CN109706967A - The construction method of external hanging type wind pavilion - Google Patents

The construction method of external hanging type wind pavilion Download PDF

Info

Publication number
CN109706967A
CN109706967A CN201910127989.5A CN201910127989A CN109706967A CN 109706967 A CN109706967 A CN 109706967A CN 201910127989 A CN201910127989 A CN 201910127989A CN 109706967 A CN109706967 A CN 109706967A
Authority
CN
China
Prior art keywords
wind pavilion
foundation pit
main body
dewatering well
pavilion
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910127989.5A
Other languages
Chinese (zh)
Inventor
戴海峰
徐圯
张宝杰
张坤
王金龙
刘梦华
王烨伟
刘帅
孟雪成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Tunnel Engineering Co Ltd
Original Assignee
Shanghai Tunnel Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Tunnel Engineering Co Ltd filed Critical Shanghai Tunnel Engineering Co Ltd
Priority to CN201910127989.5A priority Critical patent/CN109706967A/en
Publication of CN109706967A publication Critical patent/CN109706967A/en
Pending legal-status Critical Current

Links

Abstract

A kind of construction method of the present invention about external hanging type wind pavilion, outer dewatering well in hole is arranged far from main body foundation pit side in the wind pavilion foundation pit, dewatering well in hole is installed in the main body foundation pit of the other side, it is turned in main body and bracing members together is set between beam and engineering method dowel crown beam, wind pavilion structure side wall is poured using large steel moulding plate.It is an advantage of the invention that reducing the Water And Earth Pressures resultant force for acting on and going along with sb. to guard him in engineering method stake by outer dewatering well in hole;It stays in main body foundation pit and in wind pavilion foundation pit join domain and sets dewatering well, reduce main body Water Level in Foundation Pit rise bring percolating water risk;Inner support supporting point is adjusted from former main body fender post crown beam to main body and turns over beam, abolishing for former main body fender post and crown beam can be carried out with earth excavation, do mechanization operation may be implemented to accelerate speed of application, avoid the inconvenience for hanging out pile section by post-cast strip;The rapid construction for realizing structure side wall is conducive to form fender post lateral support effect, reduces foundation pit deformation risk.

Description

The construction method of external hanging type wind pavilion
Technical field
The present invention relates to a kind of civil construction method more particularly to a kind of construction methods of external hanging type wind pavilion.
Background technique
Metro Station Structure is generally divided into station main structure and accessory structure, wherein accessory structure be generally divided into wind pavilion and Two class of entrance needs just to need first to apply at this time in the longitudinally parallel setting in main body foundation pit side when wind pavilion uses external hanging type Do wind pavilion foundation pit carry out again wind pavilion structure return build.External hanging type wind pavilion is generally basement one structure, and excavation of foundation pit depth is general In 10m or so, width comprehensively considers economy and safety majority in 6~10m, design using engineering method stake building enclosure, together Shi Shixian sealing effect, is typically provided with twice inner support, and support is respectively arranged at that engineering method stake is gone along with sb. to guard him and former main structure is gone along with sb. to guard him Crown beam and pile body between.In water-rich sand layer ground, the resultant force that the load that engineering method stake is gone along with sb. to guard him is Water And Earth Pressures is acted on, by Small in level of ground water height, active earth pressure, hydraulic pressure load will account for very at high proportion.
Branch will be lost by needing to cut the inner support that original is gone along with sb. to guard him pile body, but is arranged at this time when wind pavilion structure progress structure is returned and built Support point, common way is to stay to set post-cast strip between wind pavilion structure and main structure in engineering, first carry out part backplane, side wall and Returning for top plate is built, and as support is gradually removed in the construction of part-structure, is then cut pile body between post-cast strip and is hung out, finally carries out Post-cast strip pours, and completes entire wind pavilion structure time and builds.Such arrangement and method for construction causes pile body to cut time-consuming since post-cast strip space is small Work consuming and safety is poor, while structure construction seam is increased, easily lead to later period leakage problem.
Summary of the invention
In view of the problems of the above-mentioned prior art, the purpose of the present invention is to propose to a kind of construction parties of external hanging type wind pavilion Method, mainly.
Invention broadly provides a kind of construction methods of external hanging type wind pavilion, comprising the following steps:
Interior dewatering well is cheated in setting: being set in main structure excavation of foundation pit forward position main body foundation pit and wind pavilion foundation pit join domain interval Set dewatering well in hole;
Outer dewatering well in hole is set: outer dewatering well in hole being set far from the side of main body foundation pit in wind pavilion foundation pit;
Setting bracing members: it is turned in main body and sets up bracing members between beam and engineering method dowel crown beam;
It draining and excavates: opening in aforementioned hole after dewatering well and outer dewatering well in hole, earth excavation;
Pour wind pavilion structure: after the bottom plate, side wall and top plate that sequentially pour wind pavilion structure, completion of cutting off the water.
Preferably, the construction method of the external hanging type wind pavilion, in setting is cheated in dewatering well step, along main body foundation pit Interior dewatering well is cheated according to the setting of the interval 30~35m with wind pavilion foundation pit join domain.
Preferably, the construction method of the external hanging type wind pavilion, in setting outer dewatering well in hole step, along wind pavilion foundation pit Outer dewatering well in hole is arranged according to the interval 20~25m in longitudinal direction.
Preferably, the construction method of the external hanging type wind pavilion turns over beam for main body in setting bracing members step The further settable support pier in absent region.
Preferably, the construction method of the external hanging type wind pavilion, in pouring wind pavilion configuration steps, the bottom of wind pavilion structure Plate, need to be in the pre-buried dowel of bottom plate before being poured.
Preferably, the construction method of the external hanging type wind pavilion, in pouring wind pavilion configuration steps, the side of wind pavilion structure Wall installs large steel moulding plate and tripod after construction waterproof and reinforcing bar, and anchors with pre-buried dowel.
Preferably, the construction method of the external hanging type wind pavilion, in pouring wind pavilion configuration steps, the top of wind pavilion structure It needs to remove installation large steel moulding plate and tripod before plate construction, sets up falsework system and carry out pouring for wind pavilion structure roof.
The construction method of external hanging type wind pavilion provided by the present invention, advantages of the present invention includes:
1, the present invention, which reduces to act on by outer dewatering well in hole, goes along with sb. to guard him Water And Earth Pressures in engineering method stake with joint efforts, by inner support from Twice are reduced to reduce the adverse effect that subsequent earth excavation and structure time are built in the support of setting second together.
2, the present invention sets dewatering well with staying in wind pavilion foundation pit join domain in main body foundation pit, reduces main body Water Level in Foundation Pit and returns Rise bring percolating water risk.
3, the present invention, which adjusts inner support point to main body from former main body fender post crown beam, turns over beam, can be same with earth excavation Abolishing for Shi Jinhang main body fender post and crown beam, may be implemented do mechanization operation to accelerate speed of application, avoids and pour after Band hangs out the inconvenience of pile section.
4, no setting is required post-cast strip, reduction structure construction seam quantity, the risk of reduction later period percolating water;Realize structure side wall Rapid construction, be conducive to fender post formed lateral support effect, reduce foundation pit deformation risk.
Detailed description of the invention
Fig. 1 is the arrangement schematic diagram of excavation pit of the present invention;
Fig. 2 is Hui Zhufeng pavilion structural schematic diagram of the present invention after excavation pit.
Primary clustering symbol description
Reserved 1 outer dewatering well in hole 2 of dewatering well
3 main body foundation pit enclosure stakes 4 are gone along with sb. to guard him in engineering method stake
5 bracing members 6 of main body foundation pit waterproof curtain
7 main body of engineering method dowel crown beam turns over beam 8
9 bottom plate 10 of station main body
11 top plate 12 of side wall
Pre-buried 13 tripod 14 of dowel
15 dewatering well 16 of steel form
Specific embodiment
Cooperate schema and the preferred embodiments of the invention below, the present invention is further explained to reach predetermined goal of the invention institute The technological means taken.
As shown in Figure 1 to Figure 2, a kind of construction method of external hanging type wind pavilion provided in one embodiment of the invention, packet Include following steps:
1, setting cheat in dewatering well: main structure excavation of foundation pit forward position main body foundation pit and wind pavilion foundation pit join domain according to Interior dewatering well 1 is cheated in the setting of the interval 30~35m, and the well casing for cheating interior dewatering well 1 is all made of real pipe in bottom plate above section, and dewatering well is adopted With steel tube well, well top mark height is more than initial water level, deployment of submersible pumps in well, answers during wind pavilion excavation of foundation pit and structure are returned and built Holding is drawn water state, notices that protection, guarantee can be operated normally in wind pavilion excavation of foundation pit during main structure is returned and built.
2, outer dewatering well in hole is set: going along with sb. to guard him the outer drop in setting hole outside 3 far from the side engineering method stake of main body foundation pit in wind pavilion foundation pit Well 2, the outer dewatering well in hole 2 use sand-free concrete tube, go along with sb. to guard him 3 and 5 seam crossing distance 5 of main body water-stop curtain in engineering method stake It is arranged at~8m, remaining is arranged along wind pavilion foundation pit longitudinal direction, 20~25m of spacing, deployment of submersible pumps in well, during excavation of foundation pit Outer water level will be cheated and be down to wind pavilion floor level hereinafter, reducing the Water And Earth Pressures suffered by going along with sb. to guard him.
3, be arranged bracing members: it is identical that wind pavilion engineering method dowel crown beam and main body turn over 8 top mark height of beam, on excavation topsoil to main body A distance under beam 8 is turned over, turns over erection bracing members 6, branch tie distance 3m, brace pre axial force between beam 8 and engineering method dowel crown beam 7 in main body 300kN, for main body turn over beam absent region according to bracing members position be arranged support pier, support pier section 700mm × 750mm, Close to support one side 11B28, the anchorage length away from support one side 4B28, stirrup A12@150, main reinforcement insertion top plate is main reinforcement 15d。
4, it drains and excavates: opening the dewatering well in main body reserved dewatering well 1, outer dewatering well in hole 2 and wind pavilion Foundation Pit 16, it inside and outside water level will be cheated is down to wind pavilion structure base slab and excavated hereinafter, carrying out wind pavilion pit earthwork again, with digging and abolish main body foundation pit Fender post 4 and main body water-stop curtain 5.
6, pour the bottom plate of wind pavilion structure: foundation pit is received bottom and is completed, and pours bed course, and construct waterproof slab and reinforcing bar install bottom The pre-buried dowel 13 of slab muscle Shi Liushe large steel moulding plate, in the pre-buried dowel B32 of bottom plate before wind pavilion main body bottom slab concreting, oblique 45 ° are set It sets, anchorage length is no less than 0.5m in bottom plate, to fixed large steel moulding plate.
7, the side wall of wind pavilion structure is poured: after 10 intensity of wind pavilion structure base slab is met the requirements, side wall waterproof of constructing and steel Muscle is installed large steel moulding plate 15 and tripod 14, and is anchored securely with pre-buried dowel 13, and pouring for wind pavilion structure side wall 11 is carried out, The lateral support for going along with sb. to guard him pile body is acted on being formed as early as possible, controls foundation pit deformation.
8, it pours the top plate of wind pavilion structure: after 11 intensity of wind pavilion structure side wall is met the requirements, removing installation large steel moulding plate 15 and tripod 14, it sets up falsework system and carries out pouring for wind pavilion structure roof 12.
9, complete: after 12 intensity of wind pavilion structure roof is met the requirements, form removal strutting system completes entire wind pavilion knot The construction of structure, the wind pavilion structure include the bottom plate 10 for being connected to station main structure 9, the side wall 11 for being connected to bottom plate and It is connected to the top plate 12 of side wall 11 and station main structure 9, and stops cheating interior dewatering well 1, outer dewatering well in hole 2 and wind pavilion foundation pit Dewatering well 16 in hole runs and shunts in a well, that is, completes whole construction.
Advantages of the present invention has the following:
1, be by outer dewatering well in hole reduce act on go along with sb. to guard him in engineering method stake Water And Earth Pressures resultant force, can by inner support from Twice are reduced to together, and can be reduced setting second and be supported the unfavorable shadow built to subsequent earth excavation and structure time It rings.
2, interior equipped with dewatering well in cheating with wind pavilion foundation pit join domain in main body foundation pit, reduce main body Water Level in Foundation Pit rise band The percolating water risk come.
3, inner support supporting point is adjusted from former main body fender post crown beam to main body and turns over beam, can carried out with earth excavation Abolishing for former main body fender post and crown beam, may be implemented do mechanization operation to accelerate speed of application, no setting is required post-cast strip, reduce Structure construction stitches quantity, reduces the risk of later period percolating water, avoids the inconvenience for hanging out pile section by post-cast strip.
4, the rapid construction for realizing structure side wall is conducive to form fender post lateral support effect, reduces foundation pit deformation Risk.
The above is only presently preferred embodiments of the present invention, not does limitation in any form to the present invention, though So the present invention has been disclosed as a preferred embodiment, and however, it is not intended to limit the invention, any technology people for being familiar with this profession Member, in the range of not departing from technical solution of the present invention, when the technology contents using the disclosure above make a little change or repair Decorations are the equivalent embodiment of equivalent variations, but anything that does not depart from the technical scheme of the invention content, technology according to the present invention are real Matter any simple modification, equivalent change and modification to the above embodiments, still fall within the range of technical solution of the present invention It is interior.

Claims (7)

1. a kind of construction method of external hanging type wind pavilion, which comprises the following steps:
Interior dewatering well is cheated in setting: being cheated in main structure excavation of foundation pit forward position main body foundation pit and the setting of wind pavilion foundation pit join domain interval Interior dewatering well;
Outer dewatering well in hole is set: outer dewatering well in hole being set far from the side of main body foundation pit in wind pavilion foundation pit;
Setting bracing members: it is turned in main body and sets up bracing members between beam and engineering method dowel crown beam;
It draining and excavates: opening in aforementioned hole after dewatering well and outer dewatering well in hole, earth excavation;
Pour wind pavilion structure: after the bottom plate, side wall and top plate that sequentially pour wind pavilion structure, completion of cutting off the water.
2. the construction method of external hanging type wind pavilion according to claim 1, which is characterized in that the dewatering well step in setting is cheated In, interior dewatering well is cheated according to the setting of the interval 30~35m along main body foundation pit and wind pavilion foundation pit join domain.
3. the construction method of external hanging type wind pavilion according to claim 1, which is characterized in that in setting outer dewatering well in hole step In, outer dewatering well in hole is set according to the interval 20~25m along wind pavilion foundation pit longitudinal direction.
4. the construction method of external hanging type wind pavilion according to claim 1, which is characterized in that in setting bracing members step, Beam absent region further settable support pier is turned over for main body.
5. the construction method of external hanging type wind pavilion according to any one of claim 1 to 4, which is characterized in that pouring wind In pavilion configuration steps, the bottom plate of wind pavilion structure, need to be in the pre-buried dowel of bottom plate before being poured.
6. the construction method of external hanging type wind pavilion according to claim 5, which is characterized in that pouring wind pavilion configuration steps In, the side wall of wind pavilion structure installs large steel moulding plate and tripod after construction waterproof and reinforcing bar, and anchors with pre-buried dowel.
7. the construction method of external hanging type wind pavilion according to claim 6, which is characterized in that pouring wind pavilion configuration steps In, it needs to remove installation large steel moulding plate and tripod before the top board construction of wind pavilion structure, sets up falsework system and carry out wind pavilion knot Structure top plate pours.
CN201910127989.5A 2019-02-19 2019-02-19 The construction method of external hanging type wind pavilion Pending CN109706967A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910127989.5A CN109706967A (en) 2019-02-19 2019-02-19 The construction method of external hanging type wind pavilion

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910127989.5A CN109706967A (en) 2019-02-19 2019-02-19 The construction method of external hanging type wind pavilion

Publications (1)

Publication Number Publication Date
CN109706967A true CN109706967A (en) 2019-05-03

Family

ID=66264622

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910127989.5A Pending CN109706967A (en) 2019-02-19 2019-02-19 The construction method of external hanging type wind pavilion

Country Status (1)

Country Link
CN (1) CN109706967A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112282785A (en) * 2020-10-28 2021-01-29 上海隧道工程有限公司 Tunnel portal steel ring installation device and installation method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20180044907A1 (en) * 2016-08-12 2018-02-15 Wuhan Zhihe Geotechnical Engineering Co., Ltd Inverse construction method for deep, large and long pit assembling structure of suspension-type envelope enclosure
CN108149695A (en) * 2018-02-08 2018-06-12 合肥市市政设计研究总院有限公司 For the short support construction of steel and construction method of station accessory structure foundation pit Force transmission parts
CN208039262U (en) * 2017-12-29 2018-11-02 广州地铁设计研究院有限公司 A kind of anti-drop device of shallow foundation hole support plate
CN209669931U (en) * 2019-02-19 2019-11-22 上海隧道工程有限公司 The constructing structure of external hanging type wind pavilion

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20180044907A1 (en) * 2016-08-12 2018-02-15 Wuhan Zhihe Geotechnical Engineering Co., Ltd Inverse construction method for deep, large and long pit assembling structure of suspension-type envelope enclosure
CN208039262U (en) * 2017-12-29 2018-11-02 广州地铁设计研究院有限公司 A kind of anti-drop device of shallow foundation hole support plate
CN108149695A (en) * 2018-02-08 2018-06-12 合肥市市政设计研究总院有限公司 For the short support construction of steel and construction method of station accessory structure foundation pit Force transmission parts
CN209669931U (en) * 2019-02-19 2019-11-22 上海隧道工程有限公司 The constructing structure of external hanging type wind pavilion

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112282785A (en) * 2020-10-28 2021-01-29 上海隧道工程有限公司 Tunnel portal steel ring installation device and installation method thereof

Similar Documents

Publication Publication Date Title
CN103981898B (en) A kind of inverse underground engineering construction method done of overall open cut node
CN106758841B (en) A kind of whole construction process of the double rope face low-pylon cable-stayed bridges of double tower
CN105804089B (en) Locally increase deep support system and its construction method after a kind of former deep foundation pit construction
CN211144503U (en) High steep topography bridge tunnel meets section open cut tunnel and connects long structure
CN107642252B (en) Old building free removal is double to increase rebuilding construction technique
CN2926319Y (en) Rooted foundation and anchored topped-push construction set apparatus
CN107740420A (en) Foundation ditch tears support and support replacement system and method open
CN105089670B (en) Construction method for enlarging and excavating subway station on basis of parallel interval shield tunnel
CN108797637A (en) Prefabricated board combined cast-in-situ concrete considers the underground pipe gallery construction method of structure and ground
CN110397278A (en) A kind of method of superstructure and underground structure synchronous construction
CN209179021U (en) A kind of foundation pit campshed support system
CN107326932B (en) Quasi-semi-reverse construction method for underground garage
CN209669931U (en) The constructing structure of external hanging type wind pavilion
CN110439025A (en) Portal type building pile foundation underpinning structure in narrow space and construction method
CN104131566A (en) Method for constructing basement foundation pit without horizontal braces
CN109706967A (en) The construction method of external hanging type wind pavilion
CN108978673A (en) A kind of foundation pit supporting construction and construction method of viaduct pile foundation underpinning
CN105386779A (en) Arch column method for building large-scale underground structure in shallow buried rock stratums
CN110117959B (en) Construction method for foundation pit support near river
CN116241101B (en) Construction method for removing continuous wall of connecting section of main body and auxiliary structure of subway station
CN205576934U (en) Part increases ramus profundus watch box system behind former deep foundation pit construction
CN106193120A (en) Basement is encorbelmented, and base plate is inverse makees structure and construction method
CN106677075B (en) A kind of cofferdam for Bridge Pier Construction hangs stake and method of passing the flood period
CN115821985A (en) Integrated construction method for auxiliary structure of subway open cut station
CN105421488A (en) Constriction method for changing support of foundation slab in underground composite enclosure system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination