CN209179021U - A foundation pit row pile support system - Google Patents
A foundation pit row pile support system Download PDFInfo
- Publication number
- CN209179021U CN209179021U CN201822014418.4U CN201822014418U CN209179021U CN 209179021 U CN209179021 U CN 209179021U CN 201822014418 U CN201822014418 U CN 201822014418U CN 209179021 U CN209179021 U CN 209179021U
- Authority
- CN
- China
- Prior art keywords
- pile
- steel
- support
- diagonal brace
- row
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Joining Of Building Structures In Genera (AREA)
Abstract
一种基坑排桩支护系统,包括斜撑桩基承台,排桩结构,以及支撑在斜撑桩基承台和排桩结构之间的若干组斜向支撑;所述斜撑桩基承台包括位于结构墙体正下方的支撑平台和支撑在支撑平台底部的支撑桩,所述排桩结构包括排桩、设于排桩顶面的冠梁和设于排桩中部朝向基坑一侧的腰梁,每组所述斜向支撑包括设于冠梁与支撑平台之间的钢斜撑一。本实用新型在地下结构施工任务重,工期紧周边环境复杂情况下,设计要求的支护安全性就会很高,采用桩承台为基础的钢斜撑作用在排桩冠梁、腰梁上可以满足绝大多数基坑支护的要求,同时通过斜向支撑替代水平支撑,从而解决了水平支撑拆除等繁琐工序影响基坑的施工,大大节约工期。
A pile row support system for a foundation pit, comprising a diagonally braced pile foundation cap, a pile row structure, and several sets of oblique supports supported between the diagonally braced pile foundation cap and the pile row structure; the diagonally braced pile foundation The cap includes a supporting platform directly below the structural wall and supporting piles supported at the bottom of the supporting platform. The pile row structure includes a row of piles, a crown beam arranged on the top surface of the row of piles, and a pile facing the foundation pit in the middle of the row of piles. The lumbar beam on the side, each set of oblique supports includes a steel diagonal brace one arranged between the crown beam and the supporting platform. The utility model has a heavy construction task in the underground structure and a tight construction period, and the surrounding environment is complex, and the support safety required by the design will be very high. The steel diagonal bracing based on the pile cap is used to act on the crown beam and the waist beam of the pile row. It can meet the requirements of most foundation pit support, and at the same time replace the horizontal support with oblique support, thus solving the problem of cumbersome procedures such as the removal of horizontal support that affect the construction of the foundation pit, and greatly saving the construction period.
Description
技术领域technical field
本实用新型属于基坑支护领域,尤其涉及一种基坑排桩支护系统。The utility model belongs to the field of foundation pit support, in particular to a foundation pit row pile support system.
背景技术Background technique
随着城市的增长,结合城市建设和改造开发大型地下空间已成为一种必然,这些深大基坑常常紧邻建筑物、交通干线、地铁隧道及各种地下管线,施工场地紧张,施工条件复杂、工期紧迫、所有这些导致基坑工程的设计和施工的难度越来越大,目前基坑支护形式主要有自然放坡、土钉墙、单(双)排桩、地下连续墙等,但是由于基坑周边的复杂性原因,传统的或者单一的支护形式已经无法完全满足基坑支护的需要,在使用排桩的情况下,增加一个水平力可以有效增强支护的安全性,但传统水平支撑形式严重影响工期且施工难度大。With the growth of the city, it has become inevitable to develop large-scale underground space in combination with urban construction and renovation. These deep and large foundation pits are often close to buildings, traffic arteries, subway tunnels and various underground pipelines. The construction site is tight and the construction conditions are complex. Due to the tight construction period, all these make the design and construction of foundation pit engineering more and more difficult. At present, the main forms of foundation pit support include natural slope, soil nail wall, single (double) row of piles, underground diaphragm wall, etc., but due to Due to the complexity around the foundation pit, the traditional or single support form can no longer fully meet the needs of the foundation pit support. In the case of using row piles, adding a horizontal force can effectively enhance the safety of the support, but the traditional The form of horizontal support seriously affects the construction period and the construction is difficult.
实用新型内容Utility model content
本实用新型的目的是提供一种基坑排桩支护系统,要解决现有技术单一的支护方式已经没有办法满足基坑支护需要的技术问题;并解决传统水平支撑形式严重影响工期且施工难度大的问题。The purpose of this utility model is to provide a foundation pit row pile support system, to solve the technical problem that the single support method in the prior art has no way to meet the needs of foundation pit support; and to solve the problem that the traditional horizontal support form seriously affects the construction period and The difficulty of construction.
为实现上述目的,本实用新型采用如下技术方案:In order to achieve the above object, the utility model adopts the following technical solutions:
一种基坑排桩支护系统,其特征在于:包括斜撑桩基承台,排桩结构,以及支撑在斜撑桩基承台和排桩结构之间的若干组斜向支撑;所述斜撑桩基承台包括位于结构墙体正下方的支撑平台和支撑在支撑平台底部的支撑桩,所述排桩结构包括排桩、设于排桩顶面的冠梁和设于排桩中部朝向基坑一侧的腰梁,每组所述斜向支撑包括设于冠梁与支撑平台之间的钢斜撑一。A foundation pit row pile support system is characterized in that: it includes a diagonally braced pile foundation cap, a pile row structure, and several groups of oblique supports supported between the diagonally braced pile foundation cap and the pile row structure; The inclined pile foundation cap includes a supporting platform directly below the structural wall and supporting piles supported at the bottom of the supporting platform. The pile row structure includes a pile row, a crown beam arranged on the top surface of the pile row, and a Towards the waist beam on the side of the foundation pit, each set of oblique supports includes a steel diagonal brace 1 arranged between the crown beam and the support platform.
进一步优选地,每组所述斜向支撑还包括所述设于腰梁与支撑平台之间的钢斜撑二,所述钢斜撑一和钢斜撑二均穿过结构墙体,且均由若干根钢管段通过法兰拼接而成。Further preferably, each set of diagonal supports further includes the second steel diagonal brace arranged between the waist beam and the support platform, the first steel diagonal brace and the second steel diagonal brace pass through the structural wall, and both It is formed by splicing several steel pipe sections through flanges.
进一步地,所述支撑平台顶面为平面,所述平面上设有向内凹陷、截面为三角形的承接槽,所述承接槽内部平面包括与钢斜撑一垂直的迎斜撑面和与钢斜撑一平行的背斜撑面,所述迎斜撑面上设有支座预埋钢板一,所述钢斜撑一端部设有活络头一,所述活络头一端部与支座预埋钢板一通过螺栓固定。Further, the top surface of the support platform is a plane, and the plane is provided with an inwardly recessed receiving groove with a triangular cross-section. Slanting bracing is a parallel back-slanting supporting surface, and the facing inclined supporting surface is provided with a pre-embedded steel plate 1, and one end of the steel slanting bracing is provided with a flexible joint 1, and one end of the flexible joint is embedded with the support The steel plates are fixed by bolts.
进一步地,所述支撑平台朝向排桩结构的端面为与钢斜撑二垂直的斜面,所述钢斜撑二端部设有活络头二,所述斜面上设有支座预埋钢板二,所述活络头二与支座预埋钢板二通过螺栓固定。Further, the end face of the support platform facing the pile row structure is an inclined plane perpendicular to the steel diagonal brace two, the end of the steel diagonal brace two is provided with the movable head two, and the support embedded steel plate two is provided on the inclined surface, The second movable head and the second embedded steel plate of the support are fixed by bolts.
进一步地,每组斜向支撑的所述钢斜撑一和钢斜撑二位于同一竖向平面上。Further, the first steel diagonal brace and the second steel diagonal brace of each group of diagonal supports are located on the same vertical plane.
进一步地,所述基坑排桩支护系统还包括用于支撑钢斜撑一和钢斜撑二的中心支撑格构立柱,所述中心支撑格构立柱包括上部钢立柱和下部立柱桩,所述下部立柱桩为钢筋混凝土钻孔灌注桩。Further, the foundation pit row pile support system also includes a central support lattice column for supporting the first steel diagonal brace and the second steel diagonal brace, and the central support lattice column includes an upper steel column and a lower column pile, so The lower column piles are reinforced concrete bored piles.
进一步地,所述钢斜撑一朝向冠梁的端部与固定在冠梁上的预埋钢板焊接固定,所述钢斜撑二朝向腰梁的端部与固定在腰梁上的预埋钢板焊接固定。Further, the end of the steel diagonal brace facing the crown beam is welded and fixed to the embedded steel plate fixed on the crown beam, and the end of the steel diagonal brace facing the waist beam is connected to the embedded steel plate fixed on the waist beam Welding fixed.
进一步地,所述钢斜撑一和钢斜撑二穿过结构墙体结构侧墙的部位均焊接一圈止水钢板,所述结构墙体底板供钢斜撑一和钢斜撑二穿过的部位设有通长的后浇带。Further, a circle of water-proof steel plates is welded to the part where the first steel diagonal brace and the second steel diagonal brace pass through the structural side wall of the structural wall, and the bottom plate of the structural wall allows the first steel diagonal brace and the second steel diagonal brace to pass through The parts are equipped with a long post-casting belt.
与现有技术相比本实用新型具有以下特点和有益效果:Compared with the prior art, the utility model has the following characteristics and beneficial effects:
本实用新型在地下结构施工任务重,工期紧周边环境复杂情况下,设计要求的支护安全性就会很高,采用桩承台为基础的钢斜撑作用在排桩冠梁、腰梁上可以满足绝大多数基坑支护的要求,同时通过斜向支撑替代水平支撑,从而解决了水平支撑拆除等繁琐工序影响基坑的施工,大大节约工期。The utility model has a heavy construction task in the underground structure and a tight construction period, and the surrounding environment is complex, so the safety of the support required by the design will be very high. The steel diagonal bracing based on the pile cap is used to act on the crown beam and the waist beam of the pile row. It can meet the requirements of most foundation pit support, and at the same time replace horizontal support with oblique support, thus solving the problem of cumbersome procedures such as horizontal support removal affecting the construction of foundation pit, and greatly saving the construction period.
通过在结构墙体底板在斜向支撑位置处留置后浇带创新方法,减少直接切除钢斜撑后再进行防水封堵造成的渗水隐患,通过螺栓连接钢斜撑与基础预埋钢板,后期拆除时直接拆掉减少了切割造成的材料损失浪费。Through the innovative method of post-casting strips left at the oblique support position on the bottom plate of the structural wall, the hidden danger of water seepage caused by the direct removal of the steel diagonal braces and then waterproof sealing is reduced. When it is removed directly, it reduces the loss and waste of materials caused by cutting.
本实用新型具有安全、适用等特点,有很好的推广和实用价值,广泛的推广应用后会产生良好的经济效益。The utility model has the characteristics of safety and applicability, has good popularization and practical value, and can produce good economic benefits after being widely popularized and applied.
附图说明Description of drawings
图1为本实用新型一种基坑排桩支护系统的结构示意图;Fig. 1 is the structural representation of a kind of foundation pit row pile supporting system of the utility model;
图2为本实用新型涉及的钢斜撑一的拼接结构示意图;Fig. 2 is a schematic diagram of the splicing structure of the steel brace 1 involved in the utility model;
图3是图2的剖面结构示意图;Fig. 3 is a schematic cross-sectional structure diagram of Fig. 2;
图4为本实用新型涉及的钢斜撑二与活络头二的连接结构示意图;Fig. 4 is a schematic diagram of the connection structure of the steel diagonal brace 2 and the joint head 2 involved in the present invention;
图5为本实用新型涉及的钢斜撑一与冠梁的连接结构示意图。Fig. 5 is a schematic diagram of the connection structure between the steel brace one and the crown beam involved in the present invention.
附图标记:1-结构墙体;2-支撑平台;3-支撑桩;4-排桩;5-冠梁;6-腰梁;7-钢斜撑一;8-钢斜撑二;9-法兰;10-吊环;11-承接槽;111-迎斜撑面;112-背斜撑面;13-支座预埋钢板二;14-斜面;15-活络头二;16-中心支撑格构立柱;17-活络头一。Reference signs: 1-structural wall; 2-supporting platform; 3-supporting piles; 4-row piles; 5-crown beam; 6-waist beam; -flange; 10-hanging ring; 11-accepting groove; 111-facing inclined support surface; 112-back inclined support surface; 13-support embedded steel plate 2; Lattice column; 17-active head one.
具体实施方式Detailed ways
为使本实用新型实现的技术手段、创新特征、达成目的与功效易于明白了解,下面对本实用新型进一步说明。In order to make the technical means, innovative features, goals and effects achieved by the utility model easy to understand, the utility model will be further described below.
在此记载的实施例为本实用新型的特定的具体实施方式,用于说明本实用新型的构思,均是解释性和示例性的,不应解释为对本实用新型实施方式及本实用新型范围的限制。除在此记载的实施例外,本领域技术人员还能够基于本申请权利要求书和说明书所公开的内容采用显而易见的其它技术方案,这些技术方案包括采用对在此记载的实施例的做出任何显而易见的替换和修改的技术方案。The embodiments described here are specific specific implementations of the present utility model, and are used to illustrate the concept of the present utility model. They are all explanatory and exemplary, and should not be construed as limitations on the implementation of the present utility model and the scope of the present utility model. limit. In addition to the embodiments described here, those skilled in the art can also adopt other obvious technical solutions based on the claims of the application and the contents disclosed in the description, and these technical solutions include adopting any obvious changes made to the embodiments described here. Replacement and modified technical solutions.
一种基坑排桩支护系统,包括斜撑桩基承台,排桩结构,以及支撑在斜撑桩基承台和排桩结构之间的若干组斜向支撑;斜撑桩基承台包括位于结构墙体1正下方的支撑平台2和支撑在支撑平台2底部的支撑桩3,排桩结构包括排桩4、设于排桩4顶面的冠梁5和设于排桩中部朝向基坑一侧的腰梁6,每组斜向支撑包括设于冠梁5与支撑平台2之间的钢斜撑一7。A pile row support system for a foundation pit, comprising a diagonally braced pile foundation cap, a pile row structure, and several sets of oblique supports supported between the diagonally braced pile foundation cap and the pile row structure; the diagonally braced pile foundation cap It includes a support platform 2 directly below the structural wall 1 and a support pile 3 supported on the bottom of the support platform 2. The pile row structure includes a pile row 4, a crown beam 5 arranged on the top surface of the pile row 4, and a pile row arranged in the middle of the pile toward the Waist beam 6 on one side of the foundation pit, each group of oblique supports includes a steel diagonal brace 17 arranged between crown beam 5 and support platform 2 .
每组斜向支撑还包括所述设于腰梁6与支撑平台2之间的钢斜撑二8,钢斜撑一7和钢斜撑二8均穿过结构墙体1,且均由若干根钢管段通过法兰9拼接而成。Each group of oblique supports also includes the steel diagonal brace 2 8 located between the waist beam 6 and the support platform 2, the steel diagonal brace 1 7 and the steel diagonal brace 2 8 all pass through the structural wall 1, and are composed of several The steel pipe sections are formed by splicing flanges 9 together.
支撑平台顶面为平面,平面上设有向内凹陷、截面为三角形的承接槽11,承接槽11内部平面包括与钢斜撑一7垂直的迎斜撑面111和与钢斜撑一7平行的背斜撑面112,迎斜撑面111上设有支座预埋钢板一,钢斜撑一7端部设有活络头一17,活络头一17端部与支座预埋钢板一通过螺栓固定。The top surface of the support platform is a plane, and the plane is provided with an inwardly recessed receiving groove 11 with a triangular cross section. The support surface 112 of the back slope and the surface 111 of the facing slope are provided with a support embedded steel plate 1, and the end of the steel diagonal support 17 is provided with an active head 17, and the end of the active head 17 passes through the embedded steel plate 1 of the support. Bolt on.
支撑平台2朝向排桩结构的端面为与钢斜撑二8垂直的斜面14,钢斜撑二8端部设有活络头二15,斜面14上设有支座预埋钢板二13,活络头二15与支座预埋钢板二13通过螺栓固定;每组斜向支撑的所述钢斜撑一7和钢斜撑二8位于同一竖向平面上;基坑排桩支护系统还包括用于支撑钢斜撑一7和钢斜撑二8的中心支撑格构立柱16,中心支撑格构立柱16包括上部钢立柱和下部立柱桩,下部立柱桩为钢筋混凝土钻孔灌注桩;钢斜撑一7朝向冠梁5的端部与固定在冠梁5上的预埋钢板焊接固定,钢斜撑二8朝向腰梁6的端部与固定在腰梁6上的预埋钢板焊接固定。钢斜撑一7和钢斜撑二8穿过结构墙体1结构侧墙的部位均焊接一圈止水钢板,结构墙体1底板供钢斜撑一7和钢斜撑二8穿过的部位设有通长的后浇带。The end face of the supporting platform 2 facing the pile row structure is an inclined plane 14 perpendicular to the steel diagonal brace 2 8, the end of the steel diagonal brace 2 8 is provided with an active joint 2 15, and the inclined plane 14 is provided with a support pre-embedded steel plate 2 13, and the active joint Two 15 and the support pre-embedded steel plate two 13 are fixed by bolts; the steel diagonal brace one 7 and steel diagonal brace two 8 of each group of oblique supports are located on the same vertical plane; the foundation pit row pile support system also includes For supporting the central support lattice column 16 of the steel diagonal brace 1 7 and the steel diagonal brace 2 8, the central support lattice column 16 includes an upper steel column and a lower column pile, and the lower column pile is a reinforced concrete bored cast-in-place pile; the steel diagonal brace One 7 is welded and fixed towards the end of the crown beam 5 and the embedded steel plate fixed on the crown beam 5, and the end of the steel diagonal brace 8 is welded and fixed with the embedded steel plate fixed on the waist beam 6 towards the waist beam 6. Steel diagonal brace 1 7 and steel diagonal brace 2 8 are welded with a ring of water-proof steel plates where they pass through the structural side wall of structural wall 1, and the bottom plate of structural wall 1 is for steel diagonal brace 1 7 and steel diagonal brace 2 8 to pass through The part is equipped with a long post-casting belt.
一种基坑排桩支护系统的施工方法,其特征在于,包括以下步骤:A construction method for a foundation pit row pile support system is characterized in that it comprises the following steps:
步骤一、施工排桩结构:清理大面土方,计算基坑允许开挖的深度并进行土方的第一次开挖,进行排桩结构施工,待排桩4强度达到设计强度80%以上后进行桩顶凿除,植筋后绑扎冠梁钢筋,在冠梁钢筋上焊接用于固定钢斜撑一7的预埋钢板,预埋钢板角度根据钢斜撑一7基础标高与冠梁5高度及斜撑桩基承台与排桩4的距离验算确定;Step 1. Construction of the pile row structure: clear the large area of earthwork, calculate the allowable excavation depth of the foundation pit and carry out the first excavation of the earthwork, and carry out the construction of the pile row structure. After the pile row 4 strength reaches more than 80% of the design strength, proceed The top of the pile is chiseled out, and the steel bar of the crown beam is bound after the reinforcement is planted. The pre-embedded steel plate used to fix the steel diagonal brace 17 is welded on the crown beam steel bar. The angle of the pre-embedded steel plate is based on the foundation elevation of the steel diagonal The distance between the cap of the inclined pile foundation and the row of piles 4 is checked and determined;
步骤二、施工斜撑桩基承台和钢斜撑一7:开挖支撑平台2处土方至设计标高,进行斜撑桩基承台及支座预埋钢板一和支座预埋钢板二的施工,之后将钢斜撑一7通过电动葫芦吊起位于钢斜撑一7端部的吊环10进行提升到位,安放就位后,吊机将液压千斤顶放在钢斜撑一7的活络头一17定压位置,按照设计要求施加预应力,在钢斜撑一7预穿过结构墙体1结构侧墙的部位焊接一圈止水钢板;Step 2. Construction of the inclined braced pile foundation cap and steel diagonal brace 1 7: Excavate the earthwork at 2 places of the support platform to the design elevation, and carry out the construction of the diagonal braced pile foundation cap, the pre-embedded steel plate 1 of the support and the pre-embedded steel plate 2 of the support After construction, the steel diagonal brace 17 is lifted by the electric hoist on the lifting ring 10 located at the end of the steel diagonal brace 17 to be lifted in place. After being placed in place, the crane puts the hydraulic jack on the active head of the steel diagonal brace 17 17 At the constant pressure position, prestress is applied according to the design requirements, and a circle of water-stop steel plates is welded at the part where the steel diagonal brace 1 7 pre-passes through the structural wall 1 structural side wall;
步骤三、施工腰梁6:钢斜撑一7施工完毕后进行二次土方开挖,土方顶部开挖至腰梁以下位置,然后放坡至钢斜撑二8的斜面14所在位置,预留土方边界,同时进行腰梁6施工,在排桩4处凿出钢筋并植筋,然后绑扎腰梁钢筋,将用于固定钢斜撑二8的预埋钢板焊接固定,此预埋钢板角度根据钢斜撑二8的基础标高与腰梁6高度及斜撑桩基承台与排桩4的距离验算确定;Step 3. Construction of the waist beam 6: After the construction of the steel diagonal brace 1 7, the second earthwork excavation is carried out. The top of the earthwork is excavated to the position below the waist beam, and then sloped to the position of the slope 14 of the steel diagonal brace 2 8, and reserved At the earthwork boundary, carry out the construction of the waist beam 6 at the same time, dig out the steel bars and plant the bars at the row of piles 4, then bind the waist beam steel bars, and weld and fix the pre-embedded steel plates used to fix the steel diagonal brace 28. The angle of the pre-embedded steel plates is according to The foundation elevation of steel diagonal brace No. 2 8 and the height of waist beam 6 and the distance between the diagonal brace pile foundation cap and pile row 4 are checked and determined;
步骤四、施工中心支撑格构立柱16及钢斜撑二8:施工中心支撑格构立柱16,同时按照施工钢斜撑一7的步骤施工钢斜撑二8;Step 4, construction center supporting lattice column 16 and steel diagonal brace 2 8: construction center supporting lattice column 16, and constructing steel diagonal brace 2 8 according to the steps of constructing steel diagonal brace 1;
步骤五、施工结构墙体1:对剩余土方进行开挖并进行结构墙体1的施工,钢斜撑一7和钢斜撑二8与结构墙体1底板交接触设置通长的后浇带,在具体施工时,每面基坑需要的斜向支撑通常位于同一直线上,可以在结构墙体1底板处设置通长的后浇带,且在浇筑结构墙体1的侧墙的过程中,不对钢斜撑一7和钢斜撑二8预留洞口,直接进行通长浇筑;Step 5. Construction of the structural wall 1: Excavate the remaining earthwork and carry out the construction of the structural wall 1. The first steel diagonal brace 7 and the second steel diagonal brace 8 are in contact with the bottom plate of the structural wall 1 to set up a long post-casting belt , in the specific construction, the oblique support required for each foundation pit is usually located on the same straight line, and a long post-casting belt can be set at the bottom plate of the structural wall 1, and in the process of pouring the side wall of the structural wall 1 , instead of reserving openings for steel brace 1 7 and steel brace 2 8, direct full-length pouring;
步骤六、斜向支撑拆除及结构墙体1的防水处理:斜向支撑与斜撑桩基承台固定部位松开螺栓拆除,与冠梁5和腰梁6连接的部位进行切割拆除,斜向支撑与结构墙体1结构侧墙节点处对斜向支撑切割处理,在留在结构侧墙的斜向支撑内焊接一圈止水钢板,然后浇筑防水混凝土,至此一种基坑排桩支护系统的施工方法施工完成。Step 6. Removal of oblique supports and waterproof treatment of structural wall 1: Loosen the bolts at the fixed parts of the oblique supports and the oblique brace pile caps to remove them, and cut and remove the parts connected with the crown beam 5 and the waist beam 6. Support and structure wall 1. The oblique support is cut at the node of the structural side wall, and a circle of water-stop steel plates is welded in the oblique support left on the structural side wall, and then waterproof concrete is poured. So far, it is a foundation pit row pile support system The construction method construction is completed.
下对本实用新型施工方式进行进一步的说明:Next, the utility model construction method is further described:
当设计要求支护承载力较低时,只选择钢斜撑一与冠梁连接的斜撑组合,不必施工钢斜撑二,就可以满足基坑支护要求,当设计要求支护承载力较高、安全性要求较高时选择钢斜撑一7和钢斜撑二8的组合支撑形式。When the design requires low support bearing capacity, only choose the combination of steel diagonal brace 1 connected with the crown beam, without the construction of steel diagonal brace 2, which can meet the support requirements of the foundation pit. When the design requires a relatively high support bearing capacity When the safety requirements are high, choose the combined support form of steel diagonal brace 1 7 and steel diagonal brace 2 8.
因钢斜撑一7和钢斜撑二8长度过长,通过中心支撑格构立柱10在接近钢斜撑中心点位置给两个斜撑一个竖向支撑,故而钢斜撑一7和钢斜撑二8需在竖直方向上与中心支撑格构立柱16处于同一轴线上以保证中心支撑格构立柱16能够同时支撑钢斜撑一7和钢斜撑二8。Because the length of the first steel diagonal brace 7 and the second steel diagonal brace 8 is too long, the central support lattice column 10 provides a vertical support for the two diagonal braces at a position close to the center point of the steel diagonal brace, so the first steel diagonal brace 7 and the steel diagonal brace The second brace 8 needs to be on the same axis as the central support lattice column 16 in the vertical direction to ensure that the central support lattice column 16 can support the steel diagonal brace 1 7 and the steel diagonal brace 2 8 at the same time.
钢斜撑一7支撑平台2处设置后浇带做法适宜范围为:每面需要斜撑的基坑分别处于同一直线或者有若干斜向支撑处于同一直线上,这样就可以在此处设置在斜向支撑范围内底板通长后浇带,可通过设计变更将原设计斜撑支座附近的一条后浇带变更到此处。The suitable range of setting post-casting belts at 2 places of the steel diagonal brace-7 support platform is: the foundation pits requiring diagonal braces on each side are on the same straight line or several diagonal supports are on the same straight line, so that it can be set here. The post-cast strip is extended to the bottom plate within the support range, and a post-cast strip near the originally designed diagonal support can be changed to this place through design changes.
钢斜撑一利用电动葫芦通过预埋的吊环进行提升到位,安放到位后,吊机将液压千斤顶放入活络端顶压位置,按设计要求逐级施加预应力。活络头形式需要报设计同意后使用,关于钢斜撑二支座位置处防水处理,要在斜撑钢管周圈焊接一圈止水钢板,卷材等防水材料从垫层处卷到止水钢板上,钢斜撑一和钢斜撑二在外墙位置节点处防水处理需要在钢管切割后在内部焊接一圈止水钢板然后浇筑防水混凝土。The steel diagonal brace is lifted into place by the electric hoist through the pre-embedded lifting ring. After being put in place, the crane puts the hydraulic jack into the pressing position of the active end, and applies prestress step by step according to the design requirements. The form of the flexible head needs to be used after the design is approved. Regarding the waterproof treatment at the second support of the steel diagonal brace, a circle of waterproof steel plates should be welded around the steel pipes of the diagonal braces, and waterproof materials such as coiled materials should be rolled from the cushion to the waterproof steel plates. Above, the waterproof treatment of steel diagonal brace 1 and steel diagonal brace 2 at the joints of the outer wall needs to weld a ring of waterproof steel plates inside after the steel pipe is cut, and then pour waterproof concrete.
以上所述仅为本实用新型的较佳实施例,并不用以限制本实用新型,凡在本实用新型的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本实用新型的保护范围之内。The above are only preferred embodiments of the present invention, and are not intended to limit the present invention. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of the present invention shall be included in the present invention. within the scope of protection of the utility model.
Claims (8)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201822014418.4U CN209179021U (en) | 2018-12-03 | 2018-12-03 | A foundation pit row pile support system |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201822014418.4U CN209179021U (en) | 2018-12-03 | 2018-12-03 | A foundation pit row pile support system |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN209179021U true CN209179021U (en) | 2019-07-30 |
Family
ID=67375382
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201822014418.4U Expired - Fee Related CN209179021U (en) | 2018-12-03 | 2018-12-03 | A foundation pit row pile support system |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN209179021U (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109356169A (en) * | 2018-12-03 | 2019-02-19 | 中国建筑局(集团)有限公司 | A kind of foundation pit row pile support system and construction method thereof |
| CN110847193A (en) * | 2019-11-25 | 2020-02-28 | 中国十七冶集团有限公司 | Foundation pit support beam dismantling method |
| CN114059554A (en) * | 2021-12-09 | 2022-02-18 | 深圳市基础工程有限公司 | Novel deep foundation pit inner support system with steel truss and inclined cast support and construction method |
-
2018
- 2018-12-03 CN CN201822014418.4U patent/CN209179021U/en not_active Expired - Fee Related
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109356169A (en) * | 2018-12-03 | 2019-02-19 | 中国建筑局(集团)有限公司 | A kind of foundation pit row pile support system and construction method thereof |
| CN109356169B (en) * | 2018-12-03 | 2024-04-19 | 中国建筑一局(集团)有限公司 | Foundation pit row pile supporting system and construction method thereof |
| CN110847193A (en) * | 2019-11-25 | 2020-02-28 | 中国十七冶集团有限公司 | Foundation pit support beam dismantling method |
| CN114059554A (en) * | 2021-12-09 | 2022-02-18 | 深圳市基础工程有限公司 | Novel deep foundation pit inner support system with steel truss and inclined cast support and construction method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN109356169B (en) | Foundation pit row pile supporting system and construction method thereof | |
| CN101538833B (en) | Vertical subsection double-wall steel cofferdam water stopping construction method | |
| CN103866693B (en) | A kind of mounting method of steel concrete bowstring arch bridge arch rib | |
| CN208009463U (en) | A kind of steel-pipe pile concrete bearing platform | |
| CN103882869A (en) | Inclined supporting pile structure for foundation pit support and construction method thereof | |
| CN113482011B (en) | Large-diameter PHC pipe pile and cast-in-situ bored pile combined foundation pit supporting structure and method | |
| CN110424411A (en) | A kind of irregular foundation pit assembled steel support device and its construction and application method | |
| CN209179021U (en) | A foundation pit row pile support system | |
| CN104947681A (en) | Super large super deep basement ground pit construction method | |
| CN110593269A (en) | A turnable structural support system and its construction method | |
| CN104005414B (en) | Large-size rebar cast in place concrete pile supports the constructional method of column | |
| CN108277996A (en) | The construction method of multi-storey basement is extended under a kind of protection groups of building | |
| CN217782076U (en) | Foundation pit supporting system | |
| CN210887356U (en) | Utilize to push away construction structures that steel sleeve consolidates pile foundation | |
| CN110616719B (en) | Quick construction method for U-shaped groove of upper-span existing culvert | |
| CN214832726U (en) | Supporting structure for pipe-jacking working well in deep soft soil area | |
| CN114016516A (en) | Concrete-steel structure mixed angle brace construction method | |
| CN211285658U (en) | Structure capable of carrying out deep water area hollowing repair in rapid stream state | |
| CN204780894U (en) | Can dismantle steel protects wound packages and puts | |
| CN219732023U (en) | A kind of enclosure pile and steel diagonal brace enclosure structure | |
| CN204039973U (en) | The suspension device of both sides, cofferdam, place, a kind of nearly dike shoal | |
| CN209099351U (en) | Back taper steel jacket box in water in the prefabricated constructing tie beam of pier foundation | |
| CN217480189U (en) | A kind of box culvert foundation pit support structure in the temporary housing section | |
| CN217678551U (en) | Upper bridge and lower tunnel combined construction structure | |
| CN113684837B (en) | A pile-wall foundation pit support and water-stop integrated structure and its construction method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190730 |