CN109797894A - A kind of vertical gradual change angle unit curtain wall system of Super High - Google Patents
A kind of vertical gradual change angle unit curtain wall system of Super High Download PDFInfo
- Publication number
- CN109797894A CN109797894A CN201910185287.2A CN201910185287A CN109797894A CN 109797894 A CN109797894 A CN 109797894A CN 201910185287 A CN201910185287 A CN 201910185287A CN 109797894 A CN109797894 A CN 109797894A
- Authority
- CN
- China
- Prior art keywords
- unit
- curtain wall
- profile
- vertical
- angle
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A30/00—Adapting or protecting infrastructure or their operation
- Y02A30/24—Structural elements or technologies for improving thermal insulation
- Y02A30/244—Structural elements or technologies for improving thermal insulation using natural or recycled building materials, e.g. straw, wool, clay or used tires
Landscapes
- Load-Bearing And Curtain Walls (AREA)
Abstract
The embodiment of the invention discloses a kind of vertical gradual change angle unit curtain wall systems of Super High, including multilevel-cell curtain wall, cell curtain wall includes galvanized steel plain sheet, its surface is equipped with fire prevention rock wool and heat preservation rock, the surface of fire prevention rock wool and heat preservation rock is provided with aluminium backboard, horizontal profile and unit Lower transverse section on unit are separately installed at the top and bottom of galvanized steel plain sheet and aluminium backboard, there are two unit transom profiles for the middle part surface interval installation of aluminium backboard, ox horn pedestal section is installed between two unit transom profiles, the surface of ox horn pedestal section is installed by ox horn moulding profile, unit transom profile is fixed on the vertical male material of unit and the vertical parent form material of unit, the vertical male material of unit and the vertical parent form material of unit are connect with steel hanging seat, galvanized steel plain sheet and steel hanging seat are connect with construction wall.The vertical gradual change angle unit curtain wall system of Super High of the invention solves cell curtain wall assembling, the installation adaptability problem of various different angles using standard block system.
Description
Technical field
The present invention relates to vertical gradual change angle curtain wall field more particularly to a kind of vertical gradual change angle cell curtain walls of Super High
System.
Background technique
Diverse designs or desirability during building high-rise, because of building, it is sometimes desirable to will surpass
High-rise curtain wall system builds into the inconsistent gradual change moulding of lower angle, this moulding is not only adapted to the needs of every floor,
And it is beautiful and generous, but because each floor alien invasion curtain wall angle is different when building, cause that the assembly process is complicated, installation effectiveness is low
Under, and material cost is higher, constructional difficulties.
Therefore, it is necessary to propose a kind of vertical gradual change angle unit curtain wall system of standardized Super High, it is above-mentioned to overcome
Disadvantage.
Summary of the invention
The technical problem to be solved by the embodiment of the invention is that causing group for the curtain wall system for building gradual change moulding
The problem of dress complex process, installation effectiveness is low, and material cost is higher, constructional difficulties, it is vertical to propose a kind of Super High
Gradual change angle unit curtain wall system.
In order to solve the above-mentioned technical problem, the embodiment of the invention provides a kind of vertical gradual change angle cell curtain walls of Super High
System, the vertical gradual change angle unit curtain wall system of the Super High includes multilevel-cell curtain wall, and cell curtain wall includes galvanized steel plain sheet,
Surface is equipped with fire prevention rock wool and heat preservation rock, and the surface of prevent fires rock wool and heat preservation rock is provided with aluminium backboard, galvanized steel plain sheet and
Horizontal profile and unit Lower transverse section on unit, the middle part surface interval peace of aluminium backboard are separately installed at the top and bottom of aluminium backboard
Dress is horizontal under horizontal profile and unit transom profile, unit transom profile and unit on unit there are two unit transom profile
Tempered glass is mounted between profile, the end of tempered glass is individually fixed on unit horizontal by unit transverse gusset plate profile
On profile, unit transom profile and unit Lower transverse section, ox horn pedestal section is installed between two unit transom profiles,
Ox horn moulding profile is installed on the surface of ox horn pedestal section, and screw is connected to list to two adjacent ox horn pedestal sections of left and right respectively
On first transom profile, unit transom profile is fixed on the vertical male material of unit and the vertical parent form material of unit, and unit is vertical
Male material and the vertical parent form material plug connection of unit, and the vertical male material of unit and the vertical parent form material of unit are vertical by aluminium alloy
Column adapter and aluminium alloy hook are connect with steel hanging seat, and galvanized steel plain sheet and steel hanging seat are connect with construction wall respectively.
Further, multiple rock wool nails are installed in the fire prevention rock wool between aluminium backboard and galvanized steel plain sheet.
Further, multiple backboard reinforcing ribs are installed in the one side of aluminium backboard direction fire prevention rock wool.
Further, steel hanging seat is connect by T-bolt with the construction wall, and the galvanized steel plain sheet passes through stainless steel lag screws
It is connect with the construction wall.
Further, connection is mounted on the unit of adjacent cells curtain wall between horizontal profile and unit Lower transverse section, and is connected
Locate encapsulation process, and the top and bottom for the adjacent tempered glass that horizontal profile and unit Lower transverse section outside are installed on unit pass through
The fastening of unit transverse gusset plate profile.
Further, the angle between cell curtain wall and construction wall has acute angle, right angle and obtuse angle, and angle changing exists
Between 81.7 ° to 91.6 °.
Further, the angle determination method of every layer unit curtain wall is as follows: choose specific 4 angles: 85.8 °, 88 °,
90 °, 91.6 °, the die sinking angle as profile horizontal on unit and unit Lower transverse section;The angle for determining vertical curtain wall face is 90 °;
The range that 90 ° of < makes 1.1 ° of adaptation angle=of horizontal profile and unit Lower transverse section on unit;The range that 90 ° of > makes every set list
0.8 ° of adaptation angle=of horizontal profile and unit Lower transverse section in member;It determines datum mark, eliminates the nonstandard angle list of above-mentioned determination
Horizontal profile and unit Lower transverse section side generates indoors " horizontal departure " in member;Horizontal profile downside and unit transom on unit
The mode vertical with glass surface is taken on the upside of profile, and on the downside of unit transom profile then with hang either flush;Interlayer nose of an ox
Sub- moulding position, horizontal profile and unit Lower transverse section ensure vertical with glass surface on internal element, and outside ox muzzle moulding
Main system is then corresponded to using four kinds of different angle die sinkings, reduces the outdoor collimation error.
Further, it is the vision height difference for avoiding horizontal profile and unit Lower transverse section and windowsill on unit, considers curtain wall
Horizontal profile and unit Lower transverse section and indoor window platen join on unit, select horizontal material tail point as datum mark.
The implementation of the embodiments of the present invention has the following beneficial effects: the vertical gradual change angle cell curtain wall of Super High of the invention
System is solved cell curtain wall assembling, the installation adaptability problem of various different angles using standard block system, not only reduced
Die sinking quantity, improves processing, packaging efficiency, and economic benefit is obvious.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below
There is attached drawing needed in technical description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this
Some embodiments of invention for those of ordinary skill in the art without creative efforts, can be with
It obtains other drawings based on these drawings.
Fig. 1 is that a kind of exterior walls of buildings structure of the vertical gradual change angle unit curtain wall system of Super High provided by the invention is shown
It is intended to;
Fig. 2 be cell curtain wall angle in Fig. 1 less than 90 degree when perpendicular cut open node structure schematic diagram;
Fig. 3 is that perpendicular when cell curtain wall angle in Fig. 1 is equal to 90 degree cuts open node structure schematic diagram;
Fig. 4 is the cross-sectional node structure schematic diagram of the cell curtain wall in Fig. 3;
Fig. 5 is that perpendicular when cell curtain wall angle in Fig. 1 is greater than 90 degree cuts open node structure schematic diagram;
Fig. 6 is the schematic diagram for eliminating the nonstandard horizontal material of the angle horizontal departure that side generates indoors;
Fig. 7 is the schematic diagram for selecting horizontal material tail point as datum mark;
Fig. 8 is schematic diagram vertical with glass surface on the downside of horizontal profile and on the upside of unit Lower transverse section on unit;
Fig. 9 is the schematic diagram of four kinds of angles die sinking mode of ox horn moulding profile.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete
Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on
Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other
Embodiment shall fall within the protection scope of the present invention.
Referring to Figure 1, Fig. 2, Fig. 3, Fig. 4 and Fig. 5, Fig. 1 are the vertical gradual change angles of a kind of Super High provided by the invention
The exterior walls of buildings structural schematic diagram of unit curtain wall system;Fig. 2 be cell curtain wall angle in Fig. 1 less than 90 degree when perpendicular cut open section
Point structure schematic diagram;Fig. 3 is that perpendicular when cell curtain wall angle in Fig. 1 is equal to 90 degree cuts open node structure schematic diagram;Fig. 4 is Fig. 3
In cell curtain wall cross-sectional node structure schematic diagram;Fig. 5 is that perpendicular when cell curtain wall angle in Fig. 1 is greater than 90 degree cuts open node
Structural schematic diagram.
The present invention provides a kind of vertical gradual change angle unit curtain wall system of Super High, the vertical gradual change angle lists of the Super High
First curtain wall system includes: cell curtain wall 10, galvanized steel plain sheet 11, fire prevention rock wool 12, aluminium backboard 13, horizontal profile 14, unit on unit
Lower transverse section 15, unit transom profile 16, tempered glass 17, unit transverse gusset plate profile 18, ox horn pedestal section 19, ox horn
The vertical male material 21 of moulding profile 20, unit, the vertical parent form material 22 of unit, Aluminum alloy column adapter 23, aluminium alloy hook 24,
Steel hanging seat 25, rock wool nail 26, backboard reinforcing rib 27, T-bolt 28, stainless steel lag screws 29 and heat preservation rock 33.
The vertical gradual change angle unit curtain wall system of the Super High includes multilevel-cell curtain wall 10, and cell curtain wall 10 includes zinc-plated
Steel plate 11, surface are equipped with fire prevention rock wool 12 and heat preservation rock 33, and the surface of prevent fires rock wool 12 and heat preservation rock 33 is provided with
Aluminium backboard 13, is equipped with multiple rock wools nail 26 in rock wool 12 of preventing fires, and aluminium backboard 13 is towards being equipped in the one side of fire prevention rock wool 12
Multiple backboard reinforcing ribs 27.The top and bottom of galvanized steel plain sheet 11 and aluminium backboard 13 are separately installed with horizontal profile 14 and list on unit
First Lower transverse section 15, the middle part surface interval installation of aluminium backboard 13 is there are two unit transom profile 16, horizontal profile 14 on unit
Tempered glass 17, steel are mounted between unit transom profile 16, unit transom profile 16 and unit Lower transverse section 15
The end for changing glass 17 is individually fixed in horizontal profile 14 on unit, unit transom profile 16 by unit transverse gusset plate profile 18
And on unit Lower transverse section 15.
Ox horn pedestal section 19 is installed, ox is installed on the surface of ox horn pedestal section 19 between two unit transom profiles 16
Angle moulding profile 20, screw is connected on unit transom profile 16 two adjacent ox horn pedestal sections 19 of left and right respectively, single
First transom profile 16 is fixed on the vertical male material 21 of unit and the vertical parent form material 22 of unit, the vertical male material 21 of unit and list
First vertical 22 plug connection of parent form material, and the vertical male material 21 of unit and the vertical parent form material 22 of unit are turned by Aluminum alloy column
Fitting 23 and aluminium alloy hook 24 are connect with steel hanging seat 25, and steel hanging seat 25 is connect by T-bolt 28 with construction wall 30, zinc-plated
Steel plate 11 is connect by stainless steel lag screws 29 with construction wall 30.
Connection is mounted on the unit of adjacent cells curtain wall 10 between horizontal profile 14 and unit Lower transverse section 15, and junction is close
Envelope processing, and the top and bottom for the adjacent tempered glass 17 installed on the outside of horizontal profile 14 and unit Lower transverse section 15 on unit are logical
The fastening of unit transverse gusset plate profile 18 is crossed, unit Lower transverse section 15 is fastened by interior decoration buckle 31 and indoor heat insulating layer 32.
Angle between cell curtain wall 10 and construction wall 30 has acute angle, right angle and obtuse angle, and angle changing is arrived at 81.7 °
91.6 between °.
The angle determination method of every layer unit curtain wall 10 is as follows:
Specific 4 angles: 85.8 °, 88 °, 90 °, 91.6 ° are chosen, as profile horizontal on unit and unit Lower transverse section
Die sinking angle;
The angle for determining vertical curtain wall face is 90 °;
90 ° of angle < of range of die sinking makes 1.1 ° of adaptation angle=of horizontal profile and unit Lower transverse section on unit;
90 ° of angle > of range of die sinking makes 0.8 ° of adaptation angle=of horizontal profile and unit Lower transverse section on every set unit;
Determine datum mark, eliminating horizontal profile and unit Lower transverse section in the nonstandard angle-unit of above-mentioned determination, is produced from side indoors
Raw " horizontal departure ", refers to Fig. 6.For the vision height difference for avoiding horizontal profile and unit Lower transverse section and windowsill on unit,
Consider that horizontal profile and unit Lower transverse section and indoor window platen join on curtain wall unit, selectes horizontal material (horizontal profile and list on unit
First Lower transverse section) tail point as datum mark, refers to Fig. 7, from figure 7 it can be seen that the horizontal material using 85.8 ° installs 84.7 °
Floor, 86.9 ° of floor is installed using 88 ° of horizontal material, guarantees that horizontal material tail end is concordant with indoor window platen, horizontal material front end
" horizontal departure " is only 3.2mm;
The mode vertical with glass surface is taken on the upside of unit Lower transverse section on the downside of horizontal profile on unit, and it is horizontal in unit
On the downside of frame section then with hang either flush, see Fig. 8;
Interlayer ox muzzle moulding position, horizontal profile and unit Lower transverse section ensure vertical with glass surface on internal element,
And outside ox muzzle moulding is then corresponded to main system and is opened using four kinds of different angles (85.5 °, 88.0 °, 90.0 degree and 91.5 degree)
Mould reduces the outdoor collimation error, sees Fig. 9.
The vertical gradual change angle unit curtain wall system of Super High of the invention, in the base of existing ripeness standard unit curtain wall system
On plinth, the horizontal material of several special angles is designed, every horizontal material of set adapts to a certain range of curtain wall inclination angle, it can solve above-mentioned all
Problem, and by arrangement and method for construction evaluate, be operationally it is feasible, for occurring more similar units curtain wall in recent years
Design provides certain reference value.
Super High of the invention vertical gradual change angle unit curtain wall system will be horizontal under profile horizontal on unit, unit before installation
Profile, unit transom profile, tempered glass, unit transverse gusset plate profile, ox horn pedestal section, ox horn moulding profile, unit
Vertical male material and the vertical parent form material of unit etc. inside factory overall processing, organize the unit frame of one entirety of frame section, then
It is transported to on-site hoisting (mounting with steel hanging seat), lateral interlayer fire prevention iron sheet and fire prevention rock wool are finally installed and blocked.
By the implementation of the embodiments of the present invention has the following beneficial effects: the vertical gradual change angle unit of Super High of the invention
Curtain wall system solves cell curtain wall assembling, the installation adaptability problem of various different angles using standard block system, not only
Reduce die sinking quantity, improves processing, packaging efficiency, and economic benefit is obvious.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention
Within mind and principle, any modification, equivalent replacement, improvement and so on be should all be included in the protection scope of the present invention.
Claims (8)
1. a kind of vertical gradual change angle unit curtain wall system of Super High, which is characterized in that the vertical gradual change angle list of Super High
First curtain wall system includes multilevel-cell curtain wall, and the cell curtain wall includes galvanized steel plain sheet, and surface is equipped with fire prevention rock wool and guarantor
The surface of warm rock wool, the fire prevention rock wool and heat preservation rock is provided with aluminium backboard, the top of the galvanized steel plain sheet and the aluminium backboard
Portion and bottom are separately installed with horizontal profile and unit Lower transverse section on unit, and the middle part surface interval of the aluminium backboard is equipped with two
A unit transom profile, horizontal profile and the unit transom profile, the unit transom profile and institute on the unit
It states and is mounted on tempered glass between unit Lower transverse section, the end of the tempered glass is distinguished by unit transverse gusset plate profile
It is fixed on horizontal profile on the unit, the unit transom profile and the unit Lower transverse section, two units
Ox horn pedestal section is installed, ox horn moulding profile, left and right phase are installed in the surface of the ox horn pedestal section between transom profile
Screw is connected on unit transom profile two adjacent ox horn pedestal sections respectively, and the unit transom profile is fixed
In on the vertical male material of unit and the vertical parent form material of unit, the vertical male material of unit and the vertical parent form material grafting of the unit
Connection, and the vertical male material of the unit and the vertical parent form material of the unit pass through Aluminum alloy column adapter and aluminium alloy is hung
Hook is connect with steel hanging seat, and the galvanized steel plain sheet and steel hanging seat are connect with construction wall respectively.
2. the vertical gradual change angle unit curtain wall system of Super High according to claim 1, which is characterized in that the aluminium backboard
Multiple rock wool nails are installed in the fire prevention rock wool between the galvanized steel plain sheet.
3. the vertical gradual change angle unit curtain wall system of Super High according to claim 1, which is characterized in that the aluminium backboard
Multiple backboard reinforcing ribs are installed on towards the one side of the fire prevention rock wool.
4. the vertical gradual change angle unit curtain wall system of Super High according to claim 1, which is characterized in that the steel hanging seat
It is connect by T-bolt with the construction wall, the galvanized steel plain sheet is connect by stainless steel lag screws with the construction wall.
The galvanized steel plain sheet and steel hanging seat are connect by T-bolt and stainless steel lag screws with the construction wall.
5. the vertical gradual change angle unit curtain wall system of Super High according to claim 1, which is characterized in that the adjacent list
Connection, and junction encapsulation process are mounted on the unit of first curtain wall between horizontal profile and unit Lower transverse section, and on the unit
The top and bottom for the adjacent tempered glass installed on the outside of horizontal profile and the unit Lower transverse section pass through the unit transverse button
Profile material fastening.
6. the vertical gradual change angle unit curtain wall system of Super High according to claim 1, which is characterized in that the unit curtain
Angle between wall and construction wall has acute angle, right angle and obtuse angle, and angle changing is between 81.7 ° to 91.6 °.
7. the vertical gradual change angle unit curtain wall system of Super High according to claim 6, which is characterized in that every layer of list
The angle determination method of first curtain wall is as follows: specific 4 angles: 85.8 °, 88 °, 90 °, 91.6 ° is chosen, as type horizontal on unit
The die sinking angle of material and unit Lower transverse section;The angle for determining vertical curtain wall face is 90 °;The range that 90 ° of < makes horizontal type on unit
1.1 ° of adaptation angle=of material and unit Lower transverse section;The range that 90 ° of > makes horizontal profile and unit Lower transverse section on every set unit
0.8 ° of adaptation angle=;It determines datum mark, eliminates horizontal profile and unit Lower transverse section in the nonstandard angle-unit of above-mentioned determination
" horizontal departure " that side generates indoors;It takes on the downside of horizontal profile with unit transom profile upside on unit and hangs down with glass surface
Straight mode, and on the downside of unit transom profile then with hang either flush;Interlayer ox muzzle moulding position, horizontal type on internal element
Material and unit Lower transverse section ensure vertical with glass surface, and outside ox muzzle moulding then corresponds to main system using four kinds of different angles
Degree die sinking reduces the outdoor collimation error.
8. the vertical gradual change angle unit curtain wall system of Super High according to claim 7, which is characterized in that avoid unit
The vision height difference of upper horizontal profile and unit Lower transverse section and windowsill, consider on curtain wall unit horizontal profile and unit Lower transverse section with
The handover of indoor window platen, selectes horizontal material tail point as datum mark.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910185287.2A CN109797894B (en) | 2019-03-12 | 2019-03-12 | Vertical gradual change angle unit curtain system of superelevation layer |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910185287.2A CN109797894B (en) | 2019-03-12 | 2019-03-12 | Vertical gradual change angle unit curtain system of superelevation layer |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109797894A true CN109797894A (en) | 2019-05-24 |
CN109797894B CN109797894B (en) | 2021-05-11 |
Family
ID=66562819
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910185287.2A Active CN109797894B (en) | 2019-03-12 | 2019-03-12 | Vertical gradual change angle unit curtain system of superelevation layer |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109797894B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114351915A (en) * | 2022-01-21 | 2022-04-15 | 武汉凌云建筑装饰工程有限公司 | Ultra-thick gradual change surface unit curtain wall system and construction method |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0860772A (en) * | 1994-08-18 | 1996-03-05 | Nippon Alum Co Ltd | Fitting structure for window stool for fittings |
DE9421586U1 (en) * | 1994-09-13 | 1996-08-14 | Kloss, Angelika, 44892 Bochum | Front facade with climate chamber |
CN202248410U (en) * | 2011-09-16 | 2012-05-30 | 中山盛兴股份有限公司 | Unit-type curtain wall with tilt facade |
CN102505783A (en) * | 2011-10-10 | 2012-06-20 | 苏州柯利达装饰股份有限公司 | Adjacent panel misplacement unit glass wall system |
CN202611040U (en) * | 2012-05-14 | 2012-12-19 | 沈阳远大铝业工程有限公司 | Angle-adjustable unit curtain wall corner connecting frame |
CN103321434A (en) * | 2013-06-03 | 2013-09-25 | 深圳海外装饰工程有限公司 | Arc surface unit type curtain wall construction method and structure |
CN206941918U (en) * | 2017-07-05 | 2018-01-30 | 中建不二幕墙装饰有限公司 | Pierced Aluminum Plank inclined curtain wall |
CN206941915U (en) * | 2017-06-20 | 2018-01-30 | 北京江河幕墙系统工程有限公司 | A kind of bridge insulation thermal resistance type curtain wall unit body entablature |
CN207878718U (en) * | 2017-12-20 | 2018-09-18 | 北京江河幕墙系统工程有限公司 | A kind of unit plate of non-coplanar type unitized curtain wall |
CN108756029A (en) * | 2018-05-29 | 2018-11-06 | 上海宝冶集团有限公司 | Obtuse shape glass curtain wall and its construction method |
-
2019
- 2019-03-12 CN CN201910185287.2A patent/CN109797894B/en active Active
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0860772A (en) * | 1994-08-18 | 1996-03-05 | Nippon Alum Co Ltd | Fitting structure for window stool for fittings |
DE9421586U1 (en) * | 1994-09-13 | 1996-08-14 | Kloss, Angelika, 44892 Bochum | Front facade with climate chamber |
CN202248410U (en) * | 2011-09-16 | 2012-05-30 | 中山盛兴股份有限公司 | Unit-type curtain wall with tilt facade |
CN102505783A (en) * | 2011-10-10 | 2012-06-20 | 苏州柯利达装饰股份有限公司 | Adjacent panel misplacement unit glass wall system |
CN202611040U (en) * | 2012-05-14 | 2012-12-19 | 沈阳远大铝业工程有限公司 | Angle-adjustable unit curtain wall corner connecting frame |
CN103321434A (en) * | 2013-06-03 | 2013-09-25 | 深圳海外装饰工程有限公司 | Arc surface unit type curtain wall construction method and structure |
CN206941915U (en) * | 2017-06-20 | 2018-01-30 | 北京江河幕墙系统工程有限公司 | A kind of bridge insulation thermal resistance type curtain wall unit body entablature |
CN206941918U (en) * | 2017-07-05 | 2018-01-30 | 中建不二幕墙装饰有限公司 | Pierced Aluminum Plank inclined curtain wall |
CN207878718U (en) * | 2017-12-20 | 2018-09-18 | 北京江河幕墙系统工程有限公司 | A kind of unit plate of non-coplanar type unitized curtain wall |
CN108756029A (en) * | 2018-05-29 | 2018-11-06 | 上海宝冶集团有限公司 | Obtuse shape glass curtain wall and its construction method |
Non-Patent Citations (1)
Title |
---|
高树鹏: "超高层建筑直纹渐变扭曲单元式幕墙的设计", 《建筑设计》 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114351915A (en) * | 2022-01-21 | 2022-04-15 | 武汉凌云建筑装饰工程有限公司 | Ultra-thick gradual change surface unit curtain wall system and construction method |
CN114351915B (en) * | 2022-01-21 | 2023-11-28 | 武汉凌云建筑装饰工程有限公司 | Super-thick gradual change surface unit curtain wall system and construction method |
Also Published As
Publication number | Publication date |
---|---|
CN109797894B (en) | 2021-05-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US7827746B2 (en) | Hybrid window wall/curtain wall system and method of installation | |
KR101045648B1 (en) | Combination structure of steel curtain wall | |
KR101172391B1 (en) | Eco-Friendly Insulation Curtain Wall | |
CN107503458B (en) | Curtain wall hanging piece mounting structure | |
CN109797894A (en) | A kind of vertical gradual change angle unit curtain wall system of Super High | |
KR101121149B1 (en) | Combination structure for steel curtain wall | |
EP4183965A2 (en) | Pre-glazed window wall system | |
KR200314547Y1 (en) | Window and Door Prepared by Synthetic Resin Having high Adiabatic and Airtight property | |
CA2510989C (en) | Hybrid window wall/curtain wall system and method of installation | |
CN210003117U (en) | Frame-type glass curtain wall structure based on through-shaft method | |
CN107119838B (en) | Tower curtain wall floor fire prevention node structure | |
CN213642900U (en) | Gravity type smoke-blocking vertical wall manual control device | |
CN217896900U (en) | Partial built-in unit curtain wall system | |
CN220353691U (en) | Assembled unit window system | |
CN214145282U (en) | Clean room fire window | |
CN221181442U (en) | Two-section type smoke blocking vertical wall assembly | |
CN209958582U (en) | Decorative oblique riding seam back bolt type stone curtain wall | |
CN213477159U (en) | Assembling structure of toilet | |
KR200496622Y1 (en) | Curtain wall | |
CN216740288U (en) | Curtain wall system | |
JP2000038792A (en) | Curtain wall | |
JP3897243B2 (en) | Watertight structure of curtain wall | |
JP2018123541A (en) | curtain wall | |
JP2019120062A (en) | Combination structure of window device | |
CN212118811U (en) | Novel movable smoke-blocking vertical wall |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |