keeps processed sewage up to standard Discharge.The activated sludge of sludge pump sump is temporarily stored in addition to a part flows back into integrated oxidation ditch, it is most of with remaining dirty The form of mud is by injection sludge reservoir.However, needing since excess sludge water content at this time is still very high in sludge dewatering computer room Further thickening is converted into the lower mud cake of water content, is finally again transported mud cake and grid slag outside factory together by transport vehicle.
Above-mentioned sewage disposal system, sludge treating system are fitted with corresponding set with each unit of blast aeration system Standby and instrument and meter is to complete control and monitoring function.Here, control function can refer to the start and stop of control each unit equipment and turn Speed enables entire process flow safely and conveniently to carry out, for example, controlling the operating and stopping and air blast of blender in oxidation ditch The frequency control etc. of machine.And monitoring function can refer to using instrument and meter measurement, show and record entire process flow and equipment Critical data.These data are both foundation and O&M people of the operation maintenance personnel according to water inlet with water outlet status adjusting process process Member's optimization production process is to meet the energy-saving basis for waiting requirements.Present most of monitoring systems can be according to monitoring data Abnormal conditions warning message is sent from trend operation maintenance personnel by the monitoring screen in Central Control Room.Table 1 gives at the sewage Manage each component part and the possible warning message occurred related with equipment, the state of instrument and meter and show value of factory.
Table 1
Not only quantity is big for the warning message of the monitoring system of sewage treatment plant, but also complicated, generally has following features.
(1) alarm quantity is more.
Since sewage treatment plant is related to multiple systems, and each system includes multiple units and equipment and necessary survey again Measuring appratus and instrument, in addition same instrument and meter might have it is multiple.For example, certain sewage treatment plant described in Fig. 5, oxidation The impeller of ditch outer fissure has shared 8.Theoretically, the Various types of data of sewage treatment plant can be shown and note in monitoring system Record.Correspondingly, by the suitable trigger condition of selection and bound threshold value, monitoring system shows the stateful and number with record Alert if can be also arranged in value.Therefore, in the large and medium-sized sewage treatment plant of a high degree of automation, quantity meeting of alarming Very much.
(2) alarm content is wide.
Since an equipment might have multiple monitoring data, intelligent instrument and meter may once measure multiple parameters, Therefore, the content of alarm may be very extensive.For example, the content of frequency conversion air blower and alert correlation includes work electricity in table 1 Stream and frequency.In addition, pump used in the sewage treatment plant is both provided with local and long-range two kinds of control modes, and correspondingly, alarm Information will also divide into local alarm and remote alarms.In order to guarantee that pump is in normal operating conditions with the motor in other equipment And production process is gone on smoothly, can also be arranged the alarm of motor frequent start-stop, motor ultra-long time work alarm with it is multiple Associated working status alert of motor etc..
(3) there are different types of warning messages.
In general, the type of warning message can be divided into two kinds, and one is Process Alarm information, another kind is equipment alarm Information.The characteristics of former is alarmed is that equipment self-condition is good, but exceeded situation occur in certain productions, need to make production Adjustment.The characteristics of latter is alarmed is equipment due to longtime running, aging or operation maintenance personnel misoperation etc., goes out equipment Existing performance decline or damage, lead to its partial failure or are unable to run, but relevant production run is normal.
(4) there is association between multiple alarms.
When having multiple warning messages while occurring, there may be incidence relations between part or all of warning message.Example Such as, there is direct relation between the working condition alarm and oxidation ditch DO (dissolved oxygen) Threshold Alerts of frequency conversion air blower.Because may It stops working just because of air blower, causes oxidation ditch aeration insufficient, the content for having in turn resulted in dissolved oxygen in oxidation ditch is too low. When resuming operation for air blower, into oxidation ditch, aeration quantity increases, and not only blower frequency setting alarm can release, but also aoxidize Ditch DO Threshold Alerts can may also release therewith.
(5) alert process has anxious slow.
When multiple alert if are triggered, some more urgent alarms need priority processing, and others are alarmed, right Actual production influence is smaller, can will be placed in the processing priority that it is handled below.For example, if air blower stppage alarm with Oxidation ditch outer fissure impeller stppage alarm occurs simultaneously, then the necessary priority processing of air blower stppage alarm, otherwise may cause It is exceeded in turn result in water outlet for hypoxgia for aeration zone.And oxidation ditch outer fissure shares 8 impellers, some impeller failure, it is right The influence of production technology can be smaller.
Based on association existing between multiple warning messages, after some warning message is processed, it is associated therewith its He can then automatically terminate warning message, mathematically, this incidence relation between multiple warning messages can be abstracted as cause and effect Relational graph.Here, not only quantity is big for the alarm being related to due to sewage treatment plant, but also alarm content and type of alarm are also more, this It is very big to will lead to causality figure.If retrieving or modifying warning message based on the causality figure, calculating will lead to The time-consuming of machine processing increases, and also adds the difficulty to alarm information processing, reduces the efficiency of alert process.
For this purpose, in exemplary embodiments of the present invention, based on the possibility causality figure next life between multiple warning messages At alert process sequence, and alert process sequence is supplied to operation maintenance personnel and is referred to, to reduce the difficulty of alarm information processing Degree, improves the efficiency of alert process.
Fig. 6 shows the corresponding system topology figure of three systems shown in fig. 5 according to an exemplary embodiment of the present invention. Here, in order to keep figure clear, the warning message of part components and instrument and meter in table 1 is only listed in Fig. 6.
For example, possibility causality the figure PCRG, PCRG=(V, E) of multiple alarms are a digraphs, wherein V is section Point set, node vi(vi∈ V) indicate a warning message;E is side collection, side eij=< vi,vj> ∈ E is one by node viRefer to To node vjDirected edge, indicate warning message viWith warning message vjBetween possibility causality, that is, warning message vj's Generation possibly relies on warning message vi
Here, warning message vjGeneration possibly rely on warning message viMean warning message viReleasing may promote Make warning message vjIt releases, it is also possible to not interfere with alarm vj.This phenomenon is physical presence in sewage treatment plant, for example, There are possible causalities between stopping alarm and the alarm of oxidation ditch outer fissure DO lower limit simultaneously for two air blowers.There is oxidation ditch The alarm of outer fissure DO lower limit, this illustrates that the content of dissolved oxygen in outer fissure is too low.This may be since what is supplied to outer fissure only has two Air blower all stops working, it is also possible to due to influent load is excessive, returned sludge is very few or alarm DO instrument damage etc. other Reason.If the alarm of oxidation ditch outer fissure DO lower limit is as two air blowers while caused by shutting down, two air blowers restore After a period of work, it being increased to normal level to the dissolved oxygen of outer fissure, the alarm of oxidation ditch outer fissure DO lower limit can automatically terminate, and Without other operations.Caused by if the alarm of oxidation ditch outer fissure DO lower limit is the other reasons other than shutting down as air blower, Even if two air blowers are all resumed work, the alarm of oxidation ditch outer fissure DO lower limit is still had, and at this moment to be found other reasons, be made it Release alarm.
Assuming that system to be analyzed is as shown in figure 5, the warning message occurred is respectively A1,A2,…,An(by taking n >=2 as an example).? Before generating alert process sequence using above-mentioned fault alarm method, needed first to warning message A1,A2,…,AnContent carry out Integrity detection, to ensure that the content of warning message is complete.
Fig. 7 shows the exemplary diagram of possible causality figure according to an exemplary embodiment of the present invention.
In the present example it is assumed that the monitoring system of sewage treatment plant detects following 4 warning messages:
A, oxidation ditch outer fissure DO lower limit is alarmed;
B, influent COD upper limit alarm;
C, it is discharged COD upper limit alarm;
D, 1# and 2# air blower while stopping alarm.
Moreover, it is assumed that the history alarm treatment sequence in history partial ordering relation are as follows: influent COD upper limit alarm < 1# and 2# drum Blower while stopping alarm.
In the case, using above-mentioned 4 detected warning message, search graph 6 is to obtain between 4 warning messages Possible causality figure (as shown in Figure 7).
In Fig. 7, the warning message that in-degree is 0 is influent COD upper limit alarm and 1# and 2# air blower stopping alarm simultaneously. According to history partial ordering relation, obtain two warning messages processing order (that is, processing priority) be 1# and 2# air blower simultaneously Stopping alarm is prior to influent COD upper limit alarm.
Then, deletion of node 1 (1# and 2# air blower while stopping alarm) and (the influent COD upper limit report of node 2 in Fig. 7 It is alert) and two associated sides of node.At this point, only node oxidation ditch outer fissure DO lower limit in possibility causality figure after beta pruning Alarm and water outlet COD upper limit alarm, directed edge is alarmed by node oxidation ditch outer fissure DO lower limit is directed toward water outlet COD upper limit alarm, by This can determine that the processing order of two warning messages is the alarm of node oxidation ditch outer fissure DO lower limit prior to being discharged COD upper limit report It is alert.
Pass through above-mentioned treatment process, it may be determined that go out the processing priority of 4 warning messages by the alert process sequence after arriving first Be classified as: 1# and 2# air blower simultaneously alarm prior to influent COD upper limit alarm prior to oxidation ditch outer fissure DO lower limit by stopping alarm Prior to being discharged COD upper limit alarm.
Preferably, producible alert process sequence is supplied to the monitoring system of sewage treatment plant, with other alarm contents It is shown in monitoring system simultaneously.As an example, the processing order of each warning message of numeral mark can be used, or directly It is arranged according to the processing priority of each warning message by the processing order after arriving first.
However, the present invention is not limited thereto can also show alert process sequence, for example, using list by other means Form or patterned mode show alert process sequence.
For 4 warning messages shown in Fig. 7, the reason for causing one kind of alarm most possible is sewage treatment plant's distribution Between to air blower power main circuit fuse be blown, and intake at the same there is over-standard phenomenon.In a practical situation, once The main circuit fuse powered to air blower is blown, and all air blowers stop working immediately, and monitoring system detects air blower It shuts down, 1# and 2# air blower stopping alarm simultaneously can be issued.Air blower stopping will cause a series of chain reaction.If air blast Machine is not supplied to the aerobic zone of oxidation ditch, and the dissolved oxygen concentration of oxidation ditch outer fissure can decline.Once the dissolved oxygen of oxidation ditch outer fissure Concentration is lower than some value, can trigger the alarm of oxidation ditch outer fissure DO lower limit.And oxidation ditch aerobic zone for hypoxgia, and can to live Property sludge in microorganism be difficult to keep it is enough activity to decompose the pollutant in sewage, this will cause water outlet pollutant level It is exceeded, triggering water outlet COD upper limit alarm.If the COD intake at this time occurs exceeded again, and pollutant in sewage can be made into one Step increases, and more microorganisms will require more oxygen, and making this, insufficient dissolved oxygen concentration further declines, accelerates oxidation The alarm of ditch outer fissure DO lower limit.Equally, the pollutant increased can also be accelerated to be discharged COD upper limit alarm.
For above situation, sewage treatment plant's management and the correct disposal process of operation maintenance personnel should be: firstly, more renewing Main circuit fuse, restore the power supply to air blower;The exceeded reason of influent COD is searched again, prevents the dirt of big load in time Water discharge;Whether the DO instrument and water outlet COD instrument for finally checking oxidation ditch outer fissure work normally, if cisco unity malfunction, then tie up Repair processing.
Fault alarm method according to an embodiment of the present invention, in the case where obtaining multiple warning messages, to assist sewage Treatment plant's management and operation maintenance personnel emergency disposal alarm problem provide strong help.
Further, it should be understood that not repaired, oxidation ditch outer fissure if the DO instrument of oxidation ditch outer fissure is faulty always for a period of time Just stopping alarm does not have causality to the alarm of DO lower limit simultaneously with 1# and 2# air blower, at this point, finally reprocessing oxidation ditch outer fissure The alarm of DO lower limit may be more suitable.Therefore, in actual use, the management of sewage treatment plant and operation maintenance personnel need to be according to reality Situation carrys out flexible Application based on alert process sequence provided by fault alarm method of the invention, to realize to alarm failure Quick processing.
It should be understood that exposed for sewage disposal system, sludge treating system and air blast in above-mentioned cited embodiment What the sewage treatment plant of gas system composition was introduced, and only list several warning messages of limited quantity.But the present invention Shown in fault alarm method be not limited only to the part system and warning message of above-mentioned sewage treatment plant, for sewage treatment plant Other systems and warning message be also it is applicable, the present invention no longer illustrates this one by one.
Fig. 8 shows the block diagram of the accident warning device of sewage treatment plant according to an exemplary embodiment of the present invention.
As shown in figure 8, the accident warning device of sewage treatment plant according to an exemplary embodiment of the present invention includes: topological diagram Construction unit 10, warning message acquiring unit 20, causality figure establish unit 30 and alert process sequence generating unit 40.
Particularly, topological diagram construction unit 10 constructs the system topology figure of sewage treatment plant.Here, system topological Structure chart describes the association between the component part that each system includes in sewage treatment plant.
In a preferred embodiment, system topology figure may include the property set and Bian Ji of node collection, node.That is, should System topology figure is the combination of the graphical representation of system topology figure and the property set of node.
For example, the component part that each node that node is concentrated can include for each system in sewage treatment plant, it will by side There are associated two nodes to be attached, and indicates there is connection, the category of node between two component parts connected by side Property each attribute for concentrating can prestore warning message for corresponding with node component part.
As an example, system topology figure can be stored in the form of adjacency matrix, the property set of node can be with chained list Form store.
Warning message acquiring unit 20 obtains current multiple warning messages.
Here, multiple warning messages of acquisition can be what each component part in sewage treatment plant generated at current time Warning message.As an example, the type of multiple warning messages may include equipment alarm information and/or Process Alarm information.
Causality figure establishes system topology figure of the unit 30 based on building, determines between the multiple warning message Possibility causality figure.
Here, causality figure is established unit 30 and can be determined according to sewage treatment process sequence, multiple alarm signals Causality that may be present between breath.
Fig. 9 shows the block diagram that causality figure according to an exemplary embodiment of the present invention establishes unit 30.
As shown in figure 9, causality figure according to an exemplary embodiment of the present invention establishes unit 30 can include: information matches Subelement 301, component part determine that subelement 302 and relational graph generate subelement 303.
Particularly, information matches subelement 301 is searched from the property set of node and is matched respectively with multiple warning messages Multiple prestore warning message.
Component part determine subelement 302 determine with matched multiple prestore the corresponding multiple composition portions of warning message Point.
Relational graph generates subelement 303 and is associated with pass present in the system topology figure according to multiple component parts System, generating may causality figure.
For example, relational graph, which generates subelement 303, can traverse all warning messages, multiple warning message combinations are obtained.Here, It include two warning messages in any warning message combination.It combines, is determined in the system topological knot for any warning message With the presence or absence of being connected between corresponding two component parts of two warning messages in combining in composition with any warning message Perhaps access is if there is the side or access being connected on side, then according to two component parts in system topology figure Existing incidence relation determines the cause and effect points relationship between two warning messages, according to all warning messages and it is corresponding because Fruit points relationship, generating may causality figure.
In a preferred embodiment, possible causality figure may include node collection and side collection.
For example, each node that node is concentrated can be the warning message obtained, associated two nodes will be present by side It is attached, indicates there is possible causality between two warning messages connected by side, and the Compass for passing through side Show while terminal node warning message dependent on while the warning message of start node generate.
Fig. 8 is returned to, alert process sequence generating unit 40 generates according to determining possibility causality figure and is directed to multiple reports The alert process sequence of alert information.
In a preferred embodiment, alert process sequence generating unit 40 can be by carrying out beta pruning to possible causality figure Processing, to obtain alert process sequence.
Figure 10 shows the block diagram of alert process sequence generating unit 40 according to an exemplary embodiment of the present invention.
As shown in Figure 10, alert process sequence generating unit 40 according to an exemplary embodiment of the present invention can include: search Subelement 401, storing sub-units 402 and beta pruning subelement 403.
Particularly, search subelement 401 node that search in-degree is zero from possible causality figure.
For example, search subelement 401 can first judge may causality figure whether be empty graph, if possible causality figure It is not empty graph, then the node that search in-degree is zero from possible causality figure.If possible causality figure is empty graph, then searches Large rope unit 401 is not handled possible causality figure.
If the quantity for the node that the in-degree searched is zero is not more than 1, storing sub-units 402 will enter with what is searched In the corresponding warning message deposit alert process sequence of the node that degree is zero.
If the quantity for the node that the in-degree searched is zero is greater than 1, storing sub-units 402 are according to history partial ordering relation The processing priority of the corresponding warning message of the node that determination is zero with the in-degree searched, and according to determining processing priority By be zero with the in-degree searched node corresponding warning message deposit alert process sequence in.
As an example, history partial ordering relation may include the history alarm treatment sequence between different warning messages.
If the corresponding warning message of a node in the node that each in-degree is zero is in history alarm treatment sequence Alarm treatment sequence is prior to other nodes searched, then storing sub-units 402 determine the corresponding alarm signal of a node The processing priority of breath is also first.
In addition to the above, corresponding if there is the node for being zero with the in-degree searched in history alarm treatment sequence Each warning message alarm treatment sequence mutually first each other situation, then storing sub-units 402 are according to suitable in history alert process The alarm treatment sequence frequency that formerly situation occurs of each warning message, the node that the in-degree to determine and search is zero in sequence The processing priority of corresponding warning message.
If there is no the corresponding warning messages of node for being zero with the in-degree searched in history alarm treatment sequence Alarm treatment sequence, then storing sub-units 402 are secondary according to the search for the node that search in-degree is zero from possible causality figure The processing priority of the corresponding warning message of the node that sequence determination is zero with the in-degree searched.
Node beta pruning subelement 403 node that deletion in-degree is zero from possible causality figure and be zero with in-degree Associated side, the possibility causality figure after obtaining beta pruning, search subelement 401 continue from may search in causality figure into The node that degree is zero.
In a preferred embodiment, the accident warning device of sewage treatment plant according to an exemplary embodiment of the present invention can be also Including display unit (not shown), display unit can be used for showing the alert process sequence of generation.
In addition, display unit can also show the warning reason of multiple warning messages and at the alarm of each warning message Set method.
An exemplary embodiment of the present invention also provides a kind of computing device.The computing device includes processor and storage Device.Memory is for storing computer program.The computer program is executed by processor so that processor executes above-mentioned dirt The computer program of the fault alarm method of water treatment plant.
An exemplary embodiment of the present invention also provides a kind of computer-readable storage medium for being stored with computer program Matter.The computer-readable recording medium storage has the event for making processor execute above-mentioned sewage treatment plant when being executed by a processor Hinder the computer program of alarm method.The computer readable recording medium is can to store appointing for the data read by computer system Meaning data storage device.The example of computer readable recording medium includes: read-only memory, random access memory, read-only light Disk, tape, floppy disk, optical data storage devices and carrier wave (are such as passed through wired or wireless transmission path by the data of internet It is defeated).
Using the fault alarm method and device of the sewage treatment plant of exemplary embodiment of the present, for sewage treatment plant In coupling feature between each system, it is contemplated that the incidence relation between multiple warning messages, and provide multiple reports with this The processing sequence of alert information, helps to improve the treatment effeciency to sewage treatment plant's alarm.
In addition, can be generated using the fault alarm method and device of the sewage treatment plant of exemplary embodiment of the present One alert process sequence can manage for sewage treatment plant and operation maintenance personnel positions and find that rapidly emergency problem provides side It helps, them can be assisted to adopt right measures and solve the problems, such as alarm, very well satisfy sewage treatment plant's management and operation maintenance personnel Daily need.
In addition, using the fault alarm method and device of the sewage treatment plant of exemplary embodiment of the present, for sewage Treatment plant's quantity is big, content is wide, point type, is related and has suddenly slow warning message, is found and is reported using system topology figure Possibility causality between alert information, and then find possible optimal alert process sequence, obtained alert process sequence Not only there is certain guidance to sewage treatment plant's management and operation maintenance personnel, but also avoided the true causality between warning message, opened A kind of new approaches of alarm failure processing are opened up out.
In addition, using the fault alarm method and device of the sewage treatment plant of exemplary embodiment of the present, to meet dirt Water treatment plant's management and the actual use of operation maintenance personnel are starting point, and designed method and apparatus both can be used as an independence Computer program, can also be used as monitoring system even wisdom water utilities system a functional module, be present in wisdom water utilities Among system, to reinforce the informationization and intelligent level of sewage treatment plant.
Although being particularly shown and describing the present invention, those skilled in the art referring to its exemplary embodiment It should be understood that in the case where not departing from the spirit and scope of the present invention defined by claim form can be carried out to it With the various changes in details.

Claims (22)

1. a kind of fault alarm method of sewage treatment plant characterized by comprising
The system topology figure of sewage treatment plant is constructed, the system topology figure describes each system in sewage treatment plant Including component part between association;
Obtain current multiple warning messages;
System topology figure based on building determines the possibility causality figure between the multiple warning message;
According to determining possibility causality figure, the alert process sequence for being directed to the multiple warning message is generated.
2. fault alarm method as described in claim 1, which is characterized in that the system topology figure include node collection, The property set and Bian Ji of node,
Wherein, each node that node is concentrated is the component part that each system includes in sewage treatment plant, and pass will be present by side Two nodes of connection are attached, and indicate there is connection between two component parts connected by side, in the property set of node Each attribute be that corresponding with node component part prestores warning message.
3. fault alarm method as claimed in claim 2, which is characterized in that the system topology figure is with adjacency matrix Form stores, and the property set of node stores in the form of chained list.
4. fault alarm method as claimed in claim 2, which is characterized in that the system topology figure based on building determines The step of possibility causality figure between the multiple warning message includes:
It is searched from the property set of node and the multiple warning message is matched respectively multiple prestores warning message;
Determine with matched the multiple prestore the corresponding multiple component parts of warning message;
According to the multiple component part incidence relation present in the system topology figure, the possible cause and effect is generated Relational graph.
5. fault alarm method as claimed in claim 4, which is characterized in that according to the multiple component part in the system Incidence relation present in topology diagram, the step of generating the possible causality figure include:
All warning messages are traversed, multiple warning message combinations is obtained, includes two warning messages in any warning message combination;
It combines, is determined in being combined in the system topology figure with any warning message for any warning message With the presence or absence of the side or access being connected between corresponding two component parts of two warning messages, if there is what is be connected Side or access then determine two alarms according to two component parts incidence relation present in the system topology figure Cause and effect points relationship between information;
According to all warning messages and corresponding cause and effect points relationship, the possible causality figure is generated.
6. fault alarm method as claimed in claim 5, which is characterized in that it is described possibility causality figure include node collection and Side collection,
Wherein, each node that node is concentrated is the warning message obtained, and associated two nodes will be present by side and connected Connect, indicate to exist between two warning messages connect by side may causality, and by while when being directed toward expression The warning message of terminal node is generated dependent on the warning message of the start node on side.
7. fault alarm method as described in claim 1, which is characterized in that according to determining possibility causality figure, generate For the multiple warning message alert process sequence the step of include:
The node that search in-degree is zero from possible causality figure;
If the quantity for the node that the in-degree searched is zero be not more than 1, by be zero with the in-degree searched node it is corresponding Warning message deposit alert process sequence in;
If the quantity for the node that the in-degree searched is zero is greater than 1, determined to enter with what is searched according to history partial ordering relation The processing priority of the corresponding warning message of the node that degree is zero, and according to determining processing priority by with the in-degree that searches In the corresponding warning message deposit alert process sequence of the node for being zero;
The node that in-degree is zero and the associated side of node for being zero with in-degree are deleted from possible causality figure, obtain beta pruning Possibility causality figure afterwards, and return and execute the step of searching for the node that in-degree is zero from possible causality figure.
8. fault alarm method as claimed in claim 7, which is characterized in that the history partial ordering relation includes different alarm signals History alarm treatment sequence between breath,
Wherein, the processing of the corresponding warning message of the node for being zero with the in-degree searched according to the determination of history partial ordering relation is preferential Grade the step of include:
If there is the alarm for the corresponding each warning message of node for being zero with the in-degree searched in history alarm treatment sequence Disposition sequence phase situation first each other, then it is sequentially first according to the alarm treatment of each warning message in history alert process sequence The frequency that situation occurs, to determine the processing priority of the corresponding warning message of the node for being zero with the in-degree searched.
9. fault alarm method as claimed in claim 8, which is characterized in that determine and search according to history partial ordering relation The step of processing priority of the corresponding warning message of the node that in-degree is zero further include:
If there is no the alarms for the corresponding warning message of node for being zero with the in-degree searched in history alarm treatment sequence Disposition sequence then determines to enter with what is searched according to the search-order for the node that search in-degree is zero from possible causality figure The processing priority of the corresponding warning message of the node that degree is zero.
10. fault alarm method as described in claim 1, which is characterized in that the fault alarm method further include: display life At alert process sequence, and show the warning reason of the multiple warning message and the alarm treatment for each warning message Method.
11. a kind of accident warning device of sewage treatment plant characterized by comprising
Topological diagram construction unit, constructs the system topology figure of sewage treatment plant, and the system topology figure describes dirt The association between component part that each system includes in water treatment plant;
Warning message acquiring unit obtains current multiple warning messages;
Causality figure establishes unit, the system topology figure based on building, determine between the multiple warning message can It can causality figure;
Alert process sequence generating unit is generated according to determining possibility causality figure for the multiple warning message Alert process sequence.
12. accident warning device as claimed in claim 11, which is characterized in that the system topology figure includes node The property set and Bian Ji of collection, node,
Wherein, each node that node is concentrated is the component part that each system includes in sewage treatment plant, and pass will be present by side Two nodes of connection are attached, and indicate there is connection between two component parts connected by side, in the property set of node Each attribute be that corresponding with node component part prestores warning message.
13. accident warning device as claimed in claim 12, which is characterized in that the system topology figure is with adjacency matrix Form store, the property set of node stores in the form of chained list.
14. accident warning device as claimed in claim 12, which is characterized in that causality figure establishes unit and includes:
Information matches subelement, is searched and the multiple warning message is matched respectively multiple prestores report from the property set of node Alert information;
Component part determines subelement, determine with matched the multiple prestore the corresponding multiple component parts of warning message;
Relational graph generates subelement, is associated with pass present in the system topology figure according to the multiple component part System generates the possible causality figure.
15. accident warning device as claimed in claim 14, which is characterized in that relational graph generates subelement and traverses all alarms Information obtains multiple warning message combinations, includes two warning messages in any warning message combination, for any warning message Combination determines two warning messages corresponding two in combining in the system topology figure with any warning message With the presence or absence of the side being connected, perhaps access is if there is the side or access being connected between a component part, then according to two A component part incidence relation present in the system topology figure determines that the cause and effect between two warning messages is directed toward Relationship generates the possible causality figure according to all warning messages and corresponding cause and effect points relationship.
16. accident warning device as claimed in claim 15, which is characterized in that the possibility causality figure includes node collection With side collection,
Wherein, each node that node is concentrated is the warning message obtained, and associated two nodes will be present by side and connected Connect, indicate to exist between two warning messages connect by side may causality, and by while when being directed toward expression The warning message of terminal node is generated dependent on the warning message of the start node on side.
17. accident warning device as claimed in claim 11, which is characterized in that alert process sequence generating unit includes:
Subelement is searched for, the node that search in-degree is zero from possible causality figure;
Storing sub-units, if the quantity for the node that the in-degree searched is zero be not more than 1, storing sub-units will with search In-degree be zero node corresponding warning message deposit alert process sequence in, if the node that the in-degree searched is zero Quantity is greater than 1, then the corresponding alarm of node that storing sub-units are zero with the in-degree searched according to the determination of history partial ordering relation The processing priority of information, and according to determining processing priority by be zero with the in-degree searched the corresponding alarm signal of node In breath deposit alert process sequence;
Beta pruning subelement, from may delete in causality figure node that in-degree is zero and with in-degree be zero node it is associated Side, the possibility causality figure after obtaining beta pruning, it is zero that search subelement, which continues the search in-degree from possible causality figure, Node.
18. accident warning device as claimed in claim 17, which is characterized in that the history partial ordering relation includes different alarms History alarm treatment sequence between information,
Wherein, if there is the corresponding each warning message of node for being zero with the in-degree searched in history alarm treatment sequence Alarm treatment sequence mutually first each other situation, then storing sub-units according to each warning message in history alert process sequence report The alert disposition sequence frequency that formerly situation occurs, to determine the place of the corresponding warning message of the node for being zero with the in-degree searched Manage priority.
19. accident warning device as claimed in claim 18, which is characterized in that if be not present in history alarm treatment sequence The alarm treatment sequence of the corresponding warning message of the node for being zero with the in-degree searched, then storing sub-units are according to from may be because The corresponding alarm of node that the search-order determination for the node that in-degree is zero is zero with the in-degree searched is searched in fruit relational graph The processing priority of information.
20. accident warning device as claimed in claim 11, which is characterized in that the accident warning device further include: display Unit, shows the alert process sequence of generation, and shows the warning reason of the multiple warning message and be directed to each alarm signal The alarm treatment method of breath.
21. a kind of computer readable storage medium for being stored with computer program, which is characterized in that when the computer program exists The fault alarm method of the sewage treatment plant as described in any one of claims 1 to 10 is realized when being executed by processor.
22. a kind of computing device, which is characterized in that the computing device includes:
Processor;
Memory is stored with computer program, when the computer program is executed by processor, realize as claim 1 to The fault alarm method of sewage treatment plant described in any one of 10.
CN201910217416.1A 2019-03-21 2019-03-21 Fault alarm method and device for sewage treatment plant Active CN109816940B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910217416.1A CN109816940B (en) 2019-03-21 2019-03-21 Fault alarm method and device for sewage treatment plant

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910217416.1A CN109816940B (en) 2019-03-21 2019-03-21 Fault alarm method and device for sewage treatment plant

Publications (2)

Publication Number Publication Date
CN109816940A true CN109816940A (en) 2019-05-28
CN109816940B CN109816940B (en) 2023-05-09

Family

ID=66609905

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910217416.1A Active CN109816940B (en) 2019-03-21 2019-03-21 Fault alarm method and device for sewage treatment plant

Country Status (1)

Country Link
CN (1) CN109816940B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111028487A (en) * 2019-12-27 2020-04-17 杭州青泓科技有限公司 Water treatment monitoring method and system
CN112863134A (en) * 2020-12-31 2021-05-28 浙江清华长三角研究院 Intelligent diagnosis system and method for rural sewage treatment facility abnormal operation
CN115378796A (en) * 2022-08-23 2022-11-22 中国建设银行股份有限公司 Method, device, equipment and storage medium for determining maximum fault time
CN115903679A (en) * 2022-10-18 2023-04-04 中广核工程有限公司 Nuclear power plant alarm list display method, system and device

Citations (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5581242A (en) * 1991-08-22 1996-12-03 Hitachi, Ltd. Automatic alarm display processing system in plant
JP2000224669A (en) * 1999-02-02 2000-08-11 Toshiba Corp Plant monitoring device
US20090193436A1 (en) * 2008-01-30 2009-07-30 Inventec Corporation Alarm display system of cluster storage system and method thereof
CN101634851A (en) * 2009-08-25 2010-01-27 西安交通大学 Method based on cause-and-effect relation of variables for diagnosing failures in process industry
CN102638100A (en) * 2012-04-05 2012-08-15 华北电力大学 District power network equipment abnormal alarm signal association analysis and diagnosis method
CN103440730A (en) * 2013-07-22 2013-12-11 清华大学 Relevant alarm identification method based on data extraction
CN104238527A (en) * 2014-09-24 2014-12-24 天津创业环保集团股份有限公司 Precise control method of sewage treatment plant aeration total quantity
CN104298225A (en) * 2014-09-25 2015-01-21 中国石油化工股份有限公司 Modeling and graphical displaying method for causal relationship reasoning model of unusual working conditions of chemical process
CN104931857A (en) * 2015-06-25 2015-09-23 山东大学 Power distribution network fault locating method based on D-S evidence theory
CN105096041A (en) * 2015-07-24 2015-11-25 北京中电普华信息技术有限公司 Index change traceability and prediction method and apparatus
CN105893700A (en) * 2016-04-26 2016-08-24 陆新建 Chemical production on-line fault detection and diagnosis technique based on physical-large data hybrid model
CN106843111A (en) * 2017-03-10 2017-06-13 中国石油大学(北京) The accurate source tracing method of hydrocarbon production system alarm signal root primordium and device
CN106933208A (en) * 2015-10-09 2017-07-07 费希尔-罗斯蒙特系统公司 Distributed industrial performance monitoring and analysis
CN107403223A (en) * 2017-07-10 2017-11-28 广东工业大学 A kind of causal network Structure Deduction method based on leaf node prioritizing selection
CN108171142A (en) * 2017-12-26 2018-06-15 中南大学 A kind of causal method of key variables in determining complex industrial process
CN108494591A (en) * 2018-03-16 2018-09-04 北京京东金融科技控股有限公司 system alarm processing method and device

Patent Citations (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5581242A (en) * 1991-08-22 1996-12-03 Hitachi, Ltd. Automatic alarm display processing system in plant
JP2000224669A (en) * 1999-02-02 2000-08-11 Toshiba Corp Plant monitoring device
US20090193436A1 (en) * 2008-01-30 2009-07-30 Inventec Corporation Alarm display system of cluster storage system and method thereof
CN101634851A (en) * 2009-08-25 2010-01-27 西安交通大学 Method based on cause-and-effect relation of variables for diagnosing failures in process industry
CN102638100A (en) * 2012-04-05 2012-08-15 华北电力大学 District power network equipment abnormal alarm signal association analysis and diagnosis method
CN103440730A (en) * 2013-07-22 2013-12-11 清华大学 Relevant alarm identification method based on data extraction
CN104238527A (en) * 2014-09-24 2014-12-24 天津创业环保集团股份有限公司 Precise control method of sewage treatment plant aeration total quantity
CN104298225A (en) * 2014-09-25 2015-01-21 中国石油化工股份有限公司 Modeling and graphical displaying method for causal relationship reasoning model of unusual working conditions of chemical process
CN104931857A (en) * 2015-06-25 2015-09-23 山东大学 Power distribution network fault locating method based on D-S evidence theory
CN105096041A (en) * 2015-07-24 2015-11-25 北京中电普华信息技术有限公司 Index change traceability and prediction method and apparatus
CN106933208A (en) * 2015-10-09 2017-07-07 费希尔-罗斯蒙特系统公司 Distributed industrial performance monitoring and analysis
CN105893700A (en) * 2016-04-26 2016-08-24 陆新建 Chemical production on-line fault detection and diagnosis technique based on physical-large data hybrid model
CN106843111A (en) * 2017-03-10 2017-06-13 中国石油大学(北京) The accurate source tracing method of hydrocarbon production system alarm signal root primordium and device
CN107403223A (en) * 2017-07-10 2017-11-28 广东工业大学 A kind of causal network Structure Deduction method based on leaf node prioritizing selection
CN108171142A (en) * 2017-12-26 2018-06-15 中南大学 A kind of causal method of key variables in determining complex industrial process
CN108494591A (en) * 2018-03-16 2018-09-04 北京京东金融科技控股有限公司 system alarm processing method and device

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111028487A (en) * 2019-12-27 2020-04-17 杭州青泓科技有限公司 Water treatment monitoring method and system
CN111028487B (en) * 2019-12-27 2021-07-13 杭州青泓科技有限公司 Water treatment monitoring method and system
CN112863134A (en) * 2020-12-31 2021-05-28 浙江清华长三角研究院 Intelligent diagnosis system and method for rural sewage treatment facility abnormal operation
CN112863134B (en) * 2020-12-31 2022-11-18 浙江清华长三角研究院 Intelligent diagnosis system and method for rural sewage treatment facility abnormal operation
CN115378796A (en) * 2022-08-23 2022-11-22 中国建设银行股份有限公司 Method, device, equipment and storage medium for determining maximum fault time
CN115378796B (en) * 2022-08-23 2024-08-16 中国建设银行股份有限公司 Method, device, equipment and storage medium for determining maximum fault time
CN115903679A (en) * 2022-10-18 2023-04-04 中广核工程有限公司 Nuclear power plant alarm list display method, system and device

Also Published As

Publication number Publication date
CN109816940B (en) 2023-05-09

Similar Documents

Publication Publication Date Title
CN109816940A (en) The fault alarm method and device of sewage treatment plant
CN111145378A (en) Automatic video inspection system and method for road traffic incident
CN117420283B (en) Integrated multi-channel water quality monitoring method and system
CN111832909B (en) Emergency response system and method for illegal sewage discharge
CN114578008B (en) Decision support system and method for water quality risk management of sewage plant
CN111003883A (en) Intelligent integrated real-time information alarm method and system for sewage treatment equipment
CN111404482B (en) Photovoltaic power station monitoring method and system
Cicceri et al. A novel architecture for the smart management of wastewater treatment plants
CN116562580A (en) Waste water and waste gas treatment system and method for lithium carbonate production workshop
CN116216807A (en) Intelligent dosing system based on sewage treatment
CN114545850A (en) Internet of things intelligent management system for hospital water system
CN110276549A (en) Chemical company&#39;s waste water chemical pollutant spy factor inventory construction method and device
CN108698869A (en) Industrial waste water purifying handles real-time monitoring system
CN116430821B (en) Data processing method and device for industrial production process model
CN102929241A (en) Safe operation guide system of purified terephthalic acid device and application of safe operation guide system
CN108614510A (en) sewage plant operation management method and system
CN111762824A (en) Sewage treatment monitoring system based on block chain
CN116770930A (en) Integrated sewage discharge system for modularized building
CN111381567B (en) Safety detection system and method for industrial control system
JP2005074418A (en) Monitoring and controlling net work system for cleaned water supply facility
CN216155703U (en) Water plant system
CN210313784U (en) Wisdom is integrated management system for sewage treatment
CN114706907A (en) Tracing method for pollutants in drainage pipe network
CN112631221A (en) Sewage treatment remote monitoring system and method thereof
JPH10133737A (en) Plant operation support system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20240815

Address after: Room 103, No. 780, Tanghekou Street, Tanghekou Town, Huairou District, Beijing

Patentee after: DASMART ENVIRONMENTAL TECHNOLOGIES (BEIJING) Co.,Ltd.

Country or region after: China

Address before: 100176 Building 1, 8 boxing 1st Road, Beijing Economic and Technological Development Zone, Daxing District, Beijing

Patentee before: BEIJING ETECHWIN ELECTRIC Co.,Ltd.

Country or region before: China

TR01 Transfer of patent right