CN109685328A - A kind of project under construction turns the risk score method and system of fixed assets - Google Patents

A kind of project under construction turns the risk score method and system of fixed assets Download PDF

Info

Publication number
CN109685328A
CN109685328A CN201811474161.9A CN201811474161A CN109685328A CN 109685328 A CN109685328 A CN 109685328A CN 201811474161 A CN201811474161 A CN 201811474161A CN 109685328 A CN109685328 A CN 109685328A
Authority
CN
China
Prior art keywords
audit
risk score
standardized
data
value
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811474161.9A
Other languages
Chinese (zh)
Inventor
周珑
黄华茂
蔡玲嘉
张颖
邓钧元
肖峻
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Power Grid Co Ltd
Audit Center of Guangdong Power Grid Co Ltd
Original Assignee
Guangdong Power Grid Co Ltd
Audit Center of Guangdong Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Power Grid Co Ltd, Audit Center of Guangdong Power Grid Co Ltd filed Critical Guangdong Power Grid Co Ltd
Priority to CN201811474161.9A priority Critical patent/CN109685328A/en
Publication of CN109685328A publication Critical patent/CN109685328A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0635Risk analysis of enterprise or organisation activities

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • Operations Research (AREA)
  • Game Theory and Decision Science (AREA)
  • Development Economics (AREA)
  • Marketing (AREA)
  • Educational Administration (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

This application provides the risk score method and system that a kind of project under construction turns fixed assets, and wherein method includes: to extract related data from database and be standardized;Digitlization audit is carried out according to audit regulation to the data after standardization, obtains doubtful issue list;Calculating is standardized to the relevant item amount of money of doubtful issue list, obtains the standardized value of each audit point;It will be averaged after the standardized value summation of each audit point as risk score value.The application is first guiding with risk, it combs out and is building the risk point for turning to audit admittedly and establishing audit regulation, it is then based on big data technology, digitlization audit is carried out to each risk point, quantitative analysis is carried out to auditing result, obtains risk score, score value is higher, represent the technical issues of audit point possibility of problems is higher, and the supervisor for solving traditional risk score method dependence audit expert judges to lack objectivity, cannot automate realization extensive risk score.

Description

A kind of project under construction turns the risk score method and system of fixed assets
Technical field
The risk for turning fixed assets the present invention relates to risk-oriented audit technical field more particularly to a kind of project under construction is commented Divide method and system.
Background technique
Risk-oriented audit increasingly becomes the trend of China's modern auditing work.Be different from it is traditional from inside control system, The audit that financial data sets out, from top to bottom, more targetedly, and the range of auditing objectives is wider for risk-oriented audit It is general.
It is imperative in state-owned assets auditing work that digitlization audit is applied to.Project under construction turns to increase audit of fixed assets It is one of the content of state-owned assets auditing work.The risk score method of risk-oriented has capital asset pricing model, SWOT point The methods of analysis, KSF analytic approach, EVA analytic approach, expert system approach.These methods based on expert estimation or qualitative analysis, and Non-digitalization means, and the supervisor for relying on audit expert judges to lack objectivity, cannot automate and realize that extensive risk is commented Point.
Therefore, it needs to propose a kind of digitized automatic algorithms, extensive risk score is realized in automation, improves audit effect Rate.
Summary of the invention
It is traditional for solving the present invention provides the risk score method and system that a kind of project under construction turns fixed assets The supervisor that risk score method relies on audit expert judges shortage objectivity, cannot automate the skill for realizing extensive risk score Art problem.
In view of this, the application first aspect provides a kind of risk score method that project under construction turns fixed assets, packet It includes:
Related data is extracted from database and is standardized;
Digitlization audit is carried out according to audit regulation to the data after standardization, obtains doubtful issue list;
Calculating is standardized to the relevant item amount of money of doubtful issue list, obtains the standardized value of each audit point;
It will be averaged after the standardized value summation of each audit point as risk score value.
Preferably, it is described according to audit regulation carry out digitlization audit include:
Data after standardization are compared judgement with threshold value preset in audit regulation, if being judged as more than threshold Value, then be classified as doubtful issue list for the corresponding project of the data.
It is preferably, described after extracting related data in database further include:
Derivative data is generated according to audit regulation.
Preferably, the standardized calculation is by MIN-MAX standardized algorithm by the relevant item of doubtful issue list The amount of money is converted to standardized value, wherein MIN value takes 0, MAX value to take the maximum value of the amount of money involved in doubtful issue list.
A kind of project under construction that the application second aspect provides turns the risk score systems of fixed assets, based on such as above-mentioned the The risk score method that a kind of project under construction of one side turns fixed assets scores, comprising:
Audit regulation module, for storing and providing audit regulation;
Database module, for storing data;
Data screening collects and preprocessing module, for extracting related data from database;
Standardized data module, for from database extract d volume related data be standardized;
Data operation module is obtained for carrying out digitlization audit according to audit regulation to the data after standardization Doubtful issue list;
Doubtful issue list module, for storing and showing doubtful issue list;
Be related to problem amount of money standardized module, be standardized by the relevant item amount of money to doubtful issue list based on It calculates, obtains the standardized value of each audit point;
Risk score summarizing module, for will be averaged after the standardized value summation of each audit point as risk score Value.
Preferably, the data operation module be specifically used for by after standardization data and audit regulation in it is preset Threshold value is compared judgement, if being judged as more than threshold value, the corresponding project of the data is classified as doubtful issue list.
Preferably, the data screening, which is collected, is also used to generate derivative data according to audit regulation with preprocessing module.
Preferably, the problem amount of money standardized module that is related to will be doubtful specifically for passing through MIN-MAX standardized algorithm The relevant item amount of money of issue list is converted to standardized value, wherein MIN value takes 0, MAX value to take involved in doubtful issue list The maximum value of the amount of money.
A kind of project under construction that the application third aspect provides turns the risk score equipment of fixed assets, and the equipment includes Processor and memory:
Said program code is transferred to the processor for storing program code by the memory;
The processor is used to turn solid according to the project under construction of the above-mentioned first aspect of instruction execution in said program code Determine the risk score method of assets.
A kind of computer readable storage medium that the application fourth aspect provides, the computer readable storage medium are used for Program code is stored, the project under construction that said program code is used to execute above-mentioned first aspect turns the risk score side of fixed assets Method.
As can be seen from the above technical solutions, the invention has the following advantages that
This application provides the risk score method and system that a kind of project under construction turns fixed assets, wherein method includes: Related data is extracted from database and is standardized;Data after standardization are counted according to audit regulation Wordization audit, obtains doubtful issue list;Calculating is standardized to the relevant item amount of money of doubtful issue list, is obtained each The standardized value of audit point;It will be averaged after the standardized value summation of each audit point as risk score value.The application is first It is guiding with risk, combs out and building the risk point for turning to audit admittedly and establishing audit regulation, big data technology is then based on, to each A risk point carries out digitlization audit, carries out quantitative analysis to auditing result, obtains risk score, and score value is higher, and representing should Audit point possibility of problems is higher, and the supervisor for solving traditional risk score method dependence audit expert judges to lack Objectivity cannot automate the technical issues of realizing extensive risk score.
Detailed description of the invention
It in order to illustrate the embodiments of the present invention more clearly, below will be to required use in embodiment or description of the prior art Attached drawing be briefly described, it should be apparent that, drawings in the following description are only some embodiments of the invention, for this For the those of ordinary skill of field, without any creative labor, it can also be obtained according to these attached drawings other Attached drawing.
Fig. 1 is showing for the one embodiment for the risk score method that a kind of project under construction provided by the present application turns fixed assets It is intended to;
Fig. 2 is another embodiment of the risk score method that a kind of project under construction provided by the present application turns fixed assets Schematic diagram;
Fig. 3 is showing for the one embodiment for the risk score system that a kind of project under construction provided by the present application turns fixed assets It is intended to.
Specific embodiment
It is traditional for solving the present invention provides the risk score method and system that a kind of project under construction turns fixed assets The supervisor that risk score method relies on audit expert judges shortage objectivity, cannot automate the skill for realizing extensive risk score Art problem.
In order to make the invention's purpose, features and advantages of the invention more obvious and easy to understand, below in conjunction with the present invention Attached drawing in embodiment, technical scheme in the embodiment of the invention is clearly and completely described, it is clear that disclosed below Embodiment be only a part of the embodiment of the present invention, and not all embodiment.Based on the embodiments of the present invention, this field Those of ordinary skill's all other embodiment obtained without making creative work, belongs to protection of the present invention Range.
Firstly, the part noun or term that occur during the embodiment of the present invention is described are suitable for as follows It explains:
Project under construction: project under construction refers to that the newly-built, renovating and enlarging or technological transformation of fixed corporate assets, equipment update The engineering in progress expenditure with General overhaul project etc..
Fixed assets: fixed assets refer to for manufacturer's product, utility service, taxi or management and hold, and use Service life is more than the physical assets of an accounting period.
Project under construction turns fixed assets: project under construction is to collect the process of project cost, and project under construction turns fixed assets, letter Claim to turn solid, is the process that project switchs to individual event assets, is from the management of project cost to the transformation of asset management.
Based on risk-oriented audit: it is all a kind of completely new auditing party that risk-oriented audit, which is from thinking and the mode of thinking, Method.It passes through
Identification and assessment influence various systematic risks and unsystematic risk that organizational goal is realized, to internal control Whether design perfects, and whether critical control point execution is effective, controls weak link, feasibility of innovation of governance measure etc. and proposes Assert.
Risk score: in risk-oriented audit, risk score is where judging, analyzing the risk of unit under auditing After (risk point), quantitative marking or qualitative evaluation are carried out to the risk point, are the intuitive measurements to degree of risk.Risk The method of scoring is varied, such as: risk Factor Analysis method, Field Using Fuzzy Comprehensive Assessment, internal control evaluation method, it is analytical examine Core method, Audit Risk Model method, Qualitative risk evaluation assessment, relative risk risk assessment method etc. when concrete application, are needed according to practical Depending on scene.
Referring to Fig. 1, a kind of project under construction provided by the present application turns an implementation of the risk score method of fixed assets Example, comprising:
101, related data is extracted from database and is standardized;
Further, after extracting related data in database further include:
Derivative data is generated according to audit regulation.
It should be noted that database includes the relevant massive information of engineering project.Data screening collects and pre-processes, from Related data is extracted in database, is from this initial data, the list according to required for audit regulation first extracts project The data of relevant information, such as project information, material information, financial information, contract information etc..Then these data are marked Quasi-ization processing, or need to generate derivative data according to audit regulation and (usually calculated according to the data for including in database Derivative data, such as unit price obtain total amount multiplied by number).Wherein project information includes: project name, project number, area Coding, investment amount, voltage class, project content, settlement time, project category, project manager, project application date, project verification Time, risk score value.Other information includes: buying order number, operating efficiency title, actual purchase quantity, measurement unit, adopts Buying order valence, procurement value, sub-project title, buying hour, item obtainment time, material requistion ID, neck material money title, receive quantity, Measurement unit, unit price, the amount of money, vendor name, procurement contract title, procurement contract number.
102, digitlization audit is carried out according to audit regulation to the data after standardization, obtains doubtful issue list;
Further, carrying out digitlization audit according to audit regulation includes:
Data after standardization are compared judgement with threshold value preset in audit regulation, if being judged as more than threshold Value, then be classified as doubtful issue list for the corresponding project of the data.
For example, it is 100 yuan that wherein an audit regulation, which is the threshold value of unit price of procurement, then digitizing audit can adopting project Buying order valence is compared with 100 yuan, if illustrating that the unit price of procurement has doubtful problem and risk, corresponding project more than 100 yuan Need to be listed in doubtful issue list.
After obtaining doubtful issue list, the available data to doubtful issue list are simultaneously shown, pass through display screen Doubtful issue list is shown, for staff's reference.
103, calculating is standardized to the relevant item amount of money of doubtful issue list, obtains the standardization of each audit point Value;
Further, standardized calculation is the relevant item gold by MIN-MAX standardized algorithm by doubtful issue list Volume is converted to standardized value, wherein MIN value takes 0, MAX value to take the maximum value of the amount of money involved in doubtful issue list.
After obtaining doubtful issue list, begin to prepare for digitlization risk score.In the application, to audit point The risk score of doubtful issue list is to be converted into marking according to certain algorithm according to based on the amount of money involved by the problem Standardization numerical value, using the numerical value as risk score value.Wherein " amount of money involved by the problem " examining according to each audit point Meter rule is different and different, such as the amount of money being related in audit point " still expecting in neck after putting into operation ", refers to total gold of led goods and materials Volume;" temporarily estimate before going into operation and turn solid " then refers to the total amount temporarily estimated and turn solid, these preset in audit regulation.The application adopts Transfer algorithm is MIN-MAX standardized algorithm, and wherein MIN value takes 0, MAX value to take the maximum of the amount of money involved in inventory problem Value, can preset, and can also be obtained by calculating.
104, it will be averaged after the standardized value summation of each audit point as risk score value.
Risk score summarizes, and is that standardized value obtained by the previous step of each audit point is averaged, by the value after summation As last risk score value.
The application is first guiding with risk, combs out and is building the risk point for turning to audit admittedly and establishing audit regulation, then base In big data technology, digitlization audit is carried out to each risk point, quantitative analysis is carried out to auditing result, obtains risk score, Score value is higher, represents that the audit point possibility of problems is higher, solves traditional risk score method and relies on audit The technical issues of supervisor of expert judges to lack objectivity, cannot automate realization extensive risk score.
It is the one embodiment for turning the risk score method of fixed assets to a kind of project under construction provided by the present application above It is described in detail, the another of the risk score method of fixed assets will be turned to a kind of project under construction provided by the present application below A embodiment is described in detail,
Referring to Fig. 2, a kind of project under construction provided by the present application turns another reality of the risk score method of fixed assets Apply example, comprising:
Step01: the draw standard database from asset management database, including engineering project information is extracted, goods and materials letter Breath, financial settlement information, Project contract information.
Step02: pretreatment is standardized to data.
Step03: receiving and turn solid audit regulation, receives and turns in solid audit regulation, and each rule is involved that data are clear It is single, such as the time data of procedure links, statement of account etc..
Step04: the data being related to according to turn solid audit regulation extracting rule from standard database.
Step05: receiving and turn solid audit regulation, after obtaining data, receives the logic judgment rule in audit regulation.
Step06: data operation is carried out according to audit regulation.Data operation is carried out after input data according to audit regulation Logical operation and condition judgement.
Step07: according to project information, material information, being related to problem amount information etc. and export wide table, including: project Title, project number, area code, investment amount, voltage class, project content, settlement time, project category, project manager, Project application date, the time of project verification are related to the problem amount of money (still in the neck material total amount of neck material, spending beyond the original estimation buying and neck after putting into operation Total gold of the total amount, Closing Check inaccuracy that turn solid is temporarily estimated before the total amount that is put into operation with the total amount of goods and materials, surprise, operation The total amount of volume, fixed assets of carrying down inaccuracy).
Step08: according to MIN-MAX standardized method being 0 to 100 sections by " being related to the problem amount of money " in previous step Numerical value, it is identical " being related to the problem amount of money " maximum value audited and put in issue list that wherein MIN value, which is 0, MAX value, finally will not It is averaged with the value after the standardization of audit point as risk score.
Step09: the wide table in risk score obtained in the previous step and Step7 is synthesized into chart, page in displayed page together It simultaneously issues in face.
The present invention is digitlization audit to be realized on turning solid audit, and in terms of the risk score of total digitalization, have head It is invasive.This patent is after combing out the risk point for turning solid audit, using big data technology, extracts after each risk point is related to Number of units evidence, according to the algorithm that this patent uses, the data conversion that each risk point is related to is got at risk score value, score value It is higher to represent the audit point possibility of problems for height.This patent individually carries out digitlization audit for solid audit is turned, and Digitized risk score, realizes modularization audit, and the system of this patent has a good expansibility, aspect drop it is identical or In other sub- contents that similar method is applied in Construction Audit.
It is another implementation for the risk score method for turning fixed assets to a kind of project under construction provided by the present application above Example is described in detail, and will turn the one of the risk score system of fixed assets to a kind of project under construction provided by the present application below A embodiment is described in detail.
Referring to Fig. 3, a kind of project under construction provided by the present application turns an implementation of the risk score system of fixed assets Example, the risk score method that a kind of project under construction based on such as above-described embodiment turns fixed assets score, comprising:
Audit regulation module 1-0, for storing and providing audit regulation;
Audit regulation module 1-0 is to be summarized in from the professional experiences, historical auditing issue list of auditor and build work Journey turns the decision logic rule of audit of fixed assets risk point, abbreviation audit regulation.The solid audit regulation that turns in the present invention includes 3 A aspect: do not complete first clearing, the super investment of clearing volume and turn consolidate not in time.This 3 aspect be related to risk point is distributed in The engineering neck material of engineering project, is temporarily estimated in the links such as turn solid, Engineering Settlement, final account of project, subsequent O&M operation power transmission.Wherein The risk point first settled accounts that do not complete includes and not exclusively includes: still purchasing and receive goods and materials, assault in neck material, spending beyond the original estimation after putting into operation Property put into operation, go into operation before temporarily estimate and turn solid, Closing Check amount of money inaccuracy, fixed assets of carrying down amount of money inaccuracy etc..Audit regulation is then It is the specific decision logic to these risk points, every audit regulation requires to obtain and input related information (data), and output is sentenced Disconnected result.
Database module 1-1, for storing data;
Data screening collect with preprocessing module 1-2, for extracting related data from database;Further, data Screening, which is collected, to be also used to generate derivative data according to audit regulation with preprocessing module 1-2.
Database includes the relevant massive information of engineering project.Data screening is collected and is pre-processed, and is from this initial data In, the list according to required for audit regulation first extracts the data of item related information, such as project information, goods and materials letter Breath, financial information, contract information etc..Then these data are standardized, or need to generate according to audit regulation Derivative data.Wherein project information include: project name, project number, area code, investment amount, voltage class, in engineering Appearance, settlement time, project category, project manager, project application date, project verification time, risk score value.Other information includes: Buying order number, sub-project title, is adopted operating efficiency title, actual purchase quantity, measurement unit, unit price of procurement, procurement value Purchase the time, item obtainment time, material requistion ID, neck material money title, receive quantity, measurement unit, unit price, the amount of money, vendor name, Procurement contract title, procurement contract number.
Standardized data module 1-3, for from database extract d volume related data be standardized;
Data operation module 1-4 is obtained for carrying out digitlization audit according to audit regulation to the data after standardization To doubtful issue list;Data operation is that code is write in functional module after obtaining normal data, and audit regulation is converted At the operation between data, digitlization audit is realized.Further, data operation module 1-4 be specifically used for will be after standardization Data be compared judgement with threshold value preset in audit regulation, if being judged as more than threshold value, by the corresponding item of the data Mesh is classified as doubtful issue list.
Doubtful issue list module 1-5, for storing and showing doubtful issue list;Doubtful issue list is the defeated of system Interface out.After it is data operation, the doubtful issue list that is exported according to audit regulation.
It is related to problem amount of money standardized module 1-6, is standardized for the relevant item amount of money to doubtful issue list It calculates, obtains the standardized value of each audit point;Further, it is related to problem amount of money standardized module 1-6 to be specifically used for passing through The relevant item amount of money of doubtful issue list is converted to standardized value by MIN-MAX standardized algorithm, wherein MIN value takes 0, MAX Value takes the maximum value of the amount of money involved in doubtful issue list.After being extracted doubtful issue list, begin to comment for digitlization risk Divide and prepares.It is according to the amount of money involved by the problem to the risk score of the doubtful issue list of audit point in this patent Based on, it is converted into standardized value according to certain algorithm, using the numerical value as risk score value.Wherein " involved by the problem The amount of money arrived " is different and different according to the audit regulation of each audit point, such as involved in audit point " still expecting in neck after putting into operation " The amount of money arrived refers to the total amount of led goods and materials;" temporarily estimate before going into operation and turn solid " then refers to the total amount temporarily estimated and turn solid.This patent is adopted Transfer algorithm is MIN-MAX standardized algorithm, and wherein MIN value takes 0, MAX value to take the maximum of the amount of money involved in inventory problem Value.
Risk score summarizing module 1-7, for will be averaged after the standardized value summation of each audit point as risk Score value.
Risk score summarizes, and is that standardized value obtained by the previous step of each audit point is averaged, by the value after summation As last risk score value.
The application also provides the risk score equipment that a kind of project under construction turns fixed assets, and equipment includes processor and deposits Reservoir:
Program code is transferred to processor for storing program code by memory;
Processor is used to turn fixed assets according to the project under construction of the above-mentioned first aspect of instruction execution in program code Risk score method.
The application also provides a kind of computer readable storage medium, and computer readable storage medium is for storing program generation Code, the project under construction that program code is used to execute above-mentioned first aspect turn the risk score method of fixed assets.
It is apparent to those skilled in the art that for convenience and simplicity of description, the system of foregoing description, The specific work process of device and unit, can refer to corresponding processes in the foregoing method embodiment, and details are not described herein.
In several embodiments provided herein, it should be understood that disclosed system, device and method can be with It realizes by another way.For example, the apparatus embodiments described above are merely exemplary, for example, the unit It divides, only a kind of logical function partition, there may be another division manner in actual implementation, such as multiple units or components It can be combined or can be integrated into another system, or some features can be ignored or not executed.Another point, it is shown or The mutual coupling, direct-coupling or communication connection discussed can be through some interfaces, the indirect coupling of device or unit It closes or communicates to connect, can be electrical property, mechanical or other forms.
The unit as illustrated by the separation member may or may not be physically separated, aobvious as unit The component shown may or may not be physical unit, it can and it is in one place, or may be distributed over multiple In network unit.It can select some or all of unit therein according to the actual needs to realize the mesh of this embodiment scheme 's.
It, can also be in addition, the functional units in various embodiments of the present invention may be integrated into one processing unit It is that each unit physically exists alone, can also be integrated in one unit with two or more units.Above-mentioned integrated list Member both can take the form of hardware realization, can also realize in the form of software functional units.
If the integrated unit is realized in the form of SFU software functional unit and sells or use as independent product When, it can store in a computer readable storage medium.Based on this understanding, technical solution of the present invention is substantially The all or part of the part that contributes to existing technology or the technical solution can be in the form of software products in other words It embodies, which is stored in a storage medium, including some instructions are used so that a computer Equipment (can be personal computer, server or the network equipment etc.) executes the complete of each embodiment the method for the present invention Portion or part steps.And storage medium above-mentioned includes: USB flash disk, mobile hard disk, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), magnetic or disk etc. are various can store journey The medium of sequence code.
The above, the above embodiments are merely illustrative of the technical solutions of the present invention, rather than its limitations;Although referring to before Stating embodiment, invention is explained in detail, those skilled in the art should understand that: it still can be to preceding Technical solution documented by each embodiment is stated to modify or equivalent replacement of some of the technical features;And these It modifies or replaces, the spirit and scope for technical solution of various embodiments of the present invention that it does not separate the essence of the corresponding technical solution.

Claims (10)

1. a kind of risk score method that project under construction turns fixed assets characterized by comprising
Related data is extracted from database and is standardized;
Digitlization audit is carried out according to audit regulation to the data after standardization, obtains doubtful issue list;
Calculating is standardized to the relevant item amount of money of doubtful issue list, obtains the standardized value of each audit point;
It will be averaged after the standardized value summation of each audit point as risk score value.
2. the risk score method that a kind of project under construction according to claim 1 turns fixed assets, which is characterized in that described Carrying out digitlization audit according to audit regulation includes:
Data after standardization are compared judgement with threshold value preset in audit regulation, if being judged as more than threshold value, The corresponding project of the data is then classified as doubtful issue list.
3. the risk score method that a kind of project under construction according to claim 1 turns fixed assets, which is characterized in that described After extracting related data in database further include:
Derivative data is generated according to audit regulation.
4. the risk score method that a kind of project under construction according to claim 1 turns fixed assets, which is characterized in that described Standardized calculation is that the relevant item amount of money of doubtful issue list is converted to standardized value by MIN-MAX standardized algorithm, Wherein, MIN value takes 0, MAX value to take the maximum value of the amount of money involved in doubtful issue list.
5. a kind of project under construction turns the risk score system of fixed assets, work is being built based on one kind as described in Claims 1-4 The risk score method that journey turns fixed assets scores characterized by comprising
Audit regulation module, for storing and providing audit regulation;
Database module, for storing data;
Data screening collects and preprocessing module, for extracting related data from database;
Standardized data module, for from database extract d volume related data be standardized;
Data operation module obtains doubtful for carrying out digitlization audit according to audit regulation to the data after standardization Issue list;
Doubtful issue list module, for storing and showing doubtful issue list;
It is related to problem amount of money standardized module, is standardized calculating for the relevant item amount of money to doubtful issue list, obtains To the standardized value of each audit point;
Risk score summarizing module, for will be averaged after the standardized value summation of each audit point as risk score value.
6. the risk score system that a kind of project under construction according to claim 5 turns fixed assets, which is characterized in that described Data operation module is specifically used for the data after standardization being compared judgement with threshold value preset in audit regulation, if It is judged as to be more than threshold value, then the corresponding project of the data is classified as doubtful issue list.
7. the risk score system that a kind of project under construction according to claim 5 turns fixed assets, which is characterized in that described Data screening, which is collected, to be also used to generate derivative data according to audit regulation with preprocessing module.
8. the risk score system that a kind of project under construction according to claim 5 turns fixed assets, which is characterized in that described It is related to problem amount of money standardized module and is specifically used for the relevant item gold for passing through MIN-MAX standardized algorithm for doubtful issue list Volume is converted to standardized value, wherein MIN value takes 0, MAX value to take the maximum value of the amount of money involved in doubtful issue list.
9. the risk score equipment that a kind of project under construction turns fixed assets, which is characterized in that the equipment include processor and Memory:
Said program code is transferred to the processor for storing program code by the memory;
The processor is used for according to the described in any item projects under construction of instruction execution claim 1-4 in said program code Turn the risk score method of fixed assets.
10. a kind of computer readable storage medium, which is characterized in that the computer readable storage medium is for storing program generation Code, said program code turn the risk score side of fixed assets for the perform claim requirement described in any item projects under construction of 1-4 Method.
CN201811474161.9A 2018-12-04 2018-12-04 A kind of project under construction turns the risk score method and system of fixed assets Pending CN109685328A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811474161.9A CN109685328A (en) 2018-12-04 2018-12-04 A kind of project under construction turns the risk score method and system of fixed assets

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811474161.9A CN109685328A (en) 2018-12-04 2018-12-04 A kind of project under construction turns the risk score method and system of fixed assets

Publications (1)

Publication Number Publication Date
CN109685328A true CN109685328A (en) 2019-04-26

Family

ID=66186964

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811474161.9A Pending CN109685328A (en) 2018-12-04 2018-12-04 A kind of project under construction turns the risk score method and system of fixed assets

Country Status (1)

Country Link
CN (1) CN109685328A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111160864A (en) * 2019-12-30 2020-05-15 成都工业学院 Fabricated building tracking audit management method based on risk oriented theory
CN112308467A (en) * 2020-11-26 2021-02-02 上海济邦投资咨询有限公司 Engineering project risk assessment system based on big data

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107133864A (en) * 2017-05-12 2017-09-05 云南电网有限责任公司 A kind of group employee pending accounts auditing method and device based on big data
CN107563884A (en) * 2017-07-28 2018-01-09 浙江邦盛科技有限公司 A kind of method for reducing loss of assets rate
CN107862599A (en) * 2017-10-16 2018-03-30 平安科技(深圳)有限公司 Bank risk data processing method, device, computer equipment and storage medium

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107133864A (en) * 2017-05-12 2017-09-05 云南电网有限责任公司 A kind of group employee pending accounts auditing method and device based on big data
CN107563884A (en) * 2017-07-28 2018-01-09 浙江邦盛科技有限公司 A kind of method for reducing loss of assets rate
CN107862599A (en) * 2017-10-16 2018-03-30 平安科技(深圳)有限公司 Bank risk data processing method, device, computer equipment and storage medium

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111160864A (en) * 2019-12-30 2020-05-15 成都工业学院 Fabricated building tracking audit management method based on risk oriented theory
CN112308467A (en) * 2020-11-26 2021-02-02 上海济邦投资咨询有限公司 Engineering project risk assessment system based on big data

Similar Documents

Publication Publication Date Title
KR102286415B1 (en) Online and offline information analysis service system by lifecycle according to product life cycle
CN108446972A (en) Bank's Supervision of credit method, apparatus and fund position manage system
WO2006004132A1 (en) Device for specifying company evaluation contribution factor and/or index, specifying program, and specifying method
CN109190939A (en) Shops's operation data management system
KR101324214B1 (en) Apparatus for evaluating a value of technique, method thereof, and storage media for storing a program evaluating a value of technique
CN109840847A (en) One kind going core Supply chain financing method
CN110009293A (en) Finishing management system and method
CN109598484A (en) A kind of project under construction turns fixed assets number auditing method and device
KR20170049328A (en) Apparatus and method for evaluating a value of technology or intellectual property
CN109685328A (en) A kind of project under construction turns the risk score method and system of fixed assets
CN109102396A (en) A kind of user credit ranking method, computer equipment and readable medium
KR20130083054A (en) Cost evaluation system for construction project considering organizational capability
CN107798137B (en) A kind of multi-source heterogeneous data fusion architecture system based on additive models
Vilochani et al. Consolidation of management practices for Sustainable Product Development: A systematic literature review
Härting et al. Cost-benefit considerations for data analytics-an SME-oriented framework enhanced by a management perspective and the process of idea generation
JP2007272722A (en) Method and system for analyzing set-up of branch office
KR20130083053A (en) Warning system for bad project of overseas constructions
CN115358852A (en) Bond data processing method and device
CN104408558B (en) A kind of accounting operations analogue simulation model system
Abdou et al. Modelling risk for construction cost estimating and forecasting: a review
US11552862B2 (en) Method for measuring operation performance of intelligent information system
KR20130100857A (en) System for providing financiail risk management service in software as a service
JP2018173821A (en) Point assigning system
Wetzel et al. Economies of scope in European railways: an efficiency analysis
CN113987351A (en) Artificial intelligence based intelligent recommendation method and device, electronic equipment and medium

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190426