CN109720965A - A kind of silo coal tub way steel rope replacing method and more changing device - Google Patents

A kind of silo coal tub way steel rope replacing method and more changing device Download PDF

Info

Publication number
CN109720965A
CN109720965A CN201811533909.8A CN201811533909A CN109720965A CN 109720965 A CN109720965 A CN 109720965A CN 201811533909 A CN201811533909 A CN 201811533909A CN 109720965 A CN109720965 A CN 109720965A
Authority
CN
China
Prior art keywords
guide rope
replaced
rope
guide
replacement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811533909.8A
Other languages
Chinese (zh)
Inventor
徐盟浩
程运雪
牛金廷
王刚
泮志亮
夏春忠
崔庆凯
黄正全
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Huaye Group Co Ltd
Original Assignee
China Huaye Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Huaye Group Co Ltd filed Critical China Huaye Group Co Ltd
Priority to CN201811533909.8A priority Critical patent/CN109720965A/en
Publication of CN109720965A publication Critical patent/CN109720965A/en
Pending legal-status Critical Current

Links

Landscapes

  • Emergency Lowering Means (AREA)

Abstract

The present invention provides a kind of silo coal tub way steel rope replacing methods comprising following steps: guide rope one end to be replaced is connect by the guiding device on sheave wheel platform with traction device by step 1;Step 2 is promoted guide rope to be replaced by the locking device on sheave wheel platform, and guide rope to be replaced is promoted to outer wellhead, is afterwards drawn the guide rope to be replaced to working face by traction device;Step 3 connects guide rope to be replaced with the guide rope for being used to replace, traction device draws guide rope to be replaced, until guide rope to be replaced all exits vertical shaft, and after the guide rope end for replacement is promoted to above well head, the guide rope for being used to replace is transferred to underground by the traction device and guiding device, it finally closes locking device and completes replacement, it can be to avoid high altitude operation, steel rope replacing efficiency and replacement quality are improved, ensures construction safety.

Description

A kind of silo coal tub way steel rope replacing method and more changing device
Technical field
The present invention relates to shaft hoisting technical fields, specifically, be related to a kind of silo coal tub way steel rope replacing method and More changing device.
Background technique
Cage guide is the guiding device that hoisting container is run in the wellbore, is to be used as to stablize and lead by guide rope To have from the device of underground winding cage and skip bucket, small investment, quick, maintenance is simple, runs smoothly, is easy to change The advantages of.
Since the promotion task of guide rope in actual production process is heavy, along with the reasons such as pit shaft water drenching is larger, Guide rope surface after long-time service will appear a large amount of points, abrasion corrosion situation is heavier, even guide rope There is 10 or more undergauge in part, influences normally to produce, therefore according to the pertinent regulations of Underground metal & nonmetal mines, Guide rope needs are replaced after using some cycles.
Under the prior art, the replacement of guide rope is usually by the old wire rope needed replacing and to be used to replace new Wirerope is overlapped by card of restricting, and is then replaced by the locking device on sheave wheel platform.However, it is above-mentioned it is this more It changes in method, since the aperture of the locking device centre bore on sheave wheel platform only allows steel cable to pass through, this method In by rope card overlap joint after wirerope need to once be locked on sheave wheel platform after remove again rope card, it is clear that difficulty of construction Greatly, the replacement cycle is long.Also, works as under vertical shaft relatively depth or the higher equal Construction States of derrick, need to complete in high altitude operation Guide rope more changes jobs, and there are great security risks.On the other hand, above-mentioned this substitute mode, due to using Rope card overlap joint, and also need to remove after overlap joint, cause the old wire rope in replacement process to be easy to fall off.
In view of this, should be improved to the prior art, to solve the above-mentioned technical problems in the prior art.
Summary of the invention
In order to solve the above-mentioned technical problem the present invention makes, the purpose is to provide one kind to replace the prior art In by rope card connection after lock the replacing options removed again so that new and old guide rope disposably from sheave wheel platform lock fill It passes through in setting, avoids high-altitude operation repeatedly, effective guarantee construction safety shortens the vertical shaft of the replacing construction of guide rope Guide rope replacing options and more changing device.
To achieve the goals above, the present invention provides a kind of silo coal tub way steel rope replacing methods comprising with Lower step: guide rope one end to be replaced is connect by the guiding device on sheave wheel platform with traction device by step 1; Step 2 is promoted guide rope to be replaced by the locking device on sheave wheel platform, and guide rope to be replaced is mentioned Outer wellhead is risen to, is afterwards drawn the guide rope to be replaced to working face by the traction device;Step 3, will be to The guide rope of replacement is connected with the guide rope for replacement, and traction device draws guide rope to be replaced, directly Vertical shaft is all exited to guide rope to be replaced, and the guide rope end for replacement is promoted to above well head Afterwards, the guide rope for being used to replace is transferred to underground by the traction device and guiding device, finally closes locking dress Set completion replacement.
Preferably, in the step 3, at the end of guide rope and the new guide rope for replacement to be replaced Attaching nut can be respectively welded in head, can then be connected the nut welded on two steel wire rope end heads by connector.
Again preferably, in the step 3, guide rope to be replaced and new guide rope for replacement are successive Pass through from the locking device.
Correspondingly, the present invention also provides a kind of vertical shafts based on silo coal tub way steel rope replacing method described in above content Guide rope more changing device, described device include derrick, which is set to above vertical shaft, setting above the derrick There is sheave wheel platform, is provided with locking device and guiding device on the sheave wheel platform;Traction device, the traction device are located at pit shaft Side distal end, wherein when the more changing device in use, by guide rope to be replaced and the cage guide steel wire that is used to replace The end of rope connects, and guide rope to be replaced is then drawn by the traction device, as the cage guide steel for replacement Cord end is promoted to below import, then transfers wirerope, is closed the locking device and is completed replacement.
Preferably, the attachment device includes two attaching nuts, and the connector of two attaching nuts of connection, wherein Two attaching nuts connect with the end of guide rope to be replaced and the guide rope of replacement respectively.
As described above with practice it is found that silo coal tub way steel rope replacing method of the present invention and more changing the outfit It sets, is welded to connect nut respectively in the end of guide rope and the guide rope for replacement to be replaced, then passes through Connector connects attaching nut, so that guide rope to be replaced is connected with the guide rope for replacement, then Wirerope after connection is connect by locking device with guiding device, then by traction device traction until cage guide to be replaced Outside rope hoisting to well, and the guide rope for being used to replace is promoted to above well head, finally in place by the decentralization of new wirerope, It closes locking device and completes replacement.In conclusion in silo coal tub way steel rope replacing method of the present invention and more changing device, It can replace in the prior art by locking the replacing options removed again after rope card connection, so that new and old guide rope is disposable It is passed through out of sheave wheel platform locking device, avoids high-altitude operation repeatedly, effective guarantee construction safety shortens guide rope Replacing construction.
Detailed description of the invention
Fig. 1 is flow chart, shows silo coal tub way steel rope replacing method described in one embodiment of the present of invention Process;
Fig. 2 is state diagram, shows guide rope to be replaced in one embodiment of the present of invention and for replacement State when guide rope connects;
Fig. 3 is partial enlargement diagram, shows guide rope and the cage guide steel wire for replacement to be replaced in Fig. 2 The partial structurtes of rope connection.
Specific embodiment
The reality of silo coal tub way steel rope replacing method and more changing device of the present invention described below with reference to the accompanying drawings Apply example.Those skilled in the art will recognize, without departing from the spirit and scope of the present invention, Ke Yiyong A variety of different modes are modified described embodiment.Therefore, attached drawing and description are regarded as illustrative in nature, without It is for limiting scope of protection of the claims.In addition, in the present specification, attached drawing is drawn not in scale, and identical attached Icon note indicates identical part.
Fig. 1 is flow chart, shows silo coal tub way steel rope replacing method described in one embodiment of the present of invention Process.As shown in Figure 1, in this embodiment of the invention the silo coal tub way steel rope replacing method the following steps are included: Guide rope one end to be replaced is connect by the guiding device on sheave wheel platform with traction device by step 1;Step 2 is led to The locking device crossed on sheave wheel platform promotes guide rope to be replaced, and guide rope to be replaced is promoted to well head Outside, the guide rope to be replaced is drawn to working face by the traction device afterwards;Step 3, by tank to be replaced Road wirerope is connected with the guide rope for replacement, and traction device draws guide rope to be replaced, until to be replaced Guide rope all exit vertical shaft, and after the guide rope end for replacement is promoted to above well head, pass through The traction device and guiding device transfer the guide rope for being used to replace to underground, finally close locking device and complete more It changes.
Specifically, Fig. 2 is state diagram, guide rope and use to be replaced in one embodiment of the present of invention are shown State when the guide rope connection of replacement.Fig. 3 is partial enlargement diagram, shows cage guide steel to be replaced in Fig. 2 The partial structurtes that cord is connect with the guide rope for replacement.Referring to Fig. 2 and Fig. 3, the present invention also provides one kind to be based on The silo coal tub way steel rope replacing device of silo coal tub way steel rope replacing method described in above content, including it is set to vertical shaft The derrick 11 of 10 tops, is provided with sheave wheel platform 1 above derrick 11, locking device 2 and guiding device is provided on sheave wheel platform 3,11 side of derrick distal end is provided with traction device 4.
When guide rope needs replacing, traction device 4 works, and guide rope 5 to be replaced is in traction device 4 Traction is lower to be promoted to well head from underground by guiding device 3 and locking device 2, final traction to operation platform surface.Referring to figure 3, it is welded to connect nut 7 respectively in the end of guide rope 5 and the guide rope 6 for replacement to be replaced, and pass through Connector 8 connects two attaching nuts 7, so that guide rope 5 to be replaced and the guide rope 6 for replacement connect.
Then, traction device 4 continues to draw guide rope 5 to be replaced until it exits vertical shaft 10 completely, together When, 6 end of guide rope for replacement is promoted to above well head, then continues to lead by traction device 4 and guiding device 3 Draw, put to underground, finally closes locking device 2 and complete replacement.
As described above with practice it is found that silo coal tub way steel rope replacing method of the present invention and more changing the outfit It sets, is welded to connect nut respectively in the end of guide rope and the guide rope for replacement to be replaced, then passes through Connector connects attaching nut, so that guide rope to be replaced is connected with the guide rope for replacement, then Wirerope after connection is connect by locking device with guiding device, then by traction device traction until cage guide to be replaced Outside rope hoisting to well, and the guide rope for being used to replace is promoted to above well head, finally in place by the decentralization of new wirerope, It closes locking device and completes replacement.In conclusion in silo coal tub way steel rope replacing method of the present invention and more changing device, It can replace in the prior art by locking the replacing options removed again after rope card connection, so that new and old guide rope is disposable It is passed through out of sheave wheel platform locking device, avoids high-altitude operation repeatedly, effective guarantee construction safety shortens guide rope Replacing construction.
Describe silo coal tub way steel rope replacing method according to the present invention in an illustrative manner above with reference to attached drawing And more changing device.It will be understood by those skilled in the art, however, that the silo coal tub way wirerope proposed for aforementioned present invention is more Method and more changing device are changed, various improvement can also be made on the basis of not departing from the content of present invention.Therefore, guarantor of the invention Shield range should be determined by the content of appended claims.

Claims (5)

1. a kind of silo coal tub way steel rope replacing method, which is characterized in that the silo coal tub way steel rope replacing method include with Lower step:
Guide rope one end to be replaced is connect by the guiding device on sheave wheel platform with traction device by step 1;
Step 2 promotes guide rope to be replaced by the locking device on sheave wheel platform, and by cage guide steel wire to be replaced Rope is promoted to outer wellhead, is afterwards drawn the guide rope to be replaced to working face by the traction device;
Step 3 connects guide rope to be replaced with the guide rope for being used to replace, and traction device draws to be replaced Guide rope, until guide rope to be replaced all exits vertical shaft, and the guide rope end for replacement After being promoted to above well head, the guide rope for being used to replace is transferred to underground by the traction device and guiding device, It finally closes locking device and completes replacement.
2. silo coal tub way steel rope replacing method as described in claim 1, which is characterized in that in the step 3, to more Attaching nut is respectively welded in the end of the guide rope and the new guide rope for replacement that change, then will by connector The nut connection welded on two steel wire rope end heads.
3. silo coal tub way steel rope replacing method as described in claim 1, which is characterized in that be replaced in the step 3 Guide rope and new guide rope for replacement successively pass through from the locking device.
4. one kind is based on the described in any item silo coal tub way steel rope replacing devices of claims 1 to 3, which is characterized in that described Device includes
Derrick, the derrick are set to above vertical shaft, are provided with sheave wheel platform above the derrick, are set on the sheave wheel platform It is equipped with locking device and guiding device;
Traction device, the traction device are located at the side distal end of pit shaft, wherein
When the more changing device in use, the end of guide rope to be replaced and the guide rope for being used to replace is passed through Attachment device connection, then draws guide rope to be replaced, as the cage guide steel for replacement by the traction device Cord end is promoted to below import, then transfers wirerope, is closed the locking device and is completed replacement.
5. silo coal tub way steel rope replacing device as claimed in claim 4, which is characterized in that the attachment device includes two companies Connected nut, and the connector of two attaching nuts of connection, wherein
Two attaching nuts connect with the end of guide rope to be replaced and the guide rope of replacement respectively.
CN201811533909.8A 2018-12-14 2018-12-14 A kind of silo coal tub way steel rope replacing method and more changing device Pending CN109720965A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811533909.8A CN109720965A (en) 2018-12-14 2018-12-14 A kind of silo coal tub way steel rope replacing method and more changing device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811533909.8A CN109720965A (en) 2018-12-14 2018-12-14 A kind of silo coal tub way steel rope replacing method and more changing device

Publications (1)

Publication Number Publication Date
CN109720965A true CN109720965A (en) 2019-05-07

Family

ID=66297097

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811533909.8A Pending CN109720965A (en) 2018-12-14 2018-12-14 A kind of silo coal tub way steel rope replacing method and more changing device

Country Status (1)

Country Link
CN (1) CN109720965A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110713092A (en) * 2019-07-01 2020-01-21 海瑞可(武汉)新材料有限公司 Hoisting method and hoisting mechanism for elevator synthetic fiber rope

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1605558A (en) * 2003-10-10 2005-04-13 淄博矿业集团有限责任公司许厂煤矿 Technology for exchanging hoisting cable wire of floor type friction hoist
CN101391721A (en) * 2008-10-27 2009-03-25 兖州煤业股份有限公司 Novel technology for changing hoist steel wire rope of tower type friction winder
CN101786570A (en) * 2010-03-17 2010-07-28 山东煤安矿山提升设备安装有限公司 Process for replacing hoisting ropes
CN102009917A (en) * 2010-10-26 2011-04-13 北京首钢建设集团有限公司 Method for replacing steel wire rope and gantry hook of large-scale bridge crane simultaneously
CN105016184A (en) * 2015-07-08 2015-11-04 徐州九益科技有限公司 Replacement process for lifting steel wire rope of vertical shaft multi-rope friction lifter
CN106081836A (en) * 2016-08-31 2016-11-09 山东黄金矿业(玲珑)有限公司 Vertical shaft head rope and tail rope replacing options

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1605558A (en) * 2003-10-10 2005-04-13 淄博矿业集团有限责任公司许厂煤矿 Technology for exchanging hoisting cable wire of floor type friction hoist
CN101391721A (en) * 2008-10-27 2009-03-25 兖州煤业股份有限公司 Novel technology for changing hoist steel wire rope of tower type friction winder
CN101786570A (en) * 2010-03-17 2010-07-28 山东煤安矿山提升设备安装有限公司 Process for replacing hoisting ropes
CN102009917A (en) * 2010-10-26 2011-04-13 北京首钢建设集团有限公司 Method for replacing steel wire rope and gantry hook of large-scale bridge crane simultaneously
CN105016184A (en) * 2015-07-08 2015-11-04 徐州九益科技有限公司 Replacement process for lifting steel wire rope of vertical shaft multi-rope friction lifter
CN106081836A (en) * 2016-08-31 2016-11-09 山东黄金矿业(玲珑)有限公司 Vertical shaft head rope and tail rope replacing options

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110713092A (en) * 2019-07-01 2020-01-21 海瑞可(武汉)新材料有限公司 Hoisting method and hoisting mechanism for elevator synthetic fiber rope
CN110713092B (en) * 2019-07-01 2021-06-01 海瑞可(武汉)新材料有限公司 Hoisting method and hoisting mechanism for elevator synthetic fiber rope

Similar Documents

Publication Publication Date Title
CN204251168U (en) Multi-rope friction hoist head rope changes system without stable car
CN107815969A (en) A kind of filled-type epoxy coating strand drag-line construction technology
CN203891887U (en) Split starting shield tunneling machine
CN103912257B (en) A kind of dragging multiple fracturing device with pressure
CN109720965A (en) A kind of silo coal tub way steel rope replacing method and more changing device
CN106593361B (en) A kind of oil well pump intelligent drive device and winding type pumping unit system
CN102295217A (en) On-line operation-monitoring system for cage and skip of mechanized mine
CN207453895U (en) Vehicular single cylinder lower oil tube operation device under pressure
CN206650408U (en) A kind of coal cutting roadway is servo-actuated cable-pulling chain car
CN108423586A (en) A kind of baiting method applied to CIPP based technique for in-situ remediation
CN202116257U (en) Lever for tuyere sleeve installation construction
CN204175202U (en) Oil-extractor polish-rod
CN207291997U (en) Rope hoisting device for overhead manned equipment
CN207313007U (en) A kind of pulley arrangements form of conveying trolley used in inclined shaft trailer system
CN207608191U (en) A kind of mining area vertical shaft is with vehicle signal device
CN206126702U (en) Cantilever crane formula drilling fluid aggravates device
CN205930751U (en) Mine car safety unhook instrument
CN205225104U (en) Oil pipe sliding device is down played to borehole operation high efficiency in oil field
CN108487083A (en) A kind of bridge rigid frame bridge platform overlapped construction method
CN203050635U (en) Above-ground suspension-type automatic pumping and liquid draining pumping system for testing oil in exploration well
CN209621229U (en) Rod connector
CN205472370U (en) Winch promotes wire rope's in transit controlling means
CN207018629U (en) A kind of easy device for the suspension folding and unfolding of ocean drilling and repairing machine flexible pipe
CN207498840U (en) The bridge hanging basket that can be broken the barriers
CN207260961U (en) A kind of split type oil-extraction vehicle headframe device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190507

RJ01 Rejection of invention patent application after publication