CN207847078U - Core Walls Structure shear wall converts boom device without wall without creeping formwork seat in the plane at beam - Google Patents

Core Walls Structure shear wall converts boom device without wall without creeping formwork seat in the plane at beam Download PDF

Info

Publication number
CN207847078U
CN207847078U CN201721498996.9U CN201721498996U CN207847078U CN 207847078 U CN207847078 U CN 207847078U CN 201721498996 U CN201721498996 U CN 201721498996U CN 207847078 U CN207847078 U CN 207847078U
Authority
CN
China
Prior art keywords
plane
fitting
built
creeping formwork
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721498996.9U
Other languages
Chinese (zh)
Inventor
戴宏康
张志明
周旦军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Lanyue Engineering Technology Development Co Ltd
Original Assignee
Jiangsu Lanyue Engineering Technology Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Lanyue Engineering Technology Development Co Ltd filed Critical Jiangsu Lanyue Engineering Technology Development Co Ltd
Priority to CN201721498996.9U priority Critical patent/CN207847078U/en
Application granted granted Critical
Publication of CN207847078U publication Critical patent/CN207847078U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model is related to a kind of Core Walls Structure shear walls to convert boom device without wall without creeping formwork seat in the plane at beam.Including the built-in fitting in door opening two sides is arranged(1), the built-in fitting(1)On be provided with several connecting holes(2), it is provided with conversion beam(3)Pass through the connecting hole(2)It is connected to built-in fitting(1)On, the conversion beam(3)Side is provided with connecting plate(4), the connecting plate(4)Upper connection creeping formwork seat in the plane.When the utility model constructs to structure nonstandard layer, it can maximize and shorten construction period and climbing formwork for construction safety, then under common process condition of construction, design efficiency is fully achieved above most economical, technical security.

Description

Core Walls Structure shear wall converts boom device without wall without creeping formwork seat in the plane at beam
Technical field
The utility model is related to a kind of Core Walls Structure shear walls to convert boom device without wall without creeping formwork seat in the plane at beam, belongs to building and applies Work technical field.
Background technology
For creeping formwork engineering construction moreover, vertical structure wall of only constructing, due to project duration requirement, many structures can be Underground position begins to use mould crawling process to construct, however underground structure is different from superstructure standard, and many shear wall undergrounds have Door opening either Vierendeel girder and aerial part not this kind of structural beams or door opening, is difficult to exempt from when so carrying out creeping formwork conceptual design It designs on door opening or Vierendeel girder creeping formwork seat in the plane.In this way can because of floor height difference, be less than index bed when creeping formwork without influence, but Structure will appear empty situation when being above standard, because creeping formwork climbs, template, built-in fitting are designed according to index bed.
At present in this case, Normal practice is that meeting creeping formwork using correlations such as the interim column of concreting or beams climbs Rise the component needed, time-consuming, expense, waste construction material etc..
Utility model content
The utility model solves above-mentioned construction difficult problem in view of the foregoing drawbacks, and it is an object of the present invention to provide a kind of simple and reasonable Core Walls Structure shear wall without wall without at beam creeping formwork seat in the plane convert boom device.
The technical solution adopted in the utility model is thus:The utility model includes the built-in fitting being arranged in door opening two sides (1), the built-in fitting(1)On be provided with several connecting holes(2), it is provided with conversion beam(3)Pass through the connecting hole(2)It is connected to Built-in fitting(1)On, the conversion beam(3)Side is provided with connecting plate(4), the connecting plate(4)Upper connection creeping formwork seat in the plane.
The built-in fitting(1)Towards conversion beam(3)Be provided on one side from the built-in fitting(1)The card that surface is extended Block(11), the conversion beam(3)Both sides, which are respectively arranged with, makes the fixture block(11)The card slot being caught in(31).
The built-in fitting(1)For taper.
The conversion beam(3)Side is recessed groove, the connecting plate(4)It is connected to conversion beam(3)Upper and lower both sides are simultaneously Gap is formed between the groove.
The conversion beam(3)Side is arranged and conversion beam(3)The parallel intermediate reinforcement block in upper and lower both sides(32).
The conversion beam(3)It is welded on the connecting plate(4)On.
The utility model has the advantages that:When the utility model constructs to structure nonstandard layer, shortening construction work can be maximized Phase and climbing formwork for construction safety, then under common process condition of construction, design efficiency is fully achieved above most economical, technical security.
Description of the drawings
Fig. 1 is the structural schematic diagram of the utility model.
Fig. 2 is the structural schematic diagram of the utility model built-in fitting.
Fig. 3 is the structural schematic diagram of the utility model conversion beam.
1 it is built-in fitting in figure, 2 be connecting hole, 3 be conversion beam, 4 is connecting plate;
11 it is fixture block, 31 be card slot, 32 is reinforcement block.
Specific implementation mode
The utility model includes the built-in fitting 1 being arranged in door opening two sides, and several connecting holes are provided on the built-in fitting 1 2, it is provided with conversion beam 3 and is connected on built-in fitting 1 by the connecting hole 2,3 side of the conversion beam is provided with connecting plate 4, institute It states and connects creeping formwork seat in the plane on connecting plate 4.
The built-in fitting 1 is provided with the fixture block 11 extended from 1 surface of the built-in fitting on one side towards conversion beam 3, 3 both sides of the conversion beam are respectively arranged with the card slot 31 for making the fixture block 11 be caught in.
The built-in fitting 1 is taper.
3 side of the conversion beam is recessed groove, and it is simultaneously and described that the connecting plate 4 is connected to about 3 both sides of conversion beam Gap is formed between groove.
The intermediate reinforcement block 32 parallel with about 3 both sides of conversion beam is arranged in 3 side of the conversion beam.
The conversion beam 3 is welded on the connecting plate 4.
The utility model places taper built-in fitting 1 in original empty position door opening two sides first, this kind of built-in fitting 1 is direct It is fixed with door opening side plank sheathing;After the completion of waiting for concreting, after door opening two sides plank sheathing is removed, it is mounted directly conversion beam 3.
Fixture block 11 on built-in fitting 1 is caught in into the card slot 31 on conversion beam 3 by the utility model, then passes through connecting hole 2 realize the fixation of built-in fitting 1 and conversion beam 3, and the connection of conversion beam 3 and creeping formwork seat in the plane is then realized by connecting plate 4.

Claims (6)

1. Core Walls Structure shear wall converts boom device without wall without creeping formwork seat in the plane at beam, which is characterized in that including being arranged in door opening both sides The built-in fitting on side(1), the built-in fitting(1)On be provided with several connecting holes(2), it is provided with conversion beam(3)Pass through the connection Hole(2)It is connected to built-in fitting(1)On, the conversion beam(3)Side is provided with connecting plate(4), the connecting plate(4)Upper connection is climbed Mould seat in the plane.
2. Core Walls Structure shear wall according to claim 1 converts boom device without wall without creeping formwork seat in the plane at beam, which is characterized in that The built-in fitting(1)Towards conversion beam(3)Be provided on one side from the built-in fitting(1)The fixture block that surface is extended(11), The conversion beam(3)Both sides, which are respectively arranged with, makes the fixture block(11)The card slot being caught in(31).
3. Core Walls Structure shear wall according to claim 1 converts boom device without wall without creeping formwork seat in the plane at beam, which is characterized in that The built-in fitting(1)For taper.
4. Core Walls Structure shear wall according to claim 1 converts boom device without wall without creeping formwork seat in the plane at beam, which is characterized in that The conversion beam(3)Side is recessed groove, the connecting plate(4)It is connected to conversion beam(3)Upper and lower both sides are simultaneously and described recessed Gap is formed between slot.
5. Core Walls Structure shear wall according to claim 4 converts boom device without wall without creeping formwork seat in the plane at beam, which is characterized in that The conversion beam(3)Side is arranged and conversion beam(3)The parallel intermediate reinforcement block in upper and lower both sides(32).
6. Core Walls Structure shear wall according to claim 5 converts boom device without wall without creeping formwork seat in the plane at beam, which is characterized in that The conversion beam(3)It is welded on the connecting plate(4)On.
CN201721498996.9U 2017-11-12 2017-11-12 Core Walls Structure shear wall converts boom device without wall without creeping formwork seat in the plane at beam Active CN207847078U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721498996.9U CN207847078U (en) 2017-11-12 2017-11-12 Core Walls Structure shear wall converts boom device without wall without creeping formwork seat in the plane at beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721498996.9U CN207847078U (en) 2017-11-12 2017-11-12 Core Walls Structure shear wall converts boom device without wall without creeping formwork seat in the plane at beam

Publications (1)

Publication Number Publication Date
CN207847078U true CN207847078U (en) 2018-09-11

Family

ID=63422653

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721498996.9U Active CN207847078U (en) 2017-11-12 2017-11-12 Core Walls Structure shear wall converts boom device without wall without creeping formwork seat in the plane at beam

Country Status (1)

Country Link
CN (1) CN207847078U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108691414A (en) * 2017-11-12 2018-10-23 江苏揽月工程科技发展股份有限公司 Core Walls Structure shear wall converts boom device without wall without creeping formwork seat in the plane at beam

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108691414A (en) * 2017-11-12 2018-10-23 江苏揽月工程科技发展股份有限公司 Core Walls Structure shear wall converts boom device without wall without creeping formwork seat in the plane at beam

Similar Documents

Publication Publication Date Title
CN106049691B (en) A kind of fully-prefabricated assembled steel tube confinement frame joint
CN107313506B (en) Building frame structure with boundary beam and construction method thereof
WO2016085187A1 (en) Spacer for holding truss girder and coupling structure between deck plate and truss girder using same
CN202969586U (en) Prefabricated concrete beam-column anchor welding combined structure
CN101538897A (en) Construction method for main project of reinforced concrete building
CN206053131U (en) Precast floor slab steel reinforcement cage component and floor
CN105442839A (en) Erecting method of cantilever structure formwork bent
CN103061517A (en) Method for assembling novel substructure module type preformed joint-assembled type frame structure
CN109537929B (en) Reinforcing device and reinforcing method for extracting column reconstruction
CN106149868A (en) Prefabricated buildings architectural structure system and assembly method thereof
CN203096926U (en) Novel substructure module-type prefabricated frame structure to be mounted in manner of splicing
CN207847078U (en) Core Walls Structure shear wall converts boom device without wall without creeping formwork seat in the plane at beam
KR101697360B1 (en) Connection structure of prefabricated columns
CN104895221B (en) Assembled shaped steel confined concrete shear wall structure
CN203808249U (en) Column stirrup cage assembly for beam-column joint core region
CN205875520U (en) Precast beam steel reinforcement cage component and reinforced concrete roof beam
CN211974012U (en) Cast-in-place frame of prefabricated building
CN108412099A (en) Bar connecting formula concrete prefabricated board and connection method are buried after through thickness
CN210857738U (en) Assembled frame beam with tongue-and-groove connection
CN203640257U (en) Support of overhanging type scaffold
CN106013421B (en) A kind of method of construction of the compound assembled fiber concrete building of steel wood
KR101324884B1 (en) Hybrid building construction method combining dry type and wet type
CN108691414A (en) Core Walls Structure shear wall converts boom device without wall without creeping formwork seat in the plane at beam
CN210151995U (en) Assembled shear force wall flexible connection device
CN108775086A (en) The additional assembled integral beam-column node structure and construction method for being closed connection reinforcing bar

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant