CN109779048A - In-site installation is provided with the construction method of vacuum type insulating layer exterior wall - Google Patents

In-site installation is provided with the construction method of vacuum type insulating layer exterior wall Download PDF

Info

Publication number
CN109779048A
CN109779048A CN201910093285.0A CN201910093285A CN109779048A CN 109779048 A CN109779048 A CN 109779048A CN 201910093285 A CN201910093285 A CN 201910093285A CN 109779048 A CN109779048 A CN 109779048A
Authority
CN
China
Prior art keywords
insulating layer
construction
vacuum
wall
layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910093285.0A
Other languages
Chinese (zh)
Inventor
唐鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC5 Group Shanghai Corp Ltd
Original Assignee
MCC5 Group Shanghai Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC5 Group Shanghai Corp Ltd filed Critical MCC5 Group Shanghai Corp Ltd
Priority to CN201910093285.0A priority Critical patent/CN109779048A/en
Publication of CN109779048A publication Critical patent/CN109779048A/en
Pending legal-status Critical Current

Links

Landscapes

  • Building Environments (AREA)

Abstract

The invention proposes the construction methods that a kind of in-site installation is provided with vacuum type insulating layer exterior wall, comprising: the construction of wall, the prefabricated connector on wall;Fixed bracket is connect by support bracket fastened construction with connector, and to be fixed on the metope of the exterior wall, the fixed bracket is a square frame structure, is provided with several evenly distributed rectangular unthreaded holes on fixed bracket;The insulating layer is laid on the metope in the rectangular unthreaded hole by the construction of insulating layer;The construction of vacuum layer the vacuum layer is arranged on the inner sidewall of the rectangular unthreaded hole, and contact with the insulating layer.While by the way that insulating layer is arranged on the exterior wall of wall, then the heat-insulation and heat-preservation that one layer of vacuum layer carries out house is set, so as to greatly reduce the thickness of house wall;Meanwhile by the way that fixed bracket is arranged, insulating layer and vacuum layer and wall connecting intensity are also enhanced, is peeled off after a certain period of use time so as to be effectively prevented insulating layer and vacuum layer.

Description

In-site installation is provided with the construction method of vacuum type insulating layer exterior wall
Technical field
The present invention relates to technical field of building construction, and a kind of in-site installation is provided with vacuum type heat preservation The construction method of layer exterior wall.
Background technique
Currently, in order to improve the heat insulation effect in house, while insulating layer is arranged, mostly being adopted in some cold districts With the mode of increase thickness of wall body to improve heat preservation and insulation, and increased accordingly if the thickness for increasing wall The self weight of building body increases the weighing load of building, so as to cause the generation of some safety accidents.Meanwhile increasing wall In the case where thickness, increases the usage amount of construction material, greatly waste resource, affect environmental sanitation.
Summary of the invention
In consideration of it, the invention proposes the construction methods that a kind of in-site installation is provided with vacuum type insulating layer exterior wall, it is intended to Solve the problems, such as that existing severe cold area wall is thicker.
On one side, the invention proposes the construction method that a kind of in-site installation is provided with vacuum type insulating layer exterior wall, packets Include: the construction of wall, the prefabricated connector on the wall, the connector expose the exterior wall surface in the wall;
The fixed bracket is connect, to be fixed on the metope of the exterior wall by support bracket fastened construction with the connector On, the fixed bracket is configured along the setting direction of the metope, and the fixed bracket is a square frame structure, described Several evenly distributed rectangular unthreaded holes are provided on fixed bracket;
The insulating layer is laid on the metope in the rectangular unthreaded hole by the construction of insulating layer;
The construction of vacuum layer the vacuum layer is arranged on the inner sidewall of the rectangular unthreaded hole, and with the insulating layer Contact;
The waterproof layer is laid in the surface of the fixed bracket and vacuum layer by the construction of waterproof layer.
Further, when carrying out the fixed rack construction, first through hole is offered on the support bracket fastened side wall, The first through hole is arranged along with the perpendicular direction of the setting direction of the square set, and the first through hole is described for making Connector is worn wherein.
Further, when carrying out the fixed rack construction, it is logical that second is also provided on the support bracket fastened side wall Hole, second through-hole are arranged along with the perpendicular direction of the setting direction of the first through hole.
Further, when carrying out the fixed rack construction, connection bolt, the company are equipped in second through-hole Connecting bolt is for linking together the fixed bracket with vacuum layer.
Further, when carrying out the fixed rack construction, the fixed bracket is by several square plates or rectangular Steel pipe is mutually perpendicular to intersection welding and is made.
Further, being bonded together with the insulating layer by the vacuum layer.
Further, it when carrying out vacuum layer construction, encloses on the side wall of the vacuum layer equipped with fixing piece, it is described solid The inner sidewall for determining part and the rectangular unthreaded hole is bolted or is welded together.
Further, the insulating layer includes styrofoam, polyurethane foam and inorganic heat insulation material.
Further, the vacuum layer includes STP ultrathin heat insulation board.
Further, the connector is bolt or reinforcing bar.
Compared with prior art, the beneficial effects of the present invention are on the exterior wall of wall by being arranged the same of insulating layer When, then the heat-insulation and heat-preservation that one layer of vacuum layer carries out house is set, so as to greatly reduce the thickness of house wall;Meanwhile By the way that fixed bracket is arranged, insulating layer and vacuum layer and wall connecting intensity are also enhanced, so as to be effectively prevented heat preservation Layer and vacuum layer are peeled off after a certain period of use time, and the problem of cause safety accident, the security performance of the building of guarantee. Further, by the way that vacuum layer is arranged on the outside of insulating layer, and vacuum layer has very high fire resistance, so as to effective When ground prevents fire from occurring, there is the situation for burning on fire generation in insulating layer, improves the security performance in house.Further, House wall is also significantly reduced while the thermal insulation property for improving house by setting insulating layer and vacuum layer Thickness, reduces the use of construction material, to save buildings and resources and building cost, more effectively protects environment.
Detailed description of the invention
By reading the following detailed description of the preferred embodiment, various other advantages and benefits are common for this field Technical staff will become clear.The drawings are only for the purpose of illustrating a preferred embodiment, and is not considered as to the present invention Limitation.And throughout the drawings, the same reference numbers will be used to refer to the same parts.In the accompanying drawings:
Fig. 1 is the process for the construction method that in-site installation provided in an embodiment of the present invention is provided with vacuum type insulating layer exterior wall Figure;
Fig. 2 is wall body structure cross-sectional view provided in an embodiment of the present invention;
Fig. 3 is wall body structure top view provided in an embodiment of the present invention;
Fig. 4 is fixed bracket front view provided in an embodiment of the present invention.
Specific embodiment
Exemplary embodiments of the present disclosure are described in more detail below with reference to accompanying drawings.Although showing the disclosure in attached drawing Exemplary embodiment, it being understood, however, that may be realized in various forms the disclosure without should be by embodiments set forth here It is limited.On the contrary, these embodiments are provided to facilitate a more thoroughly understanding of the present invention, and can be by the scope of the present disclosure It is fully disclosed to those skilled in the art.It should be noted that in the absence of conflict, embodiment in the present invention and Feature in embodiment can be combined with each other.The present invention will be described in detail below with reference to the accompanying drawings and embodiments.
As shown in fig.1, present embodiments providing the construction party that a kind of in-site installation is provided with vacuum type insulating layer exterior wall Method, comprising the following steps:
Step 1 S101: the construction of wall;
Step 2 S102: support bracket fastened construction;
Step 3 S103: the construction of insulating layer;
Step 4 S104: the construction of vacuum layer;
Step 5 S105: the construction of waterproof layer.
Specifically, in progress step 1 S101: when the construction of wall, the prefabricated connector on the wall, the company Fitting exposes the exterior wall surface in the wall.
Specifically, carrying out step 2 S102: when support bracket fastened construction, being opened up on the support bracket fastened side wall There is first through hole, the first through hole is arranged along with the perpendicular direction of the setting direction of the square set, and described first is logical Hole is for wearing the connector wherein.The second through-hole, second through-hole are also provided on the support bracket fastened side wall It is arranged along with the perpendicular direction of the setting direction of the first through hole.When carrying out the fixed rack construction, described second Connection bolt is equipped in through-hole, the connection bolt is for linking together the fixed bracket with vacuum layer.It will be described Fixed bracket is connect with the connector, to be fixed on the metope of the exterior wall, fixed bracket the setting along the metope It sets direction to be configured, the fixed bracket is a square frame structure, is provided on the fixed bracket several evenly distributed Rectangular unthreaded hole.Specifically, the fixed bracket is mutually perpendicular to intersection welding system by several square plates or rectangular steel tube At.
Specifically, carrying out step 3 S103: when the construction of insulating layer, the insulating layer being laid in the square light On the metope in hole;
Specifically, in progress step 4 S104: when the construction of vacuum layer, the vacuum layer being arranged in the square light On the inner sidewall in hole, and contacted with the insulating layer;By being bonded together with the insulating layer for the vacuum layer.Carrying out institute When stating vacuum layer construction, enclose on the side wall of the vacuum layer equipped with fixing piece, the inside of the fixing piece and the rectangular unthreaded hole Wall is bolted or is welded together.The insulating layer includes styrofoam, polyurethane foam and inorganic heat preservation Material.
Specifically, carrying out step 5 S105: when the construction of waterproof layer, the waterproof layer being laid in described fixed prop up The surface of frame and vacuum layer.
The above method is carrying out constructing operation by way of site operation.
In conjunction with shown in Fig. 2-4, the structure of above-mentioned exterior wall includes: wall 1, fixed bracket 2, insulating layer 3, vacuum layer 4 and prevents Water layer 5, wherein connector 6 is prefabricated on the wall 1, the connector 6 exposes the exterior wall of the wall 1;The fixed branch Frame 2 is connect with the connector 6, and to be fixed on the metope of the exterior wall, the fixed bracket 2 is along the setting side of the metope To being configured, the fixed bracket 2 is a square frame structure, is provided on the fixed bracket 2 several evenly distributed Rectangular unthreaded hole 7;The insulating layer 3 is laid on the metope in the rectangular unthreaded hole 7;The vacuum layer 4 is arranged described On the inner sidewall of rectangular unthreaded hole 7, and contacted with the insulating layer 3;The waterproof layer 5 is laid in the fixed bracket 2 and vacuum The surface of layer 4.
Specifically, vacuum layer 4 is preferably STP ultrathin heat insulation board.
As can be seen that while by the way that insulating layer 3 are arranged on the exterior wall of wall 1, then one layer of vacuum layer 4 is set and carries out room The heat-insulation and heat-preservation in room, so as to greatly reduce the thickness of house wall 1;Meanwhile by the way that fixed bracket 2 is arranged, also enhance Insulating layer 3 and vacuum layer 4 and 1 bonding strength of wall are using one so as to be effectively prevented insulating layer 3 and vacuum layer 4 The problem of being peeled off after fixing time, and causing safety accident, the security performance of the building of guarantee.Further, by protecting Vacuum layer 4 is set on the outside of warm layer 3, and vacuum layer 4 has very high fire resistance, so as to be effectively prevented fire When, there is the situation for burning on fire generation in insulating layer 3, improves the security performance in house.Further, by the way that insulating layer is arranged 3 and vacuum layer 4 also significantly reduce the thickness of house wall 1 while the thermal insulation property for improving house, reduce The use of construction material more effectively protects environment to save buildings and resources and building cost.
Specifically, offer first through hole on the side wall of the fixed bracket 2, the first through hole along with it is described rectangular The perpendicular direction setting of the setting direction of bracket, the first through hole is for wearing the connector 6 wherein.The fixation The second through-hole is also provided on the side wall of bracket 2, second through-hole is along perpendicular with the setting direction of the first through hole Direction setting.Connection bolt is equipped in second through-hole, the connection bolt is used for the fixed bracket 2 and insulating layer 3 link together.
It is made specifically, the fixed bracket 2 is mutually perpendicular to intersection welding by several square plates or rectangular steel tube. By several square plates, perhaps rectangular steel tube is mutually set up together and is bolted dry square plate or welds Or rectangular steel tube links together, to form a frame structure for having several rectangular unthreaded holes 7, that is, above-mentioned fixed branch is made Frame 2.
Specifically, being enclosed on the side wall of vacuum layer 4 equipped with fixing piece, the inside of the fixing piece and the rectangular unthreaded hole 7 Wall is bolted or is welded together.Fixing piece is preferably the metalwork of U-shaped structure, such as U-shaped steel, in vacuum Four kinds of layer 4 enclose the metalwork for setting U-shaped structure, set wherein so that vacuum layer 4 be enclosed, and the side of the metalwork in U-shaped structure Threaded hole is opened up on wall, the metalwork of U-shaped structure and fixed bracket 2 are connected to one by the connection bolt by passing through the second through-hole It rises.It is also possible that directly the metalwork of U-shaped structure and fixed bracket 2 are welded together.
Specifically, the size and shape of vacuum layer 4 and the size and shape of rectangular unthreaded hole 7 are oppositely arranged, vacuum layer 4 is answered When that can be placed on just in rectangular unthreaded hole 7, to reduce the gap between vacuum layer 4 and rectangular unthreaded hole 7.
Specifically, connector 6 is when wall 1 is poured or built with regard to the prefabricated predeterminated position in wall 1, connector 6 one end are plugged in wall 1, and the other end exposes exterior wall surface, and connector 6 and the position of first through hole are oppositely arranged, from And connector 6 is threaded through in first through hole, and then fixed bracket 2 is fixed on exterior wall surface.
Specifically, the connector 6 can be bolt or reinforcing bar.When connector 6 is bolt, bolt is threaded through the It in one through-hole, will be connected together between fixation with connector 6 by nut, when connector 6 is reinforcing bar, reinforcing bar be threaded through the In one through-hole, reinforcing bar and low pass hole are welded as a whole by welding, so that fixed bracket 2 is fixed on exterior wall table Face.
Specifically, the vacuum layer 4 is bonded together by way of bonding with the insulating layer 3, it is true to enhance The installation strength of dead level 4 is connect so that vacuum layer 4 is stronger with wall 1.
Specifically, insulating layer 3 includes styrofoam, polyurethane foam and inorganic heat insulation material.Insulating layer 3 passes through coating Mode, coated in all rectangular unthreaded holes 7.
Specifically, waterproof layer 5 is that waterproof material is formed by way of coating.Waterproof layer 5 is coated in fixed 2 He of bracket On the outer surface of vacuum layer 4, that is, waterproof layer 5 is coated in the outermost of exterior wall, and waterproof layer 5 can not only prevent wall 1 Water, additionally it is possible to effectively fill fixed bracket 2 and vacuum layer 4, and it is fixed between gap between exterior wall surface, it is anti-reaching The purpose of water is simultaneously, moreover it is possible to further improve heat insulation effect.
Specifically, fixed bracket 2 is identical as the size and shape of outer surface of wall, i.e., fixed bracket 2 covers entire exterior wall Metope.
It will be appreciated by persons skilled in the art that while by the way that insulating layer 3 are arranged on the exterior wall of wall 1, then set The heat-insulation and heat-preservation that one layer of vacuum layer 4 carries out house is set, so as to greatly reduce the thickness of house wall 1;Meanwhile by setting Fixed bracket 2 is set, insulating layer 3 and vacuum layer 4 and 1 bonding strength of wall are also enhanced, so as to be effectively prevented insulating layer 3 The problem of being peeled off after a certain period of use time with vacuum layer 4, and causing safety accident, the security performance of the building of guarantee. Further, by the way that vacuum layer 4 is arranged on the outside of insulating layer 3, and vacuum layer 4 has very high fire resistance, so as to When being effectively prevented fire generation, there is the situation for burning on fire generation in insulating layer 3, improves the security performance in house.Into one Step ground also significantly reduces house while the thermal insulation property for improving house by setting insulating layer 3 and vacuum layer 4 The thickness of wall 1, reduces the use of construction material, to save buildings and resources and building cost, more effectively protects ring Border.
Above-mentioned external wall structure is configured during engineering construction by field erected mode, by wall 1 Interior setting vacuum layer 4, or on the outside of wall 1 be arranged vacuum layer 4, by vacuum layer 4 be arranged thermal insulation layer match with into Row is heat-insulated, and vacuum layer 4, which improves heat-insulating capability, reduces 1 thickness of wall, further also improves the efficiency of construction.
Obviously, various changes and modifications can be made to the invention without departing from essence of the invention by those skilled in the art Mind and range.In this way, if these modifications and changes of the present invention belongs to the range of the claims in the present invention and its equivalent technologies Within, then the present invention is also intended to include these modifications and variations.

Claims (10)

1. the construction method that a kind of in-site installation is provided with vacuum type insulating layer exterior wall characterized by comprising
The construction of wall, the prefabricated connector on the wall, the connector expose the exterior wall surface in the wall;
The fixed bracket is connect by support bracket fastened construction with the connector, to be fixed on the metope of the exterior wall, institute The setting direction that fixed bracket is stated along the metope is configured, and the fixed bracket is a square frame structure, the fixation Several evenly distributed rectangular unthreaded holes are provided on bracket;
The insulating layer is laid on the metope in the rectangular unthreaded hole by the construction of insulating layer;
The construction of vacuum layer the vacuum layer is arranged on the inner sidewall of the rectangular unthreaded hole, and contact with the insulating layer;
The waterproof layer is laid in the surface of the fixed bracket and vacuum layer by the construction of waterproof layer.
2. the construction method that in-site installation according to claim 1 is provided with vacuum type insulating layer exterior wall, which is characterized in that When carrying out the fixed rack construction, offer first through hole on the support bracket fastened side wall, the first through hole along with The perpendicular direction setting of the setting direction of the square set, the first through hole is for wearing the connector wherein.
3. the construction method that in-site installation according to claim 2 is provided with vacuum type insulating layer exterior wall, which is characterized in that When carrying out the fixed rack construction, the second through-hole, second through-hole edge are also provided on the support bracket fastened side wall It is arranged with the perpendicular direction of the setting direction of the first through hole.
4. the construction method that in-site installation according to claim 3 is provided with vacuum type insulating layer exterior wall, which is characterized in that When carrying out the fixed rack construction, connection bolt is equipped in second through-hole, the connection bolt is used for will be described Fixed bracket links together with the vacuum layer.
5. the construction method that in-site installation according to claim 1 is provided with vacuum type insulating layer exterior wall, which is characterized in that When carrying out the fixed rack construction, the fixed bracket is mutually perpendicular to intersection weldering by several square plates or rectangular steel tube It connects and is made.
6. the construction method that in-site installation according to claim 1 is provided with vacuum type insulating layer exterior wall, which is characterized in that By being bonded together with the insulating layer for the vacuum layer.
7. the construction method that in-site installation according to claim 1 is provided with vacuum type insulating layer exterior wall, which is characterized in that When carrying out vacuum layer construction, enclose on the side wall of the vacuum layer equipped with fixing piece, the fixing piece and the square light The inner sidewall in hole is bolted or is welded together.
8. the construction method that in-site installation according to claim 1 is provided with vacuum type insulating layer exterior wall, which is characterized in that The insulating layer includes styrofoam, polyurethane foam and inorganic heat insulation material.
9. the construction method that in-site installation according to claim 1 is provided with vacuum type insulating layer exterior wall, which is characterized in that The vacuum layer includes STP ultrathin heat insulation board.
10. -9 described in any item in-site installations are provided with the construction method of vacuum type insulating layer exterior wall according to claim 1, It is characterized in that, the connector is bolt or reinforcing bar.
CN201910093285.0A 2019-01-30 2019-01-30 In-site installation is provided with the construction method of vacuum type insulating layer exterior wall Pending CN109779048A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910093285.0A CN109779048A (en) 2019-01-30 2019-01-30 In-site installation is provided with the construction method of vacuum type insulating layer exterior wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910093285.0A CN109779048A (en) 2019-01-30 2019-01-30 In-site installation is provided with the construction method of vacuum type insulating layer exterior wall

Publications (1)

Publication Number Publication Date
CN109779048A true CN109779048A (en) 2019-05-21

Family

ID=66503809

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910093285.0A Pending CN109779048A (en) 2019-01-30 2019-01-30 In-site installation is provided with the construction method of vacuum type insulating layer exterior wall

Country Status (1)

Country Link
CN (1) CN109779048A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112459284A (en) * 2020-11-19 2021-03-09 山东高速齐鲁建设集团有限公司 Construction method of composite heat-insulating layer

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205100395U (en) * 2015-11-05 2016-03-23 孙丽 Building sound insulation fire prevention heat preservation outer wall
CN205840013U (en) * 2016-07-04 2016-12-28 高洁 A kind of external heat insulation board device of civil construction project
CN106677358A (en) * 2017-02-23 2017-05-17 李淑娟 Framework for construction heat preservation wall body
CN206346337U (en) * 2016-12-27 2017-07-21 潍坊亨利达钢结构有限公司 A kind of assembled lightgage steel joist
CN207245163U (en) * 2017-09-01 2018-04-17 天津德曼瑞克科技有限公司 A kind of aluminium frame Wood-plastic formwork with insulating layer
CN207892079U (en) * 2018-01-25 2018-09-21 张湘南 A kind of thermal-insulating waterproof wall apparatus

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205100395U (en) * 2015-11-05 2016-03-23 孙丽 Building sound insulation fire prevention heat preservation outer wall
CN205840013U (en) * 2016-07-04 2016-12-28 高洁 A kind of external heat insulation board device of civil construction project
CN206346337U (en) * 2016-12-27 2017-07-21 潍坊亨利达钢结构有限公司 A kind of assembled lightgage steel joist
CN106677358A (en) * 2017-02-23 2017-05-17 李淑娟 Framework for construction heat preservation wall body
CN207245163U (en) * 2017-09-01 2018-04-17 天津德曼瑞克科技有限公司 A kind of aluminium frame Wood-plastic formwork with insulating layer
CN207892079U (en) * 2018-01-25 2018-09-21 张湘南 A kind of thermal-insulating waterproof wall apparatus

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112459284A (en) * 2020-11-19 2021-03-09 山东高速齐鲁建设集团有限公司 Construction method of composite heat-insulating layer
CN112459284B (en) * 2020-11-19 2021-08-20 山东高速齐鲁建设集团有限公司 Construction method of composite heat-insulating layer

Similar Documents

Publication Publication Date Title
CN106320574A (en) Light-gauge steel joist composite concrete wallboard
CN203361380U (en) Ultra-thin efficient composite heat preservation template of permanent cast-in-place concrete
CN105839782B (en) Modularized house
CN108824648A (en) Space module house
CN105133729B (en) A kind of special-shaped beam column steel frame with battenboard and its construction method
CN109235708A (en) A kind of assembled heat insulation decoration and structure-integrated wall and its prepare mounting process
CN209958534U (en) Low-energy-consumption energy-saving building system
CN109779048A (en) In-site installation is provided with the construction method of vacuum type insulating layer exterior wall
CN208981643U (en) A kind of prefabricated composite exterior wall of assembled light steel skeleton
CN202577654U (en) Concrete-covered wall supporting structure of prefabricated part of heat insulating sandwich wall
CN109779047A (en) Assembled vacuum heat preserving exterior wall
CN206189771U (en) A protect mould integration board for building external thermal insulation system
CN209891589U (en) Gutter waterproof node structure in prefabricated roofing of assembled
CN107035027A (en) A kind of assembled steel reinforced concrete structure light wt compound external wall panel
CN109779073A (en) Pass through the field erected exterior wall for being provided with vacuum type insulating layer
CN216475593U (en) Big board outer wall structure node with girder steel floor whole pouring
CN212689293U (en) Effectual steel construction outer wall insulates against heat and gives sound insulation
CN206752827U (en) A kind of steel wire net rack mortar sandwich STP heat-insulating plate structure integrated plate for heat insulation
CN114319643A (en) Green type external thermal insulation wall structure
CN217580673U (en) Building heat preservation and structure integrated energy-saving heat preservation wall structure
CN107882256A (en) A kind of construction method of heat bridge partition-type containment system
CN109779069A (en) The construction method of assembled vacuum heat preserving exterior wall
CN210439472U (en) Assembled outer wall structure with vacuum waterproof layer
CN210459594U (en) Assembled vacuum heat-insulation external wall
CN109779041A (en) It is provided with the external wall structure of vacuum waterproof layer

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190521