CN109707036A - A kind of detachable pre-fabricated one and its assembly method based on fashioned iron connection - Google Patents

A kind of detachable pre-fabricated one and its assembly method based on fashioned iron connection Download PDF

Info

Publication number
CN109707036A
CN109707036A CN201811530623.4A CN201811530623A CN109707036A CN 109707036 A CN109707036 A CN 109707036A CN 201811530623 A CN201811530623 A CN 201811530623A CN 109707036 A CN109707036 A CN 109707036A
Authority
CN
China
Prior art keywords
steel
column
buckle
prefabricated post
fabricated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811530623.4A
Other languages
Chinese (zh)
Other versions
CN109707036B (en
Inventor
李祚华
童建坤
滕军
齐一鹤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Graduate School Harbin Institute of Technology
Original Assignee
Shenzhen Graduate School Harbin Institute of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Graduate School Harbin Institute of Technology filed Critical Shenzhen Graduate School Harbin Institute of Technology
Priority to CN201811530623.4A priority Critical patent/CN109707036B/en
Publication of CN109707036A publication Critical patent/CN109707036A/en
Application granted granted Critical
Publication of CN109707036B publication Critical patent/CN109707036B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

A kind of detachable frame structure and its assembly method based on fashioned iron connection, its structure includes prefabricated post, precast beam and buckle, wherein, prefabricated post split point is arranged near pillar inflection point, connection between prefabricated post and prefabricated post is mutually nested with inner cylinder by the inner ring for being respectively provided at prefabricated post both ends, at the same outer ring and outer cylinder be mutually butted after fixed using buckle;The buckle includes tack buckle and plagiocephaly buckle;Prefabricated post bean column node position is equipped with the steel node of column and beam being welded by square steel tube and column I-steel, it is fixed after docking between prefabricated post and precast beam is connect by the beam I-steel of column I-steel on steel node of column and beam and precast beam wherein one end and by cover board and bolt, the present invention is also based on the structure and proposes a kind of assembly method.The present invention is a kind of dry connection type, that is, connects and use, and quality of connection is reliable and easily detection, realizes detachable in structure type, and form of construction work is succinct, can reach faster, the more reliable, standard more saved.

Description

A kind of detachable pre-fabricated one and its assembly method based on fashioned iron connection
Technical field
The invention belongs to technical field of building construction, especially a kind of detachable pre-fabricated one based on fashioned iron connection And its assembly method.
Background technique
Prefabricated construction (lower abbreviation: precast construction) has extensive application all over the world, and precast construction can be real Existing building industrialization production.In the case where demographic dividend reduces, building-site construction personnel's cost is high, precast construction Development may be a completely new building constructive direction.Simultaneously precast construction energy conservation and environmental protection, that building site can be greatly decreased is existing The adverse effect of field construction, under epipodium guaranteed request, the cast-in-place operation in construction site will receive impact.And use full precast construction can To overcome on-site noise, dust etc. to pollute well, while speed of application and available promotion, shorten the completion time of project, saves Construction cost.
Existing precast construction splicing relies primarily on prefabricated components node wet connection, and way is designed according to structure, in frame Structure is split at frame node, makes prefabricated post and precast beam, prefabricated components end reserved steel bar.When installation, hang at the construction field (site) Prefabricated components are filled, prefabricated components is docked, is fixed the reserved steel bar docked up and down by sleeve connection, then pass through filling concrete Sleeve realizes the connection of vertical muscle up and down.After connecting reserving rib, then the node progress formwork and second coagulation soil of fractionation are poured It builds, realizes prefabricated components splicing after maintenance is good.
Under the prior art, at following three aspects, there are problems:
(1) first in terms of construction quality, the secondary uncertain energy and prefabricated components concrete of pouring of node have good combination.
(2) secondly in terms of structural behaviour, after pour node, it is difficult to guarantee the design of the weak component of strong node.
(3) complicated for operation to node support mold pouring concrete finally for construction technology, node process of setting needs Special supporting, it is time-consuming.
Moreover, splicing construction is disposable, the splicing not reproducible use of component under wet connection.
Summary of the invention
For in the prior art, the invention proposes a kind of based on the detachable pre- of fashioned iron connection Frame structure and its assembly method processed.
A kind of detachable pre-fabricated one based on fashioned iron connection, including prefabricated post, precast beam and buckle, it is described prefabricated Column includes prefabricated post ontology, is located at the upper steel attachment base of prefabricated post ontology upper end, the lower steel attachment base of lower end, connect with upper steel Column steel reinforcement cage and embedding column steel reinforcement cage and part upper the steel attachment base, lower steel attachment base that seat, lower steel attachment base weld together Concrete column;
The precast beam includes precast beam body, be embedded in respectively the left and right end of precast beam body beam i shaped steel, with it is left and right The beam i shaped steel of beam steel cage and the left and right end of embedding beam steel cage and part that the beam i shaped steel at end welds together Concrete beam body;
The buckle includes the first buckle and the second buckle;
The upper steel attachment base is welded with inner barrel and outer barrel, and lower steel attachment base is welded with inner ring and outer ring, outer ring and outer cylinder to pre- The sidewall edge of column outer body processed is the high inclined-plane in intermediate low both sides;When column connects, inner ring in different prefabricated posts with Inner cylinder is nested to form gapless sleeve, after outer ring is docked with outer cylinder, first passes through and consolidates at the second buckle inclined-plane high to both sides It is fixed, then by being fixed at the first buckle inclined-plane low to centre;
The steel column beam section being welded by square steel tube and column I-steel is equipped at the middle part bean column node of the prefabricated post ontology Point, except the exposed prefabricated post ontology of column I-steel, when column beam connects: column I-steel is bolted with beam I-steel.
As the further improvement of invention, the upper steel attachment base includes upper steel connecting plate, and the upper steel connecting plate is to pre- Last time font steel ring is welded on the inside of column ontology processed;The lower steel attachment base includes lower steel connecting plate, and the lower steel connecting plate is to pre- Font steel ring next time is welded on the inside of column ontology processed;Inside the last time font steel ring, next time font steel ring and concrete column The welding of column steel reinforcement cage.
As the further improvement of invention, last time font steel ring, next time font steel ring are also welded with J-shaped bar dowel respectively It connects, for being anchored inside concrete column.
As the further improvement of invention, it is external to prefabricated post sheet that the inner cylinder, outer cylinder are respectively welded at steel connecting plate Side;The inner ring, outer ring are respectively welded at lower steel connecting plate to prefabricated post outer body.
As the further improvement of invention, the upper lower flange of the beam I-steel and the upper and lower vertical muscle inside precast beam body It is connected and fixed.
As the further improvement of invention, when column beam connects: column I-steel is connect by bolt with cover board with beam I-steel, Realize the detachability of precast beam and prefabricated post.
As the further improvement of invention, the outer cylinder and outer ring are rectangular-ambulatory-plane structure, and 4 sides of rectangular-ambulatory-plane structure Wall is the high inclined-plane in intermediate low both sides, is first put into the second buckle from the intermediate gap on inclined-plane and is pushed again to both sides clamping, then Be clamped on intermediate opening position for first, it may be assumed that installed by the intermediate gap of outer ring one side, into intermediate gap after to two sides Slide clamping outer ring;The closure of intermediate gap, limitation plagiocephaly buckle sliding are realized simultaneously.
As the further improvement of invention, it is horizontal plane that the high inclined-plane in the low both sides in the centre, which includes: intermediate opening position, two Side is the slope surface that gradient is less than steel angle of friction;First buckle is that tack buckles, and second buckle is plagiocephaly clamp;Institute The gradient for stating the second buckle is consistent with outer cylinder, the slope surface gradient of outer ring.
As the further improvement of invention, the gradient of the slope surface is less than 24 °.
A kind of assembly method of the detachable pre-fabricated one as described above based on fashioned iron connection, including walk as follows It is rapid:
The connection of S1, prefabricated post and precast beam, when installation, by the steel column beam section of the beam I-steel of precast beam one end and prefabricated post Exposed same specification column I-steel docking at point, by cover board and is bolted, and bolt is removed when the later period dismantles can be realized weight Recycling;
S2, after two different prefabricated posts are docked up and down, by the first buckle of installation and the second buckle, by outer cylinder and outer ring After clamping, cross spot welding form will mounted first buckle, second buckle fixed position, when disassembly, first remove spot welding and connect, tear open Lower first buckle and the second buckle, realize disassembly.
For compared with prior art, the beneficial effects of the present invention are:
A kind of detachable pre-fabricated one based on fashioned iron connection of the invention is a kind of dry connection type, on realizing intensity Etc. being better than outside cast in place frame, the weak component of strong node is functionally more met than cast-in-place structural, the controllable antidetonation of beam-ends plastic hinge is set Meter requires, and can split according to target framework form in structure type, can simplify existing precast construction construction in construction It is required that reach faster, the more reliable, standard more saved.
Detailed description of the invention
Fig. 1 is a kind of schematic diagram of the detachable pre-fabricated one based on fashioned iron connection of the present invention.
Fig. 2 is a kind of exploded view of precast beam of the present invention.
Fig. 3 is a kind of structural schematic diagram of prefabricated post of the present invention.
Fig. 4 is a kind of exploded view of prefabricated post of the present invention.
Fig. 5 is a kind of outer cylinder/outer ring of the present invention and the structural schematic diagram that snaps connection.
Fig. 6 is a kind of outer cylinder/outer ring of the present invention and the exploded view that snaps connection.
Fig. 7 is a kind of structural schematic diagram of tack buckle of the invention.
Fig. 8 is a kind of structural schematic diagram of plagiocephaly buckle of the invention.
Appended drawing reference: 100- precast beam, 200- buckle, 300- prefabricated post, 1- beam i shaped steel, 2- concrete beam body, 3- Tack buckle, 4- plagiocephaly buckle, 5- concrete column, the upper steel connecting plate of 6-, steel connecting plate under 7-, 8- last time font steel ring, 9- Font steel ring next time, 10- inner cylinder, 11- outer cylinder, 12- inner ring, the outer ring 13-, 14- cross partition, 15- square steel tube, 16- column I-shaped Steel.
Specific embodiment
In order to illustrate the technical solutions in the embodiments of the present application or in the prior art more clearly, with reference to the accompanying drawing and specifically The present invention is further described for embodiment.
Embodiment 1
As shown in figures 1-8, a kind of detachable pre-fabricated one based on fashioned iron connection of the invention includes following three parts: pre- Beam 100 processed, buckle 200, prefabricated post 300.
First introduce precast beam 100.As shown in Fig. 2, the precast beam 100 includes precast beam body, it is embedded in respectively prefabricated The beam steel cage that the beam i shaped steel 1 at the left and right end of beam ontology and the beam i shaped steel 1 at left and right end weld together is (in figure not Show) and the left and right end of embedding beam steel cage and part i shaped steel 1 concrete beam body 2.Above structure imparts pre- The reinforced concrete structure on the basis of beam processed, ensure that its basic connection attribute and intensity.
Further, the beam I-steel 1 is connect by lower flange thereon with the upper and lower vertical muscle inside precast beam body 2, It is formed reliable fixed.The upper lower flange thickness of beam I-steel 1 is removed by after vertical muscle sectional dimension cross-section conversion up and down, also to be expired Requirement of the sufficient composite structure about minimum steel plate thickness.
Secondly buckle 300 is introduced.As Figure 7-8, the buckle 200 is preferably that tack buckles 3 Hes in the present embodiment Plagiocephaly buckle 4, tack buckle 3 and plagiocephaly buckle 4 are for the connection between two prefabricated posts 300 after docking up and down.It is right Being further described for buckle is described below.
Next introduces prefabricated post 300, and as seen in figures 3-6, the prefabricated post includes prefabricated post ontology, is located at prefabricated post ontology The column steel reinforcement cage that the upper steel attachment base of upper end, the lower steel attachment base of lower end and upper steel attachment base, lower steel attachment base weld together The concrete column 5 of the upper steel attachment base of (not shown) and embedding column steel reinforcement cage and part, lower steel attachment base.Above-mentioned knot Structure imparts the reinforced concrete structure on the basis of prefabricated post, ensure that its basic connection attribute and intensity.
Further, the upper steel attachment base includes upper steel connecting plate 6, and the lower steel attachment base includes lower steel connecting plate 7. In the present invention, the pedestal of upper steel connecting plate 6, lower steel connecting plate 7 as steel attachment base needs to undertake following three as shown in figures 3-8 The effect that aspect is formed a connecting link:
(1) the upper steel connecting plate 6 is welded with last time font steel ring 8 to prefabricated post ontology inside;The lower steel connecting plate 7 is to pre- Font steel ring 9 next time is welded on the inside of column ontology processed;In the last time font steel ring 8, next time font steel ring 9 and concrete column 5 The column steel reinforcement cage in portion welds, and by welding with J-shaped bar dowel, for being anchored inside concrete column, strengthens each steel and connects Bonding strength between fishplate bar and concrete column.
(2) the upper steel connecting plate 6 is welded with inner cylinder 10 and outer cylinder 11, the lower steel connecting plate to prefabricated post outer body 7 are welded with inner ring 12 and outer ring 13 to prefabricated post outer body.Up and down in two prefabricated posts after docking, inner ring 12 can be nested into In inner cylinder 10, gapless sleeve is formed, the inner cylinder after nesting is mainly used to transmit the shearing of prefabricated intercolumniation and torque and biography Pass axis pressure.In order to which the fixation after docking is better achieved, the outer cylinder 11 and outer ring 13 are rectangular-ambulatory-plane structure, and are wanted Ask: outer cylinder 11 and outer ring 13 to 4 sidewall edges of prefabricated post outer body be the high inclined-plane in intermediate low both sides, the spy on the inclined-plane Property are as follows: intermediate opening position is horizontal plane, and both sides are the slope surface that gradient is less than steel angle of friction.In order to mutually be fitted with the inclined-plane characteristic It answers, the gradient requirement of plagiocephaly buckle 4 is consistent with outer cylinder, the slope surface gradient of outer ring, can agree with completely.
When then prefabricated post is docked up and down with prefabricated post, the inner ring 12 of the prefabricated post in top and the prefabricated post being below Inner cylinder 10 be nested, be now in top prefabricated post outer ring 13 and the prefabricated post being below about 11 outer cylinder it is right It connects, at this point, plagiocephaly buckle 4 is put by the intermediate opening position of outer ring 13, the inclined-plane of outer cylinder 11, then pushes, push to both sides Plagiocephaly buckle 4 is further away from intermediate gap in the process, to outer ring 13, outer cylinder 11 generate to be pressed down against power bigger, successively will in this way Plagiocephaly buckle 4 installs, and tack buckle 3 is finally placed in intermediate opening position, blocks intermediate gap, it is therefore intended that limitation Plagiocephaly buckle 4 is glided, is loosened, and buckle plays the role of transmission axle pulling force herein;When disassembly, is realized and blocked using inverse process Button disassembly.
Scheme still more preferably is that slope surface gradient is less than 24 ° of steel Self-locking angle.
Scheme still more preferably is that the tensile bearing capacity of buckle is weaker than the outer rim tensile bearing capacity of buckle clamping.
(3) steel connecting plate 7 is also welded with cross partition 14 to prefabricated post outer body under, for improving the inner cylinder after nesting Intensity, be more advantageous to the shearing for transmitting prefabricated intercolumniation and torque and transmission axle pressure.
The prefabricated post 300 further includes with flowering structure, for the connection with precast beam:
The steel column being welded by square steel tube 15 and column I-steel 16 is built-in at the middle part inflection point of the prefabricated post ontology Girder connection, except the exposed prefabricated post ontology of column I-steel 16.
When then prefabricated post and precast beam are installed, by the steel column of the beam I-steel 1 of 200 one end of precast beam and prefabricated post 300 Exposed same specification column I-steel 16 docks at girder connection, then by cover board and is bolted, and realizes precast beam and prefabricated post Detachability;Dismounting bolt, which can be realized, when later period dismantles returns receipts.In this scheme, prefabricated post split point is arranged in pillar Near portion's inflection point, the fractionation of bean column node is avoided, ensure that node globality.
It is further preferred that the 15 four sides property of can choose of square steel tube is welded, to realize that different role converts, such as: side column, angle Column, inner prop.
Embodiment 2
Optimal technical solution based on embodiment 1 is formed by a kind of detachable pre-fabricated one based on fashioned iron connection, Assembly method is as follows:
The connection of S1, prefabricated post and precast beam, when installation, by the steel column of the beam I-steel of precast beam one end and prefabricated post beam column Exposed same specification column I-steel docking at girder connection, by cover board and is bolted, and removing bolt when the later period dismantles can be real Now return receipts;
S2 after docking two different prefabricated posts up and down, is buckled, by outer cylinder and outer ring by installation tack buckle and plagiocephaly It after clamping, crosses that mounted tack buckle by spot welding form, plagiocephaly buckles fixed position, when disassembly, first removes spot welding and connect, tear open Lower tack buckle and plagiocephaly buckle, realize disassembly.
Above-described embodiment illustrates that the present invention is better than outside cast in place frame on realizing intensity etc., functionally more than cast-in-place structural Meet the weak component of strong node, the controllable Seismic Design Requirements of beam-ends plastic hinge can be according to target framework shape in structure type Formula is split, and can simplify existing precast construction construction requirement in construction, reach faster, the more reliable, standard more saved, specifically Achieve following advantages: 1. realizations are prefabricated detachable;2. building-site construction can be greatly decreased in precast construction energy conservation and environmental protection Adverse effect.3. full precast construction can be very good to overcome on-site noise, dust etc. to pollute, at the same speed of application with it is available It is promoted, shortens the completion time of project, save construction cost;4. maintenance cost is low;5. merging precision height etc..
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention Made any modifications, equivalent replacements, and improvements etc., should all be included in the protection scope of the present invention within mind and principle.

Claims (10)

1. a kind of detachable pre-fabricated one based on fashioned iron connection, which is characterized in that including prefabricated post, precast beam and card Button, the prefabricated post includes prefabricated post ontology, be located at the upper steel attachment base of prefabricated post ontology upper end, the lower steel attachment base of lower end, The upper steel attachment base of the column steel reinforcement cage and embedding column steel reinforcement cage that weld together with upper steel attachment base, lower steel attachment base and part, The concrete column of lower steel attachment base;
The precast beam includes precast beam body, be embedded in respectively the left and right end of precast beam body beam i shaped steel, with it is left and right The beam i shaped steel of beam steel cage and the left and right end of embedding beam steel cage and part that the beam i shaped steel at end welds together Concrete beam body;
The buckle includes the first buckle and the second buckle;
The upper steel attachment base is welded with inner barrel and outer barrel, and lower steel attachment base is welded with inner ring and outer ring, outer cylinder and outer ring to pre- The sidewall edge of column outer body processed is the high inclined-plane in intermediate low both sides;When column connects, inner ring in different prefabricated posts with Inner cylinder is nested to form gapless sleeve, after outer ring is docked with outer cylinder, first passes through and consolidates at the second buckle inclined-plane high to both sides It is fixed, then by being fixed at the first buckle inclined-plane low to centre;
The steel node of column and beam being welded by square steel tube and column I-steel, column are equipped at the bean column node of the prefabricated post ontology Except the exposed prefabricated post ontology of I-steel, when column beam connects: column I-steel is bolted with beam I-steel.
2. the detachable pre-fabricated one according to claim 1 based on fashioned iron connection, which is characterized in that the upper steel Attachment base includes upper steel connecting plate, and the upper steel connecting plate welds last time font steel ring to prefabricated post ontology inside;The lower steel Attachment base includes lower steel connecting plate, and the lower steel connecting plate welds font steel ring next time to prefabricated post ontology inside;The last time Column steel reinforcement cage inside font steel ring, next time font steel ring and concrete column welds.
3. the detachable pre-fabricated one according to claim 2 based on fashioned iron connection, which is characterized in that upper rectangular-ambulatory-plane Steel ring, next time font steel ring are also welded with J-shaped bar dowel respectively, for being anchored inside concrete column.
4. the detachable pre-fabricated one according to claim 2 based on fashioned iron connection, which is characterized in that in described Cylinder, outer cylinder are respectively welded at steel connecting plate to prefabricated post outer body;The inner ring, outer ring are respectively welded at lower steel connecting plate To prefabricated post outer body.
5. the detachable pre-fabricated one according to claim 1 based on fashioned iron connection, which is characterized in that the Liang work The upper lower flange of word steel is connected and fixed with the upper and lower vertical muscle inside precast beam body.
6. the detachable pre-fabricated one according to claim 1 based on fashioned iron connection, which is characterized in that the connection of column beam When: column I-steel is connect by bolt with cover board with beam I-steel.
7. the detachable pre-fabricated one according to claim 1-6 based on fashioned iron connection, which is characterized in that The outer cylinder and outer ring are rectangular-ambulatory-plane structure, and 4 side walls of rectangular-ambulatory-plane structure are the high inclined-plane in intermediate low both sides, first will Second buckle is put into from the intermediate gap on inclined-plane to be pushed again to both sides clamping, then is clamped on intermediate opening position for first, is sealed Stifled intermediate gap.
8. the detachable pre-fabricated one according to claim 7 based on fashioned iron connection, which is characterized in that the centre The high inclined-plane in low both sides includes: that intermediate opening position is horizontal plane, and both sides are the slope surface that gradient is less than steel angle of friction;Described first Buckle is that tack buckles, and second buckle is plagiocephaly clamp;The gradient of second buckle and the slope surface gradient of outer cylinder, outer ring Unanimously.
9. the detachable pre-fabricated one according to claim 8 based on fashioned iron connection, which is characterized in that the slope surface Gradient less than 24 °.
10. a kind of assembly side of the described in any item detachable pre-fabricated ones based on fashioned iron connection of such as claim 1-9 Method, which comprises the following steps:
The connection of S1, prefabricated post and precast beam, when installation, by the steel column beam section of the beam I-steel of precast beam one end and prefabricated post Exposed same specification column I-steel docking at point, by cover board and is bolted, and bolt is removed when the later period dismantles can be realized weight Recycling;
S2, after two different prefabricated posts are docked up and down, by the first buckle of installation and the second buckle, by outer cylinder and outer ring After clamping, cross spot welding form will mounted first buckle, second buckle fixed position, when disassembly, first remove spot welding and connect, tear open Lower first buckle and the second buckle, realize disassembly.
CN201811530623.4A 2018-12-14 2018-12-14 Detachable prefabricated frame structure based on section steel connection and assembling method thereof Active CN109707036B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811530623.4A CN109707036B (en) 2018-12-14 2018-12-14 Detachable prefabricated frame structure based on section steel connection and assembling method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811530623.4A CN109707036B (en) 2018-12-14 2018-12-14 Detachable prefabricated frame structure based on section steel connection and assembling method thereof

Publications (2)

Publication Number Publication Date
CN109707036A true CN109707036A (en) 2019-05-03
CN109707036B CN109707036B (en) 2020-02-14

Family

ID=66256454

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811530623.4A Active CN109707036B (en) 2018-12-14 2018-12-14 Detachable prefabricated frame structure based on section steel connection and assembling method thereof

Country Status (1)

Country Link
CN (1) CN109707036B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110145026A (en) * 2019-06-20 2019-08-20 安徽建筑大学 A kind of connecting elements of assembly concrete frame beam column
CN112854479A (en) * 2021-03-04 2021-05-28 羿射旭减隔震张家口有限公司 Assembled building beam column node
CN113123458A (en) * 2021-03-06 2021-07-16 河北工业大学 Connecting column type steel connection energy dissipation support frame system and construction method
CN114434057A (en) * 2022-02-23 2022-05-06 安徽蔚能环保科技有限公司 Dust removal filter bag skeleton welding processingequipment

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0396544A (en) * 1989-09-07 1991-04-22 Taisei Corp Jointing method for precast steel frame reinforced concrete column having beam steel frame
CN202220403U (en) * 2011-09-08 2012-05-16 张吉华 Prefabricated reinforced concrete structural column used in fabricated building
CN104912190A (en) * 2015-06-17 2015-09-16 淮海工学院 Dry type joggle frame structure
CN206737144U (en) * 2017-05-10 2017-12-12 刘艳 A kind of fully-prefabricated assembled post column connected node
CN108571071A (en) * 2018-07-11 2018-09-25 上海应用技术大学 Prefabricated PC beams of concrete column connected node and construction method
CN207998925U (en) * 2018-03-19 2018-10-23 建研科技股份有限公司 Full-prefabricated assembled concrete frame
CN108797800A (en) * 2018-06-19 2018-11-13 福建农林大学 The prefabricated column connected node of assembly concrete-filled steel tube and its construction method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0396544A (en) * 1989-09-07 1991-04-22 Taisei Corp Jointing method for precast steel frame reinforced concrete column having beam steel frame
CN202220403U (en) * 2011-09-08 2012-05-16 张吉华 Prefabricated reinforced concrete structural column used in fabricated building
CN104912190A (en) * 2015-06-17 2015-09-16 淮海工学院 Dry type joggle frame structure
CN206737144U (en) * 2017-05-10 2017-12-12 刘艳 A kind of fully-prefabricated assembled post column connected node
CN207998925U (en) * 2018-03-19 2018-10-23 建研科技股份有限公司 Full-prefabricated assembled concrete frame
CN108797800A (en) * 2018-06-19 2018-11-13 福建农林大学 The prefabricated column connected node of assembly concrete-filled steel tube and its construction method
CN108571071A (en) * 2018-07-11 2018-09-25 上海应用技术大学 Prefabricated PC beams of concrete column connected node and construction method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110145026A (en) * 2019-06-20 2019-08-20 安徽建筑大学 A kind of connecting elements of assembly concrete frame beam column
CN112854479A (en) * 2021-03-04 2021-05-28 羿射旭减隔震张家口有限公司 Assembled building beam column node
CN113123458A (en) * 2021-03-06 2021-07-16 河北工业大学 Connecting column type steel connection energy dissipation support frame system and construction method
CN114434057A (en) * 2022-02-23 2022-05-06 安徽蔚能环保科技有限公司 Dust removal filter bag skeleton welding processingequipment
CN114434057B (en) * 2022-02-23 2023-08-22 安徽蔚能环保科技股份有限公司 Dedusting filter bag framework welding processing device

Also Published As

Publication number Publication date
CN109707036B (en) 2020-02-14

Similar Documents

Publication Publication Date Title
CN109707036A (en) A kind of detachable pre-fabricated one and its assembly method based on fashioned iron connection
CN105386405B (en) Based on bolted Precast Concrete Segmental Bridges concrete pier of steel tube
CN201567530U (en) Assembly-type combined box girder and component unit body
CN105088971B (en) Mid-span closure construction method of corrugated steel web PC box girder cable-stayed bridge
CN107574924A (en) The component and construction method of a kind of assembly concrete framework for the connection of steel joint
KR101318957B1 (en) Sump Pit
CN202466844U (en) Top layer node connecting structure for concrete-filled steel tube column and steel reinforced concrete beam
CN215407022U (en) Prefabricated staircase for subway station entrance/exit
CN112962824B (en) Short-leg steel plate shear wall with replaceable energy consumption components and construction method thereof
CN107574923A (en) A kind of prefabricated assembled concrete framework connected using steel joint
CN206902913U (en) A kind of high-altitude long-span overhung structure
CN111576196A (en) On-site splicing pouring construction process for prefabricated pier column segment shell and bent cap
CN109707069A (en) One kind connecting detachable prefabricated modularization shear wall and its assembly method based on fashioned iron
CN203640257U (en) Support of overhanging type scaffold
CN206554385U (en) Combining structure for assembled architecture
CN215330012U (en) Prefabricated pin-connected panel underpass interface frame construction
CN212743026U (en) Prefabricated shear wall panel structure without door and window opening
CN205502058U (en) Pin -connected panel tower crane foundation
CN108018943A (en) A kind of complete prefabricated beam column attachment device and its construction method
CN209836774U (en) Connecting structure of steel web and precast concrete slab of assembled steel web combined box girder
CN207847078U (en) Core Walls Structure shear wall converts boom device without wall without creeping formwork seat in the plane at beam
CN210216119U (en) Transverse connecting structure for bridge deck of concrete girder
CN207048365U (en) It is a kind of to have enough to meet the need steel member suitable for shear wall external reinforcement at tower crane attachment
CN218643195U (en) Temporary buttress device capable of being assembled
CN105019362A (en) Pier top block of precast beam constructed by stub matching method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant