CN109736593B - 地下工程群坑中隔墙凿除方法 - Google Patents

地下工程群坑中隔墙凿除方法 Download PDF

Info

Publication number
CN109736593B
CN109736593B CN201910144252.4A CN201910144252A CN109736593B CN 109736593 B CN109736593 B CN 109736593B CN 201910144252 A CN201910144252 A CN 201910144252A CN 109736593 B CN109736593 B CN 109736593B
Authority
CN
China
Prior art keywords
chiseling
intermediate wall
wall
pit
chiseled
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201910144252.4A
Other languages
English (en)
Other versions
CN109736593A (zh
Inventor
杨建新
宋正刚
濮松权
吴波
彭逸勇
韦汉
蒙国往
石雷
何山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ningbo Track Traffic Group Co ltd Construction Branch
Guangxi University
Fifth Engineering Co Ltd of China Railway No 10 Engineering Group Co Ltd
Original Assignee
Guangxi University
Fifth Engineering Co Ltd of China Railway No 10 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangxi University, Fifth Engineering Co Ltd of China Railway No 10 Engineering Group Co Ltd filed Critical Guangxi University
Priority to CN201910144252.4A priority Critical patent/CN109736593B/zh
Publication of CN109736593A publication Critical patent/CN109736593A/zh
Application granted granted Critical
Publication of CN109736593B publication Critical patent/CN109736593B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

本发明公开了一种地下工程群坑中隔墙凿除方法,包括以下步骤:(1)划分好待凿除部分中隔墙和保留部分中隔墙;(2)将待凿除部分中隔墙进行分块,然后对分块的中隔墙进行凿除,凿除过程中两块分块中间预留临时保留部分中隔墙;(3)分块的中隔墙凿除完毕后,建造基坑中隔墙间永久性的构造柱;(4)待构造柱建造完成后,凿除临时保留部分中隔墙;(5)待凿除部分中隔墙全部凿除完后,清理废弃混凝土渣,进行后浇带施工。本发明地下工程群坑中隔墙凿除方法,在施工过程中,保留临时部分中隔墙作为施工过程中的临时承力结构,能很好的保证施工过程中的安全。在凿除过程中,能很好的控制凿除洞口的质量,也有较好的施工效率。

Description

地下工程群坑中隔墙凿除方法
技术领域
本发明涉及地下工程建筑施工领域,特别涉及一种地下工程群坑中隔墙凿除方法。
背景技术
近年来越来越来多的城市开始修建地铁,地铁车站的结构也更加复杂,车站基坑中群坑所占的比例逐渐增大,在单个基坑施工技术日趋成熟完善的情况下,优化地下工程中群坑的施工技术尤为重要。其中,中隔墙是群基坑工程中不同于单个基坑工程的部分之一,群坑中的中隔墙在基坑施工的后期要凿除一部分作为车站运营期间车站内各个部分之间的出入口。在基坑工程施工过程中中隔墙的拆除施工是一个繁杂的过程,中隔墙自身作为受力的部分连接着两侧的基坑涉及结构安全和施工安全。目前的凿除工法大多数是将要凿除的部分划分,进行凿除,再建结构柱。然而在地质条件复杂,内部结构强度较低的基坑工程中这样方法容易对基坑内部结构造成破坏,往往需要进行复杂的加固保护措施。而现在的群坑中隔墙凿除方法中,较少涉及如何安全,高效的凿除方法。
公开于该背景技术部分的信息仅仅旨在增加对本发明的总体背景的理解,而不应当被视为承认或以任何形式暗示该信息构成已为本领域一般技术人员所公知的现有技术。
发明内容
本发明的目的在于提供一种地下工程群坑中隔墙凿除方法,保证了中隔墙凿除过程中中隔墙和基坑的安全,不需要附加的加固措施,而且方法灵活可靠,能大大降低施工费用。
为实现上述目的,本发明提供了一种地下工程群坑中隔墙凿除方法,包括以下步骤:
(1)划分好待凿除部分中隔墙和保留部分中隔墙;
(2)将待凿除部分中隔墙进行分块,然后对分块的中隔墙进行凿除,凿除过程中两块分块中间预留临时保留部分中隔墙;
(3)分块的中隔墙凿除完毕后,建造基坑中隔墙间永久性的构造柱;
(4)待构造柱建造完成后,凿除临时保留部分中隔墙;
(5)待凿除部分中隔墙全部凿除完后,清理废弃混凝土渣,进行后浇带施工。
优选地,上述技术方案中,步骤(2)中进行分块为,将待凿除部分中隔墙进行分块,每块长度为5-10m。
优选地,上述技术方案中,步骤(2)中预留临时保留部分中隔墙的长度为0.5-1.5m。
优选地,上述技术方案中,每个分块的中隔墙凿除方法步骤如下:
(1)根据门洞图纸尺寸,按洞口尺寸向内偏移15-25cm处标记洞门切割控制线;
(2)钻孔打眼,使用绳锯切割机按绳锯金刚石切割线进行切割,切割分三部分凿除,中间留宽度1.5-3.0m自上而下后凿除,两边部分自下而上先凿除。
优选地,上述技术方案中,基坑之间通过中隔墙和地连墙连接,当对多层基坑进行施工时,待凿除部分中隔墙的凿除从上至下,先凿除上层的中隔墙和上层的地连墙,然后凿除下层的中隔墙和下层的地连墙。
优选地,上述技术方案中,待凿除部分中隔墙全部凿除完后,开始凿除顶板后浇带范围上翻梁位置的地连墙。
优选地,上述技术方案中,凿除期间,在基坑上每幅地连墙中心架设一道钢支撑,钢支撑底部距离基坑的上翻梁有一定距离。
优选地,上述技术方案中,钢支撑底部距离基坑的上翻梁5-15cm。
优选地,上述技术方案中,钢支撑两侧固定于侧墙牛腿上。
与现有技术相比,本发明具有如下有益效果:
(1)本发明地下工程群坑中隔墙凿除方法,在施工过程中,保留临时部分中隔墙作为施工过程中的临时承力结构,能很好的保证施工过程中的安全。
(2)在凿除过程中,用绳锯切割、人工凿除的方法,能很好的控制凿除洞口的质量,也有较好的施工效率。
附图说明
图1是根据本发明的地下工程群坑中隔墙凿除方法的施工流程图。
图2是根据本发明的凿除方法的中隔墙凿除纵剖面示意图。
图3是根据本发明的方法中隔墙凿除过程中临时保留部分中隔墙的纵剖面示意图。
图4是根据本发明的方法中隔墙凿除过程中建造构造柱的纵剖面示意图。
图5是根据本发明的方法中隔墙凿除完成后的纵剖面示意图。
图6是根据本发明的方法中隔墙单块凿除的结构示意图。
图7是根据本发明的方法中隔墙凿除横剖面示意图。
图8是根据本发明的方法中隔墙凿除对顶板后浇带范围上翻梁位置地连墙凿除的横剖面示意图
图9是根据本发明的方法中隔墙凿除完成后的横剖面示意图。
图10是根据本发明的方法中中隔墙凿除过程中架设钢支撑的横剖面示意图。
具体实施方式
下面结合附图,对本发明的具体实施方式进行详细描述,但应当理解本发明的保护范围并不受具体实施方式的限制。
除非另有其它明确表示,否则在整个说明书和权利要求书中,术语“包括”或其变换如“包含”或“包括有”等等将被理解为包括所陈述的元件或组成部分,而并未排除其它元件或其它组成部分。
如图1至图10所示,根据本发明具体实施方式的一种地下工程群坑中隔墙凿除方法,本实施例以一段长约100米的中隔墙凿除为例,举例的基坑为实际工程中占大部分的双层基坑,分为站厅层和站台层。对单层或多层基坑连接处的中隔墙,此方法也可适用。具体包括以下步骤:
(1)划分好待凿除部分中隔墙和保留部分中隔墙;如图2所示,以一段长约100米的中隔墙凿除为例,分为待凿除部分中隔墙1和保留部分中隔墙2,站厅层和站台层都有待凿除部分中隔墙。
(2)将待凿除部分中隔墙1进行分块,然后对分块的待凿除部分中隔墙进行凿除,凿除过程中两块分块中间预留临时保留部分中隔墙3。
具体为,如图3-6所示,将待凿除部分中隔墙1进行分块,每块长度为5-12m。对每个分块的中隔墙凿除,凿除方法包括,根据门洞图纸尺寸,按洞口尺寸向内偏移20cm处标记洞门切割控制线4。然后人工钻孔打眼,得到洞眼5,将绳锯金刚石切割线6伸入洞眼5内,使用绳锯切割机7牵引绳锯金刚石切割线6进行切割,切割分三部分凿除,中间为凿除门洞区域,中间留宽度2m自上而下后凿除,两边部分自下而上先凿除。先两边后中间能保证单块凿除部分的受力平衡,同时也保证了凿除的高效率。
两块分块待凿除部分中隔墙中间预留0.8m左右长度的临时保留部分中隔墙3,临时保留的部分能作为临时的竖向支撑结构,支撑中隔墙凿除后落空的部分,保证凿除施工过程中基坑结构安全。
(3)分块的待凿除部分中隔墙1凿除完毕后,建造基坑中隔墙间永久性的构造柱8。
(4)待构造柱8建造完成后,凿除临时保留部分中隔墙3。
(5)待凿除部分中隔墙全部凿除完后,清理废弃混凝土渣,进行后浇带施工,拆除支架。
如图7-9所示,本实施例分为两个基坑,即基坑A和基坑B,基坑之间通过中隔墙和地连墙连接。当对多层基坑进行施工时,待凿除部分中隔墙的凿除从上至下,先凿除站厅层的中隔墙和地连墙,然后凿除站台层的中隔墙和地连墙。
具体为,基坑A施工完毕封顶,基坑B内部结构已完成,满堂支架9还未拆除,后浇带待完成,中隔墙连接两个基坑(基坑A和基坑B),中隔墙的凿除从上至下,先凿除站厅层的中隔墙,工人在搭设的支架10上进行作业,支架立杆搭设间距900*900mm,横杆步距1200mm,底、顶部30cm设置横纵向扫地杆,平台四周设置剪刀撑。操作平台悬挑至地连墙边30cm,悬挑部分由支架体系抛出2道斜撑,斜撑至少与2道立杆扣死支撑平台。操作平台下纵向钢管间距30cm,上铺设竹篱笆。
站厅层的中隔墙和地连墙凿除完成后,开始凿除站台层中隔墙和地连墙。待站台层中隔墙和地连墙破除完成后,开始凿除顶板后浇带范围上翻梁位置地连墙11,此部分支架12利用基坑B现有的满堂支架9,悬挑部分1.6m,平台距离地连墙30cm,设置一道斜撑。本实施例中,基坑B有施工完基坑内部结构尚未拆除的满堂支架,利用此满堂支架加斜撑即可作为凿除顶板后浇带范围上翻梁位置地连墙的支架。实际工程中若基坑内无满堂支架,则重新按照要求搭设支架即可。中隔墙部分全部凿除完后,进行底板后浇带13、中板后浇带14、顶板后浇带15施工,拆除支架,清理废弃混凝土渣。
优选地,如图10所示,凿除期间,现场需准备几根钢支撑,如果导改路面一侧(基坑A)侧向土压力造成顶板以上临空地墙侧移,立即采取应急措施。在基坑B上在每幅地连墙中心架设一道钢支撑16,钢支撑16底部距离上翻梁10cm。钢支撑16底部不得贴于顶板上翻梁,两侧固定于侧墙牛腿上。采用钢支撑架设作为应急措施,能保证一侧基坑的侧向土压力造成临空地墙侧移时遏制侧移的位移量。
前述对本发明的具体示例性实施方案的描述是为了说明和例证的目的。这些描述并非想将本发明限定为所公开的精确形式,并且很显然,根据上述教导,可以进行很多改变和变化。对示例性实施例进行选择和描述的目的在于解释本发明的特定原理及其实际应用,从而使得本领域的技术人员能够实现并利用本发明的各种不同的示例性实施方案以及各种不同的选择和改变。本发明的范围意在由权利要求书及其等同形式所限定。

Claims (9)

1.一种地下工程群坑中隔墙凿除方法,其特征在于,包括以下步骤:
(1)划分好待凿除部分中隔墙和保留部分中隔墙;
(2)将待凿除部分中隔墙进行分块,然后对分块的中隔墙进行凿除,凿除过程中两块分块中间预留临时保留部分中隔墙;
(3)分块的中隔墙凿除完毕后,建造基坑中隔墙间永久性的构造柱;
(4)待构造柱建造完成后,凿除临时保留部分中隔墙;
(5)待凿除部分中隔墙全部凿除完后,清理废弃混凝土渣,进行后浇带施工。
2.根据权利要求1所述的地下工程群坑中隔墙凿除方法,其特征在于,步骤(2)中进行分块为,将待凿除部分中隔墙进行分块,每块长度为5-10m。
3.根据权利要求1所述的地下工程群坑中隔墙凿除方法,其特征在于,步骤(2)中预留临时保留部分中隔墙的长度为0.5-1.5m。
4.根据权利要求1所述的地下工程群坑中隔墙凿除方法,其特征在于,每个分块的中隔墙凿除方法步骤如下:
(1)根据门洞图纸尺寸,按洞口尺寸向内偏移15-25cm处标记洞门切割控制线;
(2)钻孔打眼,使用绳锯切割机按绳锯金刚石切割线进行切割,切割分三部分凿除,中间留宽度1.5-3.0m自上而下后凿除,两边部分自下而上先凿除。
5.根据权利要求1所述的地下工程群坑中隔墙凿除方法,其特征在于,基坑之间通过中隔墙和地连墙连接,当对多层基坑进行施工时,待凿除部分中隔墙的凿除从上至下,先凿除上层的中隔墙和上层的地连墙,然后凿除下层的中隔墙和下层的地连墙。
6.根据权利要求1所述的地下工程群坑中隔墙凿除方法,其特征在于,待凿除部分中隔墙全部凿除完后,开始凿除顶板后浇带范围上翻梁位置的地连墙。
7.根据权利要求1所述的地下工程群坑中隔墙凿除方法,其特征在于,凿除期间,在基坑上每幅地连墙中心架设一道钢支撑,钢支撑底部距离基坑的上翻梁有一定距离。
8.根据权利要求7所述的地下工程群坑中隔墙凿除方法,其特征在于,钢支撑底部距离基坑的上翻梁5-15cm。
9.根据权利要求7所述的地下工程群坑中隔墙凿除方法,其特征在于,钢支撑两侧固定于侧墙牛腿上。
CN201910144252.4A 2019-02-27 2019-02-27 地下工程群坑中隔墙凿除方法 Expired - Fee Related CN109736593B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910144252.4A CN109736593B (zh) 2019-02-27 2019-02-27 地下工程群坑中隔墙凿除方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910144252.4A CN109736593B (zh) 2019-02-27 2019-02-27 地下工程群坑中隔墙凿除方法

Publications (2)

Publication Number Publication Date
CN109736593A CN109736593A (zh) 2019-05-10
CN109736593B true CN109736593B (zh) 2021-01-15

Family

ID=66368508

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910144252.4A Expired - Fee Related CN109736593B (zh) 2019-02-27 2019-02-27 地下工程群坑中隔墙凿除方法

Country Status (1)

Country Link
CN (1) CN109736593B (zh)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114351761B (zh) * 2022-01-24 2023-10-13 中国建筑第八工程局有限公司 地下结构的中隔墙处的预埋框架柱的施工方法
CN114351762A (zh) * 2022-01-26 2022-04-15 中国建筑第八工程局有限公司 一种地下室回筑阶段中隔墙明拆施工方法
CN114855884B (zh) * 2022-06-09 2024-03-29 安徽建工集团股份有限公司总承包分公司 一种便于地下基础结构后浇带提前回填土的施工方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009068275A (ja) * 2007-09-14 2009-04-02 Toda Constr Co Ltd 地下構造物の上床版撤去方法
CN103726494A (zh) * 2013-12-30 2014-04-16 上海建工二建集团有限公司 半逆作法下基坑间分隔墙拆除方法
CN104264685A (zh) * 2014-09-28 2015-01-07 上海建工七建集团有限公司 一种中隔墙区域结构合拢的施工方法
CN105421491A (zh) * 2015-09-06 2016-03-23 上海建工七建集团有限公司 一种中隔墙拆除及两侧结构连接的施工方法
CN106499199A (zh) * 2016-12-14 2017-03-15 上海建工二建集团有限公司 临近地铁超深基坑中隔墙临时换撑及其施工方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009068275A (ja) * 2007-09-14 2009-04-02 Toda Constr Co Ltd 地下構造物の上床版撤去方法
CN103726494A (zh) * 2013-12-30 2014-04-16 上海建工二建集团有限公司 半逆作法下基坑间分隔墙拆除方法
CN104264685A (zh) * 2014-09-28 2015-01-07 上海建工七建集团有限公司 一种中隔墙区域结构合拢的施工方法
CN105421491A (zh) * 2015-09-06 2016-03-23 上海建工七建集团有限公司 一种中隔墙拆除及两侧结构连接的施工方法
CN106499199A (zh) * 2016-12-14 2017-03-15 上海建工二建集团有限公司 临近地铁超深基坑中隔墙临时换撑及其施工方法

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
城市轨道交通工程拆除地下连续墙施工技术;朱拥军;《低碳世界》;20170225;全文 *
复杂工况下深基坑临时分隔地下连续墙拆除技术;马春元;《施工技术》;20171215;第46卷(第23期);全文 *
邻地铁的建筑深基坑中隔墙支撑换撑及墙体拆除施工技术;费巍;《建筑施工》;20101230;第32卷(第12期);全文 *

Also Published As

Publication number Publication date
CN109736593A (zh) 2019-05-10

Similar Documents

Publication Publication Date Title
CN109736593B (zh) 地下工程群坑中隔墙凿除方法
CN113090065B (zh) 一种城市核心区多层建筑加固改造工程顺逆结合施工方法
CN210086295U (zh) 一种复合装配式地下结构
CN111058455A (zh) 深基坑支护结构及深基坑施工方法
CN111794254A (zh) 一种铁路边坡预制拼装后浇式骨架护坡结构及其施工方法
CN110820608A (zh) 既有铁路旅客进站天桥拆除方法
CN110847915A (zh) 浅埋粉细砂层双侧壁临时支撑跳割拆除分段回顶施工工艺
CN106065668B (zh) 一种建筑施工方法
CN110685459A (zh) 一种启闭机排架从下部拆除的破碎锤拆除施工方法
CN112160247B (zh) 一种有限空间桥墩群空心高墩异步液压爬模施工方法
CN105386779A (zh) 浅埋岩层中修建大型地下结构物的拱柱法
CN112921986A (zh) 一种装配式地下结构及其与基坑一体化施工方法
CN110424459B (zh) 一种不影响现有道路通行的下穿通道施工工艺
CN112610023B (zh) 一种既有轨道运营区间上拆除建筑物的施工方法
KR200263526Y1 (ko) 매달아 내려치고 되올려치는 콘크리트 구조물 구축장치
CN212129909U (zh) 后浇带侧固内撑钢丝网组合支模体系
DE10256421A1 (de) Verfahren und Vorrichtung zum Herstellen eines Tunnels oder eines Troges
CN210117724U (zh) 一种车库基础结构
CN105714856A (zh) 一种结构负一层和负二层分别顺作的地铁风道建造方法
JP3977700B2 (ja) 既存地下躯体を利用した解体および新築工法
AU2016102393A4 (en) A Method of constructing a column, a tunnel, and a tunnel made from the method
CN114673377B (zh) 历史建筑外墙保留、内部掏空重制施工方法
CN117536262B (zh) 一种暗盖挖结合的地铁车站结构及施工方法
CN219343473U (zh) 一种跨街连廊安装结构
CN220621194U (zh) 一种适用于既有铁路地下通道的新增扶梯结构

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Yang Jianxin

Inventor after: Song Zhenggang

Inventor after: Pu Songquan

Inventor after: Wu Bo

Inventor after: Peng Yiyong

Inventor after: Wei Han

Inventor after: Meng Guowang

Inventor after: Shi Lei

Inventor after: He Shan

Inventor before: Wu Bo

Inventor before: Peng Yiyong

Inventor before: Yang Jianxin

Inventor before: Song Zhenggang

Inventor before: Pu Songquan

Inventor before: Meng Guowang

Inventor before: Wei Han

Inventor before: Shi Lei

Inventor before: He Shan

CB03 Change of inventor or designer information
TA01 Transfer of patent application right

Effective date of registration: 20200206

Address after: 215000 No.9, Jinzhuang street, Jinfeng Road, Suzhou high tech Zone, Suzhou, Jiangsu Province

Applicant after: THE FIFTH ENGINEERING CO., LTD.OF CHINA RAILWAY NO.10 ENGINEERING GROUP Co.,Ltd.

Applicant after: GUANGXI University

Address before: 530004 the Guangxi Zhuang Autonomous Region XiXiangTang Nanning University Road No. 100

Applicant before: GUANGXI University

Applicant before: China Railway Tenth Group Co.,Ltd.

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant
CB03 Change of inventor or designer information

Inventor after: Yang Jianxin

Inventor after: Shi Lei

Inventor after: Song Zhenggang

Inventor after: Pu Songquan

Inventor after: Wu Bo

Inventor after: Peng Yiyong

Inventor after: Wei Han

Inventor after: Meng Guowang

Inventor after: He Shan

Inventor before: Yang Jianxin

Inventor before: Song Zhenggang

Inventor before: Pu Songquan

Inventor before: Wu Bo

Inventor before: Peng Yiyong

Inventor before: Wei Han

Inventor before: Meng Guowang

Inventor before: Shi Lei

Inventor before: He Shan

CB03 Change of inventor or designer information
TA01 Transfer of patent application right

Effective date of registration: 20210108

Address after: 215000 9 Jinzhuang street, Jinfeng Road, Suzhou high tech Zone, Suzhou City, Jiangsu Province

Applicant after: THE FIFTH ENGINEERING CO., LTD.OF CHINA RAILWAY NO.10 ENGINEERING GROUP Co.,Ltd.

Applicant after: NINGBO TRACK TRAFFIC GROUP Co.,Ltd. CONSTRUCTION BRANCH

Applicant after: GUANGXI University

Address before: 215000 9 Jinzhuang street, Jinfeng Road, Suzhou high tech Zone, Suzhou City, Jiangsu Province

Applicant before: THE FIFTH ENGINEERING CO., LTD.OF CHINA RAILWAY NO.10 ENGINEERING GROUP Co.,Ltd.

Applicant before: GUANGXI University

TA01 Transfer of patent application right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210115

CF01 Termination of patent right due to non-payment of annual fee