CN109740904A - A kind of BIM construction management system - Google Patents

A kind of BIM construction management system Download PDF

Info

Publication number
CN109740904A
CN109740904A CN201811601408.9A CN201811601408A CN109740904A CN 109740904 A CN109740904 A CN 109740904A CN 201811601408 A CN201811601408 A CN 201811601408A CN 109740904 A CN109740904 A CN 109740904A
Authority
CN
China
Prior art keywords
construction
bim
construction personnel
end operations
background server
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811601408.9A
Other languages
Chinese (zh)
Inventor
许城瑜
王有旗
石超
宋筱
李双美
常顺
刘普前
辛柱桥
宋昱宇
李苗
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 25th Bureau Group Co Ltd
Fifth Engineering Co Ltd of China Railway 25th Bureau Group Co Ltd
Original Assignee
China Railway 25th Bureau Group Co Ltd
Fifth Engineering Co Ltd of China Railway 25th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 25th Bureau Group Co Ltd, Fifth Engineering Co Ltd of China Railway 25th Bureau Group Co Ltd filed Critical China Railway 25th Bureau Group Co Ltd
Priority to CN201811601408.9A priority Critical patent/CN109740904A/en
Publication of CN109740904A publication Critical patent/CN109740904A/en
Pending legal-status Critical Current

Links

Abstract

The present invention relates to a kind of BIM construction management systems comprising background server and front-end operations terminal are mounted with BIM model system, construction personnel's location registration system and central database in background server;Front-end operations terminal is mounted with positioning system and communication system;Construction personnel's encoded information is written to RFID label tag in front-end operations terminal control RFID reader, and it controls RFID reader and calls construction personnel's encoded information, the encoded information is transmitted to the BIM model system on background server, three-dimensional artificial, the analysis of visual Data Integration are realized in BIM model system and is shown.This BIM construction management system enables that dispatcher is intuitive, image understands each region construction personnel location information in construction site and glide path, and the working efficiency of construction personnel has been significantly greatly increased;It according to the network condition of the area Gui Hang construction site, is equipped with two kinds of communication systems collocation and uses, so that the deployment of traffic order is much sooner and accurately.

Description

A kind of BIM construction management system
Technical field
The present invention relates to a kind of BIM construction management systems, in particular to a kind of to simulate (BIM) platform based on architecture information The construction management system for positioning and dispatching for realizing the area Gui Hang construction personnel.
Background technique
In order to ensure construction speed and quality, the way of engineering construction field is most of at present is planned by engineer Construction personnel's scheduling scheme forms typing computer after table or drawing, construction personnel is monitored and is adjusted in the construction process It is dynamic, but since to transfer route many and diverse by construction personnel, table and not intuitive etc. enough factors of drawing presentation mode, so that the later period to construction The retrospect of problem is cumbersome and inefficiency, this greatly weakens design engineer and executes to the control and monitoring of construction site and scheduling Dynamics, especially in-orbit row area constructing tunnel section, personal scheduling is more difficult, and reason is on the one hand from above-mentioned Traditional project The inherent shortcoming of personnel positioning and scheduling mode causes the area Gui Hang to make on the other hand from tunnel signal blind area difficult communication Industry link up speed slowly, it is inefficiency, with high costs, in addition it is public not yet to introduce operator for the area the Gui Hang partial sector of construction period The examination and approval procedures of net signal, temporary erection public network base station are cumbersome and cost is higher.
Summary of the invention
The technical problem to be solved by the present invention is to how overcome the drawbacks described above of the prior art, provide a kind of based on building letter The construction management system for positioning and dispatching for realizing the area Gui Hang construction personnel of breath simulation (BIM) platform.
In order to solve the above technical problems, this BIM construction management system includes background server and front-end operations terminal, In, BIM model system, construction personnel's location registration system and central database are mounted in the background server;Before described End operating terminal is mounted with positioning system and communication system, and the positioning system includes RFID label tag and RFID reader;It is described Construction personnel's encoded information is written to RFID label tag in front-end operations terminal control RFID reader, and controls RFID reader calling The encoded information is transmitted to the BIM model system on background server, in BIM model system by construction personnel's encoded information It realizes three-dimensional artificial, the analysis of visual Data Integration and shows;Background server each position out of laying in-orbit row area Front-end operations terminal receive be located at this at construction personnel's encoded information, in BIM model system carry out three-dimensional artificial, visualization Data Integration analysis and emulation show;Displaying result in BIM model system is passed through network transmission simultaneously by background server To front-end operations terminal, monitoring and analysis based on BIM model system are carried out, and analysis result is generated into corresponding electronic report forms, The construction personnel's location registration system being transmitted on background server, electronic report forms of construction personnel's location registration system to upload Carry out unified view and management;The BIM model system is by the encoded information of construction personnel and its locating front-end operations terminal After location information parameter, three-dimensional artificial is synchronized to parametric data at backstage and terminal two and is visualized, and is led to The communication system crossed in front-end operations terminal realizes the scheduling of construction personnel.
Further, the positioning system uses the positioning system based on signal transmission time or time difference;It is described RFID label tag is divided into chest card type, wrist type, safe shape for hat, corresponding to be worn on construction personnel front, wrist, safety cap top.
Further, the communication system packet, which expands, is covered in the area Gui Hang has been introduced into runner public-network Signal construction region the One communication network group and it is covered in the second communication network group that the area Gui Hang is not introduced into the construction area of runner public-network signal.
Further, the first communication network group is wire net group comprising locating base station, optical fiber, optical fiber transceiving Device, POE interchanger and cable;If mating a pair of of the fiber optical transceiver of each locating base station in the area Gui Hang, a POE interchanger, Dry optical fiber and cable.
Further, the second communication network group is wireless communication networks group, and 5.8G is laid by the way of region overlay Wireless bridge base station.
A kind of BIM construction management system of the present invention carries out the area Gui Hang personnel positions based on the analogue simulation mode of BIM real When locating and monitoring, analogue simulation and alignment analysis so that dispatcher can intuitive, image understand each area in construction site Domain construction personnel's location information and glide path, auxiliary carry out science, efficient scheduling and management;It is fixed by site operation personnel With no paper, the networking, visualized operation of position, have been significantly greatly increased the working efficiency of construction personnel;According to the area Gui Hang construction site Network condition, be equipped with the collocation of two kinds of communication systems and use, by 5.8G it is pure wirelessly quickly extend in the way of devise in section The wireless network of all standing cooperates the video monitoring cable network disposed in cable network section to access wireless transmission base station, makes Traffic order deployment much sooner and accurately.
Detailed description of the invention
BIM construction management system of the present invention is described further with reference to the accompanying drawing:
Fig. 1 is total framework line frame graph of this BIM construction management system;
Fig. 2 is the framework line frame graph of this BIM construction management system front-end operations terminal.
Specific embodiment
Embodiment: as shown in Figure 1, 2, this BIM construction management system includes background server and front-end operations terminal, In, BIM model system, construction personnel's location registration system and central database are mounted in the background server;Before described End operating terminal is mounted with positioning system and communication system, and the positioning system includes RFID label tag and RFID reader;It is described Construction personnel's encoded information is written to RFID label tag in front-end operations terminal control RFID reader, and controls RFID reader calling The encoded information is transmitted to the BIM model system on background server, in BIM model system by construction personnel's encoded information It realizes three-dimensional artificial, the analysis of visual Data Integration and shows;Background server each position out of laying in-orbit row area Front-end operations terminal receive be located at this at construction personnel's encoded information, in BIM model system carry out three-dimensional artificial, visualization Data Integration analysis and emulation show;Displaying result in BIM model system is passed through network transmission simultaneously by background server To front-end operations terminal, monitoring and analysis based on BIM model system are carried out, and analysis result is generated into corresponding electronic report forms, The construction personnel's location registration system being transmitted on background server, electronic report forms of construction personnel's location registration system to upload Carry out unified view and management;The BIM model system is by the encoded information of construction personnel and its locating front-end operations terminal After location information parameter, three-dimensional artificial is synchronized to parametric data at backstage and terminal two and is visualized, and is led to The communication system crossed in front-end operations terminal realizes the scheduling of construction personnel.
The positioning system uses the positioning system based on signal transmission time or time difference;The RFID label tag is divided into Chest card type, wrist type, safe shape for hat, it is corresponding to be worn on construction personnel front, wrist, safety cap top.
The communication system packet expansion is covered in the first communication network that the area Gui Hang has been introduced into runner public-network Signal construction region Group and it is covered in the second communication network group that the area Gui Hang is not introduced into the construction area of runner public-network signal.
The first communication network group is wire net group comprising locating base station, optical fiber, fiber optical transceiver, POE exchange Machine and cable;Mating a pair of of the fiber optical transceiver of each locating base station, a POE interchanger, several optical fiber and net in the area Gui Hang Line.
The second communication network group is wireless communication networks group, and 5.8G wireless network abutment is laid by the way of region overlay It stands.
This BIM construction management system positions the area Gui Hang personnel positions based on the analogue simulation mode of BIM in real time Monitoring, analogue simulation and alignment analysis, so that dispatcher being capable of intuitive, the image understanding each region constructor in construction site Member's location information and glide path, auxiliary carry out science, efficient scheduling and management;By site operation personnel positioning without paper The working efficiency of construction personnel has been significantly greatly increased in change, networking, visualized operation;According to the network feelings of the area Gui Hang construction site Condition is equipped with the collocation of two kinds of communication systems and uses, by 5.8G it is pure wirelessly quickly extend in the way of devise all standing in section Wireless network cooperates the video monitoring cable network disposed in cable network section to access wireless transmission base station, so that scheduling life The deployment of order is much sooner and accurately.
Above embodiment, which is intended to illustrate the present invention, to be realized or use for professional and technical personnel in the field, to above-mentioned Embodiment, which is modified, will be readily apparent to those skilled in the art, therefore the present invention includes but is not limited to Above embodiment, it is any to meet the claims or specification description, meet with principles disclosed herein and novelty, The method of inventive features, technique, product, fall within the scope of protection of the present invention.

Claims (5)

1. a kind of BIM construction management system, it is characterized in that: including background server and front-end operations terminal, wherein the backstage BIM model system, construction personnel's location registration system and central database are mounted in server;The front-end operations terminal dress It is loaded with positioning system and communication system, the positioning system includes RFID label tag and RFID reader;The front-end operations terminal It controls RFID reader and construction personnel's encoded information is written to RFID label tag, and control RFID reader and call construction personnel's coding The encoded information is transmitted to the BIM model system on background server by information, in BIM model system realize three-dimensional artificial, Visual Data Integration analysis and displaying;The front-end operations terminal of background server each position out of laying in-orbit row area It receives and is located at construction personnel's encoded information at this, three-dimensional artificial, the analysis of visual Data Integration are carried out in BIM model system It is shown with emulation;Background server simultaneously by the displaying result in BIM model system by network transmission to front-end operations terminal, Monitoring and analysis based on BIM model system are carried out, and analysis result is generated into corresponding electronic report forms, is transmitted to background server On construction personnel's location registration system, construction personnel's location registration system carries out unified view and pipe to the electronic report forms of upload Reason;After the BIM model system parameterizes the encoded information of construction personnel and its locating front-end operations terminal positional information, It synchronizes three-dimensional artificial to parametric data at backstage and terminal two to visualize, and by front-end operations terminal The scheduling of communication system realization construction personnel.
2. BIM construction management system according to claim 1 is passed it is characterized in that: the positioning system is used based on signal The positioning system of defeated time or time difference;The RFID label tag is divided into chest card type, wrist type, safe shape for hat, and correspondence is worn on Construction personnel front, wrist, safety cap top.
3. BIM construction management system according to claim 2, it is characterized in that: communication system packet expansion is covered in rail row Area, which has been introduced into the first communication network group in runner public-network Signal construction region and is covered in the area Gui Hang, is not introduced into runner public-network letter Number construction area the second communication network group.
4. BIM construction management system according to claim 3, it is characterized in that: the first communication network group is wire communication Net group comprising locating base station, optical fiber, fiber optical transceiver, POE interchanger and cable;Each locating base station is matched in the area Gui Hang Cover a pair of of fiber optical transceiver, a POE interchanger, several optical fiber and cable.
5. BIM construction management system according to claim 3, it is characterized in that: the second communication network group is wireless communication Net group lays 5.8G wireless bridge base station by the way of region overlay.
CN201811601408.9A 2018-12-26 2018-12-26 A kind of BIM construction management system Pending CN109740904A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811601408.9A CN109740904A (en) 2018-12-26 2018-12-26 A kind of BIM construction management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811601408.9A CN109740904A (en) 2018-12-26 2018-12-26 A kind of BIM construction management system

Publications (1)

Publication Number Publication Date
CN109740904A true CN109740904A (en) 2019-05-10

Family

ID=66361325

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811601408.9A Pending CN109740904A (en) 2018-12-26 2018-12-26 A kind of BIM construction management system

Country Status (1)

Country Link
CN (1) CN109740904A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111050283A (en) * 2019-11-22 2020-04-21 南京金海设计工程有限公司 BIM model-based real-time positioning method for construction site
CN112364424A (en) * 2020-11-16 2021-02-12 河南黄埔建筑安装有限公司 BIM-based central air conditioner installation system and method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103473720A (en) * 2013-09-06 2013-12-25 上海大学 Shield tunnel construction management system based on BIM
CN106779447A (en) * 2016-12-28 2017-05-31 南京建工集团有限公司 Builder's intelligent management system and method for a kind of RFID of fusion BIM
CN106779448A (en) * 2016-12-28 2017-05-31 南京建工集团有限公司 Construction equipment intelligent management apapratus and the intelligent management system of the device is set
CN107832961A (en) * 2017-11-20 2018-03-23 中铁工程装备集团技术服务有限公司 A kind of constructing tunnel dynamic real-time monitor system
CN108615204A (en) * 2018-05-06 2018-10-02 北京工业大学 A kind of building based on BIM and UWB faces side hole safety management system and method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103473720A (en) * 2013-09-06 2013-12-25 上海大学 Shield tunnel construction management system based on BIM
CN106779447A (en) * 2016-12-28 2017-05-31 南京建工集团有限公司 Builder's intelligent management system and method for a kind of RFID of fusion BIM
CN106779448A (en) * 2016-12-28 2017-05-31 南京建工集团有限公司 Construction equipment intelligent management apapratus and the intelligent management system of the device is set
CN107832961A (en) * 2017-11-20 2018-03-23 中铁工程装备集团技术服务有限公司 A kind of constructing tunnel dynamic real-time monitor system
CN108615204A (en) * 2018-05-06 2018-10-02 北京工业大学 A kind of building based on BIM and UWB faces side hole safety management system and method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111050283A (en) * 2019-11-22 2020-04-21 南京金海设计工程有限公司 BIM model-based real-time positioning method for construction site
CN112364424A (en) * 2020-11-16 2021-02-12 河南黄埔建筑安装有限公司 BIM-based central air conditioner installation system and method

Similar Documents

Publication Publication Date Title
US6467039B1 (en) Device in a system operating with can-protocol and in a control and/or supervision system
CN104569657B (en) A kind of LTE radio communications intelligent substation mutual inductor simulating test device
CN109740904A (en) A kind of BIM construction management system
CN103945285A (en) Efficient access to connectivity information using cable identification
CN110210628A (en) A kind of automation equipment intelligence O&M upkeep operation method of augmented reality
CN104076767B (en) Railway signal equipment overhauling control system and method
US9905089B2 (en) Physical layer system with support for multiple active work orders and/or multiple active technicians
CN105610612A (en) Intelligent digital distributing frame system and application method thereof
CN110138601A (en) Centralized monitoring method and device
CN104992583A (en) Subway train dispatching simulation training system
CN107585181A (en) A kind of train positioning system based on deep learning
CN103279897B (en) Power scheduling monitoring information methods of exhibiting and system
CN104601220B (en) LTE (Long Term Evolution) wireless communication intelligent substation test device
CN108908342A (en) Intelligent Mobile Robot and scheduling system business operations linkage system and method
CN106548666A (en) A kind of learning method and system of mobile base station operation and maintenance
CN101022358A (en) Method for realizing resource cluster and management control in IP telecommunication network system
CN202662072U (en) Staff in-position monitoring device
CN109525433A (en) A kind of router bgp status information batch monitoring method
CN104537090B (en) User profile standardized data treating method and apparatus
CN205983542U (en) Chain operation management system based on thing networking
JP7283541B2 (en) CABLE CONNECTION SUPPORT SYSTEM, CABLE CONNECTION SUPPORT METHOD, AND CABLE CONNECTION SUPPORT PROGRAM
Verma et al. Multi-Agent Communication Based Train Control System for Indian Railways: The Structural Design.
CN209182854U (en) A kind of part management system of offing normal based on UWB label
CN208572106U (en) A kind of system for the alarm of power communication access path
CN104240027A (en) Transaction schedule tracking management method and device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190510