CN109767099A - A kind of maintenance project project base construction method - Google Patents

A kind of maintenance project project base construction method Download PDF

Info

Publication number
CN109767099A
CN109767099A CN201811631406.4A CN201811631406A CN109767099A CN 109767099 A CN109767099 A CN 109767099A CN 201811631406 A CN201811631406 A CN 201811631406A CN 109767099 A CN109767099 A CN 109767099A
Authority
CN
China
Prior art keywords
project
maintenance
option
library
resource
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811631406.4A
Other languages
Chinese (zh)
Inventor
张晨
曹江
卢杨
常成利
李娟�
王�锋
杨鑫
赵恒�
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHONGGONG HI-TECH CONSERVATION TECHNOLOGY CO LTD
Original Assignee
ZHONGGONG HI-TECH CONSERVATION TECHNOLOGY CO LTD
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHONGGONG HI-TECH CONSERVATION TECHNOLOGY CO LTD filed Critical ZHONGGONG HI-TECH CONSERVATION TECHNOLOGY CO LTD
Priority to CN201811631406.4A priority Critical patent/CN109767099A/en
Publication of CN109767099A publication Critical patent/CN109767099A/en
Pending legal-status Critical Current

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention provides a kind of maintenance project project library Component, is related to database technical field.Maintenance project project library Component provided by the invention includes: the composition range for obtaining maintenance project project library to be built;Resource is distributed for the maintenance project project library to be built, the capacity of the maintenance project project library to be built according to the resource acquisition;According to pre-selection criteria, multiple pre- option of the maintenance project project library to be built are obtained;Resource quantity needed for obtaining each pre- option;According to screening conditions, all pre- option are screened;According to resource quantity and the resource needed for the selection result, the corresponding each pre- option of the selection result, maintenance project project library is constructed.Technical solution of the present invention can construct the maintenance project project library of road maintenance engineering adaptation, allow and utmostly meet all requirements such as maintenance demand, limited fund, returns of investment according to the maintenance project project library project implementation.

Description

A kind of maintenance project project base construction method
Technical field
The present invention relates to database technical field more particularly to a kind of maintenance project project base construction methods.
Background technique
In road maintenance management, maintenance theory just from " be broken and repair again " to " preventive maintenance " changes, policymaker's demand Understand Maintenance Project of Highway plan of needs situation in following certain time section, regularly to combine maintenance policy, support Shield fund etc. is practical, and science decision mid-term conserves investment planning.
Road maintenance engineering refers to the pavement maintenaince for concentrating whithin a period of time and implementing and being managed according to project, But will be from the pipe maintenance division of substantial amounts and Decision Making Effect factor complexity, maintenance need can utmostly be met by filtering out Ask, the project of all requirements such as limited fund, returns of investment is executed, be a complexity and there is very high practical value Problem.
Summary of the invention
The present invention provides a kind of maintenance project project base construction method, can construct the maintainer of road maintenance engineering adaptation Journey project library allows and utmostly meets maintenance demand, limited fund, throwing according to the maintenance project project library project implementation Provide all requirements such as benefit.
The present invention provides a kind of maintenance project project base construction method, adopts the following technical scheme that
The maintenance project project base construction method includes:
Obtain the composition range of maintenance project project library to be built;
Resource, the maintenance project to be built according to the resource acquisition are distributed for the maintenance project project library to be built The capacity of project library;
According to pre-selection criteria, multiple pre- option of the maintenance project project library to be built are obtained;
Resource quantity needed for obtaining each pre- option;
According to screening conditions, all pre- option are screened;
According to resource quantity and the resource needed for the selection result, the corresponding each pre- option of the selection result, Construct maintenance project project library.
Optionally, the maintenance project project library to be built includes first item group and second item group.
Optionally, described to distribute resource for the maintenance project project library to be built, according to the resource acquisition to The capacity of building maintenance project project library includes: to distribute resource for the first item group, according to the resource acquisition of distribution The capacity of first item group;Resource, the second item group according to the resource acquisition of distribution are distributed for the second item group Capacity.
Optionally, described according to pre-selection criteria, obtain multiple pre- option packets of the maintenance project project library to be built It includes: obtaining the multiple first pre- option for meeting first condition, and obtain the multiple second pre- option for meeting second condition, The first pre- option is corresponding with the first item group, and the second pre- option is corresponding with the second item group.
Further, described to obtain the multiple first pre- option for meeting first condition, and obtain and meet second condition The multiple second pre- option include: the first parameter, the second parameter and third parameter according to project, whether judge the project Meet the first condition or the second condition, multiple first pre-selections for meeting first condition are obtained according to judging result Project, and obtain the multiple second pre- option for meeting second condition.
Further, described according to screening conditions, carrying out screening to all pre- option includes: according to described first Parameter is ranked up the multiple first pre- option, and according to the first screening conditions to the multiple first after sequence Pre- option is screened, and the first the selection result is obtained.
Further, described according to screening conditions, all pre- option are screened further include: pre- according to second Mapping relations between option and priority level determine the corresponding priority level of each second pre- option;According to the 4th Parameter is ranked up in the other multiple second pre- option of same priority.
Further, described according to screening conditions, all pre- option are screened further include: according to second Mapping relations between pre- option and priority level, before determining the corresponding priority level of each second pre- option, root According to the 5th parameter, each second pre- option is retained, is merged or delete processing.
Further, described according to the 5th parameter, each second pre- option is retained, is merged or delete processing Include:
The described second pre- option that 5th parameter is greater than or equal to preset value is retained;
Executing subject is identical, and the 5th parameter is less than the preset value and continuous multiple second pre- option, closes It and is a second new pre- option;
5th parameter is less than the preset value, and the second scattered pre-selection deletion of items.
Optionally, described to comprise determining that the maintenance to be built for the maintenance project project library distribution resource to be built The executing subject in engineering project library;It is the maintainer to be built according to the mapping relations of the executing subject and the resource Journey project library distributes resource.
The present invention provides a kind of maintenance project project base construction method, which includes: Obtain the composition range of maintenance project project library to be built;Resource is distributed for the maintenance project project library to be built, according to institute State the capacity of maintenance project project library to be built described in resource acquisition;According to pre-selection criteria, the maintenance project to be built is obtained Multiple pre- option of project library;Resource quantity needed for obtaining each pre- option;According to screening conditions, to all described pre- Option is screened;According to resource quantity and institute needed for the selection result, the corresponding each pre- option of the selection result Resource is stated, maintenance project project library is constructed.It is suitable that road maintenance engineering can be constructed using the maintenance project project base construction method The maintenance project project library answered, allow according to the maintenance project project library project implementation utmostly meet maintenance demand, The all requirements such as limited fund, returns of investment.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below There is attached drawing needed in technical description to be briefly described, it should be apparent that, the accompanying drawings in the following description is this hair Bright some embodiments for those of ordinary skill in the art without any creative labor, can be with It obtains other drawings based on these drawings.
Fig. 1 is the flow chart of maintenance project project base construction method provided in an embodiment of the present invention.
Specific embodiment
In order to make the object, technical scheme and advantages of the embodiment of the invention clearer, below in conjunction with the embodiment of the present invention In attached drawing, technical scheme in the embodiment of the invention is clearly and completely described, it is clear that described embodiment is A part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, those of ordinary skill in the art Every other embodiment obtained without making creative work, shall fall within the protection scope of the present invention.
It should be noted that each technical characteristic in the embodiment of the present invention can be tied mutually in the absence of conflict It closes.
The embodiment of the invention provides a kind of maintenance project project base construction methods, and specifically, as shown in FIG. 1, FIG. 1 is this The flow chart for the maintenance project project base construction method that inventive embodiments provide, the maintenance project project base construction method include:
Step S1, the composition range of maintenance project project library to be built is obtained;
Maintenance project project library to be built includes first item group and second item group.To construct road maintenance engineering adaptation Maintenance project project library for, need to be included in maintenance project project library to be built maintenance project project be divided into prosthetic maintenance item Mesh group (i.e. second item group) and preventive maintenance project team (i.e. first item group), wherein prosthetic maintenance project team can divide For overhaul and Zhong Xiuliangge group.
Step S2, resource is distributed for maintenance project project library to be built, according to resource acquisition maintenance project project to be built The capacity in library;
Optionally, resource is distributed for maintenance project project library to be built comprise determining that maintenance project project library to be built Executing subject;According to the mapping relations of executing subject and resource, resource is distributed for maintenance project project library to be built.
For the maintenance project project library that building road maintenance engineering adapts to, which can be fund.According to executing master The average annual maintenance project subsidy fund overall control principle of body (highway administration organ and highway operation enterprise etc.), determines to be built support The capacity of nurse's journey project library, different executing subjects can according to actual conditions set maintenance project subsidy fund control number C and on Lower floating number α, i.e., the capacity limited fund of maintenance project project library to be built are C ± α.
It include that first item group and second item group are optionally supported to be to be built based on maintenance project project library to be built Nurse's journey project library distributes resource, and the capacity according to resource acquisition maintenance project project library to be built includes: for first item group Resource is distributed, according to the capacity of the resource acquisition first item group of distribution;Resource is distributed for second item group, according to the money of distribution The capacity of source acquisition second item group.
Step S3, according to pre-selection criteria, multiple pre- option of maintenance project project library to be built are obtained;
It include first item group and second item group based on maintenance project project library to be built, step S3 may include: to obtain The the multiple first pre- option for meeting first condition are taken, and obtain the multiple second pre- option for meeting second condition, first Pre- option is corresponding with first item group, and the second pre- option is corresponding with second item group.
Further, the multiple first pre- option for meeting first condition are obtained, and obtains and meets the more of second condition A second pre- option includes: the first parameter, the second parameter and third parameter according to project, judges whether project meets first Condition or second condition obtain the multiple first pre- option for meeting first condition according to judging result, and obtain and meet Multiple second pre- option of second condition.
For the maintenance project project library that building road maintenance engineering adapts to, the purpose of step S3 is to maintenance project road Section demand is analyzed, and maintenance demand analysis, merely from road conditions angle, is being referred in the case where not considering limited fund Under the conditions of determining maintenance criteria, maintenance analysis on Necessity is carried out to road network.
It can be according to executing subject when each section Evaluation of Highway Technology Status result of the year before last state provincial highway network of highways, maintenance criteria And correlation model, it carries out maintenance project project library and plans year [N0+1~N0+x] the highway condition evaluation result in each year calculates, with Determine the maintenance of road network prosthetic and the distribution of preventive maintenance engineering demand section.Above-described correlation model may include maintenance Decision model, performance prediction model, maintenance costs model, priority ordering model, pavement structural strength prediction model etc..
Wherein it is possible to for by carrying out calibration analysis to analysis personnel road conditions detailed data over the years, by different road surface classes Type, surface thickness, the volume of traffic and road age etc. establish the performance prediction model for being suitable for the common arterial highway of analysis personnel, are road Face management system and Highway Comprehensive decision support system provide pavement technique situation performance prediction method.
Specifically, medium-capital overhauling maintenance project standard (i.e. second condition): for pavement damage PCI (the first parameter) or flatness RQI (the second parameter) single index is lower than 85 points of section, implements medium-capital overhauling maintenance project.Be specifically based on pavement damage PCI and Flatness RQI evaluation result carries out pavement structural strength PSSI (third parameter) index by pavement structural strength prediction model Prediction, for prediction, (Class I highway PSSI < 83 divides, second level and following level highway PSSI in pavement structural strength deficiency section < 70 divides) implement overhaul maintenance project, for predicting the section of road surface result intensity abundance, maintenance project is repaired in implementation.
Preventive maintenance engineering specification (i.e. first condition): preventive maintenance project section is only for pavement structural strength (Class I highway predicts pavement structural strength PSSI >=83 to PSSI, and second level and following level highway predict pavement structural strength enough PSSI >=70), flatness RQI >=90, the bituminous pavement sections of pavement damage PCI >=85 carries out preventive maintenance engineering.
Wherein it is possible to predict the structural strength PSSI in each section by " NetPMS pavement management system ", made with this For the foundation of medium-capital overhauling Maintenance Decision making.
Step S4, resource quantity needed for obtaining each pre- option;
The maintenance costs of the common arterial highway of executing subject, including different zones, different technologies standard highway can be investigated Maintenance plan and expense, provide foundation for maintenance of surface demand and fee calculating.Common arterial highway is saved the following table is certain to support Nurse Cheng Sheng mends exemplary standard.
Certain saves common arterial highway maintenance project and saves benefit standard
Step S5, according to screening conditions, all pre- option are screened;
According to screening conditions, carrying out screening to all pre- option includes: according to the first parameter to the multiple first pre- options Mesh is ranked up, and is screened according to the first screening conditions to the multiple first pre- option after sequence, and the first sieve is obtained Select result.
Specifically, according to preventive maintenance forecast in the maintenance demand analysis of executing subject state provincial highway network of highways section As a result, host country provincial highway preventive maintenance engineering section project constitutes Item Sets Up, according to UpIn each section pavement damage PCI by It is small to arrive big sequence rank { Up, existed with executing subject preventive maintenance engineering construction mileage accounting (i.e. the first screening conditions) Mpro% is that (Mpro >=5 meet in Department of Transportation " highway maintenance management development outline ", and common state's provincial highway is preventative for control Conserve the requirement that implementation ratio is not less than 5%), it successively chooses, the preventative of maintenance project maintenance project project library is included in determination Maintenance project section project rank { Up_Mpro, correspond to preventive maintenance engineering total cost C in maintenance project project libraryp_Mpro
According to screening conditions, all pre- option are screened further include: according to the second pre- option and priority level Between mapping relations, determine the corresponding priority level of each second pre- option;According to the 4th parameter in same priority Other multiple second pre- option are ranked up.
Specifically, conserving forecast according to prosthetic in the maintenance demand analysis of executing subject state provincial highway network of highways section As a result, host country provincial highway prosthetic maintenance project section project constitutes Item Sets Ur, this method is according to section management attribute and skill Two level of art attribute establishes two stages prosthetic maintenance project decision optimization maintenance project project library screening technique.
First stage project screening carries out Preliminary division to Item Sets Ur according to " maintenance section management attribute " condition, is formed A, totally 4 class highway section Maintenance Decision making Optimal schedulings combine by B, C, D.Section management attribute is conserved to combine to the inspection of highway technology situation Assessment provisioning request divides maintenance project project section, and A class-state's inspection may extract section, B class-state in two years before the year before last Inspection supervisor section, C class-residue state road segment segment and D class-rank of province's road segment segment four, UrDivision forms Ur_A、Ur_B、 Ur_C、Ur_D Four sequence combinations, maintenance project priority successively reduce.
Second stage complex optimum considers in projects combination that " maintenance section technical attributes " optimize decision, proposes public Road maintenance level indices PMaintenance level index, i.e. the 4th parameter, according to PMaintenance level indexSize priority ordering determine maintenance project priority. PMaintenance level indexMeasuring and calculating based on it is each maintenance section i Pavement Performance PQI evaluation result or performance prediction result, the volume of traffic (AADT) and road age (Y) respectively according to 30%, 30% and 40% Weight Measurement.
Specifically, PMaintenance level index _ i=30%*PQI+30%*AADT+40%*Y
It is above-mentioned, based on management, supplemented by technology, by technical attributes on the basis of management attribute is preferential “PMaintenance level index" sort from high to low, form new Item Sets rank { Ur_A、Ur_B、Ur_C、 Ur_D, carry out maintenance project project library Optimal Decision-making screens, each prosthetic maintenance project Project Cost C in Item SetsR_p maintenance level index,
It is limitation (C with the average annual prosthetic maintenance project fund of analysis personnelr=C ± α-Cp_Mpro), according to Item Sets rank {Ur_A、Ur_B、Ur_C、Ur_DIn maintenance project project section priority ranking, be successively included in annual maintenance engineering maintenance project item Mesh library, until(the prosthetic maintenance project ranked items section number that m is screening storage) reaches and works as Year prosthetic maintenance project fund limitation CrUntil, that is, it is included in the prosthetic maintenance project maintenance project item of maintenance project project library Mesh library integrates as rank { Ur_m|Ur_A、Ur_B、Ur_C、Ur_D}。
Further, according to screening conditions, all pre- option are screened further include: according to the second pre- option Mapping relations between priority level are right according to the 5th parameter before determining the corresponding priority level of each second pre- option Each second pre- option retained, is merged or delete processing.
Further, according to the 5th parameter, each second pre- option is retained, merged or deleted include:
The second pre- option that 5th parameter is greater than or equal to preset value is retained;
Executing subject is identical, and the 5th parameter is less than preset value and continuous multiple second pre- option, merges into one The pre- option of new second;
5th parameter is less than preset value, and the second scattered pre-selection deletion of items.
Specifically, the setting continuous combination principle in prosthetic maintenance project section, sets to continuous length (the 5th parameter) >=l The same maintenance project project (section after merging does not change medium-capital overhauling maintenance property), continuous length are merged into the section of km Scattered section less than l km is rejected, i.e., the engineering construction mileage of each prosthetic project is no less than l kilometers, and pile No. is continuous but feeding The inconsistent section of pipe unit cannot then merge." l " conserves practical determine according to it by different analysis personnels.Preventive maintenance road Section nonjoinder, using 1km as project implementation mileage unit.
Wherein, the project section P after the 1~n project subsections mergenceMaintenance level indexTake each section PMaintenance level index _ iAverage value, I.e.
Wherein, n >=l.
Step S6, resource quantity and resource according to needed for the selection result, the selection result corresponding each pre- option, building are supported Nurse's journey project library.
Finally, determining maintenance project maintenance project project library includes rank { Up_Mpro}∪rank{Ur_m| Ur_A、Ur_B、 Ur_C、Ur_D}。
The embodiment of the invention provides a kind of maintenance project project base construction method, the maintenance project project base construction methods It include: the composition range for obtaining maintenance project project library to be built;Resource, root are distributed for the maintenance project project library to be built According to the capacity of maintenance project to be built project library described in the resource acquisition;According to pre-selection criteria, the maintenance to be built is obtained Multiple pre- option in engineering project library;Resource quantity needed for obtaining each pre- option;According to screening conditions, to all institutes Pre- option is stated to be screened;According to resource quantity needed for the selection result, the corresponding each pre- option of the selection result With the resource, maintenance project project library is constructed.Highway maintenance work can be constructed using the maintenance project project base construction method The maintenance project project library of Cheng Shiying allows and utmostly meets maintenance need according to the maintenance project project library project implementation It asks, all requirements such as limited fund, returns of investment.
In this way, the embodiment of the present invention carries out depth analysis utilization to state's provincial highway highway maintenance demand analysis and the result of decision, It establishes a set of can optimize according to maintenance section performance condition, demand analysis, limited fund situation and administrative decision to require, and relies on Information system carrys out state's provincial highway road maintenance engineering maintenance project project library system of intelligent selection optimum portfolio, supports to specification Nurse's journey maintenance project project library is established and scientific management is of great significance, and has practical value in engineering practice, and will This kind of method saves in the investment maintenance project project library foundation of next three years road maintenance engineering using Mr. Yu, current based on the province On the basis of the common Trunk highway highway foundation database of year (2018) the whole province and Decision making for pavement maintenance model, in conjunction with the whole province The actual conditions such as common Trunk highway maintenance policy, maintenance fund finally propose 2019~2,021 3 years using the method for the present invention Maintenance invest Rolling Planning suggestion.
Maintenance project project base construction method provided in an embodiment of the present invention can pass through computer, server, intelligent hand Machine, intelligent terminal etc. execute, be stored in the various storage mediums such as ROM, RAM, hard disk, the embodiment of the present invention without It limits.
Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention., rather than its limitations;To the greatest extent Pipe present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that: its according to So be possible to modify the technical solutions described in the foregoing embodiments, or to some or all of the technical features into Row equivalent replacement;And these are modified or replaceed, various embodiments of the present invention technology that it does not separate the essence of the corresponding technical solution The range of scheme.

Claims (10)

1. a kind of maintenance project project base construction method characterized by comprising
Obtain the composition range of maintenance project project library to be built;
Resource, the maintenance project project to be built according to the resource acquisition are distributed for the maintenance project project library to be built The capacity in library;
According to pre-selection criteria, multiple pre- option of the maintenance project project library to be built are obtained;
Resource quantity needed for obtaining each pre- option;
According to screening conditions, all pre- option are screened;
According to resource quantity and the resource needed for the selection result, the corresponding each pre- option of the selection result, building Maintenance project project library.
2. maintenance project project base construction method according to claim 1, which is characterized in that the maintenance project to be built Project library includes first item group and second item group.
3. maintenance project project base construction method according to claim 2, which is characterized in that described is described to be built feeding Nurse's journey project library distributes resource, and the capacity of the maintenance project project library to be built according to the resource acquisition includes: for institute State first item group distribution resource, the capacity of first item group according to the resource acquisition of distribution;For the second item group Distribute resource, the capacity of second item group according to the resource acquisition of distribution.
4. maintenance project project base construction method according to claim 2, which is characterized in that it is described according to pre-selection criteria, The multiple pre- option for obtaining the maintenance project project library to be built include: to obtain multiple first pre-selections for meeting first condition Project, and obtain the multiple second pre- option for meeting second condition, the first pre- option and the first item group Corresponding, the second pre- option is corresponding with the second item group.
5. maintenance project project base construction method according to claim 4, which is characterized in that the acquisition meets first Multiple first pre- option of part, and obtain meet second condition the multiple second pre- option include: according to project the One parameter, the second parameter and third parameter, judge whether the project meets the first condition or the second condition, The the multiple first pre- option for meeting first condition are obtained according to judging result, and are obtained and met multiple the second of second condition Pre- option.
6. maintenance project project base construction method according to claim 5, which is characterized in that it is described according to screening conditions, Carrying out screening to all pre- option includes: to be arranged according to first parameter the multiple first pre- option Sequence, and the multiple first pre- option after sequence is screened according to the first screening conditions, obtain the first screening knot Fruit.
7. maintenance project project base construction method according to claim 6, which is characterized in that it is described according to screening conditions, All pre- option are screened further include: according to the mapping relations between the second pre- option and priority level, really The corresponding priority level of fixed each second pre- option;According to the 4th parameter in same priority other multiple described the Two pre- option are ranked up.
8. maintenance project project base construction method according to claim 7, which is characterized in that it is described according to screening conditions, All pre- option are screened further include: according to the mapping relations between the second pre- option and priority level, Before determining the corresponding priority level of each second pre- option, according to the 5th parameter, to each second pre- option into Row reservation, merging or delete processing.
9. maintenance project project base construction method according to claim 8, which is characterized in that it is described according to the 5th parameter, Each second pre- option is retained, is merged or delete processing includes:
The described second pre- option that 5th parameter is greater than or equal to preset value is retained;
Executing subject is identical, and the 5th parameter is less than the preset value and continuous multiple second pre- option, merges into One the second new pre- option;
5th parameter is less than the preset value, and the second scattered pre-selection deletion of items.
10. maintenance project project base construction method according to claim 1, which is characterized in that described is described to be built Maintenance project project library distribution resource comprises determining that the executing subject of the maintenance project project library to be built;It is held according to described The mapping relations of row main body and the resource distribute resource for the maintenance project project library to be built.
CN201811631406.4A 2018-12-28 2018-12-28 A kind of maintenance project project base construction method Pending CN109767099A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811631406.4A CN109767099A (en) 2018-12-28 2018-12-28 A kind of maintenance project project base construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811631406.4A CN109767099A (en) 2018-12-28 2018-12-28 A kind of maintenance project project base construction method

Publications (1)

Publication Number Publication Date
CN109767099A true CN109767099A (en) 2019-05-17

Family

ID=66452284

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811631406.4A Pending CN109767099A (en) 2018-12-28 2018-12-28 A kind of maintenance project project base construction method

Country Status (1)

Country Link
CN (1) CN109767099A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114819212A (en) * 2022-04-14 2022-07-29 东南大学 Dynamic partitioning method for asphalt pavement maintenance road section considering spatial continuity

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102402510A (en) * 2010-09-09 2012-04-04 金蝶软件(中国)有限公司 Method and system for constructing service pattern library
CN106682257A (en) * 2016-11-16 2017-05-17 上海建工集团股份有限公司 Construction facility BIM component library construction method
CN107153928A (en) * 2017-06-28 2017-09-12 江苏智通交通科技有限公司 Visual highway maintenance decision system

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102402510A (en) * 2010-09-09 2012-04-04 金蝶软件(中国)有限公司 Method and system for constructing service pattern library
CN106682257A (en) * 2016-11-16 2017-05-17 上海建工集团股份有限公司 Construction facility BIM component library construction method
CN107153928A (en) * 2017-06-28 2017-09-12 江苏智通交通科技有限公司 Visual highway maintenance decision system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114819212A (en) * 2022-04-14 2022-07-29 东南大学 Dynamic partitioning method for asphalt pavement maintenance road section considering spatial continuity
CN114819212B (en) * 2022-04-14 2023-02-14 东南大学 Dynamic partitioning method for asphalt pavement maintenance road section considering spatial continuity

Similar Documents

Publication Publication Date Title
KR101705247B1 (en) System for performance measurement of social infrastructure, and method for the same
CN113255811B (en) BIM-based beam bridge multi-source heterogeneous data fusion decision system
Miliotis et al. A hierarchical location model for locating bank branches in a competitive environment
Lathrop et al. An Opportunity-Accessieility Model for Allocating Regional Growth
CN106682809A (en) Enterprise BIM technology application capability quantification assessment method
CN109636137A (en) Electric automobile charging station planning and distributing method and system based on step analysis
CN111612294A (en) City physical examination system based on space-time big data
CN111125286A (en) Intelligent highway comprehensive management platform based on traffic big data
CN107292484A (en) The recognition methods of urban redevelopment soil and system based on city space big data
CN103761618A (en) Control method and system of science and technology item
CN109829607A (en) A kind of integrated evaluating method of Sustainable Development for Urban Traffic System
CN108921425A (en) A kind of method, system and the server of asset item classifcation of investment
Li et al. The functional assessment of agricultural ecosystems in Hubei Province, China
CN109767099A (en) A kind of maintenance project project base construction method
CN109829658A (en) A kind of parking position distribution method based on different crowd demand
CN109948957A (en) A kind of town road net grade Maintenance Design aid decision-making system
Gu et al. Enhancing market service and enterprise operations through a large-scale GIS-based distribution system
Kerali et al. Role of the new HDM-4 in highway management
Sun et al. An AHP-Fuzzy comprehensive evaluation model for parking lots in urban CBD area
CN109948926A (en) A kind of highway concrete-bridge maintenance technology Selection Method based on project period
CN113723719B (en) Distribution transformation-based near-intermediate load prediction method, device, equipment and medium
Huang et al. Modeling Agricultural Logistics Distribution Center Location Based on ISM.
Kadar et al. The Impact of various maintenance strategies on unsealed road deterioration to achieve an acceptable maintenance budget & road performance
CN109299971A (en) A kind of optimal bread under random distribution is supplied method and system
CN110196916B (en) Road type identification method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190517

RJ01 Rejection of invention patent application after publication