CN109763513A - A kind of anchor cable lattice and the compound retaining structure of Modified soil retaining wall and its construction method - Google Patents

A kind of anchor cable lattice and the compound retaining structure of Modified soil retaining wall and its construction method Download PDF

Info

Publication number
CN109763513A
CN109763513A CN201811507824.2A CN201811507824A CN109763513A CN 109763513 A CN109763513 A CN 109763513A CN 201811507824 A CN201811507824 A CN 201811507824A CN 109763513 A CN109763513 A CN 109763513A
Authority
CN
China
Prior art keywords
construction
slot
retaining wall
anchor cable
depth
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811507824.2A
Other languages
Chinese (zh)
Other versions
CN109763513B (en
Inventor
刘龙武
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changsha University of Science and Technology
Original Assignee
Changsha University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changsha University of Science and Technology filed Critical Changsha University of Science and Technology
Priority to CN201811507824.2A priority Critical patent/CN109763513B/en
Publication of CN109763513A publication Critical patent/CN109763513A/en
Application granted granted Critical
Publication of CN109763513B publication Critical patent/CN109763513B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses a kind of anchor cable lattices and the compound retaining structure of Modified soil retaining wall and its construction method, a kind of anchor cable lattice and the compound retaining structure of Modified soil retaining wall includes anchor cable lattice and two parts of Modified soil retaining wall, wherein Modified soil retaining wall provides basic horizontal direction supporting and retaining system power, anchor cable lattice then provides the insufficient part of horizontal in retaining wall top to supporting and retaining system power, is a kind of new construction of alternative friction pile anchor cable composite construction.The construction method of a kind of anchor cable lattice and the compound retaining structure of Modified soil retaining wall disclosed by the invention, fast, low cost, the advantage that construction method is simple and working security is good with speed of application, particularly suitable for the reinforcing for the double-decked slope that culm and residual soil slope form.

Description

A kind of anchor cable lattice and the compound retaining structure of Modified soil retaining wall and its construction method
Technical field
The present invention relates to a kind of anchor cable lattices and the compound retaining structure of Modified soil retaining wall, especially relate to a kind of anchor The construction method of rope lattice and the compound retaining structure of Modified soil retaining wall.
Background technique
With the large-scale railway in China, the high speed development of highway and real estate construction, some rare special soils side slopes Problem is also increasingly appearing in side slope consolidation projects.In south China, it is formed due to culm and residual soil slope Double-decked slope it is widely distributed, when the interface such side slope Tu Yan has local perched water underground water and is bedding rock sloper When, under the effect of drying and watering cycle repeatedly of perched water, the interface of severely-weathered shale and residual soil slope can gradually inundated intenerating, formed Secondary Soft Soil Layer of a layer thickness in 0.1m ~ 1.0m or so.Due to the secondary Soft Soil Layer Forming Mechanism and the regularity of distribution lack Weary research is difficult to be found in practical prospecting process, therefore, slope earth-retaining wall destruction is caused to happen occasionally.In recent years, in China The ground such as southern Chenzhou, Hunan Province, Shaoyang, Baise of Guangxi, Zhaoqing Guangdong, special soils seminar, Institutes Of Technology Of Changsha have found at nearly 10 The example that such retaining wall destroys, 1 day especially nearest May in 2018, in Shaoyang real estate construction building site 13m high carbonaceous There are 80 meters of long broken piles and slope surface cracking destruction by the retaining wall of Anchor anti-slide piles structure in shale side slope, punishes to side slope Propose new technical problem.Such slide slope disease, which is difficult to punish, mainly the problem of two aspects: on the one hand, Anchor anti-slide piles knot After extensive broken pile and slope surface cracking destruction occur for structure, the not only supporting and retaining system power wretched insufficiency at broken pile, the anchor force that anchor cable provides Because big displacement deformation also loss is serious, recovery technique can not be destroyed to restore the supporting and retaining system power at broken pile by existing pile body, and And have also appeared the dangerous situation of slope and land slide destruction;On the other hand, Anchor anti-slide piles structure has been the higher slope reinforcement of cost Structure redesigns Anchor anti-slide piles structure or more expensive RC Continuous wall construction, not only because repairing duration mistake The long needs for being unsatisfactory for emergency work, often owner is also difficult to receive diseconomy.Therefore, it is badly in need of developing a kind of speed of application Fastly, good economy performance, the novel side slope retaining structure of technically reliable and its construction method, to solve culm and residual soil slope two The reinforcing problem that the secondary weak soil type landslide of meta structure side slope is destroyed.
Summary of the invention
Technical problem underlying to be solved by this invention is to develop a kind of to administer culm+residual soil slope binary The novel slope reinforcement structure and its construction method, the new construction that the secondary weak soil type landslide of structure side slope is destroyed must have construction Speed is fast, good economy performance, technically reliable and the effect that can substitute Anchor anti-slide piles retaining wall.
The present invention using Modified soil have can rapid construction, intensity is high, advantage at low cost, and utilize big width Modified soil Wall has larger gravity and can reach the feature of the horizontal bearing force of friction pile, by quickly building Modified soil gravity type gear Cob wall substitutes friction pile, provides basic horizontal direction supporting and retaining system power for slope reinforcement.Finally, by Modified soil gravity type earth-retaining Anchor cable lattice is built on wall top, provides the horizontal direction supporting and retaining system power of auxiliary for the hypodynamic retaining wall upper slope of horizontal direction supporting and retaining system, To form the novel slope supporting of a kind of fast with speed of application, at low cost, technically reliable, alternative Anchor anti-slide piles structure Structure.
A kind of anchor cable lattice provided by the invention and the compound retaining structure of Modified soil retaining wall (Fig. 1) include Modified soil gravity Two parts of formula retaining wall and anchor cable cancelled structure, Modified soil retaining wall of first constructing, then anchor cable lattice part of constructing.Due to anchor cable Lattice part can construct according to a conventional method, and therefore, construction Difficulties are how to solve to excavate when being modified the construction of native retaining wall The gib of crater wall and stable problem.The present invention solves to excavate crater wall using rapid construction slot Sub-region and hierarchical method construction method Gib problem.The rapid construction slot Sub-region and hierarchical method construction method includes: 1. first by proposed retaining wall along length Direction is divided into several construction slots, and construction groove width is not more than 5m;2. construction exploratory trench is divided by upper layer (h2) and lower layer (h1) Totally 4 regions are constructed for upper left area (1), lower-left area (2), bottom right area (3) and upper right area 4;3. construction procedure are as follows: excavation construction Upper left area (1)-excavation construction slot upper right area (4)-that the upper left area (1)-of slot pours into modified soil paste backfill construction slot, which is excavated, to apply The lower-left area (2)-of work slot pours into lower-left area (2)-excavation construction slot bottom right area (3)-backfill of modified soil paste backfill construction slot The bottom right area (3)-the upper right area (4) of backfill construction slot-of construction slot is separated by 10m and constructs to next construction slot.
A kind of anchor cable lattice provided by the invention and the compound retaining structure of Modified soil retaining wall, using the layering point of construction slot Area's construction method is constructed.The construction method can first be formed by the light section that slot has of constructing when layered and blocked excavation Of short duration interim soil arching effect is come the of short duration interim stabilization of exploratory trench wall that keeps constructing, to guarantee facing for modified earthen backfill construction period Shi Wending, the formation for the quick support construction for recycling subregion quickly stuffing and quick freezing action to realize, it is single to reach guarantee The stable purpose of slot construction time crater wall of constructing;It is short-term due to interim soil arching effect, it is necessary to accelerate the upper left area (1) of construction slot The hardening of cob wall is modified with the backfill of lower-left area (2), to accomplish to harden substantially before interim soil arching effect fails, for this purpose, The present invention pours into after mixing and stirring pulp by blender scene using cement 30%+ waterglass early strength agent 10% and high liquid limit soil and water To realize the rapid hardening hardening of the partially modified cob wall.In order to save cost, improve speed of application, the upper right area (3) for slot of constructing and The modified cob wall of the backfill in bottom right area (4) is then to pass through excavator using cement 10%+ waterglass early strength agent 3% and high liquid limit soil and water After hard plastic shape is mixed and stirred at scene, by made of digging machine compaction in layers.Due to the upper left area (1) and lower-left area (2) of construction slot Modified soil paste is backfilled without compacting but can quickly form supporting intensity, realizes gib, playing ensures the modified cob wall construction time Between construct slot crater wall stabilization.Therefore, the present invention by using construction slot layering and zoning construction method, realize gib with The consistency of support retaining wall construction, saves the project amount in addition to support engineering is in addition arranged, significantly fast short construction period and section Saved construction cost, meanwhile, by construct slot upper left area (1) and lower-left area (2) backfill modification soil paste without compacting process Backfill and quick-hardening solve the unstable problem of construction crater wall, have been finally reached quickly and the purpose of low cost construction.
A kind of anchor cable lattice provided by the invention and the compound retaining structure of Modified soil retaining wall and its construction method have and apply Advantages, the alternative Anchor anti-slide piles such as work speed is fast, slurry trench stability of constructing, construction quality is easily controllable, project cost is low are compound Structure, particularly suitable for the reinforcing on the secondary weak soil type landslide of double-decked slope that culm and residual soil slope form.
Detailed description of the invention
Fig. 1 is the schematic diagram of a kind of anchor cable lattice and the compound retaining structure of Modified soil retaining wall and construction method.
Specific embodiment
With reference to the accompanying drawing 1 and at Hunan Shaoyang culm+residual soil slope double-decked slope interface Tu Yan time The Specific construction example for the improvement that raw weak soil type landslide is destroyed, the invention will be further described.
A kind of anchor cable lattice provided by the invention and the compound retaining structure of Modified soil retaining wall include Modified soil gravity type gear Two parts of cob wall and anchor cable cancelled structure.First using construction slot layering and zoning construction method construction Modified soil earth-retaining when construction Wall, then anchor cable lattice part of constructing according to a conventional method, construction procedure are characterized in:
(1), it is single construction slot length using the width of proposed retaining wall and proposed retaining wall 5m length is taken to visit as single construction Proposed retaining wall is divided into several construction slots, and carries out construction lofting at the scene by the width of slot;
(2), it requires to be separated by 10m between successive two constructions slot when constructing, and is ranked up in order accordingly, carry out each construction one by one The construction of slot;
(3), it in the selected quasi- construction groove location constructed, is excavated with upper left area 1 of the excavator to construction slot, simultaneously Pay attention to guaranteeing, 3m is not to be exceeded in 1 bottom excavation length range b1 of upper left area, and upper layer cutting depth h2 should be no more than 6m;When proposed When retaining wall depth h is less than 12m, upper layer cutting depth h2 should be no more than the 1/2 of the proposed retaining wall depth h;When proposed gear Cob wall depth h is greater than 12m, it is not recommended that is directly constructed using the patented method;
(4), using the high liquid limit soil that digs out from construction slot, by cement 30%, waterglass early strength agent 10%, high liquid limit soil 60% Weight mixed ratio is added suitable quantity of water and mixes and stirs pulp by blender scene to the shape that liquefies, then pours into construction slot upper left area 1 Range is excavated, and is consolidated with digging machine;
(5), after completing the backfill to construction slot upper left area 1,5 hours to Modified soil should be waited to starch basic hardening, then with excavation Machine excavation construction slot upper right area 4, bottom excavation width should reach scope of design b4;
(6), it is excavated with lower-left area 2 of the excavator to construction slot, while note that lower-left area (2) bottom excavation length range 3m is not to be exceeded in b2, and cutting depth reaches projected depth h1, and guarantees that construction groove depth reaches the projected depth h of modified cob wall; Modified soil paste, the excavation range in backfill construction slot lower-left area 2 are prepared referring to step (4);
(7), 5 hours to the modification soil paste for pouring into construction slot lower-left area 2 is waited to harden substantially, then with excavator excavation construction slot Bottom right area 3, cutting depth reaches projected depth h1, and the groove depth that guarantees to construct reaches the projected depth h of modified cob wall;
(8) obtained high liquid limit soil is excavated using 10% cement, 3% waterglass and 87%, is added suitable quantity of water to hard plastic shape, is used After excavator scene is mixed and stirred, material layering will be mixed and stirred and paved in the range in construction slot bottom right area 3, notices that single layer backfill thickness is not more than 0.3m, and made real by digging machine bucket, until filling up the bottom right area 3 of construction slot;
(9), referring to step (8), the upper right area 4 of construction slot is filled up with Modified soil;
(10), the sequence for pressing step (2) completes the construction of all construction slots referring to step (3) ~ step (9), entire to accelerate The speed of application of engineering can also carry out the construction of multiple construction slots when the sequence of construction for meeting step (2) requires simultaneously;
(11), after completing all constructions of construction slot, drain hole 9 of constructing according to a conventional method;
(12), after the construction for completing whole drain holes 9, anchor cable cancelled structure 5 of constructing according to a conventional method pays attention to it is ensured that anchor cable For anchoring section 8 completely into hard formation 7, guaranteeing that anchoring depth L1 reaches design length, the length of the free segment 6 of anchor cable can be according to hard The location-appropriate adjustment of layer 7;
(13), proposed retaining wall foundation gutter and platform 10 are built;
(14), proposed retaining walls top margin slope 11 is modified.
On June 24, -2018 years on the 4th May in 2018, using a kind of anchor cable lattice and Modified soil for originally declaring patent offer The compound retaining structure of barricade and its construction method, to Hunan Shaoyang culm+residual soil slope double-decked slope part The secondary weak soil type landslide destruction in the interface Tu Yan of 60m long, 12m high are reinforced, which has been subjected to twice so far Heavy Rainfall Process, earth's surface maximum displacement is always less than 5mm after the completion of surface observation pile beacon point tracking measurement shows construction, shows Slope stability Fig. 1.Engineering practice shows a kind of anchor cable lattice and the compound supporting and retaining system knot of Modified soil barricade of originally declaring patent offer Structure and its construction method are practical.

Claims (2)

1. a kind of anchor cable lattice disclosed by the invention and the compound retaining structure of Modified soil retaining wall include Modified soil gravity type earth-retaining Two parts of wall and anchor cable cancelled structure, sequence of construction are first using construction slot layering and zoning construction method construction Modified soil earth-retaining Wall, then anchor cable lattice part of constructing according to a conventional method.
2. a kind of a kind of construction method of anchor cable lattice and the compound retaining structure of Modified soil retaining wall as described in claim 1, Its steps characteristic is:
1) it is single construction slot length using the width of proposed retaining wall and takes proposed retaining wall 5m length as single construction exploratory trench Width, proposed retaining wall is divided into several construction slots, and carries out construction lofting at the scene;
2) it requires to be separated by 10m between successive two constructions slot when constructing, and is ranked up in order accordingly, carry out each construction slot one by one Construction;
3) it in the selected quasi- construction groove location constructed, is excavated with upper left area (1) of the excavator to construction slot, simultaneously Pay attention to guaranteeing, 3m is not to be exceeded in upper left area (1) bottom excavation length range (b1), and upper layer cutting depth (h2) should be no more than 6m; When proposed retaining wall depth (h) is less than 12m, upper layer cutting depth (h2) should be no more than the proposed retaining wall depth (h) 1/2;When proposed retaining wall depth (h) is greater than 12m, it is not recommended that directly constructed using the patented method;
4) using the high liquid limit soil that digs out from construction slot, by cement 30%, waterglass early strength agent 10%, high liquid limit soil 60% Weight mixed ratio is added suitable quantity of water and mixes and stirs pulp by blender scene to the shape that liquefies, then pours into construction slot upper left area (1) Excavation range, and consolidated with digging machine;
5) after completing the backfill to construction slot upper left area (1), 5 hours to Modified soil should be waited to starch basic hardening, then with excavation Machine excavation construction slot upper right area (4), bottom excavation width should reach scope of design (b4);
6) it is excavated with lower-left area (2) of the excavator to construction slot, while note that lower-left area (2) bottom excavation length range (b2) 3m is not to be exceeded, cutting depth reaches projected depth (h1), and guarantees that construction groove depth reaches the design depth of modified cob wall It spends (h);Modified soil paste, the excavation range of backfill construction slot lower-left area (2) are prepared referring to step 4);
7) 5 hours to the modification soil paste for pouring into construction slot lower-left area (2) is waited to harden substantially, then with excavator excavation construction slot Bottom right area (3), cutting depth reaches projected depth (h1), and the groove depth that guarantees to construct reaches the projected depth of modified cob wall (h);
8) obtained high liquid limit soil is excavated using 10% cement, 3% waterglass and 87%, adds suitable quantity of water to hard plastic shape, After being mixed and stirred with excavator scene, material layering will be mixed and stirred and paved in the range of construction slot bottom right area (3), pays attention to single layer backfill thickness not It is made real greater than 0.3m, and by digging machine bucket, until filling up the bottom right area (3) of construction slot;
9) referring to step 8), the upper right area (4) of construction slot is filled up with Modified soil;
10) sequence for pressing step 2) completes the construction of all construction slots referring to step 3)~step 9), to accelerate entire engineering Speed of application, meet step 2) sequence of construction require when, can also carry out simultaneously it is multiple construction slots construction;
11) after completing all constructions of construction slot, drain hole (9) are constructed according to a conventional method;
12) it after the construction for completing whole drain holes (9), constructs anchor cable cancelled structure (5), is paid attention to it is ensured that anchor cable according to a conventional method Anchoring section (8) completely into hard formation (7), guarantee that anchoring depth (L1) reaches design length, the free segment (6) of anchor cable Length can be adjusted according to the location-appropriate of hard formation (7);
13) proposed retaining wall foundation gutter and platform (10) are built;
14) proposed retaining walls top margin slope (11) are modified.
CN201811507824.2A 2018-12-11 2018-12-11 Construction method of anchor cable lattice and modified soil retaining wall composite supporting and retaining structure Active CN109763513B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811507824.2A CN109763513B (en) 2018-12-11 2018-12-11 Construction method of anchor cable lattice and modified soil retaining wall composite supporting and retaining structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811507824.2A CN109763513B (en) 2018-12-11 2018-12-11 Construction method of anchor cable lattice and modified soil retaining wall composite supporting and retaining structure

Publications (2)

Publication Number Publication Date
CN109763513A true CN109763513A (en) 2019-05-17
CN109763513B CN109763513B (en) 2021-04-20

Family

ID=66451230

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811507824.2A Active CN109763513B (en) 2018-12-11 2018-12-11 Construction method of anchor cable lattice and modified soil retaining wall composite supporting and retaining structure

Country Status (1)

Country Link
CN (1) CN109763513B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110865172A (en) * 2019-10-23 2020-03-06 长沙理工大学 Geotechnical test method for determining emergency construction parameters of soft plastic modified soil foundation
CN114396071A (en) * 2022-01-14 2022-04-26 中铁二院工程集团有限责任公司 Soil retaining assembly and connecting and bar planting anchoring method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3532641A1 (en) * 1985-09-12 1987-03-19 Geotech Lizenz Ag WALL WITH A MASS STRUCTURE, RELATED COMPONENT AND METHOD FOR PRODUCING THE WALL
EP0227605A1 (en) * 1985-12-23 1987-07-01 Occava Anstalt Method for anchoring a hollow-stones wall
CN103410167A (en) * 2013-08-29 2013-11-27 深圳市福田建安建设集团有限公司 Three-dimensional reinforced rigid-soft composite ecological retaining wall and construction method
CN105201011A (en) * 2015-09-18 2015-12-30 山东大学 Complex anchored-plate retaining wall and construction method thereof
CN106351239A (en) * 2016-10-28 2017-01-25 长沙理工大学 Cement modified soil strengthened geogrid reinforced soil structure and construction method thereof
CN108661069A (en) * 2018-04-02 2018-10-16 山东建筑大学 Close on the wall piled anchor composite structure and method of old Retaining Wall Reinforcement under the load of river road surface

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3532641A1 (en) * 1985-09-12 1987-03-19 Geotech Lizenz Ag WALL WITH A MASS STRUCTURE, RELATED COMPONENT AND METHOD FOR PRODUCING THE WALL
EP0227605A1 (en) * 1985-12-23 1987-07-01 Occava Anstalt Method for anchoring a hollow-stones wall
CN103410167A (en) * 2013-08-29 2013-11-27 深圳市福田建安建设集团有限公司 Three-dimensional reinforced rigid-soft composite ecological retaining wall and construction method
CN105201011A (en) * 2015-09-18 2015-12-30 山东大学 Complex anchored-plate retaining wall and construction method thereof
CN106351239A (en) * 2016-10-28 2017-01-25 长沙理工大学 Cement modified soil strengthened geogrid reinforced soil structure and construction method thereof
CN108661069A (en) * 2018-04-02 2018-10-16 山东建筑大学 Close on the wall piled anchor composite structure and method of old Retaining Wall Reinforcement under the load of river road surface

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110865172A (en) * 2019-10-23 2020-03-06 长沙理工大学 Geotechnical test method for determining emergency construction parameters of soft plastic modified soil foundation
CN110865172B (en) * 2019-10-23 2022-12-23 长沙理工大学 Soil test method for determining emergency compaction construction parameters of soft plastic modified soil replacement foundation
CN114396071A (en) * 2022-01-14 2022-04-26 中铁二院工程集团有限责任公司 Soil retaining assembly and connecting and bar planting anchoring method thereof

Also Published As

Publication number Publication date
CN109763513B (en) 2021-04-20

Similar Documents

Publication Publication Date Title
CN104153380B (en) A kind of antiseepage cofferdam structure and construction technology
CN107503257B (en) One kind being close to mountain high-filled subgrade stabilization and Deformation control structure and construction method
CN105019422B (en) Topsoil is cured in situ the foundation construction method that carrying is combined with stake
CN103882884A (en) Anchor rope geogrid retaining structure and method for constructing same
CN108798684B (en) A kind of method of completely decomposed fine sand stratum tunnel excavation
CN111851505A (en) Construction method and structure of pouring type impervious core earth-rock dam
RU2392387C2 (en) Device and method for reinforcement of mast base
CN101008178B (en) Soft base processing construction process using excavating and stirring method
CN104895111B (en) The construction method of integrated pipe canal in weak soil ground
CN111676987A (en) Construction method for backfilling construction of construction fertilizer tank by vibrating, slurry-flushing and ramming method
CN109763513A (en) A kind of anchor cable lattice and the compound retaining structure of Modified soil retaining wall and its construction method
CN208604438U (en) The high embankment retaining structure in soft clay area
CN101029490B (en) Method for preventing and managing rock/upper side slope
CN106884427A (en) Immersed tube tunnel and immersed tube tunnel changeover portion soft soil foundation reinforcing method under water
CN110080232A (en) A kind of deep basal pit earth-filling method of underground high water level
CN105780764A (en) Light cemented soil composite mixing pile
CN109537389B (en) EPS (expandable polystyrene) lower embankment structure and construction method thereof
CN108570979A (en) A kind of construction method for building antiseepage composite foundation on dolomite stratigraph
JP3583181B2 (en) Embankment construction method
CN204608701U (en) A kind of gravity type quay being applicable to roadbed of alluvial silt
CN209293009U (en) A kind of multilayer block stone fill foundation dynamic replacement ruggedized construction
CN106703043A (en) Soft soil foundation pit construction method by using dynamic compaction block stone displacement instead of supporting
CN106087941B (en) The method for processing foundation of big thickness lattice cement soil padding wall in weak soil
CN207331698U (en) A kind of mud deep basal pit pipe alley structure
CN111851185A (en) Self-compacting cement soil widening roadbed and construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant