CN109750662A - 一种穿越溶洞段的基桩施工方法 - Google Patents

一种穿越溶洞段的基桩施工方法 Download PDF

Info

Publication number
CN109750662A
CN109750662A CN201910021762.2A CN201910021762A CN109750662A CN 109750662 A CN109750662 A CN 109750662A CN 201910021762 A CN201910021762 A CN 201910021762A CN 109750662 A CN109750662 A CN 109750662A
Authority
CN
China
Prior art keywords
solution cavity
cylindrical balloon
stake holes
pile
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910021762.2A
Other languages
English (en)
Other versions
CN109750662B (zh
Inventor
刘永莉
郭斌
肖衡林
李丽华
马强
周文佐
万娟
刘伦
胡智
庄心善
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hubei University of Technology
Original Assignee
Hubei University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hubei University of Technology filed Critical Hubei University of Technology
Priority to CN201910021762.2A priority Critical patent/CN109750662B/zh
Publication of CN109750662A publication Critical patent/CN109750662A/zh
Application granted granted Critical
Publication of CN109750662B publication Critical patent/CN109750662B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

本发明公开了一种穿越溶洞段的基桩施工方法,首先勘探地质情况,确认桩孔位置;然后采用无泥浆参与的桩孔施工工艺进行穿越溶洞的桩孔施工;选择一个柱形气囊进行初步充气膨胀;将初步充气膨胀的柱形气囊下放至桩孔内,继续充气使位于溶洞内部区域的柱形气囊继续膨胀,使柱形气囊中部直径大于桩孔直径;利用预设在柱形气囊周边的导管向溶洞内部输送膨胀材料,利用膨胀材料对柱形气囊周边的溶洞空间进行填充;待膨胀材料将柱形气囊周边溶洞填充固化后,对柱形气囊进行放气回收;在桩孔内下放钢筋笼,然后浇注混凝土,完成变截面的基桩施工。本发明提施工工艺简单,具有降低成本,提高承载力,对溶洞地质环境扰动小,施工简单等优点。

Description

一种穿越溶洞段的基桩施工方法
技术领域
本发明属于土木工程中桩基础施工技术领域,具体涉及一种穿越溶洞段的基桩施工方法,解决了桩身穿透大型溶洞时混凝土不易灌注的问题。
背景技术
我国岩溶地区面积辽阔,随着城市开发和交通建设的迅猛发展,在工程建设中经常会遇到岩溶地质条件,溶洞给基础的稳定带来很大危害。岩溶地区桩基础的使用也越来越广泛,当桩基础需要穿透溶洞以达到承载能力要求时,一般采用水泥,片石等材料对溶洞内部进行填充,此种施工方法会造成施工填料的大量浪费。并且在后续还需要对填充材料进行二次成孔,增加了桩基础施工的复杂度。
发明内容
本发明为了解决穿透溶洞的桩身混凝土不易灌注的问题,解决穿透溶洞的桩基础施工困难,造价高昂的问题,解决了施工后溶洞顶板易坍塌问题提供了一种穿越溶洞段的基桩施工方法,同时尽可能围护了溶洞原始生态地质环境。
为了解决上述技术问题,本发明采用的技术方案是:
一种穿越溶洞段的基桩施工方法,其特征在于,包括以下步骤:
步骤1、勘探地质情况,确认桩孔位置;
步骤2、平整施工场地,采用无泥浆参与的桩孔施工工艺进行穿越溶洞的桩孔施工,直到桩孔深度达到溶洞底部的桩身设计深度;
步骤3、桩孔施工结束后,选择一个柱形气囊进行初步充气膨胀,膨胀至柱形气囊的柱身直径小于桩孔直径即可;
步骤4、下放经过初步充气处理后的柱形气囊至溶洞区域的桩孔底部,对柱形气囊进行再次充气,使柱形气囊顶部和底部分别卡在溶洞顶部和底部的桩孔内,与桩壁紧密结合,继续充气使位于溶洞内部区域的柱形气囊继续膨胀,使柱形气囊中部直径大于桩孔直径;
步骤5、利用预设在柱形气囊周边的导管向溶洞内部输送膨胀材料,利用膨胀材料对柱形气囊周边的溶洞空间进行填充;
步骤6、待膨胀材料将柱形气囊周边溶洞填充完成,固化后,对柱形气囊进行放气回收;
步骤7、在桩孔内下放钢筋笼,然后浇注混凝土,完成变截面的基桩施工。
作为改进,所述膨胀材料为聚氨酯发泡剂。
作为改进,所述柱形气囊高度=溶洞底部岩层桩孔深度+溶洞高度+0.5~1.0m。
作为改进,所述柱形气囊为圆柱形的橡胶柱形气囊。
作为改进,当灌注桩需要穿越多个溶洞时,按照步骤2至步骤6从上至下依次对穿越多个溶洞的桩孔施工,之后按照步骤7浇注混凝土完成变截面的基桩施工。
作为改进,所述桩孔采用全套管全回转钻机施工工艺施工。
作为改进,步骤6中,回收柱形气囊后,利用导管对桩孔进行清孔处理。
本发明有益效果是:
相比较于传统的施工方法,本发明采用一种新颖的施工技术,通过聚氨酯膨胀材料进行穿越溶洞的桩孔施工。保证在溶洞填充后不需要再次对溶洞填充材料成孔,并其在溶洞内桩身产生扩径效应有效提高桩身承载力。
附图说明
图1为利用无泥浆参与的施工工艺在岩溶地区成孔;
图2为利用吊装设备下放经过初次充气处理的柱形气囊;
图3为柱形气囊下放至桩孔内平稳后对其进行二次充气处理;
图4为利用柱形气囊周边导管将聚氨酯膨发泡剂注入溶洞内部,使之膨胀填充满桩孔周边溶洞区域;
图5为待聚氨酯膨发泡剂具有一定强度后将柱形气囊放气回收;
图6为下放钢筋笼,导管,并利用导管进行清孔;
图7为灌注混凝土示意图;
图8为桩身成型图。
图9为柱状柱形气囊扩展过程俯视图。
图10为柱状柱形气囊扩展过程正视图。
图11为桩基础穿透两个溶洞时的桩基础完工图。
1-柱形气囊,2-溶洞,3-溶洞上部覆盖层,4-溶洞底部岩层,5-钢护筒,6-桩孔,7-吊装设备,8-膨胀材料,9-灌注桩,10-导管。
具体实施方式
下面结合附图对本发明的方式和实施步骤进一步的说明。
如图1至图10所示,一种穿越溶洞段的基桩施工方法,包括以下步骤:
步骤1、勘探地质情况,确认桩孔6位置;
步骤2、如图1所示,平整施工场地,采用无泥浆参与的桩孔施工工艺进行穿越溶洞2的桩孔施工(本实施例中桩孔6采用全套管全回转钻机施工工艺施工),直到桩孔6深度达到溶洞2底部的桩身设计深度;
步骤3、如图2所示,桩孔6施工结束后,选择一个柱形的柱形气囊1进行初步充气膨胀,膨胀至柱形气囊1柱身直径小于桩孔6直径即可;
步骤4、如图3所示,利用吊装设备7下放经过初步充气处理后的柱形气囊1至溶洞区域的桩孔6底部,对柱形气囊1进行再次充气,使柱形气囊1顶部和底部分别卡在溶洞2顶部和底部的桩孔6内,与桩壁紧密结合,继续充气使位于溶洞2内部区域的柱形气囊1继续膨胀,使柱形气囊1中部直径大于桩孔6直径,所述柱形气囊1高度=溶洞底部岩层桩孔深度+溶洞2高度+0.5~1.0m;
步骤5、如图4所示,利用预设在柱形气囊1周边的导管10向溶洞2内部输送膨胀材料8,利用膨胀材料对8柱形气囊1周边的溶洞空间进行填充;
步骤6、如图5所示,待膨胀材料8将柱形气囊1周边溶洞2填充完成,固化后,对柱形气囊1进行放气回收,回收柱形气囊1后,利用导管对桩孔6进行清孔处理;
步骤7、如图6和图7所示,利用吊装设备7在桩孔6内下放钢筋笼,然后浇注混凝土,完成变截面灌注桩9施工,如图8所示。
本实施例中,所述膨胀材料8为聚氨酯发泡剂,所述柱形气囊1为圆柱形的橡胶柱形气囊,柱形气囊1充气变形过程如图9和图10所示。
当灌注桩9需要穿越多个溶洞2时,按照步骤2至步骤6从上至下依次对穿越多个溶洞2的桩孔6施工,之后按照步骤7浇注混凝土完成变截面灌注桩9施工,如图11所示,为穿越两个溶洞2的灌注桩9示意图。

Claims (7)

1.一种穿越溶洞段的基桩施工方法,其特征在于,包括以下步骤:
步骤1、勘探地质情况,确认桩孔位置;
步骤2、平整施工场地,采用无泥浆参与的桩孔施工工艺进行穿越溶洞的桩孔施工,直到桩孔深度达到溶洞底部的桩身设计深度;
步骤3、桩孔施工结束后,选择一个柱形气囊进行初步充气膨胀,膨胀至柱形气囊的柱身直径小于桩孔直径即可;
步骤4、下放经过初步充气处理后的柱形气囊至溶洞区域的桩孔底部,对柱形气囊进行再次充气,使柱形气囊顶部和底部分别卡在溶洞顶部和底部的桩孔内,与桩壁紧密结合,继续充气使位于溶洞内部区域的柱形气囊继续膨胀,使柱形气囊中部直径大于桩孔直径;
步骤5、利用预设在柱形气囊周边的导管向溶洞内部输送膨胀材料,利用膨胀材料对柱形气囊周边的溶洞空间进行填充;
步骤6、待膨胀材料将柱形气囊周边溶洞填充完成,固化后,对柱形气囊进行放气回收;
步骤7、在桩孔内下放钢筋笼,然后浇注混凝土,完成变截面的基桩施工。
2.如权利要求1所述的基桩施工方法,其特征在于:所述膨胀材料为聚氨酯发泡剂。
3.如权利要求1所述的基桩施工方法,其特征在于:所述柱形气囊高度=溶洞底部岩层桩孔深度+溶洞高度+0.5~1.0m。
4.如权利要求1所述的基桩施工方法,其特征在于:所述柱形气囊为圆柱形的橡胶柱形气囊。
5.如权利要求1所述的基桩施工方法,其特征在于:当灌注桩需要穿越多个溶洞时,按照步骤2至步骤6从上至下依次对穿越多个溶洞的桩孔施工,之后按照步骤7浇注混凝土完成变截面的基桩施工。
6.如权利要求1所述的基桩施工方法,其特征在于:所述桩孔采用全套管全回转钻机施工工艺施工。
7.如权利要求1所述的基桩施工方法,其特征在于:步骤6中,回收柱形气囊后,利用导管对桩孔进行清孔处理。
CN201910021762.2A 2019-01-10 2019-01-10 一种穿越溶洞段的基桩施工方法 Active CN109750662B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910021762.2A CN109750662B (zh) 2019-01-10 2019-01-10 一种穿越溶洞段的基桩施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910021762.2A CN109750662B (zh) 2019-01-10 2019-01-10 一种穿越溶洞段的基桩施工方法

Publications (2)

Publication Number Publication Date
CN109750662A true CN109750662A (zh) 2019-05-14
CN109750662B CN109750662B (zh) 2020-07-10

Family

ID=66405280

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910021762.2A Active CN109750662B (zh) 2019-01-10 2019-01-10 一种穿越溶洞段的基桩施工方法

Country Status (1)

Country Link
CN (1) CN109750662B (zh)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111218926A (zh) * 2019-11-28 2020-06-02 湖北工业大学 一种穿越溶洞的干作业孔灌注桩施工工艺
CN111739397A (zh) * 2020-07-31 2020-10-02 湖北工业大学 一种多溶洞地质模型制备方法
CN112855029A (zh) * 2021-04-26 2021-05-28 中铁九局集团第七工程有限公司 一种采空区钻孔外扩管施工方法
CN113217092A (zh) * 2021-05-31 2021-08-06 山东大学 一种可变形溶洞的填充方法
CN113481986A (zh) * 2021-07-30 2021-10-08 广东康润达建设工程有限公司 一种溶岩地区的抗浮锚杆施工方法
CN114645543A (zh) * 2022-04-27 2022-06-21 中国矿业大学 一种岩溶地区桩孔定点注浆方法和定点注浆装置
CN114922156A (zh) * 2022-06-02 2022-08-19 民航机场规划设计研究总院有限公司 一种地下溶洞处理方法及结构
CN117051841A (zh) * 2023-10-11 2023-11-14 上海建工集团股份有限公司 一种穿越溶洞区桩体隔离成桩方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106013049A (zh) * 2016-06-13 2016-10-12 黄泽普 岩溶地区基桩工程施工方法
CN107905218A (zh) * 2017-11-28 2018-04-13 中国冶集团有限公司 一种应用于岩溶地区钻孔灌注桩施工中的溶洞处理方法
CN108589718A (zh) * 2018-03-30 2018-09-28 中交路桥北方工程有限公司 岩溶区桩基施工方法
CN109056706A (zh) * 2018-08-03 2018-12-21 上海宝冶集团有限公司 一种岩溶地质灌注桩基施工方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106013049A (zh) * 2016-06-13 2016-10-12 黄泽普 岩溶地区基桩工程施工方法
CN107905218A (zh) * 2017-11-28 2018-04-13 中国冶集团有限公司 一种应用于岩溶地区钻孔灌注桩施工中的溶洞处理方法
CN108589718A (zh) * 2018-03-30 2018-09-28 中交路桥北方工程有限公司 岩溶区桩基施工方法
CN109056706A (zh) * 2018-08-03 2018-12-21 上海宝冶集团有限公司 一种岩溶地质灌注桩基施工方法

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111218926A (zh) * 2019-11-28 2020-06-02 湖北工业大学 一种穿越溶洞的干作业孔灌注桩施工工艺
CN111739397A (zh) * 2020-07-31 2020-10-02 湖北工业大学 一种多溶洞地质模型制备方法
CN112855029A (zh) * 2021-04-26 2021-05-28 中铁九局集团第七工程有限公司 一种采空区钻孔外扩管施工方法
CN113217092A (zh) * 2021-05-31 2021-08-06 山东大学 一种可变形溶洞的填充方法
US11933178B2 (en) 2021-05-31 2024-03-19 Shandong University Method for filling deformable karst cave
CN113481986A (zh) * 2021-07-30 2021-10-08 广东康润达建设工程有限公司 一种溶岩地区的抗浮锚杆施工方法
CN114645543A (zh) * 2022-04-27 2022-06-21 中国矿业大学 一种岩溶地区桩孔定点注浆方法和定点注浆装置
CN114645543B (zh) * 2022-04-27 2023-01-24 中国矿业大学 一种岩溶地区桩孔定点注浆方法和定点注浆装置
CN114922156A (zh) * 2022-06-02 2022-08-19 民航机场规划设计研究总院有限公司 一种地下溶洞处理方法及结构
CN117051841A (zh) * 2023-10-11 2023-11-14 上海建工集团股份有限公司 一种穿越溶洞区桩体隔离成桩方法
CN117051841B (zh) * 2023-10-11 2023-12-08 上海建工集团股份有限公司 一种穿越溶洞区桩体隔离成桩方法

Also Published As

Publication number Publication date
CN109750662B (zh) 2020-07-10

Similar Documents

Publication Publication Date Title
CN109750662A (zh) 一种穿越溶洞段的基桩施工方法
CN113250200B (zh) 一种新型环保纤维水泥分层注浆装置
CN206016824U (zh) 一种防止盾构空推管片位移的限位装置
CN109653197A (zh) 一种可三维拓展的桩基施工方法
CN106284317B (zh) 一种建筑桩基施工方法
KR101125082B1 (ko) 관형상 부재와, 이를 이용한 약액주입장치 및 약액주입방법
CN105672241B (zh) 喷气破土联合气囊挤土处理深厚震陷性黄土的装置及方法
CN105201518A (zh) 一种大直径泥水平衡盾构洞内接收解体方法
CN213805383U (zh) 一种小型溶洞地区桩基施工围护装置
CN112127373A (zh) 一种深基坑桩撑一体化支护体系结构及分段精确注浆施工技术
CN106050277A (zh) 一种软塑坍塌体岩溶隧道加固工艺
CN209686391U (zh) 一种溶洞段桩身围护装置
CN107676108A (zh) 一种地铁隧道高强度支护结构及其施工方法
CN110700843A (zh) 基于分区爆破的隧道三台阶同步开挖施工方法
CN109629563A (zh) 一种桩基围护施工方法
CN113217092B (zh) 一种可变形溶洞的填充方法
CN106480878A (zh) 一种上、下部扩大型水泥土复合管桩
CN209686385U (zh) 一种穿越溶洞的变截面桩及桩基围护装置
CN110645001A (zh) 由既有横通道扩挖为风道的施工方法
CN110700278A (zh) 内支撑结构、基坑围护体系及其施工方法
CN207181165U (zh) 一种简易模袋混凝土支架模拟装置
JP2006342629A (ja) 充填材の空洞への充填手段および充填方法
CN114293993B (zh) 上下交叠隧道施工竖向变形修复结构及施工方法
CN110528512A (zh) 一种用于岩溶区摩擦型灌注桩的边界体分段预压施工方法
CN106836203A (zh) 模袋桩体和淤泥硬化体的联合结构及其施工方法

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant