CN109707383A - Pipe jacking construction method - Google Patents

Pipe jacking construction method Download PDF

Info

Publication number
CN109707383A
CN109707383A CN201811645746.2A CN201811645746A CN109707383A CN 109707383 A CN109707383 A CN 109707383A CN 201811645746 A CN201811645746 A CN 201811645746A CN 109707383 A CN109707383 A CN 109707383A
Authority
CN
China
Prior art keywords
jacking construction
construction method
steel pipe
pipe
well
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811645746.2A
Other languages
Chinese (zh)
Inventor
王焕
李占先
苏国举
刘秀芝
高艳花
袁洋
郭勇
曹晶
李腾
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 14th Bureau Group Co Ltd
Original Assignee
China Railway 14th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 14th Bureau Group Co Ltd filed Critical China Railway 14th Bureau Group Co Ltd
Priority to CN201811645746.2A priority Critical patent/CN109707383A/en
Publication of CN109707383A publication Critical patent/CN109707383A/en
Pending legal-status Critical Current

Links

Abstract

The present invention provides a kind of pipe jacking construction methods, it include: to carry out the jacking position and angle that jacking construction measurement includes: the head using laser testing instrument detection push-bench, it is compared according to the result detected with expected effect, and controls direction of advance and the position of the head of push-bench by controller;Mud displacement is carried out after jacking work, filling hole is opened up on the soil body of the outer wall of steel pipe, third grouting pipeline is installed on filling hole, third grouting pipeline is for being passed through cement mortar or water of coal ash cement mortar to replace the thixotropic slurry at outer wall of steel pipe, to improve the structural strength of the soil body at steel pipe to prevent surface subsidence;After mud replacement completion, third grouting pipeline is removed, and filling hole is subjected to filling closure, and in the outside in filling hole setting sealing plate to be sealed.The poor technical problem of construction effect to solve pipe jacking construction method in the prior art.

Description

Pipe jacking construction method
Technical field
The present invention relates to tunnelling technical fields, in particular to a kind of pipe jacking construction method.
Background technique
Currently, pipe jacking construction method is a kind of construction method of no-dig technique, by the construction method can in few excavation or Person carries out piping laying in the case where not excavating.At work, the top power that push-bench generates is for overcoming pipe for pipe jacking construction method Pipeline is headed by the gradient of design into soil layer, and the earthwork is transported by the frictional force in road and surrounding soil.With push-bench Work, pipeline will by active well pass through soil layer enter in received well.
But the construction effect of pipe jacking construction method in the prior art is bad, is easy to cause larger construction deviation.
Summary of the invention
The main purpose of the present invention is to provide a kind of pipe jacking construction methods, to solve pipe jacking construction method in the prior art The poor technical problem of construction effect.
To achieve the goals above, the present invention provides a kind of pipe jacking construction methods, comprising: active well is excavated, wait work After well completion, the first building enclosure is set in active well, the first aperture is opened up in the first building enclosure, at the first aperture Pre-buried first orifice tube;Received well is excavated, received well and active well interval are arranged, and after well completion to be received, set in received well The second building enclosure is set, the second aperture is offered in the second building enclosure, pre-buried second orifice tube at the second aperture, second Orifice tube with the second grouting pipeline for connecting to carry out pre-grouting reinforcing or ejection for water plugging;Push pipe is placed in active well Machine, push-bench are headed into the solum between received well and active well, are headed into received well steel pipe to push-bench, are being connect It receives and steel pipe is received in well;Jacking construction measurement is carried out, to guarantee the quality of jacking construction, wherein carry out jacking construction Measurement includes: jacking position and the angle of the head using laser testing instrument detection push-bench, according to the result that detects with Expected effect is compared, and direction of advance and the position of the head of push-bench are controlled by controller;It works in jacking After carry out mud displacement, filling hole is opened up on the soil body of the outer wall of steel pipe, on filling hole install third grouting pipeline, Third grouting pipeline is for being passed through cement mortar or water of coal ash cement mortar to replace the thixotropic slurry at outer wall of steel pipe, to improve The structural strength of the soil body is at steel pipe to prevent surface subsidence;After mud replacement completion, third grouting pipeline is removed, and by filling hole Filling closure is carried out, and in the outside in filling hole setting sealing plate to be sealed.
Further, jacking construction measures further include: in the jack-in process of steel pipe, is monitored simultaneously to the position of steel pipe Measurement, to reduce deviation of the steel pipe in jack-in process.
Further, in the jack-in process of steel pipe, pipe jacking construction method further include: carry out slurrying, mud is used for It is passed through third grouting pipeline.
Further, after the completion of the first orifice tube is pre-buried, pipe jacking construction method further include: first is set up in active well Workbench.
Further, after the completion of the first workbench is set up, pipe jacking construction method further include: the erector in active well Make equipment and is debugged.
Further, steel pipe is being headed into the solum between active well and received well, pipe jacking construction method also wraps It includes: tube coupling is installed on steel pipe, to make steel pipe forming curves pipeline by tube coupling.
Further, after the completion of the second aperture is pre-buried, pipe jacking construction method further include: the second work is set up in received well Make platform, equipment is operated on the second workbench.
Further, receive to steel pipe includes: the installation reception sleeve in received well, to be received by receiving sleeve Steel pipe.
Further, after reception sleeve is installed, pipe jacking construction method further include: adjust the appearance of the head of push-bench State carries out head reception in received well.
It applies the technical scheme of the present invention, monitors position and the appearance of the head of push-bench in real time by laser testing State, and by the comparison with expected trajectory, can push-bench timely be rectified a deviation and be changed.Therefore, it mentions through the invention The technical solution of confession is able to solve the poor technical problem of the construction effect of pipe jacking construction method in the prior art.
Detailed description of the invention
The accompanying drawings constituting a part of this application is used to provide further understanding of the present invention, and of the invention shows Examples and descriptions thereof are used to explain the present invention for meaning property, does not constitute improper limitations of the present invention.In the accompanying drawings:
Fig. 1 shows the construction process figure of the jacking construction of embodiment according to the present invention offer.
Specific embodiment
It should be noted that in the absence of conflict, the features in the embodiments and the embodiments of the present application can phase Mutually combination.The present invention will be described in detail below with reference to the accompanying drawings and embodiments.
As shown in Figure 1, the embodiment of the invention provides a kind of pipe jacking construction methods, comprising: active well is excavated, to active well After completion, the first building enclosure is set in active well, the first aperture is opened up in the first building enclosure, it is pre- at the first aperture Bury the first orifice tube.Received well is excavated, received well and active well interval are arranged, and after well completion to be received, are arranged in received well Second building enclosure offers the second aperture in the second building enclosure, pre-buried second orifice tube, the second hole at the second aperture Mouth pipe is for connecting with the second grouting pipeline to carry out pre-grouting reinforcing or ejection for water plugging.Push-bench is placed in active well, Push-bench is headed into the solum between received well and active well, is headed into received well steel pipe to push-bench, is being received Steel pipe is received in well.Jacking construction measurement is carried out, to guarantee the quality of jacking construction, wherein carry out jacking construction survey Amount includes: jacking position and the angle of the head using laser testing instrument detection push-bench, according to the result detected and in advance The effect of phase is compared, and direction of advance and the position of the head of push-bench are controlled by controller.It works and ties in jacking Mud displacement is carried out after beam, filling hole is opened up on the soil body of the outer wall of steel pipe, and third grouting pipeline is installed on filling hole, the Three grouting pipelines are for being passed through cement mortar or water of coal ash cement mortar to replace the thixotropic slurry at outer wall of steel pipe, to improve steel The structural strength of the soil body is at pipe to prevent surface subsidence.After mud replacement completion, remove third grouting pipeline, and by filling hole into Row filling blocks, and in the outside in filling hole setting sealing plate to be sealed.
It applies the technical scheme of the present invention, monitors position and the appearance of the head of push-bench in real time by laser testing State, and by the comparison with expected trajectory, can push-bench timely be rectified a deviation and be changed.Therefore, it mentions through the invention The technical solution of confession is able to solve the poor technical problem of the construction effect of pipe jacking construction method in the prior art.The present embodiment In measurement further include measurement fixed point and monitoring measurement.
Specifically, the jacking construction measurement in the present embodiment further includes in the jack-in process of steel pipe, to the position of steel pipe It is monitored and measures, to reduce deviation of the steel pipe in jack-in process.Using such setting, construction can be further increased Accuracy, be construction effect preferably to improve.
In the present embodiment, in the jack-in process of steel pipe, pipe jacking construction method further include: carry out slurrying, mud For being passed through third grouting pipeline.
In the present embodiment, after the completion of the first orifice tube is pre-buried, pipe jacking construction method further include: set up in active well First workbench.
In the present embodiment, after the completion of the first workbench is set up, pipe jacking construction method further includes pacifying in active well Dress working equipment is simultaneously debugged.
In the present embodiment, steel pipe is being headed into the solum between active well and received well, pipe jacking construction method It further include that tube coupling is installed on steel pipe, to make steel pipe forming curves pipeline by tube coupling.
In the present embodiment, after the completion of the second aperture is pre-buried, pipe jacking construction method further includes that is set up in received well Two workbenches operate equipment on the second workbench.
In the present embodiment, receive to steel pipe includes the installation reception sleeve in received well, by receiving sleeve Receive steel pipe.
In the present embodiment, after reception sleeve is installed, pipe jacking construction method further includes the head for adjusting push-bench Posture carries out head reception in received well.
It can be seen from the above description that the above embodiments of the present invention realized the following chievements: improving top The construction effect of pipe construction.
The foregoing is only a preferred embodiment of the present invention, is not intended to restrict the invention, for the skill of this field For art personnel, the invention may be variously modified and varied.All within the spirits and principles of the present invention, made any to repair Change, equivalent replacement, improvement etc., should all be included in the protection scope of the present invention.

Claims (9)

1. a kind of pipe jacking construction method characterized by comprising
Active well is excavated, after active well completion, the first building enclosure is set in the active well, is enclosed described first The first aperture is opened up on protection structure, pre-buried first orifice tube at first aperture;
Received well is excavated, the received well and the active well interval are arranged, after received well completion, in the received well The second building enclosure of interior setting, offers the second aperture in second building enclosure, pre-buried at second aperture Two orifice tubes, second orifice tube with the second grouting pipeline for connecting to carry out pre-grouting reinforcing or ejection for water plugging;
Push-bench is placed in the active well, the push-bench is headed into the soil body between the received well and the active well In layer, steel pipe is headed into the received well to the push-bench, the steel pipe is received in the received well;
Jacking construction measurement is carried out, to guarantee the quality of jacking construction, wherein carrying out jacking construction measurement includes:
Using laser testing instrument detection push-bench head jacking position and angle, according to the result detected with it is expected Effect is compared, and direction of advance and the position of the head of the push-bench are controlled by controller;
Mud displacement is carried out after jacking work, filling hole is opened up on the soil body of the outer wall of the steel pipe, in the note It fills and third grouting pipeline is installed on hole, the third grouting pipeline is for being passed through cement mortar or water of coal ash cement mortar to replace Thixotropic slurry at the outer wall of steel pipe, to improve the structural strength of the soil body at the steel pipe to prevent surface subsidence;
After mud replacement completion, the third grouting pipeline is removed, and the filling hole is subjected to filling closure, and in the note The outside setting sealing plate in hole is filled to be sealed.
2. pipe jacking construction method according to claim 1, which is characterized in that the jacking construction measurement further include:
In the jack-in process of the steel pipe, the position of the steel pipe is monitored and is measured, to reduce the steel pipe in institute State the deviation in jack-in process.
3. pipe jacking construction method according to claim 1, which is characterized in that described in the jack-in process of the steel pipe Pipe jacking construction method further include:
Slurrying is carried out, the mud is for being passed through the third grouting pipeline.
4. pipe jacking construction method according to claim 1, which is characterized in that after the completion of first orifice tube is pre-buried, The pipe jacking construction method further include:
The first workbench is set up in the active well.
5. pipe jacking construction method according to claim 4, which is characterized in that set up completion in first workbench Afterwards, the pipe jacking construction method further include:
It installment work equipment and is debugged in the active well.
6. pipe jacking construction method according to claim 1, which is characterized in that head by the steel pipe to the active well Before solum between the received well, the pipe jacking construction method further include:
Tube coupling is installed on the steel pipe, to make the steel pipe forming curves pipeline by the tube coupling.
7. pipe jacking construction method according to claim 1, which is characterized in that after the completion of second orifice tube is pre-buried, The pipe jacking construction method further include:
The second workbench is set up in the received well, and equipment is operated on second workbench.
8. pipe jacking construction method according to claim 1, which is characterized in that carrying out reception to the steel pipe includes:
Installation receives sleeve in the received well, to receive the steel pipe by the reception sleeve.
9. pipe jacking construction method according to claim 8, which is characterized in that described after the reception sleeve is installed Pipe jacking construction method further include:
The posture for adjusting the head of the push-bench carries out head reception in the received well.
CN201811645746.2A 2018-12-30 2018-12-30 Pipe jacking construction method Pending CN109707383A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811645746.2A CN109707383A (en) 2018-12-30 2018-12-30 Pipe jacking construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811645746.2A CN109707383A (en) 2018-12-30 2018-12-30 Pipe jacking construction method

Publications (1)

Publication Number Publication Date
CN109707383A true CN109707383A (en) 2019-05-03

Family

ID=66260415

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811645746.2A Pending CN109707383A (en) 2018-12-30 2018-12-30 Pipe jacking construction method

Country Status (1)

Country Link
CN (1) CN109707383A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110106961A (en) * 2019-06-06 2019-08-09 广东隆建工程有限公司 Drainage management construction method
CN110318419A (en) * 2019-06-20 2019-10-11 中国十七冶集团有限公司 The construction method of the lining door opening supporting of underpass type piping lane one
CN111075474A (en) * 2020-01-08 2020-04-28 中铁十一局集团城市轨道工程有限公司 Rectangular pipe jacking construction method for subway station access and exit channel
CN111236390A (en) * 2020-01-19 2020-06-05 中建四局安装工程有限公司 Push pipe trenchless construction method
CN111335912A (en) * 2019-12-17 2020-06-26 中建水务环保有限公司 Large-pipe-diameter mechanical pipe jacking construction process for soft soil foundation in collapsible loess area
CN112503248A (en) * 2020-12-08 2021-03-16 中国化学工程第六建设有限公司 Long-distance concrete culvert pipe curve jacking pipe installation method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103322989A (en) * 2013-06-06 2013-09-25 上海米度测量技术有限公司 Measuring device and method of dynamic real-time measurement of position and posture of pipe pushing jack
CN104265321A (en) * 2014-08-06 2015-01-07 上海隧道工程有限公司 Ultra-large full-face rectangular pipe jacking tunneling construction method
CN109059879A (en) * 2018-08-03 2018-12-21 华中科技大学 A kind of guidance method for determining the small-bore Curve Pipe Jacking of curvature

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103322989A (en) * 2013-06-06 2013-09-25 上海米度测量技术有限公司 Measuring device and method of dynamic real-time measurement of position and posture of pipe pushing jack
CN104265321A (en) * 2014-08-06 2015-01-07 上海隧道工程有限公司 Ultra-large full-face rectangular pipe jacking tunneling construction method
CN109059879A (en) * 2018-08-03 2018-12-21 华中科技大学 A kind of guidance method for determining the small-bore Curve Pipe Jacking of curvature

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110106961A (en) * 2019-06-06 2019-08-09 广东隆建工程有限公司 Drainage management construction method
CN110318419A (en) * 2019-06-20 2019-10-11 中国十七冶集团有限公司 The construction method of the lining door opening supporting of underpass type piping lane one
CN110318419B (en) * 2019-06-20 2021-03-19 中国十七冶集团有限公司 Construction method of one-lining door opening support of underpass type pipe gallery
CN111335912A (en) * 2019-12-17 2020-06-26 中建水务环保有限公司 Large-pipe-diameter mechanical pipe jacking construction process for soft soil foundation in collapsible loess area
CN111335912B (en) * 2019-12-17 2022-03-11 中建水务环保有限公司 Large-pipe-diameter mechanical pipe jacking construction process for soft soil foundation in collapsible loess area
CN111075474A (en) * 2020-01-08 2020-04-28 中铁十一局集团城市轨道工程有限公司 Rectangular pipe jacking construction method for subway station access and exit channel
CN111075474B (en) * 2020-01-08 2021-02-02 中铁十一局集团城市轨道工程有限公司 Rectangular pipe jacking construction method for subway station access and exit channel
CN111236390A (en) * 2020-01-19 2020-06-05 中建四局安装工程有限公司 Push pipe trenchless construction method
CN112503248A (en) * 2020-12-08 2021-03-16 中国化学工程第六建设有限公司 Long-distance concrete culvert pipe curve jacking pipe installation method

Similar Documents

Publication Publication Date Title
CN109707383A (en) Pipe jacking construction method
CN106837352A (en) Fault belt surrounding rock tunnel construction method
CN101429764B (en) Infiltration water detection and plugging renovation devices and methods for underground continuous wall groove segment seam
CN109653755B (en) Construction method for large-diameter slurry shield to pass through ballastless track roadbed without settlement
CN103821544B (en) Tunneling and underground engineering high-pressure high-flow is dashed forward Water outburst treatment method
CN105422078B (en) Country rock Mining failure scope sectionalization test method
CN109723443B (en) Tunnel construction method
CN106641440A (en) Underground pipeline jacking construction method capable of transversely passing through railway line
CN107119669A (en) For shield, the pre-pouring grout consolidated subsoil method in house is worn in side in water-rich sand layer
CN102635119A (en) Supporting method for construction of swirl well
CN106245627A (en) A kind of quick positioning construction method of steel pipe stanchion
CN107503755A (en) A kind of construction method for exempting from button arch flat-top cavern-pile method construction subway station
CN103410522A (en) Continuous close-range underpass railway bridge construction method employing shallow tunneling method
JP2023500745A (en) A Comprehensive Construction Method for a Tunnel with Low Overburden Section Using the Regional Railway Mining Method
CN110130901A (en) On across both wired Urban Underground mining sectbn construction methods
CN104100272A (en) Quick construction method of tunnels traversing unfavorable geology
CN107268688A (en) I-shaped steel joint of diaphragm wall reinforces the construction method of sealing
CN103696430A (en) Construction process of non-grouted recyclable steel-pipe piles
CN201424658Y (en) Water leakage detection of underground continuous wall groove seams and block repair device
CN109162635A (en) A kind of new pressure measuring drill hole construction technology
CN110514184A (en) One kind being used for deeper formation deformation measurement easy device and its method for measurement
CN107165641B (en) High inclination-angle ladder way opposite direction excavating construction method in thin layer breaking up hard rock stratum
CN109681229B (en) Tunnel water stop assembly
CN104315251B (en) Artificial pipe jacking construction method under soil stone combination geological conditions
CN111623168B (en) In-situ deviation rectification design construction method for jacking pipe

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190503