CN109723487A - Air pulsing quantum energy is implanted into presplitting permeability-increasing gas pumping method and device - Google Patents

Air pulsing quantum energy is implanted into presplitting permeability-increasing gas pumping method and device Download PDF

Info

Publication number
CN109723487A
CN109723487A CN201910036646.8A CN201910036646A CN109723487A CN 109723487 A CN109723487 A CN 109723487A CN 201910036646 A CN201910036646 A CN 201910036646A CN 109723487 A CN109723487 A CN 109723487A
Authority
CN
China
Prior art keywords
gas
air
quantum
drilling
implanted
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910036646.8A
Other languages
Chinese (zh)
Other versions
CN109723487B (en
Inventor
高九华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guizhou Tiandi Juneng Mining Engineering Technology Co., Ltd.
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201910036646.8A priority Critical patent/CN109723487B/en
Publication of CN109723487A publication Critical patent/CN109723487A/en
Application granted granted Critical
Publication of CN109723487B publication Critical patent/CN109723487B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Earth Drilling (AREA)
  • Drilling And Exploitation, And Mining Machines And Methods (AREA)

Abstract

The present invention provides a kind of air pulsing quantum energy implantation presplitting permeability-increasing gas pumping method and device.The present invention carries out pressurization presplitting to coal seam by pulsation type gas, to solve the problems, such as that the explosion of liquid carbon dioxide phase change expansion is uncontrollable and induces gas explosion in recovery process, improves gas production safety.And it also solves soft seam and weakens penetrating problem and cracks in coal seam and the high hydraulic pressure problem of hole closing, reduce exploitation difficulty.Further hold that gas more by quantum energy implantation to be detached from coal seam, improve extraction efficiency.

Description

Air pulsing quantum energy is implanted into presplitting permeability-increasing gas pumping method and device
Technical field
The invention belongs to coal mine gas Treatment process fields more particularly to a kind of air pulsing quantum energy to be implanted into presplitting Permeability-increasing gas pumping method and device.
Background technique
The anti-reflection property in coal seam is improved, the effective gas discharged in coal seam is mine region prevention and treatment gas coal and gas prominent Most one of effective measure.Seam gas content and pressure can be reduced by gas drainage under suction, to eliminate coal and gas prominent Hidden danger.It is domestic at present mainly to use high pressure waterjet drilling technique, utilize CO2The increasing in coal seam is improved in phase transformation and high pressure water pressure break coal seam Permeability.
CO2Phase transformation fracturing technology is to utilize liquid CO2At a certain temperature rapid vaporization expand and a kind of physics for developing Blasting technique.Be blast pressure process can not pre-control, coal-bed gas can be induced prominent;Followed by CO2Add Heat pipe installation and careless manipulation can lure and cause gas explosion;Third is a large amount of CO2Expansion will lead to the O of environment2Content decline.
High pressure water fracturing technology is to permeate after water pressurizes along the stratification in coal seam and joint, and high pressure water acts on the wall of a borehole coal On body, coal body stress is crushed, original crack is expanded, to create channel for Gas Flow, plays increase gas permeability of coal seam With infiltrative effect.The problem is that high pressure water easily causes high pressure water itself to seal up for safekeeping in coal during injecting pressure break first In layer, coal-bed gas can be induced prominent;Followed by for part fine coal, the immersion of a large amount of water blocks joint and crack sometimes, Reduce the permeability of coal body;Third is that apparatus and process complexity installation and transportation are cumbersome, and overall cost is high.
Summary of the invention
In order to solve the above technical problems, the present invention provides a kind of air pulsing quantum energy implantation presplitting permeability-increasing gas pumping side Method and device.In order to which some aspects of the embodiment to disclosure have a basic understanding, simple summary is shown below.It should Summarized section is not extensive overview, nor to determine key/critical component or describe the protection scope of these embodiments. Its sole purpose is that some concepts are presented with simple form, in this, as the preamble of following detailed description.
The present invention adopts the following technical scheme:
In some alternative embodiments, a kind of air pulsing quantum energy implantation presplitting permeability-increasing gas pumping method is provided, It include: that pulsation type gas is delivered in drilling by quantum implantation storehouse by the way that the hole packer of hole month is arranged in;In the quantum While implantation storehouse conveys the pulsation type gas into the drilling, the supersonic generator in quantum implantation storehouse is generated The ultrasonic wave of ultrasonic wave, generation enters the drilling with the pulsation type gas.
In some alternative embodiments, before this method further include:, will during drilling machine promotes drilling rod and drill bit Pressure medium is delivered to drill bit from the internal channel of drilling rod, and will carry the medium of cutting slag from the outer tunnel of the drilling rod It extracts and goes out;Stop drilling, pressure medium is boosted, the pressure medium after boosting sprays Cutting Rock by water knife to form knife Seam extracts drilling rod and drill bit out.
In some alternative embodiments, the air pulsing quantum energy is implanted into presplitting permeability-increasing gas pumping method, also It include: the air that air source heat pump generation has heat, and will be in the air delivery to gas tank with heat;Pressure-air Jerk pump generates the pulsation type gas using the air with heat in the gas tank as air-source, and is delivered to described Quantum is implanted into storehouse.
In some alternative embodiments, the pressure medium is pressure (hydraulic) water or high pressure gas;The pressure of the pressure (hydraulic) water For 5-20Mpa;The pressure of the high pressure gas is 1.2-2 times of coal seam compression strength;The high pressure gas is air or nitrogen.
In some alternative embodiments, the air pulsing quantum energy is implanted into presplitting permeability-increasing gas pumping method, also It include: to carry the medium of cutting slag to be delivered to slag gas separating device, the slag gas separating device separation discharge slag, water and gas.
In some alternative embodiments, the frequency for the ultrasonic wave that the supersonic generator generates is 0.02MHz- 8MHz。
In some alternative embodiments, a kind of air pulsing quantum energy implantation presplitting permeability-increasing gas pumping device is provided, It include: quantum implantation storehouse and hole packer;Hole packer setting in hole month, the quantum implantation storehouse by pipeline with it is described Supersonic generator is arranged in storehouse in hole packer connection, the quantum implantation;Quantum implantation storehouse passes through the hole packer for arteries and veins Dynamic formula gas is delivered in drilling;While quantum implantation storehouse conveys the pulsation type gas into the drilling, institute It states supersonic generator and generates ultrasonic wave, the ultrasonic wave of generation enters the drilling with the pulsation type gas.
In some alternative embodiments, the air pulsing quantum energy is implanted into presplitting permeability-increasing gas pumping device, also It include: drilling machine;The drilling machine includes: drilling rod and drill bit, and the front end of the drilling rod is arranged in the drill bit;The drilling rod is bilateral Road drilling rod, comprising: internal channel and outer tunnel;During drilling machine promotes drilling rod and drill bit, pressure medium is by the drilling rod Internal channel is delivered to drill bit, and the medium for carrying cutting slag is extracted from the outer tunnel of the drilling rod.
In some alternative embodiments, the air pulsing quantum energy is implanted into presplitting permeability-increasing gas pumping device, also It include: air source heat pump, gas tank and pressure-air jerk pump;The air source heat pump generates the air with heat, and by institute It states in the air delivery with heat to the gas tank;The pressure-air jerk pump is by the sky with heat in the gas tank Gas generates the pulsation type gas as air-source, and is delivered in quantum implantation storehouse.
In some alternative embodiments, the air pulsing quantum energy is implanted into presplitting permeability-increasing gas pumping device, also It include: slag gas separating device;The end of the drilling rod is arranged in the slag gas separating device, and slag is cut in carrying for being extracted Medium is delivered in the slag gas separating device, and mud hole, gas vent and medium input hole are opened up on the slag gas separating device.
The utility model has the advantages that compared with the existing technology, the present invention carries out coal seam by pulsation type gas brought by of the invention It is pressurized presplitting, so that it is uncontrollable and induce asking for gas explosion to solve liquid carbon dioxide phase change expansion explosion in recovery process Topic improves gas production safety.And it also solves soft seam and weakens penetrating problem and cracks in coal seam and hole closing height Hydraulic pressure problem reduces exploitation difficulty.Further hold that gas more by quantum energy implantation to be detached from coal seam, improves extraction effect Rate.
For the above and related purposes, one or more embodiments include being particularly described below and in claim In the feature that particularly points out.Certain illustrative aspects are described in detail in the following description and the annexed drawings, and its instruction is only Some modes in the utilizable various modes of the principle of each embodiment.Other benefits and novel features will be under The detailed description in face is considered in conjunction with the accompanying and becomes obvious, the disclosed embodiments be all such aspects to be included and they Be equal.
Detailed description of the invention
Structural schematic diagram when Fig. 1 is drill hole of drilling machine of the present invention;
Structural schematic diagram when Fig. 2 is quantum implantation of the present invention storehouse implantation quantum energy;
Fig. 3 is the connection schematic diagram in quantum implantation of the present invention storehouse and hole packer;
Fig. 4 is the structural schematic diagram of slag gas separating device of the present invention;
Fig. 5 is the structural schematic diagram of drilling rod of the present invention.
Specific embodiment
The following description and drawings fully show specific embodiments of the present invention, to enable those skilled in the art to Practice them.Other embodiments may include structure, logic, it is electrical, process and other change.Embodiment Only represent possible variation.Unless explicitly requested, otherwise individual components and functionality is optional, and the sequence operated can be with Variation.The part of some embodiments and feature can be included in or replace part and the feature of other embodiments.This hair The range of bright embodiment includes equivalent obtained by the entire scope of claims and all of claims Object.
As shown in Fig. 1 to 5, in some illustrative embodiments, the present invention provides a kind of air pulsing quantum energy implantation Presplitting permeability-increasing gas pumping device, comprising: quantum is implanted into storehouse 1, hole packer 3, drilling machine, air source heat pump 19, gas tank 20, high pressure sky Gas jerk pump 21 and drainage pump 22.
Drilling machine includes: drilling rod 2, damping drilling rod 4, water knife 6, drill bit 7 and slag gas separating device 8.Drilling rod 2 is arranged in drill bit 7 The end of drilling rod 2 is arranged in front end, slag gas separating device 8.
Drilling rod 2 is binary channels drilling rod, comprising: outer tube 24 and the inner tube 25 being arranged in inside outer tube 24, the inside of inner tube 25 As internal channel 26, outer tunnel 27 is formed between the outer surface of inner tube 25 and the inner surface of outer tube 24.It punches and is formed on outer tube 24 Sieve.During drilling machine promotes drilling rod 2 and drill bit 7, pressure medium is delivered to drill bit 2 by the internal channel of drilling rod 2, carries The medium of cutting slag is extracted from the outer tunnel 27 of drilling rod 2, realizes deslagging in drilling machine, and spray orifice accident is avoided to occur, and And drilling precision can be improved, it avoids deviateing.
Pressure medium is pressure (hydraulic) water or high pressure gas;The pressure of pressure (hydraulic) water is 5-20Mpa;The pressure of high pressure gas is coal seam 1.2-2 times of compression strength;High pressure gas is air or nitrogen, and preferably nitrogen, nitrogen safety is higher.
The medium for carrying cutting slag being extracted is delivered in the chamber 12 of slag gas separating device 8, slag gas separating device 8 On open up mud hole 11, gas vent 10 and medium input hole 28.Pressure medium is entered in drilling rod 2 by medium input hole 28, slag Gas separating device 8 realizes that pulp water separates discharge with gas.
The oral area of drilling 102 is arranged in hole packer 3, and for blocking drilling 102, it is deep to pass through hole packer 3 for drilling rod 2 when drilling It in drilling 102, is drilled by drill bit 7, after the completion of drilling, high -pressure water cutting rock mass 103 is projected by water knife, rock mass is cut Knife seam 101 is formed, knife seam is annulus of the diameter in 3m or so.3 liters of hole packer open up hole packer gas vent 16 and hole packer deslagging Hole 15, timely deslagging exhaust.
Quantum implantation storehouse 1 is connected to by pipeline with hole packer 3, is formed after knife seam, drilling rod 2 leaves drilling 102, connects at this time Flux is implanted into storehouse 1 and hole packer 3.Quantum, which is implanted into storehouse 1, is arranged supersonic generator 23, and quantum is implanted into storehouse 1 and passes through hole packer 3 Pulsation type gas is delivered in drilling 102, while quantum is implanted into storehouse 1 and conveys pulsation type gas into drilling 102, ultrasound Wave producer 23 generates ultrasonic wave, and the ultrasonic wave of generation enters drilling 102 with pulsation type gas.The frequency of ultrasonic wave is 0.02MHz-8MHz.Pulsation type gas is generated by pressure-air jerk pump 21.
Air source heat pump 19 is connect by pipeline with gas tank 20, and pressure-air jerk pump is connect by pipeline with gas tank 20, Drainage pump 22 is implanted into storehouse 1 with quantum by pipeline and connect.Air source heat pump 19 generates the air with heat, and will have heat Air delivery to gas tank 20 in, pressure-air jerk pump 19 is produced using the air with heat in gas tank 20 as air-source Raw pulsation type gas, and be delivered in quantum implantation storehouse 1.Pressure-air jerk pump is made of air compressor and jerk pump, empty Air compressor compresses the gas from gas tank, compressed gas is exported by jerk pump pulsating, to generate pulsating gas Body, pressurization in 10 to 30 minutes are primary.For no coal seam outstanding, preferably using the air with heat.
Quantum is implanted into storehouse 1 and carries out carrying out quantum implantation to coal seam from drilling with pulsation type gas, by ultrasonic wave with pulsating Gas is implanted into coal seam, increases the crack in coal seam using gas as medium, and presplitting is pressurized and depressurized to coal body, increases the penetrating of rock mass Property, while the gas existence for the energy changes rock mass such as be implanted into ultrasonic wave, heat, gas adsorption is reduced, the pumping of gas is improved Adopt efficiency.
The present invention also provides a kind of air pulsing quantum energies to be implanted into presplitting permeability-increasing gas pumping method, comprising:
S1: during drilling machine promotes drilling rod and drill bit, pressure medium is delivered to drill bit from the internal channel of drilling rod, is bored First rock mass is cut into slag, and the medium for carrying cutting slag is extracted from the outer tunnel of drilling rod.It realizes in drilling machine Deslagging avoids spray orifice accident from occurring, and the accuracy of punching can be improved, and avoids deviateing, avoids collapse hole.
Pressure medium is pressure (hydraulic) water or high pressure gas.The pressure of pressure (hydraulic) water is 5-20Mpa.The pressure of high pressure gas is coal seam 1.2-2 times of compression strength, high pressure gas are air or nitrogen, and preferably nitrogen, nitrogen safety is higher.
S2: the medium for carrying cutting slag is delivered to slag gas separating device, slag gas separating device separation discharge slag, water and gas. Realize gas liquid separation, slag gas separating device, which can connect slush pump, facilitates the construction of deep hole deslagging, is convenient for deslagging and environmental protection.
S3: in boring procedure, stop drilling, pressure medium is boosted, the pressure medium after boosting is cut by the ejection of water knife Rock mass is cut to form knife seam, extracts drilling rod and drill bit out.It drills in drilling process, is cut into knife seam release with water knife in drilling.
When medium is pressure (hydraulic) water, then pressure (hydraulic) water is raised to 20-100Mpa from 5-20Mpa, water knife internal valve is closed, high pressure water Cutting Rock is projected from water knife.
S4: after extraction drilling rod and drill bit, connection quantum implantation storehouse and the hole packer that hole month is arranged in, quantum are implanted into storehouse Pulsation type gas is delivered in drilling by hole packer.
While quantum implantation storehouse conveys pulsation type gas into drilling, quantum is implanted into the supersonic generator in storehouse and produces Raw ultrasonic wave, the ultrasonic wave of generation enter drilling with pulsation type gas.The frequency of ultrasonic wave that supersonic generator generates is 0.02MHz-8MHz.Pulsation type gas is generated by pressure-air jerk pump.
Quantum is implanted into storehouse and carries out carrying out quantum implantation to coal seam from drilling with pulsation type gas, increases coal by medium of gas The crack of layer is pressurized and is depressurized to coal body presplitting by ultrasonic wave in pulsation type gas implantation coal seam, increase the penetrating of rock mass Property, the gas existence of implantation ultrasonic wave change rock mass reduces gas adsorption, improves the extraction efficiency of gas.
S5: air source heat pump generates the air with heat, and by the air delivery to gas tank with heat, high pressure is empty Gas jerk pump generates pulsation type gas using the air with heat in gas tank as air-source, and is delivered to quantum implantation storehouse It is interior.Drilling is implanted into ultrasonic wave, thermal energy changes gas existence, improves the extraction efficiency of gas.
For no coal seam outstanding, preferably using the air with heat.
Pressure-air jerk pump is made of air compressor and jerk pump, and air compressor compresses the gas from gas tank, will Compressed gas is exported by jerk pump pulsating, to generate pulsation type gas, pressurization in 10 to 30 minutes is primary.
Step S1-S5 is repeated, repeatedly punching, deslagging and conveying pulsation type gas carry out anti-reflection.
It should also be appreciated by one skilled in the art that various illustrative logical boxs, mould in conjunction with the embodiments herein description Electronic hardware, computer software or combinations thereof may be implemented into block, circuit and algorithm steps.In order to clearly demonstrate hardware and Interchangeability between software surrounds its function to various illustrative components, frame, module, circuit and step above and carries out It is generally described.Hardware is implemented as this function and is also implemented as software, depends on specific application and to entire The design constraint that system is applied.Those skilled in the art can be directed to each specific application, be realized in a manner of flexible Described function, still, this realization decision should not be construed as a departure from the scope of protection of this disclosure.

Claims (10)

1. air pulsing quantum energy is implanted into presplitting permeability-increasing gas pumping method characterized by comprising
Pulsation type gas is delivered in drilling by quantum implantation storehouse by the way that the hole packer of hole month is arranged in;
It is super in the quantum implantation storehouse while quantum implantation storehouse conveys the pulsation type gas into the drilling Sonic generator generates ultrasonic wave, and the ultrasonic wave of generation enters the drilling with the pulsation type gas.
2. air pulsing quantum energy according to claim 1 is implanted into presplitting permeability-increasing gas pumping method, which is characterized in that should Before method further include:
During drilling machine promotes drilling rod and drill bit, pressure medium is delivered to drill bit from the internal channel of drilling rod, and will take Medium with cutting slag is extracted from the outer tunnel of the drilling rod;
Stop drilling, pressure medium is boosted, the pressure medium after boosting sprays Cutting Rock by water knife to form knife seam, takes out Drilling rod and drill bit out.
3. air pulsing quantum energy according to claim 1 or 2 is implanted into presplitting permeability-increasing gas pumping method, feature exists In, further includes:
Air source heat pump generates the air with heat, and will be in the air delivery to gas tank with heat;
Pressure-air jerk pump generates the pulsation type gas using the air with heat in the gas tank as air-source, And it is delivered in quantum implantation storehouse.
4. air pulsing quantum energy according to claim 2 is implanted into presplitting permeability-increasing gas pumping method, which is characterized in that institute Stating pressure medium is pressure (hydraulic) water or high pressure gas;
The pressure of the pressure (hydraulic) water is 5-20Mpa;
The pressure of the high pressure gas is 1.2-2 times of coal seam compression strength;
The high pressure gas is air or nitrogen.
5. air pulsing quantum energy according to claim 4 is implanted into presplitting permeability-increasing gas pumping method, which is characterized in that also It include: to carry the medium of cutting slag to be delivered to slag gas separating device, the slag gas separating device separation discharge slag, water and gas.
6. air pulsing quantum energy according to claim 1 is implanted into presplitting permeability-increasing gas pumping method, which is characterized in that institute The frequency for stating the ultrasonic wave of supersonic generator generation is 0.02MHz-8MHz.
7. air pulsing quantum energy is implanted into presplitting permeability-increasing gas pumping device characterized by comprising quantum is implanted into storehouse and sealing of hole Device;The hole packer setting is connected to by pipeline with the hole packer in hole month, the quantum implantation storehouse, and the quantum is planted Put in storage interior setting supersonic generator;
Pulsation type gas is delivered in drilling by quantum implantation storehouse by the hole packer;
While quantum implantation storehouse conveys the pulsation type gas into the drilling, the supersonic generator is generated The ultrasonic wave of ultrasonic wave, generation enters the drilling with the pulsation type gas.
8. air pulsing quantum energy according to claim 7 is implanted into presplitting permeability-increasing gas pumping device, which is characterized in that also It include: drilling machine;The drilling machine includes: drilling rod and drill bit, and the front end of the drilling rod is arranged in the drill bit;
The drilling rod is binary channels drilling rod, comprising: internal channel and outer tunnel;During drilling machine promotes drilling rod and drill bit, add Medium is pressed to be delivered to drill bit by the internal channel of the drilling rod, the medium for carrying cutting slag is taken out from the outer tunnel of the drilling rod It takes.
9. air pulsing quantum energy according to claim 7 or 8 is implanted into presplitting permeability-increasing gas pumping device, feature exists In, further includes: air source heat pump, gas tank and pressure-air jerk pump;The air source heat pump generates the air with heat, and It will be in the air delivery with heat to the gas tank;The pressure-air jerk pump will have heat in the gas tank Air generate the pulsation type gas as air-source, and be delivered in quantum implantation storehouse.
10. air pulsing quantum energy according to claim 8 is implanted into presplitting permeability-increasing gas pumping device, which is characterized in that Further include: slag gas separating device;The end of the drilling rod is arranged in the slag gas separating device, and what is be extracted carries cutting slag Medium be delivered in the slag gas separating device, mud hole, gas vent and medium input hole are opened up on the slag gas separating device.
CN201910036646.8A 2019-01-15 2019-01-15 Gas pulsation quantum energy implantation pre-splitting permeability-increasing gas extraction method and device Active CN109723487B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910036646.8A CN109723487B (en) 2019-01-15 2019-01-15 Gas pulsation quantum energy implantation pre-splitting permeability-increasing gas extraction method and device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910036646.8A CN109723487B (en) 2019-01-15 2019-01-15 Gas pulsation quantum energy implantation pre-splitting permeability-increasing gas extraction method and device

Publications (2)

Publication Number Publication Date
CN109723487A true CN109723487A (en) 2019-05-07
CN109723487B CN109723487B (en) 2021-04-30

Family

ID=66299057

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910036646.8A Active CN109723487B (en) 2019-01-15 2019-01-15 Gas pulsation quantum energy implantation pre-splitting permeability-increasing gas extraction method and device

Country Status (1)

Country Link
CN (1) CN109723487B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110529090A (en) * 2019-09-25 2019-12-03 高九华 One kind is impulsed pressure break coal petrography permeability improvement device and method with blasting fume shock wave

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101644166A (en) * 2009-07-14 2010-02-10 中国矿业大学 Method for extracting gas from high gas low permeability coal seam by punching, slotting, pressure releasing, and permeability increasing
CN104481574A (en) * 2014-09-29 2015-04-01 中国矿业大学(北京) Method for improving coal seam gas permeability through high energy acoustoelectric composite technology
CN104563990A (en) * 2015-01-06 2015-04-29 中国矿业大学 Drilling and blanking integrated and heat injection coordinated enhancing method for extracting coal seam gas
CN105507938A (en) * 2015-12-31 2016-04-20 河南理工大学 Construction method of hydraulic flushing and presplit blasting combined permeability-increasing extraction system in drill holes
CN105863596A (en) * 2016-05-05 2016-08-17 中国矿业大学 Ultrasonic wave and hydrofracture compound coal-body fracturing simulation device and method for underground coal mine
CN106499366A (en) * 2016-11-01 2017-03-15 中国矿业大学 A kind of coal bed gas enhanced recovery method that microwave is mutually cooperateed with ultrasound wave
CN107676127A (en) * 2017-10-20 2018-02-09 四川大学 Variant-frequency vibration permeability-increasing gas pumping method and device in hole
CN107725100A (en) * 2017-09-22 2018-02-23 重庆大学 A kind of liquid nitrogen combines laser alternating hot and cold mash gas extraction system and method
CN108104866A (en) * 2018-02-06 2018-06-01 高九华 It is a kind of using gas as the anti-reflection technology of pulsation pressure break creep and its device of medium
CN108104737A (en) * 2018-02-06 2018-06-01 高九华 The self-positioning drilling rod of binary channels
CN108301811A (en) * 2018-03-27 2018-07-20 兖矿集团有限公司 A kind of efficient pumping method of hypotonicity coal-bed gas
CN109113701A (en) * 2017-06-24 2019-01-01 高九华 Using air as the anti-reflection technology of pulsating pressure-air creep pressure break and device of medium

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101644166A (en) * 2009-07-14 2010-02-10 中国矿业大学 Method for extracting gas from high gas low permeability coal seam by punching, slotting, pressure releasing, and permeability increasing
CN104481574A (en) * 2014-09-29 2015-04-01 中国矿业大学(北京) Method for improving coal seam gas permeability through high energy acoustoelectric composite technology
CN104563990A (en) * 2015-01-06 2015-04-29 中国矿业大学 Drilling and blanking integrated and heat injection coordinated enhancing method for extracting coal seam gas
CN105507938A (en) * 2015-12-31 2016-04-20 河南理工大学 Construction method of hydraulic flushing and presplit blasting combined permeability-increasing extraction system in drill holes
CN105863596A (en) * 2016-05-05 2016-08-17 中国矿业大学 Ultrasonic wave and hydrofracture compound coal-body fracturing simulation device and method for underground coal mine
CN106499366A (en) * 2016-11-01 2017-03-15 中国矿业大学 A kind of coal bed gas enhanced recovery method that microwave is mutually cooperateed with ultrasound wave
CN109113701A (en) * 2017-06-24 2019-01-01 高九华 Using air as the anti-reflection technology of pulsating pressure-air creep pressure break and device of medium
CN107725100A (en) * 2017-09-22 2018-02-23 重庆大学 A kind of liquid nitrogen combines laser alternating hot and cold mash gas extraction system and method
CN107676127A (en) * 2017-10-20 2018-02-09 四川大学 Variant-frequency vibration permeability-increasing gas pumping method and device in hole
CN108104866A (en) * 2018-02-06 2018-06-01 高九华 It is a kind of using gas as the anti-reflection technology of pulsation pressure break creep and its device of medium
CN108104737A (en) * 2018-02-06 2018-06-01 高九华 The self-positioning drilling rod of binary channels
CN108301811A (en) * 2018-03-27 2018-07-20 兖矿集团有限公司 A kind of efficient pumping method of hypotonicity coal-bed gas

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110529090A (en) * 2019-09-25 2019-12-03 高九华 One kind is impulsed pressure break coal petrography permeability improvement device and method with blasting fume shock wave

Also Published As

Publication number Publication date
CN109723487B (en) 2021-04-30

Similar Documents

Publication Publication Date Title
CN109025937B (en) Hydraulic slotting and multistage combustion shock wave combined fracturing coal body gas extraction method
CN105971660B (en) Ultrasonic cavitation and hydraulic fracturing joint incentive coal bed gas pumping method
CN105625946B (en) Coal bed gas horizontal well supercritical CO2Jet stream makes chamber and multistage synchronizes explosion fracturing method
CN109252846B (en) The high pressure air pulse ripples periodically hammering anti-reflection system and method for coal body
CN105332684B (en) A kind of water under high pressure is quick-fried and CO2The coal bed gas displacement extraction technique that pressure break is combined
CN108397182A (en) Electric pulse cooperates with the device and method in the anti-reflection coal seam of frozen-thawed
CN106285681A (en) A kind of hard coal seam top board fracturing device and method
CN109915199A (en) Gas drainage device and its application method are strengthened in anti-reflection coal seam step by step
CN106988719B (en) Anti-reflection system and anti-reflection method for circularly injecting hot water and liquid nitrogen into coal seam
CN115539130B (en) Coal seam gas exploitation and CO (carbon monoxide) enhancement of non-shearable layer 2 Sealing method
CN108361061A (en) Hypotonic coal seam electric detonation shake and microwave radiation technology frozen-thawed permeability improvement device and method
CN107816340B (en) Process method for thermally extracting shale gas by combining high-power ultrasonic waves with branch horizontal well
CN107725100B (en) A kind of liquid nitrogen joint laser alternating hot and cold mash gas extraction system and method
CN110195580A (en) A kind of gas-liquid two-phase synergy coal seam anti-reflection method
CN107476794A (en) Method for increasing coal gas permeability by injecting high-temperature nitrogen after liquid nitrogen gasification circulation
CN103510979B (en) Dry ice explosion and air-permeability-enhancing device and method for drawing out gas by using same
CN102418549B (en) Technical method for extracting coal bed methane from constructed coal development area
CN106703773A (en) Liquid carbon dioxide bomb, propping agent blasting anti-reflection method and device
CN103867119A (en) Coal reservoir well completion transformation method
CN104213896A (en) Fracturing and cavern integrated completion method for coal-bed gas reservoir
CN105804786B (en) A kind of weak seam bottom plate layer-through drilling pressure rushes anti-reflection method
CN108194125A (en) A kind of coal seam cooperates with anti-reflection method step by step
RU2298650C1 (en) Coal formation hydraulic processing method
CN110924900A (en) Method for hydraulic power-liquid nitrogen composite uniform fracturing of coal body
CN108801086A (en) Deep hole loosens stress pre-released hydraulically blasting method and device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20220811

Address after: Room 423, Management Committee, Zhongshan Development Zone, Liupanshui City, Guizhou Province, 553000

Patentee after: Guizhou Tiandi Juneng Mining Engineering Technology Co., Ltd.

Address before: 6-c-1905, Guangxi Homeland, Chaoyang District, Beijing, 100028

Patentee before: Gao Jiuhua