CN109803884A - The independent suspension type parallelepiped module made of armored concrete realizes the System and method for from suspension seabed tunnel - Google Patents
The independent suspension type parallelepiped module made of armored concrete realizes the System and method for from suspension seabed tunnel Download PDFInfo
- Publication number
- CN109803884A CN109803884A CN201780059712.2A CN201780059712A CN109803884A CN 109803884 A CN109803884 A CN 109803884A CN 201780059712 A CN201780059712 A CN 201780059712A CN 109803884 A CN109803884 A CN 109803884A
- Authority
- CN
- China
- Prior art keywords
- tunnel
- module
- wirerope
- seabed
- modules
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/063—Tunnels submerged into, or built in, open water
- E02D29/067—Floating tunnels; Submerged bridge-like tunnels, i.e. tunnels supported by piers or the like above the water-bed
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B21/00—Tying-up; Shifting, towing, or pushing equipment; Anchoring
- B63B21/50—Anchoring arrangements or methods for special vessels, e.g. for floating drilling platforms or dredgers
- B63B21/502—Anchoring arrangements or methods for special vessels, e.g. for floating drilling platforms or dredgers by means of tension legs
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B5/00—Hulls characterised by their construction of non-metallic material
- B63B5/14—Hulls characterised by their construction of non-metallic material made predominantly of concrete, e.g. reinforced
- B63B5/18—Hulls characterised by their construction of non-metallic material made predominantly of concrete, e.g. reinforced built-up from elements
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Combustion & Propulsion (AREA)
- Mechanical Engineering (AREA)
- Ocean & Marine Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- Chemical & Material Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
The invention discloses a kind of System and method for for realizing floated tunnel, which is polymerized by parallelepiped shape, armored concrete material floated module.These modules form a monomer by the special wirerope of interspersed, drawing and are able to be polymerized to an entirety, these wireropes pass through entire tunnel and are classified as independent section, and enter in the sheath being arranged in module wall, by extracting out and locking in the position, wirerope compresses the structure to enhance its durability.Wirerope can be put along the vertical and horizontal directions.
Description
The present invention relates to a kind of System and method for for realizing submerged floating tunnel, which hangs made of armored concrete
Floating parallelepiped module is polymerized.These modules form a monomer by the special wirerope of interspersed, drawing and are gathered
It is combined into an entirety, these wireropes pass through entire tunnel and are classified as independent section, and enter the sheath being arranged in module wall
Interior, by extracting out and locking in the position, wirerope compresses the structure to enhance its durability.Wirerope can be along the vertical and horizontal directions
It places.This method and existing system are further characterized in that tunnel quota will not change with tide and its load born.In order to
Different continent parts is connected, is for the demand of the floated tunnel even immersed tube tunnel of middle and high depth at present
Greatly.Modular system in the prior art is by cylindrical tunnel construction sections polymerization, is solidified togather to realize submerged floating tunnel.
Currently used scheme is to be based on: tunnel module is tunnel duct piece, and wherein the section of tunnel wall is solid or by one group
Solid non-suspending module condenses together to form tunnel construction sections, and the tunnel construction sections of the two are formed by solid wall, and very heavy, this is right
The suspension in tunnel is clearly unfavorable, it is therefore desirable to which the additional floating body of external application reaches enough suspension thrust in tunnel construction sections.This
The system and method for invention form tunnel wall by using hollow, single floated module to overcome these defects.By the group
Module combines to form tunnel construction sections, and this tunnel construction sections no longer have solid wall, and weight is extremely light, can make tunnel without additional floating body
Road floats.Since under the action of a large amount of bone ribs, the tunnel change in wall that hollow mold block is combined together to form is firm, and tunnel wall
Inside has partition, to increase durability, while making the average weight of total, therefore this tunnel is extremely light and resistance to
With.Tunnel module uses the reinforced concrete structure with conventional rebar, in conjunction with method are as follows: will " big reach " steel bar, press afterwards
Wirerope is inserted into appropriate sheath, is tensed and is locked, and being subsequently injected into cement mortar solidifies sheath and wirerope.The invention also achieves
Tunnel quota does not change this advantage with overload and tide, implementation are as follows: submerges the module section for constituting tunnel, makes
It sinks down into aequum, and then, after anchor hawser is fastened on seabed, the water that emptying module is accumulated more pushes away to generate
Power floats it, further that connection component is firm on seabed, and fighting pretension can, institute is loaded, and such as: ocean current generates
Load.Yet another advantage of the present invention is that the speed of tunnel assembling is identical as prefabricated and sea-freight speed.
According to the present invention, tunnel is realized in horizontal plane and/or underwater suspension, to address on realizing by a system
Other purposes.The system features are, the composition side in tunnel by it is one group of independent levitation, interior it is empty, can be connected together to form it is close
The module 4 for sealing tunnel construction sections forms.Tunnel is independent levitation, and without other floating bodies or block, tunnel is by one group 4 groups of suspending module
At, wherein the connecting side between module 4 connected has seal sand slurry.Module 4 is by bolt connecting type reinforcing bar and after tensing
It compresses wirerope 1 afterwards and wirerope 2 connects into an entirety, these modules 4 are parallelepiped shape, and are connected in its side
It connects;These modules 4 are reinforced concrete structure, at least one internal armored concrete partition 20;Constitute the module 4 in tunnel
With post-tensioning wirerope 1 and wirerope 2;The rear compression wirerope of module is fixed in the sheath 9 in the upper and lower region of module wall;This
A little sheaths are perpendicular to the contact wall of module 4 and in conjunction with wall;The upper and lower region of partition 20 in module is also equally to be arranged;After press
Contracting wirerope 1 and wirerope 2 pass through module 4, and so on to all modules, to form tunnel;Wirerope 1,2 vertically 21,
22 settings, the rear wirerope 1,2 that compresses are in tensioning state;The rear compression wirerope 1,2 of tensioning is in entire tunnel internal, the two and its
It is connected between related sheath with cement mortar, so that wirerope 1,2 and sheath 9 be connected, tunnel is anchored on seabed 12, and
Counterweight 13 is lain in rope or chain 14 or is anchored on the foundation pile in seabed 12, or is lain on the basis of the integral type of seabed;Tunnel phase
For the line that normally floats submergence amount at least equal under the influence of acting on the peak load in tunnel being applied, its sinking
Maximum tide offset.
Target of the present invention is to realize that this method is characterized in by a kind of method of achievable submerged floating tunnel, first can anchor
Gu the counterweight in tunnel is fixed on seabed, or builds foundation pile or the basis that can anchor tunnel on seabed, next, reinforcing bar is mixed
It is that solidifying soil is constituted, with parallelepiped shape and at least with the longer sides of the first suspending module of one piece of internal partition sealing and the
Two modules connect, and center line is aligned with the longer sides of the second module, are then bolted reinforcing bar occasional combination with appropriate
Get up, then repeatedly second stage, that is, increase more multimode and obtain the downside in tunnel, when these block combiners are at constituting under tunnel
When the number of modules of side, equal modules are anchored on seabed with wirerope or chain;Followed by by the way that post-tensioning wirerope is inserted into
It in the respective sheath in the upper and lower region of module and divider upright wall and is pulled, solidifies aggregation module.Wirerope is compressed by after
Along the insertion of vertical wall direction, the precompressed perpendicular to the long and short side of module, to form the downside of submerged floating tunnel, in post-tensioning wirerope and shield
Inner room injection cement mortar both makes to became one, and so that it is sunk down into right amount by aggregation module is partially submerged in next step, from
And it conveniently positioning, polymerizeing these modules to form the vertical wall in tunnel, while be tensioned the connection component in seabed again;With
Afterwards, the module for constituting Vertical tunnel wall and enhancing are placed and separates the potential partition of the tunnel construction sections of tunnel section, the module
Combination follow compact model after the combination on the downside of tunnel described in occasional combination model identical and previous steps, followed by
It realizes on the upside of tunnel, is interconnected to constitute on the upside of tunnel by module respectively, mode is the implementation pattern on the downside of above-mentioned tunnel;With
Tunnel downside and vertical edge, partition are sunk down into the correct depth apart from the water surface together afterwards, to be convenient to positioning, connection tunnel
On the upside of road.Meanwhile seabed connection component is tensioned again;Positioning on the upside of tunnel in Vertical tunnel wall with installation is connected by reinforcing bar
Realization is connect, the rear injection for compressing the interspersed of wirerope, drawing and mortar followed by submergence as previously mentioned, form on the upside of tunnel
Module, so that tunnel is normally sunk, then, take out the water emptying caisson previously accumulated, tense and the connection group in tunnel and seabed
Part, final step be empty in entire finished product tunnel, as use and tunnel transit domain in water.
As shown in the picture, but it is not limited to attached drawing, wherein Fig. 1 display module 4, module 4 is transparent general module, with dotted line 3
Indicate the jacket passage of wirerope 1,2 after storage is compressed.
Fig. 2 shows the general module that prototype is realized as first, and module 4 is made of armored concrete, has conventional
Reinforcing bar and the preset sheath 9 that compression wirerope passes through after can making.Shown threaded rod 8 is used to other modules being suspended to the module
On, it is compressed after then being carried out to wirerope, protrusion 7 and depressed section 6 is painted in Fig. 2, depressed section 6 is the negative of protrusion
Form, these protrusions and depressed section are the center of module to be polymerized, finally, Fig. 2 shows the sealing for entering module 4 is living
Plate door 5.
Fig. 3 shows the combination of the certain module of 10 downside of composition tunnel, and insertion has the water on surface 11 on the downside of tunnel 10
In mirror surface, which is fixed on seabed 12 by counterweight 13, and is connected with steel chain 14, in addition, indicating post-tensioning wirerope with dotted line 15
Channel, the channel extend to the rest part in tunnel.
Fig. 4 shows the step of vertical wall 16 is fixed to 17 on the downside of tunnel, and the water surface is indicated with 11, and seabed is indicated with 12, sea
Counterweight 13 on bottom is connected on the connection wirerope 14 in tunnel, and dotted line element 1 and 2 indicates the channel of post-tensioning wirerope, which prolongs
Continue to the rest part in tunnel.
Fig. 5 shows the tunnel cross-section 23 with 18 associated upper of tunnel, that is, such as Fig. 3, connects the module to one as indicated at 4
Rise, the water surface 11, seabed 12, the counterweight on seabed is 13, and seabed anchor cable is 14, dotted line element 1 and 2 indicate tunnel remaining
The channel for the post-tensioning wirerope that part extends.
Fig. 6 is shown by the section in several finished product tunnels 19 being partially fabricated, as shown in figure 5, in Fig. 6, tunnel
19 are located under the water surface 11 and by counterweight 13 and the anchoring of wirerope 14 15 to seabed 12.In the figure, tunnel 19, which has emptied, applies
It is interior aqueous during work step is rapid.Seabed can be anchored to by several ways, counterweight can be used, it is possible to use foundation pile is inserted into seabed, or logical
Cross other known technological system.The certain module of composition platform can increase its height, or different from other modules, to meet structure
It is required that and/or platform application practice requirement.Post-stretching cable is inserted into specific shell with specific metal key after tensioning
In be fixed, fixed module constructs together with required shell.
Claims (8)
1. for realizing tunnel in the water surface and underwater hovering system, it is characterized in that, tunnel constitute side by one group of independent levitation,
The interior composition of module 4 that is empty, can be connected together to form sealing tunnel construction sections.Tunnel is independent levitation, without other floating bodies or
Block, tunnel are made of one group of suspending module 4, wherein the connecting side between module 4 connected has seal sand slurry.Module 4
Rear compression wirerope 1 and wirerope 2 by bolt connecting type reinforcing bar and after tensing connect into an entirety, these modules 4 are parallel
Hexahedral shape, and be attached in its side;These modules 4 are reinforced concrete structure, at least one internal reinforcing bar
Concrete diaphragm 20;The module 4 for constituting tunnel has post-tensioning wirerope 1 and wirerope 2;The rear compression wirerope of module is fixed on positioned at mould
In sheath 9 in the upper and lower region of block wall;These sheaths are perpendicular to the contact wall of module 4 and in conjunction with wall;Partition 20 in module
Upper and lower region is also equally to be arranged;Compression wirerope 1,2 passes through module 4 afterwards, and so on to all modules, to form tunnel;
Vertically 21,22 setting of wirerope 1,2, the rear wirerope 1,2 that compresses are in tensioning state;The rear compression wirerope 1,2 of tensioning is in
Entire tunnel internal is connected with cement mortar between the two sheath associated therewith, so that wirerope 1,2 and sheath 9 are connected,
Tunnel is anchored on seabed 12, and in counterweight 13 or is anchored on the foundation pile in seabed 12 with rope or chain system 14, or lie in sea
On the basis of the integral type of bottom;Tunnel relative to normal floating line submergence amount at least equal to the shadow in the peak load for acting on tunnel
Under sound, the maximum tide for applying its sinking is deviated.
2. system according to claim 1, which is characterized in that armored concrete tunnel is added with conventional rebar and rear compressed steel cable
Gu.
3. system according to claim 1, which is characterized in that the geometric dimension of certain module is different from other modules, this
Sample can meet specific structure requirement, geometry or the functional requirement in tunnel.
4. system according to claim 1, which is characterized in that shell will be inserted into some modules to press after tensing and locking
Contracting wirerope.
5. system according to claim 1, which is characterized in that the tunnel construction sections can be circle.
6. the method for realizing submerged floating tunnel, which is characterized in that the counterweight that can anchor tunnel is fixed on seabed in the first stage,
Or built on seabed and can anchor foundation pile or the basis in tunnel, next, armored concrete is constituted, there is parallelepiped
The longer sides of shape and the first suspending module at least sealed with one piece of internal partition are connected with the second module, i.e., by its center
Line is aligned for the first time with the longer sides of the second module, is then bolted reinforcing bar occasional combination with appropriate, then logical
It crosses and increases more multimode to repeat second stage, to obtain on the downside of tunnel, constituted on the downside of tunnel connecting a large amount of modules
When, equal modules are anchored on seabed with wirerope or chain;Followed by by the way that post-tensioning wirerope insertion module and partition are erected
It in the respective sheath in the upper and lower region of straight wall and is pulled, solidifies aggregation module.Compression wirerope is along perpendicular to module by after
The insertion of vertical wall direction, the precompressed on long and short side to form the downside of submerged floating tunnel inject cement between post-tensioning wirerope and sheath
Mortar both makes to became one, then that aggregation module is partially submerged, it is made to sink down into right amount, thus be convenient to positioning,
It polymerize these modules to form the vertical wall in tunnel, while is tensioned the connection component in seabed again;Then, it places and constitutes tunnel
The module of vertical wall and enhancing and the potential tunnel construction sections partition for separating tunnel section, the combination of the module follow occasional combination
Same mode and previous steps described in the rear compact model that combines on the downside of tunnel, followed by being implemented separately on the upside of tunnel,
It is interconnected to constitute on the upside of tunnel by module, mode is the implementation pattern on the downside of above-mentioned tunnel;It then will be with vertical edge, partition
Tunnel on the downside of sink down into correct depth apart from the water surface, to be convenient to positioning, on the upside of connection tunnel.Meanwhile seabed connects
Connected components are tensioned again;Positioning on the upside of tunnel in Vertical tunnel wall is that realization is connect by reinforcing bar with installation, compresses steel afterwards
The injection of the interspersed of cable, drawing and mortar keeps tunnel normal as previously mentioned, followed by the module formed on the upside of tunnel is submerged
Sink, then, takes out the water emptying caisson previously accumulated, to tense the connection component in tunnel and seabed, final step is clear
In empty entire finished product tunnel, as use and tunnel transit domain in water.
7. method according to claim 6, which is characterized in that tunnel is that segmentation is realized, and by limited independent tunnel
Section is combined into entire tunnel.
8. method according to claim 6, which is characterized in that it is the assembling by tunnel construction sections that tunnel, which is anchored to seabed step,
What ratio gradually carried out.
Applications Claiming Priority (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
IT102016000096669A IT201600096669A1 (en) | 2016-09-27 | 2016-09-27 | System and method for the realization of autonomously floating underwater tunnels formed by individually floating parallelepiped-shaped modules made of reinforced concrete |
IT102016000096669 | 2016-09-27 | ||
PCT/IT2017/000202 WO2018061043A2 (en) | 2016-09-27 | 2017-09-25 | System and method for the realization of self-floating submarine tunnel formed by individually floating parallelepiped-shaped modules made of reinforced concrete |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109803884A true CN109803884A (en) | 2019-05-24 |
Family
ID=58054401
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201780059712.2A Pending CN109803884A (en) | 2016-09-27 | 2017-09-25 | The independent suspension type parallelepiped module made of armored concrete realizes the System and method for from suspension seabed tunnel |
Country Status (3)
Country | Link |
---|---|
CN (1) | CN109803884A (en) |
IT (1) | IT201600096669A1 (en) |
WO (1) | WO2018061043A2 (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112878374A (en) * | 2021-01-18 | 2021-06-01 | 重庆交通大学 | Suspension tunnel connecting member |
CN113833025A (en) * | 2019-07-06 | 2021-12-24 | 王建平 | Water suspension type steel-concrete structure road and railway traffic engineering |
KR102585366B1 (en) * | 2022-08-12 | 2023-10-06 | 한국건설기술연구원 | Casing typed shear connecting apparatus, concrete marine buoyancy structure connection method and concrete marine buoyancy structure using the same |
WO2024084425A1 (en) * | 2022-10-21 | 2024-04-25 | Politecnico Di Torino | Floatation platform |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109653248B (en) * | 2018-11-07 | 2020-08-04 | 浙江大学 | Adjustable anchor cable device for anchoring suspended tunnel pipe body |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3788254A (en) * | 1971-12-28 | 1974-01-29 | J Sheil | Floating platform |
FR2597826B1 (en) * | 1986-04-29 | 1991-01-04 | Gey Robert | MODULAR FLOAT AND METHOD FOR ASSEMBLING A PLURALITY OF SUCH FLOATS TO CONSTITUTE A FLOATING MACHINE |
US5107785A (en) * | 1990-12-07 | 1992-04-28 | Baxter Hal T | Floating dock and breakwater |
US5899635A (en) * | 1997-05-09 | 1999-05-04 | Kuja; Michael W. | Transportation underwater tunnel system |
US20050103250A1 (en) * | 2003-10-31 | 2005-05-19 | Thomson Howard M. | Corrosion resistant prestressed concrete float system |
-
2016
- 2016-09-27 IT IT102016000096669A patent/IT201600096669A1/en unknown
-
2017
- 2017-09-25 CN CN201780059712.2A patent/CN109803884A/en active Pending
- 2017-09-25 WO PCT/IT2017/000202 patent/WO2018061043A2/en active Application Filing
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113833025A (en) * | 2019-07-06 | 2021-12-24 | 王建平 | Water suspension type steel-concrete structure road and railway traffic engineering |
CN112878374A (en) * | 2021-01-18 | 2021-06-01 | 重庆交通大学 | Suspension tunnel connecting member |
KR102585366B1 (en) * | 2022-08-12 | 2023-10-06 | 한국건설기술연구원 | Casing typed shear connecting apparatus, concrete marine buoyancy structure connection method and concrete marine buoyancy structure using the same |
WO2024084425A1 (en) * | 2022-10-21 | 2024-04-25 | Politecnico Di Torino | Floatation platform |
Also Published As
Publication number | Publication date |
---|---|
WO2018061043A2 (en) | 2018-04-05 |
IT201600096669A1 (en) | 2018-03-27 |
WO2018061043A3 (en) | 2018-05-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109803884A (en) | The independent suspension type parallelepiped module made of armored concrete realizes the System and method for from suspension seabed tunnel | |
EP2212479B1 (en) | Underwater suspended tunnel | |
JP2964640B2 (en) | Construction method of gravity type offshore structure and its structure | |
CN105350531B (en) | The pile tube anchor pole composite foundation and construction technology of tension compression bidirectional load can be born | |
CN110984213A (en) | Offshore wind power single pile-friction cone composite foundation and construction method thereof | |
JP2015155655A (en) | Construction method for offshore wind power generation facility | |
CN107794952A (en) | Garbage pool and its method of construction | |
CN110939148A (en) | Construction method of double-wall steel suspension box cofferdam serving as drilling platform | |
CN108951607A (en) | The hollow continuous underground wall structure of cast-in-place post-tensioned prestressed concrete and its construction method | |
NO20092241L (en) | Subsoil foundations, as well as methods for installing the foundation | |
ITMI992383A1 (en) | BREAK BARRIERS FOR THE DEFENSE OF THE COAST | |
EP3344531B1 (en) | System and method for the realization of floating platforms made of post-compressed reinforced concrete with floating quota fixed and invariable | |
US4092944A (en) | Underwater anchor for the mooring of floating structures as well as a method for the placing of such an anchor | |
JP5681988B2 (en) | Breakwater reinforcement method and reinforced breakwater | |
CN207794148U (en) | Garbage pool | |
JPH07247539A (en) | Method of constructing deep foundation structure and the structure | |
RU2436892C2 (en) | Manufacturing method of soil geocontainer | |
CN221000841U (en) | Be applied to high intensity, high water level's storehouse district pier barricade | |
CN210507477U (en) | Side slope retaining structure | |
JP2004162426A (en) | Foundation cell, cell foundation structure, and construction method for cell foundation structure | |
CN110593286B (en) | Removable cofferdam rapid construction geotechnical formwork bag net hanging structure and construction method thereof | |
SU1073366A1 (en) | Dam | |
JPS59179924A (en) | Construction of foundation for marine structure | |
US637935A (en) | Block for building moles, dams, piers, & c. | |
US1137601A (en) | Process and apparatus for having artificial blocks cast or settled on spot to build piers, quays, and like structures. |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20190524 |