CN109736841A - Precast lining abutment wall overlap joint cannelure seam in tunnel pours end mould and device - Google Patents

Precast lining abutment wall overlap joint cannelure seam in tunnel pours end mould and device Download PDF

Info

Publication number
CN109736841A
CN109736841A CN201811649672.XA CN201811649672A CN109736841A CN 109736841 A CN109736841 A CN 109736841A CN 201811649672 A CN201811649672 A CN 201811649672A CN 109736841 A CN109736841 A CN 109736841A
Authority
CN
China
Prior art keywords
tunnel
side wall
end mould
mould
contact plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811649672.XA
Other languages
Chinese (zh)
Other versions
CN109736841B (en
Inventor
林春刚
王培传
王百泉
高攀
尚伟
李荆
谢韬
邹翀
陈艺升
王百朋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Tunnel Group Co Ltd CRTG
CRTG Survey and Design Institute Co Ltd
Original Assignee
China Railway Tunnel Group Co Ltd CRTG
CRTG Survey and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Tunnel Group Co Ltd CRTG, CRTG Survey and Design Institute Co Ltd filed Critical China Railway Tunnel Group Co Ltd CRTG
Priority to CN201811649672.XA priority Critical patent/CN109736841B/en
Publication of CN109736841A publication Critical patent/CN109736841A/en
Application granted granted Critical
Publication of CN109736841B publication Critical patent/CN109736841B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses provide a kind of tunnel precast lining abutment wall overlap joint cannelure seam to pour end mould and device, the longitudinal joint end mould includes a contact plate, contact plate is used to be covered in the top of side wall form end, the upper end of contact plate is extended with lug boss to tunnel-side direction, forms the closed cavity for pouring the lining of side wall two between part, side wall form and tunnel-side face that lug boss, the contact plate of longitudinal joint end mould stretch out above the wall form of side;The shape of lug boss meets the following conditions: forming side wall two pouring and serves as a contrast and after removing longitudinal joint end mould, the position where lug boss forms mounting groove, mounting groove is used to mutually be equipped with the end of arch prefabricated pipe section on the top wall surface that side wall two serves as a contrast.Realize the equipped of arch prefabricated pipe section and side wall form.

Description

Precast lining abutment wall overlap joint cannelure seam in tunnel pours end mould and device
Technical field
The invention belongs to Tunneling by mining method two to serve as a contrast technical field of construction, and in particular to precast lining abutment wall overlap joint in tunnel is vertical The line of rabbet joint pours end mould and device.
Background technique
Railroad train driving as railway tunnel accumulative mileage increases, railroad train speed is further promoted, in tunnel Safety requirements is higher and higher, and wherein tunnel arch mass defect disease seriously threatens train operating safety.Be mainly reflected in Under several aspects: 1. secondary lining occurs cracking and percolating water phenomenon, not only affects tunnel service life, but also to contact net Equal charging equipments constitute security risk;2. dew muscle and voids and pits phenomenon occurs in secondary lining surface, secondary lining is reduced Also the overall beautiful of tunnel is affected while intensity;3. coming to nothing behind often occurs in Arch lining, intensity thickness is insufficient and Phenomena such as mass defects such as chip off-falling cause secondary lining intensity that design value is not achieved, and overall structure load ability declines, chip off-falling is more It is to have seriously threatened traffic safety.For this purpose, comprehensively considering from construction quality, safe operation and economy, needing to explore can be protected Hinder the Tunnel Second Lining new method of tunnel arch quality, and designs the new equipment applied in new method.
The object of the present invention is to provide a kind of Tunnel Second Lining Construction new methods, secondary to solve previous domain pouring type The problem of lining construction process.
Summary of the invention
Technical problem to be solved by the present invention lies in view of the above shortcomings of the prior art, provide a kind of tunnel pin-connected panel Lining side wall overlap joint cannelure seam pours end mould and device, realizes the equipped of arch prefabricated pipe section and side wall form.
In order to solve the above technical problems, the technical solution adopted by the present invention is that, tunnel precast lining abutment wall overlaps cannelure Seam pours end mould, which includes a contact plate, and contact plate is used to be covered in the top of side wall form end, contact plate Upper end be extended with lug boss to tunnel-side direction, lug boss, the contact plate of longitudinal joint end mould stretch out above the wall form of side Part, the closed cavity for pouring the lining of side wall two is formed between side wall form and tunnel-side face;The shape of lug boss meets The following conditions: it to form side wall two pouring and serves as a contrast and after removing longitudinal joint end mould, the position where lug boss is served as a contrast in side wall two Mounting groove is formed on the wall surface of top, mounting groove is used to mutually be equipped with the end of arch prefabricated pipe section.
Further, which includes the vertical panel with the perpendicular connection in the end of contact plate, the trend of vertical panel with The edge of the end of contact plate is consistent;The end of vertical panel is connected with the slot template perpendicular with it, and slot template is located at and connects The opposite side of touch panel;The shape of slot template is integrated two parts of connection, and the part far from vertical panel is located at close to vertical panel Partial top;When contact plate is covered in the top of side wall form end, vertical panel and slot template are located at close to tunnel side Wall side, and slot template end is closely affixed on tunnel-side.
Further, one end opposite with end where vertical panel of the contact plate is connected with guiding fagging, guiding support vertically Plate and vertical panel are located at two relative walls of contact plate;It is connected in the outside wall surface of guiding fagging and is arranged at intervals with two end mould limits Plate.
Further, which is a section or more piece, and when for more piece, each longitudinal joint end mould is in the longitudinal direction sequentially Connection, the width after connection are consistent with the width of side wall form.
The invention also discloses tunnel precast lining abutment wall overlap joint cannelure seams to pour device, including above-mentioned longitudinal joint end Mould further includes the power device for controlling the installation of longitudinal joint end mould and demoulding;
Power device includes that two end moulds support guide bracket, and each shape for holding mould support guide bracket is inverted "L" shape, and galianconism end passes through de- Mould oil cylinder is connected with the upper wall surface of contact plate, and the wall surface of demoulding oil jar and contact plate is vertically arranged;Its is long-armed positioned at contact plate One end opposite with protrusion, and be located between two end mould limit plates, fitted closely with the outside wall surface for being oriented to fagging, end For hinged with the outside wall surface of side wall form;Demoulding oil jar and end mould support guide bracket match, and longitudinal joint end mould is driven to move up and down; Wherein, guide bracket is supportted at least provided with an end mould on each contact plate.
Further, the end mould support guide bracket long-armed width between two end mould limit plates at a distance from it is consistent.
Further, which further includes overturning oil cylinder, one end of overturning oil cylinder and the long-armed hinge of end mould support guide bracket It connects, longitudinal joint end mould is driven to move to close to or far from tunnel-side.
Further, the other end of the overturning oil cylinder and horizontally disposed overturning oil cylinder support are hinged, at work, overturning Cylinder support is installed on formwork jumbo.
The invention also discloses above-mentioned tunnel precast lining abutment wall overlap joint cannelure seams to pour end mould in tunnel vault pipe Application in piece assembly, which is characterized in that the longitudinal joint end mould is used cooperatively with side wall form, and longitudinal joint end mould is for being covered in side The top of sidewall template end, and fitted closely with its upper wall surface, after pouring, longitudinal joint end mould, which is closely affixed on, to be poured to form side wall The top wall surface of two linings;After the lining solidification of side wall two, end mold device and side wall form are removed, in the top wall that side wall two serves as a contrast Mounting groove is formed on face, is mutually equipped with for the end with arch prefabricated pipe section, after being equipped with, the lining of side wall two and arch prefabricated pipe section Together form Tunnel Second Lining;Side wall form is an arc panel, and consistent with the radian of tunnel-side, height is lower than The height in tunnel, the two sides for being placed in tunnel, side wall of the convex side towards respective side;Positioned at two sides corresponding position It is prefabricated pipe section installation site in arch at tunnel vault between the end of two side wall forms.
A kind of tunnel side wall cannelure seam of the present invention pours end mould and device has the advantages that for side wall longitudinal slot Type section pours, and Template Location and is convenient in demoulding, and structure is simple, while the end mold device can be conveniently mounted at side wall mould On pallet vehicle.
Detailed description of the invention
Fig. 1 is the perspective view that precast lining abutment wall in tunnel of the present invention overlaps that cannelure seam pours end mould and device.
Fig. 2 is the positional diagram of each component in the mould of longitudinal joint end;
Fig. 3 is the longitudinal joint end mould perspective view equipped with end mould limit plate;
Fig. 4 is that end mould supports guide bracket perspective view;
Fig. 5 position main view in tunnel for the device in the present invention;
Fig. 6 is that the device in the present invention demoulds original state partial enlarged view;
Fig. 7 is that demoulding oil jar contraction longitudinal joint end mould demoulds state partial enlarged view completely;
Fig. 8 overturning oil cylinder shrinks longitudinal joint end mould rollover states partial enlarged view;
Fig. 9 template oil cylinder shrinks longitudinal joint end mould and demoulds state partial enlarged view completely with side wall form;
The arch Figure 10 prefabricated pipe section assembles position main view;
The longitudinal spliced seam partial enlarged view of the arch Figure 11 piece pipe;
Wherein: 1. longitudinal joint end moulds;1a. slot template;1b. channel mould web;1c. is oriented to fagging;The end 1d mould limit plate;1e. is fixed Position pin hole;1f bolt connecting hole;1g. contact plate;1h. vertical panel;2. end mould supports guide bracket;The first otic placode of 2a.;The second otic placode of 2b.; 2c. supports guide bracket limited block;3. demoulding oil jar;4. overturning oil cylinder;5. overturning oil cylinder support;6. side wall form;7. side wall two Lining;8. arch prefabricated pipe section;9. seam waterproof gasket;10. side mode oil cylinder;11. side wall formwork jumbo.
Specific embodiment
Tunnel precast lining abutment wall overlap joint cannelure seam of the present invention pours end mould, as shown in Fig. 1,2,3 and 4, the longitudinal joint end Mould 1 includes a contact plate 1g, and contact plate 1g is used to be covered in the top of 6 end of side wall form, and the upper end of contact plate 1g is to tunnel Road sidewall direction is extended with lug boss, lug boss, the contact plate 1g of longitudinal joint end mould 1 stretch out part above side wall form 6, The closed cavity for pouring the lining of side wall two 7 is formed between side wall form 6 and tunnel-side face;The shape of lug boss meets following item Part: it is pouring to form the lining of side wall two 7 and after removing longitudinal joint end mould 1, the position where lug boss, on the top of the lining of side wall two 7 Mounting groove is formed on portion's wall surface, mounting groove is used to mutually be equipped with the end of arch prefabricated pipe section 8.
Above-mentioned protrusion includes the vertical panel 1h with the perpendicular connection in the end of contact plate 1g, the trend of vertical panel 1h with connect The edge of the end of touch panel 1g is consistent;The end of vertical panel 1h is connected with the slot template 1a perpendicular with it, and slot template 1a Positioned at the opposite side of contact plate 1g;The shape of slot template 1a is integrated two parts of connection, and the part far from vertical panel 1h is located at Close to the top of the part of vertical panel 1h;When contact plate 1g is covered in the top of 6 end of side wall form, vertical panel 1h and slot Template 1a is located at close to tunnel-side side, and the end slot template 1a is closely affixed on tunnel-side.Contact plate 1g's and vertical panel The opposite one end in end where 1h is connected with guiding fagging 1c vertically, and guiding fagging 1c and vertical panel 1h are located at the two-phase of contact plate 1g To wall surface;It is connected in the outside wall surface of guiding fagging 1c and is arranged at intervals with two end mould limit plate 1d.Longitudinal joint end mould 1 is a section or more Section, when for more piece, each longitudinal joint end mould 1 is sequentially connected in the longitudinal direction, the width of the width after connection and side wall form 6 It is consistent.
The invention also discloses tunnel precast lining abutment wall overlap joint cannelure seam pour end mold device, with realize construction from Dynamicization further includes the power device for controlling the installation of longitudinal joint end mould 1 and demoulding including above-mentioned longitudinal joint end mould 1;Power device Support guide brackets 2 including two end moulds, each shape for holding mould support guide bracket 2 is inverted "L" shape, galianconism end by demoulding oil jar 3 with contact The upper wall surface of plate 1g is connected, and demoulding oil jar 3 and the wall surface of contact plate 1g are vertically arranged;Its it is long-armed positioned at contact plate 1g with it is prominent The opposite one end in the portion of rising, and be located between two end mould limit plate 1d, it is fitted closely with the outside wall surface of guiding fagging 1c, end is used In hinged with the outside wall surface of side wall form 6;Demoulding oil jar 3 and end mould support guide bracket 2 match, and drive and move down on longitudinal joint end mould 1 It is dynamic;Wherein, guide bracket 2 is supportted at least provided with an end mould on each contact plate 1g.
Hold mould support guide bracket 2 long-armed width between two end mould limit plate 1d at a distance from it is consistent.
Power device further includes overturning oil cylinder 4, and one end of overturning oil cylinder 4 and end mould support the long-armed hinged of guide bracket 2, drive vertical Seam end mould 1 is moved to close to or far from tunnel-side.The other end of overturning oil cylinder 4 and horizontally disposed overturning oil cylinder support 5 Hingedly, at work, overturning oil cylinder support 5 is installed on formwork jumbo.
Construction is served as a contrast using the independent prefabricated Tunneling by mining method two in arch, that is, standardizes the arch prefabricated pipe section 8 of batch production, And only, in tunnel, avris pours the lining of side wall two 7, to solve arch prefabricated pipe section 8, pours the assembly between the lining of side wall two 7 with side Problem, the invention also discloses above-mentioned tunnel side wall cannelure seams to pour application of the end mould in tunnel vault pipe sheet assembling, The longitudinal joint end mould 1 is used cooperatively with side wall form 6, and longitudinal joint end mould 1 is used to be covered in the top of 6 end of side wall form, and It is fitted closely with its upper wall surface, after pouring, longitudinal joint end mould 1 is closely affixed on the top wall surface for pouring and forming the lining of side wall two 7;Side After 7 solidification of the lining of wall two, end mold device and side wall form 6 are removed, forms mounting groove on the top wall surface of the lining of side wall two 7, It is mutually equipped with for the end with arch prefabricated pipe section 8, after being equipped with, the lining of side wall two 7 together forms tunnel with arch prefabricated pipe section 8 Road secondary lining;Side wall form 6 is an arc panel, consistent with the radian of tunnel-side, and height is lower than the height in tunnel, Two sides for being placed in tunnel, side wall of the convex side towards respective side;Positioned at two side walls of two sides corresponding position It is prefabricated pipe section 8 installation site in arch at tunnel vault between the end of template 6.
As shown in FIG. 10 and 11, the arch prefabricated pipe section for standardizing batch production has stringent size and required precision, together When precision also poured to matched side wall cannelure seam propose to be strict with.The assembly of arch prefabricated pipe section 8 needs in place It to serve as a contrast 7 longitudinal slots with side wall two tightly to cooperate, the mounting groove after arch prefabricated pipe section 8 assembles in place is filled with seam waterproof Gasket 9.
For the intensity for enhancing longitudinal joint end mould 1, at longitudinal joint end, the upper wall surface of mould 1 is arranged at intervals with multiple channel mould web 1b, slot Mould web 1b is arranged along the cross section of longitudinal joint end mould 1.Bolt company is offered on the channel mould web 1b at 1 both ends of longitudinal joint end mould Hole 1e and dowel hole 1f are met, to realize being detachably connected for two neighboring longitudinal joint end mould 1.
Since the width of side wall form 6 is up to 12 meters, from the point of view of safety and facilitating construction, longitudinal joint end mould 1 It may be configured as more piece, more piece is successively spliced, and after splicing, the length of longitudinal joint end mould 1 is consistent with the width of side wall form 6.It spells When connecing, it is connected by the bolt connecting hole 1e opened up on channel mould web 1b with dowel hole 1f.If not considering cost and applying Convenience during work, theoretically and can be only with a longitudinal joint end mould 1, the length and side wall of the longitudinal joint end mould 1 The width of template 6 is consistent.When longitudinal joint end mould 1 is integral, then two end moulds support guide brackets are arranged in interval on longitudinal joint end mould 1 2 and oil cylinder engaged therewith.When longitudinal joint end mould 1 is multiple, only in the upper each setting one of two in 6 both ends of side wall form A end mould support guide bracket 2 and oil cylinder engaged therewith.
The long arm end of end mould support guide bracket 2 is provided with the first otic placode 2a, for the ear with the corresponding position on side wall form 6 Plate is hinged, and the long-armed two opposite side wall surfaces in end are provided with support guide bracket limited block 2c, when installation, is located at corresponding end plate and limits Position block 1d side is provided with the second otic placode 2b on long-armed side wall, hinged with one end of overturning oil cylinder 4.
Precast lining abutment wall in tunnel of the present invention overlap joint cannelure seam pours end mold device in use, in-site installation, specifically such as Under:
Step 1: the ear that mould support guide bracket 2 will be held to pass through the corresponding position on the otic placode 2a and side wall form 6 being arranged thereon Plate is hinged, the otic placode 2b being arranged on mould support guide bracket 2 and one end of overturning oil cylinder 4 will be held hinged.
Step 2: by the end of overturning oil cylinder support 5 with side wall formwork jumbo 11 is detachable is fixedly connected, connection position It sets and boundary condition and 4 model of overturning oil cylinder are overturn according to end mould support guide bracket 2 determines, and by the other end of overturning oil cylinder 4 and overturning Otic placode on cylinder support 5 is hinged.As shown in Figure 5.
Step 3: longitudinal joint end mould 1 is placed in position by human assistance, that is, it is covered in the top of 6 end of side wall form Vertical panel 1h and slot template 1a is located at close to tunnel-side side, and the outer end of slot template 1a is closely affixed on tunnel-side.Overturning oil 4 end mould of cylinder support the long-armed of guide bracket 2 is stuck between two end mould limit plate 1d, and the outer surface long-armed guiding fagging 1c is closely pasted It closes.
Step 4: 2 galianconism of guide bracket is supportted in cylinder body one end welding of demoulding oil jar 3 or the detachable end mould that is fixedly connected on End, piston rod welding or the detachable upper surface for being fixedly connected on contact plate 1g by demoulding oil jar 3.After connection, indulge Stitching end mould 1 can slide with the flexible of 3 piston rod of demoulding oil jar along the end mould support long-armed face of guide bracket 2.
When longitudinal joint end mould 1 is in place, step 1: the jacking of demoulding oil jar 3 pushes longitudinal joint end mould 1 to make that mould limit plate 1d is held to reach end Mould supports guide bracket limited block 2c and limits transition, i.e. end mould limit plate 1d is affixed on the top of end mould support guide bracket limited block 2c;Step 2: turning over Turn the jacking of oil cylinder 4, promote-side mould supports guide bracket 2 and pours the overturning of section exterior normal direction around the hinged axial direction of otic placode 2a, makes slot template 1a pours face and is bonded completely with 6 top wall surface of side wall form, completes the relative positioning of longitudinal joint end mould 1 and side wall form 6;The Three steps: the side mode oil cylinder 10 of side wall formwork jumbo 11 jacks affixed side sidewall template 6, and longitudinal joint end mould 1 is complete with side wall form 6 At state positioning is finally poured, after-pouring is positioned.
After 7 solidification of the lining of side wall two, longitudinal joint end mould 1 is demoulded, and side wall seam pours device demoulding original state partial enlarged view As shown in Figure 6.It is specific as follows:
Step 1: shrinking demoulding oil jar 3, so that slot template 1a and side wall is poured longitudinal groove profile section and demould, avoid machinery Destruction is formed to two chemise bodies are completed, demoulding oil jar shrinks longitudinal joint end mould and demoulds state partial enlarged view such as Fig. 7 and 8 institute completely Show.
Step 2: shrinking overturning oil cylinder 4, make longitudinal joint end mould 1, end mould support guide bracket 2 and demoulding oil jar 3 around the hinged of otic placode 2a Axially pour the overturning of section inter normal direction, it is therefore an objective to avoid turning over the interference of 8 subsequent installation corollary equipment of arch prefabricated pipe section It is as shown in Figure 7 to turn oil cylinder contraction longitudinal joint end mould rollover states partial enlarged view.
Step 3: contraction edge mould oil cylinder 10, makes side wall form 6 realize complete demoulding, longitudinal joint end mould 1 is with side wall form Demoulding state partial enlarged view completely is as shown in Figure 9.After demoulding, mounting groove is formed on the top wall surface of the lining of side wall two 7, with The end of arch prefabricated pipe section 8 is mutually equipped with.As shown in figs. 9-10, end phase when installation, in mounting groove with arch prefabricated pipe section 8 Contact position is placed with seam waterproof gasket 9.

Claims (9)

1. precast lining abutment wall overlap joint cannelure seam in tunnel pours end mould, which is characterized in that the longitudinal joint end mould (1) includes a contact Plate (1g), the contact plate (1g) are used to be covered in the top of side wall form (6) end, the upper end of the contact plate (1g) to Tunnel-side direction is extended with lug boss, and lug boss, the contact plate (1g) of longitudinal joint end mould (1) are stretched out in side wall form (6) it is formed between the part, side wall form (6) and tunnel-side face above and pours the closed cavity that side wall two serves as a contrast (7);It is described The shape of lug boss meets the following conditions: it to form side wall two pouring and serves as a contrast (7) and after removing longitudinal joint end mould (1), it is described Position where lug boss, forms mounting groove on the top wall surface of the side wall two lining (7), and the mounting groove is used for and arch The end of portion's prefabricated pipe section (8) is mutually equipped with.
2. tunnel precast lining abutment wall overlap joint cannelure seam according to claim 1 pours end mould, which is characterized in that described Protrusion includes the vertical panel (1h) with the perpendicular connection in end of contact plate (1g), the trend of the vertical panel (1h) with contact The edge of the end of plate (1g) is consistent;The end of the vertical panel (1h) is connected with the slot template perpendicular with it (1a), and The slot template (1a) is located at the opposite side of contact plate (1g);The shape of the slot template (1a) is integrated two parts of connection, Part far from vertical panel (1h) is located at the top close to the part of vertical panel (1h);When the contact plate (1g) is covered in side When the top of wall form (6) end, the vertical panel (1h) and slot template (1a) are located at the close tunnel-side side, and described The end slot template (1a) is closely affixed on tunnel-side.
3. according to right want 2 described in tunnel precast lining abutment wall overlap joint cannelure seam pour end mould, which is characterized in that described One end opposite with end where vertical panel (1h) of contact plate (1g) is connected with guiding fagging (1c), the guiding fagging vertically (1c) and vertical panel (1h) is located at two relative walls of contact plate (1g);Setting is spaced in the outside wall surface of guiding fagging (1c) There are two hold mould limit plate (1d).
4. tunnel precast lining abutment wall overlap joint cannelure seam according to claim 5 pours end mould, which is characterized in that described Longitudinal joint end mould (1) is a section or more piece, and when for more piece, each longitudinal joint end mould (1) is sequentially connected in the longitudinal direction, connection Width afterwards is consistent with the width of side wall form (6).
5. precast lining abutment wall overlap joint cannelure seam in tunnel pours device, which is characterized in that including any one of claim 1-4 The longitudinal joint end mould (1) further includes the power device for controlling longitudinal joint end mould (1) installation and demoulding;
The power device includes that two end moulds support guide bracket (2), and the shape of each end mould support guide bracket (2) is inverted "L" shape, short Arm end is connected by demoulding oil jar (3) with the upper wall surface of contact plate (1g), the wall of the demoulding oil jar (3) and contact plate (1g) Face is vertically arranged;Its long-armed one end opposite with protrusion positioned at contact plate (1g), and it is located at two end mould limit plates (1d) Between, it is fitted closely with the outside wall surface of guiding fagging (1c), end is used for hinged with the outside wall surface of side wall form (6);It is described Demoulding oil jar (3) and end mould support guide bracket (2) match, and longitudinal joint end mould (1) is driven to move up and down;Wherein, each contact plate Guide bracket (2) are supportted at least provided with an end mould on (1g).
6. tunnel precast lining abutment wall overlap joint cannelure seam according to claim 7 pours device, which is characterized in that described Hold mould support guide bracket (2) long-armed width between two end mould limit plates (1d) at a distance from it is consistent.
7. tunnel precast lining abutment wall overlap joint cannelure seam according to claim 7 or 8 pours device, which is characterized in that The power device further includes overturning oil cylinder (4), and one end of the overturning oil cylinder (4) and end mould support the long-armed hinged of guide bracket (2), Longitudinal joint end mould (1) is driven to move to close to or far from tunnel-side.
8. tunnel precast lining abutment wall overlap joint cannelure seam according to claim 9 pours device, which is characterized in that described The other end of overturning oil cylinder (4) and horizontally disposed overturning oil cylinder support (5) hingedly, at work, the overturning oil cylinder support (5) it is installed on formwork jumbo.
9. tunnel precast lining abutment wall overlap joint cannelure seam of any of claims 1-4 pours end mould in tunnel vault Application in pipe sheet assembling, which is characterized in that the longitudinal joint end mould (1) is used cooperatively with side wall form (6), longitudinal joint end mould (1) it for being covered in the top of side wall form (6) end, and is fitted closely with its upper wall surface, after pouring, longitudinal joint end mould (1) it is closely affixed on and pours to form the top wall surface that side wall two serves as a contrast (7);After side wall two serves as a contrast (7) solidification, the end mould dress is removed Set with side wall form (6), side wall two serve as a contrast (7) top wall surface on form mounting groove, be used for and arch prefabricated pipe section (8) End be mutually equipped with, after being equipped with, side wall two serves as a contrast (7) and arch prefabricated pipe section (8) and together forms Tunnel Second Lining;
The side wall form (6) is an arc panel, consistent with the radian of tunnel-side, and height is lower than the height in tunnel, Two sides for being placed in tunnel, side wall of the convex side towards respective side;Positioned at two side walls of two sides corresponding position It is arch prefabricated pipe section (8) installation site at tunnel vault between the end of template (6).
CN201811649672.XA 2018-12-30 2018-12-30 Tunnel split type lining side wall lap joint longitudinal slot pouring end die and device Active CN109736841B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811649672.XA CN109736841B (en) 2018-12-30 2018-12-30 Tunnel split type lining side wall lap joint longitudinal slot pouring end die and device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811649672.XA CN109736841B (en) 2018-12-30 2018-12-30 Tunnel split type lining side wall lap joint longitudinal slot pouring end die and device

Publications (2)

Publication Number Publication Date
CN109736841A true CN109736841A (en) 2019-05-10
CN109736841B CN109736841B (en) 2020-06-30

Family

ID=66362948

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811649672.XA Active CN109736841B (en) 2018-12-30 2018-12-30 Tunnel split type lining side wall lap joint longitudinal slot pouring end die and device

Country Status (1)

Country Link
CN (1) CN109736841B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110566246A (en) * 2019-09-29 2019-12-13 中铁十七局集团第一工程有限公司 Tunnel arc-shaped side top plate laying device and method
CN111456759A (en) * 2020-01-23 2020-07-28 中铁二院工程集团有限责任公司 Assembled tunnel lining structure
CN113417669A (en) * 2021-07-29 2021-09-21 中铁隧道集团一处有限公司 Lining construction method for side wall cast-in-place and arch prefabricated segment spherical joint assembly

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EA012014B1 (en) * 2007-04-24 2009-06-30 Федор Серафимович Темников A brake block for high-speed locomotive and gasoline locomotive railway rolling stock
CN202055263U (en) * 2011-04-21 2011-11-30 中国水利水电第五工程局有限公司 Reinforced concrete corridor
CN205370593U (en) * 2016-02-25 2016-07-06 中交一公局第三工程有限公司 Two lining edge walls and cable duct integral type construction formwork
CN105822324A (en) * 2016-04-05 2016-08-03 中铁三局集团有限公司 Full-automatic tunnel end form
CN105909278A (en) * 2016-06-28 2016-08-31 中国冶集团有限公司 Combined automatic control mold rack and use method
CN107060829A (en) * 2017-05-24 2017-08-18 福州大学 Precast lining structure for tunnel model test and preparation method thereof
CN207212356U (en) * 2017-05-22 2018-04-10 中国铁建大桥工程局集团有限公司 A kind of Tunnel Second Lining termination folding template
CN108019226A (en) * 2017-12-29 2018-05-11 中国铁道科学研究院铁道建筑研究所 A kind of tunnel lining trolley end head formwork
CN207513609U (en) * 2017-11-23 2018-06-19 中铁十四局集团有限公司 A kind of two lining trolley end head formworks of Fast Installation positioning

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EA012014B1 (en) * 2007-04-24 2009-06-30 Федор Серафимович Темников A brake block for high-speed locomotive and gasoline locomotive railway rolling stock
CN202055263U (en) * 2011-04-21 2011-11-30 中国水利水电第五工程局有限公司 Reinforced concrete corridor
CN205370593U (en) * 2016-02-25 2016-07-06 中交一公局第三工程有限公司 Two lining edge walls and cable duct integral type construction formwork
CN105822324A (en) * 2016-04-05 2016-08-03 中铁三局集团有限公司 Full-automatic tunnel end form
CN105909278A (en) * 2016-06-28 2016-08-31 中国冶集团有限公司 Combined automatic control mold rack and use method
CN207212356U (en) * 2017-05-22 2018-04-10 中国铁建大桥工程局集团有限公司 A kind of Tunnel Second Lining termination folding template
CN107060829A (en) * 2017-05-24 2017-08-18 福州大学 Precast lining structure for tunnel model test and preparation method thereof
CN207513609U (en) * 2017-11-23 2018-06-19 中铁十四局集团有限公司 A kind of two lining trolley end head formworks of Fast Installation positioning
CN108019226A (en) * 2017-12-29 2018-05-11 中国铁道科学研究院铁道建筑研究所 A kind of tunnel lining trolley end head formwork

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
杨秀仁等: "地铁车站预制装配新技术研究策略", 《都市快轨交通》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110566246A (en) * 2019-09-29 2019-12-13 中铁十七局集团第一工程有限公司 Tunnel arc-shaped side top plate laying device and method
CN111456759A (en) * 2020-01-23 2020-07-28 中铁二院工程集团有限责任公司 Assembled tunnel lining structure
CN113417669A (en) * 2021-07-29 2021-09-21 中铁隧道集团一处有限公司 Lining construction method for side wall cast-in-place and arch prefabricated segment spherical joint assembly
CN113417669B (en) * 2021-07-29 2023-12-15 中铁隧道集团一处有限公司 Lining construction method for cast-in-situ side wall and assembling arch prefabricated segment spherical joint

Also Published As

Publication number Publication date
CN109736841B (en) 2020-06-30

Similar Documents

Publication Publication Date Title
CN109736841A (en) Precast lining abutment wall overlap joint cannelure seam in tunnel pours end mould and device
CN104594918B (en) Split integrated underground passage steel mold plate trolley and construction method thereof
CN109681238A (en) The lining of tunnel side wall two pours and vault prefabricated pipe section transfer formwork jumbo
CN111594228B (en) Lining of round water delivery tunnel steel mould trolley and construction method
CN109869164A (en) Combination hydraulic formwork jumbo pours the construction method of porous separate tunnel
CN110905554A (en) Tunnel inverted arch and filled concrete paver and construction process
CN109958143A (en) A kind of piping lane prefabricated mould and piping lane construction method
CN203756193U (en) Steel end template of dual-hinged overturning-applicable tunnel lining trolley
CN111441574A (en) Method and structure for pouring concrete floor post-cast strip by adopting inflatable template
CN211314235U (en) Tunnel inverted arch and filling concrete paver
CN110924988B (en) Tunnel secondary lining concrete chute pouring system and construction method
CN206419032U (en) A kind of side and roof arch band mid-board lining cutting chassis
CN110106788B (en) Post-cast section construction method for butt joint of track beams
CN106050268B (en) Round rectangle section tunnel concrete liner telescoping steel form
CN109605547A (en) A kind of prefabricated piping lane rapid molding device and method
CN113463683A (en) Double-pipe gallery slip form trolley and double-pipe gallery construction method
CN112746857A (en) Full-hydraulic highway tunnel cable trench lining construction device and construction method
CN108181145A (en) The prefabricated pre-embedded device of tunnel-liner and method in a kind of geomechanical model test
CN109629437A (en) A kind of mobile whole hole in-situ depositing equipment of box beam and its application method
CN111441239B (en) Prefabricated cover beam prestress deep-buried anchor sleeve and installation process thereof
CN214464241U (en) Full-hydraulic lining construction device for cable trench of highway tunnel
CN103821110A (en) Box culvert inner form steel form trolley
CN210422643U (en) Tunnel center drainage ditch pouring template
CN205955750U (en) Rounded rectangle cross -section tunnel steel mould trolley for concrete lining
CN209619827U (en) Full-hydraulic crawler-type self trestle

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant