A kind of project under construction turns fixed assets number auditing method and device Download PDF

Info

Publication number
CN109598484A
CN109598484A CN201811475736.9A CN201811475736A CN109598484A CN 109598484 A CN109598484 A CN 109598484A CN 201811475736 A CN201811475736 A CN 201811475736A CN 109598484 A CN109598484 A CN 109598484A
Authority
CN
China
Prior art keywords
audit
data
regulation
articles
under construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811475736.9A
Other languages
Chinese (zh)
Inventor
周珑
王鑫根
张颖
蔡玲嘉
姜睿
陈瑜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Power Grid Co Ltd
Audit Center of Guangdong Power Grid Co Ltd
Original Assignee
Guangdong Power Grid Co Ltd
Audit Center of Guangdong Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Power Grid Co Ltd, Audit Center of Guangdong Power Grid Co Ltd filed Critical Guangdong Power Grid Co Ltd
Priority to CN201811475736.9A priority Critical patent/CN109598484A/en
Publication of CN109598484A publication Critical patent/CN109598484A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Engineering & Computer Science (AREA)
  • General Business, Economics & Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • Marketing (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Data Mining & Analysis (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The embodiment of the present application discloses a kind of project under construction and turns fixed assets number auditing method, comprising: the initial value of default N is 1, S1: according to the audit demand got, from transferring in database and the associated data information of trial engineering in audit demand;S2: the N articles audit regulation is read from default audit regulation table;S3: it is extracted and the N articles associated Audit data of audit regulation from data information;S4: sentencing formula according to the logic in the N articles audit regulation, and the logic operation result of corresponding the N articles audit regulation is calculated using Audit data;S5: if logic operation result is very, Audit data to be labeled as problem data;S6: making the N that N+1 is new, judges the audit regulation item number whether new N is greater than in default audit regulation table, if it is not, S2 is returned to, if so, terminating;It solves in traditional audit, auditor's heavy workload, low efficiency, audit project technical problem at high cost.

Description

A kind of project under construction turns fixed assets number auditing method and device
Technical field
This application involves fields of automation technology more particularly to a kind of project under construction to turn fixed assets number auditing party Method, device and storage medium.
Background technique
Project under construction can regard the process for collecting project cost as, and project under construction is changed into fixed assets (letter Claim to turn solid), it is the process that project switchs to individual event assets, and from the management of project cost to the transformation of asset management.
Turn one of the content that solid audit is state-owned assets auditing work.When carrying out turning to audit admittedly, auditor is by looking into Engineering project archives papery document file is read, inquiry correlation is by auditor, in conjunction with systems such as operation system, the asset management systems Derived underlying assets list audits relevant information point according to auditor's professional experiences one by one, and makes specially Industry judgement.However, in this mode of operation, no matter simple or complicated, all project information require auditor Processing, workload is huge, heavy operating pressure is brought to auditor, and audit efficiency is low.
Summary of the invention
The embodiment of the present application, which provides a kind of project under construction and turns fixed assets number auditing method, device and storage, to be situated between Matter is solved when turning to audit admittedly, and all project datas require auditor's processing, and auditor's pressure is overweight and examines The technical issues of counting inefficiency.
In view of this, the application first aspect, which provides a kind of project under construction, turns fixed assets number auditing method, wrap Include: the initial value of default N is 1,
S1: it according to the audit demand got, is associated with from being transferred in database with the trial engineering in the audit demand Data information;
S2: the N articles audit regulation is read from default audit regulation table;
S3: it is extracted and the associated Audit data of the N articles audit regulation from the data information;
S4: sentencing formula according to the logic in the N articles audit regulation, calculates the corresponding N using the Audit data The logic operation result of audit regulation;
S5: if the logic operation result is very, the Audit data to be labeled as problem data;
S6: the N for keeping N+1 new, judge the audit the rule whether new N is greater than in the default audit regulation table Then item number, if it is not, the S2 is returned to, if so, terminating.
Preferably, after the S5 further include:
Described problem data are output to audit issues inventory.
Preferably, after the S5 further include:
Described problem data are graphically associated with the N articles audit regulation and export display.
Preferably, the S1 is specifically included:
According to the audit demand got, transferred from goods and materials database, financial database and project database and institute State the associated data information of trial engineering in audit demand.
Preferably, after the S1 further include:
The data information is screened, invalid data is removed.
Preferably, described that the data information is screened, after removal invalid data further include:
The data information is exported to display in the form of wide table.
The application second aspect provides a kind of project under construction and turns fixed assets number audit device, comprising:
Module is reset, the initial value for presetting N is 1.
Data transfer module, for according to the audit demand that gets, from transferred in database in the audit demand The associated data information of trial engineering;
Read module, for reading the N articles audit regulation from default audit regulation table;
Extraction module, for being extracted and the associated Audit data of the N articles audit regulation from the data information;
Logical operation module utilizes the Audit data meter for sentencing formula according to the logic in the N articles audit regulation Calculate the logic operation result of corresponding the N articles audit regulation;
Mark module, if being very, the Audit data to be labeled as problem data for the logic operation result;
Cycle criterion module, the N for keeping N+1 new judge whether the new N is greater than the default audit rule The then audit regulation item number in table, if it is not, the S2 is returned to, if so, terminating.
Preferably, further includes:
Audit issues inventory generation module, for described problem data to be output to audit issues inventory.
Preferably, further includes:
Chart generating module, for being graphically associated with described problem data simultaneously with the N articles audit regulation Output display.
The application third aspect provides a kind of computer readable storage medium, and the computer readable storage medium is used for Program code is stored, said program code turns amount of fixed assets for executing any project under construction described in above-mentioned first aspect Word auditing method.
As can be seen from the above technical solutions, the embodiment of the present application has the advantage that
In the embodiment of the present application, provides a kind of project under construction and turn fixed assets number auditing method, by setting in advance Determine audit regulation table, can will simply summarize the audit regulation come and be described in the form of logic sentences formula.Also, it is each Audit regulation is associated with logic and sentences the Audit data for needing to use in formula, therefore when there is audit demand, can be purposeful Property according to the related information between audit regulation and Audit data, extract the audit number in the data information of trial engineering According to.Using the Audit data, formula can be sentenced with arithmetic logic, the logic operation result of obtained this audit regulation.If logic is transported It is true for calculating result, then it represents that the Audit data does not meet audit regulation, is suspectable data, therefore be marked as problem Data, auditor need to only investigate the corresponding objective evidence of problem data, so that it may obtain compliance audit judging result.
It can be seen that method provided by the embodiments of the present application realizes the audit of the digitlization to engineering project data, by setting in advance Determine audit regulation table, enabling to turn compliance audit in solid audit work is to audit, and auditor only needs by computer generation Other auditing objectives, the audit work amounts such as the objective evidence verification and post project evaluation of concern compliance audit greatly reduce, The efficiency of audit is also improved while mitigating auditor's operating pressure.
Detailed description of the invention
Fig. 1 is one embodiment that a kind of project under construction provided by the present application turns fixed assets number auditing method Flow chart;
Fig. 2 is second embodiment that a kind of project under construction provided by the present application turns fixed assets number auditing method Flow chart;
Fig. 3 is one embodiment that a kind of project under construction provided by the present application turns fixed assets number audit device Flow chart.
Specific embodiment
In order to make those skilled in the art more fully understand application scheme, below in conjunction in the embodiment of the present application Attached drawing, the technical scheme in the embodiment of the application is clearly and completely described, it is clear that described embodiment is only this Apply for a part of the embodiment, instead of all the embodiments.Based on the embodiment in the application, those of ordinary skill in the art exist Every other embodiment obtained under the premise of creative work is not made, shall fall in the protection scope of this application.
Project under construction refers to that the newly-built, renovating and enlarging or technological transformation of fixed corporate assets, equipment updates and general overhaul The engineering expenditure in progress such as engineering.And fixed assets refer to for manufacturer's product, utility service, taxi or management and hold Have, service life is more than the physical assets of an accounting period.Project under construction can be changed into solid from project under construction in the finished Determine assets, and this also means that from the management of project cost to the transformation of asset management.
The solid process of assets turn, inside control system, laws and regulations are very clear, turn solid audit, principally fall into compliance audit.
The process that compliance audit is found the problem is exactly substantially that potential problems point is collected and combs problem and relates to And the information arrived is come then according to laws and regulations and inside control system, business administration principle, the even common sense that is recognized and confirms Information is combed, and is made a decision.Some problems are plain, it is clear that, then the data being related to are few, rule compared with It is simple;There are some problems more complicated, needs multiple precondition that can just be judged, then the data being related to are more, rule It is complex.It is either simple or complicated, it transfers to computer to carry out if the part can work, is first carried out before audit work The digitlization of computer is audited, then can largely reduce the workload of auditor.
Below referring to Figure 1, Fig. 1 is that a kind of project under construction provided by the present application turns fixed assets number auditing method The flow chart of one embodiment, this method comprises:
Before the method for execution the step of, it is necessary first to which the initial value of default N is 1.It should be noted that N expression one is whole Number, but before method execution, it is preset equal to 1, certainly, step content can be answered in the implementation procedure of method and is become Change, and on-fixed is equal to 1.
The audit demand that step 101, basis are got, is associated with from transferring in database with the trial engineering in audit demand Data information.
Audit demand is that auditor fills in and sends, and it includes the trial engineerings for having auditor to want to audit Title, therefore can summarize in database according to the title of the trial engineering and transfer relevant data information.
In turning solid audit, the data information for needing to audit has very much, generally includes following data: project information data, Material information data, financial information data, contract information data.Wherein, project information include: project name, project number, Area's coding, voltage class, project content, settlement time, project category, project manager, the project application date, is stood investment amount The item time, risk score value;Other information include buying order number, operating efficiency title, actual purchase quantity, measurement unit, Unit price of procurement, sub-project title, buying hour, item obtainment time, material requistion ID, neck material money title, receives number at procurement value Amount, measurement unit, unit price, the amount of money, buying first for the goods and materials amount of money, receive first for the goods and materials amount of money, cancelling stocks first for the goods and materials amount of money, budgetary estimate When middle first stops power transmission record, power transmission for the goods and materials amount of money, project time of completion, project settlement time, project production time, project Between, production time, temporarily estimate turn a solid time, production time, the financial system project neck material amount of money, the goods and materials system item neck material amount of money, Vendor name, procurement contract title etc..
Step 102 reads the N articles audit regulation from default audit regulation table.
Default audit regulation table be according to the professional standing and experience of auditor, historical auditing problem, laws and regulations and Inside control system, easily determines when to audit and judging result is clear uniquely partially refines, summarize by a rule The audit regulation table that audit regulation is formed.
There are many formulation modes of default audit regulation table, and the application provides the exemplary example of a default audit regulation table Son, use for reference only, not to the restriction of default audit regulation table, which, which presets audit regulation, specifically may include three Aspect: do not complete first clearing, the super investment of clearing volume and turn consolidate not in time.The audit point that these three aspects are related to is distributed in work Journey item purpose engineering neck material, is temporarily estimated in turn solid, Engineering Settlement, subsequent O&M link operation power transmission.
It is interim, it does not complete the audit point first settled accounts and audit regulation includes:
1, the operating efficiency arrival time is greater than production time, and needing to input information has: the project purchasing goods and materials arrival time (A), the logical operation of project production time (B), corresponding audit regulation are: A >=B.
2, still expect that needing to input information has: project goods and materials item obtainment time (A), project production time in neck after project puts into operation (B), the logical operation of corresponding audit regulation is: A >=B.
3, spending beyond the original estimation purchase and receive first for goods and materials, needing to input information has: buying first for the goods and materials amount of money (A), receive first For the goods and materials amount of money (B), cancelling stocks first for first in the goods and materials amount of money (C), budgetary estimate for the goods and materials amount of money (D), the logic fortune of corresponding audit regulation At last: A+B-C > D.
4, end of the year surprise puts into operation, and needing to input information has: project time of completion (A), project settlement time (B), project The logical operation of production time (C), corresponding audit regulation is: C >=and in November (B >=November orA >=November).
5, without power transmission record is stopped, needing to input information has for scheduling: project stops power transmission record (A), and corresponding audit regulation is patrolled Collecting operation is: A is null.
6, stop electric power feeding time and production time gap is excessive, needing to input information has: electric power feeding time (A), production time (B), the logical operation of threshold value (C), corresponding audit regulation are: A-B > C.
7, temporarily estimate before going into operation and turn solid, needing to input information has: temporarily estimating and turn solid time (A), production time (B), corresponding audit The logical operation of rule is: B > A.
8, Closing Check content and live completion content are inconsistent, and needing to input information has: site inspection situation (A) shows Closing Check content (B) corresponding to content is reconnoitred in field, and the logical operation of corresponding audit regulation is: A<>B.
9, remember the expense of idleness, needing to input information has: clearing work holdup expense (A), according to visa and log recording calculating The logical operation of work holdup expense (B), corresponding audit regulation is: A > B.
10, finance neck material data and logistics neck material data mismatch, and needing to input information has: financial system project neck material gold The logical operation of volume (A), the goods and materials system item neck material amount of money (B), corresponding audit regulation is: A<>B.
11, without operational plan or test plan after putting into operation, needing to input information has: project puts into operation record (A), operational plan (B), test plan record (C) are recorded, the logical operation of corresponding audit regulation is: A is not null and (B is null or C is null)。
As it can be seen that default audit regulation table contains a plurality of preset audit regulation, and in the step, have read N Audit regulation, for method is initial, due to N=1, that is, what is read is the 1st article of audit regulation.
Step 103 is extracted and the N articles associated Audit data of audit regulation from data information.
By, as it can be seen that each audit regulation, which sets logic, sentences formula, logic sentences the fortune of formula in the explanation of above-mentioned steps 102 Calculation is needed using Audit data, therefore each audit regulation can be associated in advance with the Audit data that it is needed, in data The Audit data of needs then can be accurately obtained when extracting data in information according to the association.
Step 104 sentences formula according to the logic in the N articles audit regulation, calculates corresponding the N articles audit using Audit data and advises Logic operation result then.
Using the Audit data extracted, substitutes into logic and sentence formula progress logical operation, this audit regulation can be calculated Corresponding logic operation result, the i.e. corresponding logic operation result of the N articles audit regulation.
If step 105, logic operation result are very, Audit data to be labeled as problem data.
If logic operation result is true, it is believed that Audit data does not meet audit regulation, it is likely that there are problems, need at this time Auditor's further progress judgement, it is therefore desirable to problematic Audit data under a cloud is labeled as problem data, for examining Meter personnel carry out secondary audit.
Further, if logic operation result is vacation, with no treatment, step is performed the next step.
It should be noted that logic operation result is true only a kind of illustrative statement, indicate in the present embodiment Audit regulation is not met, but by simply changing, can also make logic operation result is false to indicate not meeting audit regulation, ability Field technique personnel should know.
Step 106, the N for keeping N+1 new judge the audit regulation item number whether new N is greater than in default audit regulation table, If it is not, return step 102, if so, terminating.
The step realizes the audit regulation read in default audit regulation table one by one, when new N is greater than default audit rule The then audit regulation item number in table, it is meant that all preset audit regulations have passed through computer auditing, can be with ending method. Certainly, the application uses the scheme audited one by one, but can also audit simultaneously to a plurality of audit regulation.
In the application one embodiment, provides a kind of project under construction and turn fixed assets number auditing method, pass through Audit regulation table is preset, the audit regulation come can will be simply summarized and is described in the form of logic sentences formula.And And each audit regulation is associated with logic and sentences the Audit data for needing to use in formula, therefore when there is audit demand, it can be with It is purposive according to the related information between audit regulation and Audit data, extract examining in the data information of trial engineering It counts.Using the Audit data, formula can be sentenced with arithmetic logic, the logic operation result of obtained this audit regulation.If patrolling It is true for collecting operation result, then it represents that the Audit data does not meet audit regulation, is suspectable data, therefore be marked as Problem data facilitates the secondary audit of auditor.
It can be seen that method provided by the embodiments of the present application realizes the audit of the digitlization to engineering project data, by setting in advance Determine audit regulation table, enable to turn in solid audit work it is more suspenseful, can the part of unartificial judgement be by computer generation Audit, and auditor need to only veritify the corresponding objective evidence of problem data, audit work amount greatly reduces, and improves careful The efficiency of meter.
The above are first implementations for turning fixed assets number auditing method to a kind of project under construction provided by the present application The detailed description of example, refers to Fig. 2 below, and Fig. 2 is that a kind of project under construction provided by the present application turns the audit of fixed assets numberization The flow chart of second embodiment of method, this method comprises:
The audit demand that step 201, basis are got, from goods and materials database, financial database and project database It transfers and the associated data information of trial engineering in audit demand.
Data information of the engineering project in goods and materials field, financial field and project fields is required to audit, and three The data information of aspect usually stores in respective database, that is, goods and materials database, financial database and item number According to library, therefore the data information of needs can be transferred from three libraries respectively.
Step 202 screens data information, removes invalid data, and data information is exported in the form of wide table Display.
It specifically may be various types of documents in the data information transferred out, wherein also include many invalid data, For example null value or abnormal data, these data can remove these invalid datas in pretreatment without reference to value.
It is of course also possible to carry out classification or by the data summarization of same type at data module to data, then by data Information is exported with wide sheet form and is shown, auditor is facilitated to consult.
Step 203 reads the N articles audit regulation from default audit regulation table.
The step is identical as the step 102 in the application one embodiment, repeats no more.
Step 204 is extracted and the N articles associated Audit data of audit regulation from data information.
The step is identical as the step 103 in the application one embodiment, repeats no more.
Step 205 sentences formula according to the logic in the N articles audit regulation, calculates corresponding the N articles audit using Audit data and advises Logic operation result then.
The step is identical as the step 104 in the application one embodiment, repeats no more.
If step 206, logic operation result are very, Audit data to be labeled as problem data.
The step is identical as the step 105 in the application one embodiment, repeats no more.
Problem data is output to audit issues inventory by step 207.
Audit data can be convenient auditor's access labeled as problem data, but by the way that problem data to be directly output to In audit issues inventory, problem data after auditor being made more intuitively to be summarized analyze problem data.
Problem data is graphically associated with the N articles audit regulation and exports display by step 208.
The step associates problem data with the audit regulation for finding the problem data, is exported by way of chart It has been shown that, facilitates auditor to check.
Step 209, the N for keeping N+1 new judge the audit regulation item number whether new N is greater than in default audit regulation table, If it is not, return step 103, if so, terminating.
The step is identical as the step 106 in the application one embodiment, repeats no more.
In second embodiment of the application, provides a kind of project under construction and turn fixed assets number auditing method, pass through Audit regulation table is preset, the audit regulation come can will be simply summarized and is described in the form of logic sentences formula.And And each audit regulation is associated with logic and sentences the Audit data for needing to use in formula, therefore when there is audit demand, it can be with It is purposive according to the related information between audit regulation and Audit data, extract examining in the data information of trial engineering It counts.Using the Audit data, formula can be sentenced with arithmetic logic, the logic operation result of obtained this audit regulation.If patrolling It is true for collecting operation result, then it represents that the Audit data does not meet audit regulation, is suspectable data, therefore be marked as Problem data facilitates the secondary audit of auditor.
Compared to one embodiment, data information has been carried out pretreatment and will by second embodiment provided by the present application Data information is aggregated into Output of for ms, also graphically carries out table with the form of audit issues inventory for problem data It is existing, apparent intuitive for auditor, its convenient audit work.
Method provided by the embodiments of the present application realizes the audit of the digitlization to engineering project data, careful by presetting Rule list is counted, makes to turn compliance audit in solid audit work and is audited by computer generation, and auditor only needs to examine default Rest part not to be covered is audited in meter rule list, and audit work amount greatly reduces, and is mitigating auditor's operating pressure While also improve the efficiency of audit.
The above are second implementations for turning fixed assets number auditing method to a kind of project under construction provided by the present application The detailed description of example, refers to Fig. 3 below, and Fig. 3 is that a kind of project under construction provided by the present application turns the audit of fixed assets numberization The flow chart of one embodiment of device, the device include:
Module 301 is reset, the initial value for presetting N is 1.
Data transfer module 302, for according to the audit demand that gets, from transferred in database in audit demand The associated data information of trial engineering;
Read module 303, for reading the N articles audit regulation from default audit regulation table;
Extraction module 304, for being extracted and the N articles associated Audit data of audit regulation from data information;
Logical operation module 305 utilizes Audit data calculating pair for sentencing formula according to the logic in the N articles audit regulation Answer the logic operation result of the N articles audit regulation;
Mark module 306, if being very, Audit data to be labeled as problem data for logic operation result;
Cycle criterion module 307, the N for keeping N+1 new judge whether new N is greater than in default audit regulation table Audit regulation item number, if it is not, S2 is returned to, if so, terminating.
Further, further includes: audit issues inventory generation module 308, for problem data to be output to audit issues Inventory.
Further, further includes: chart generating module 309, for by problem data and the N articles audit regulation with chart Form is associated with and exports display.
This application provides one embodiment that a kind of project under construction turns fixed assets number audit device, by pre- Audit regulation table is first set, the audit regulation come can will be simply summarized and is described in the form of logic sentences formula.Also, Each audit regulation is associated with logic and sentences the Audit data for needing to use in formula, therefore when there is audit demand, Ke Yiyou Purpose according to the related information between audit regulation and Audit data, extract the audit in the data information of trial engineering Data.Using the Audit data, formula can be sentenced with arithmetic logic, the logic operation result of obtained this audit regulation.If logic Operation result is true, then it represents that the Audit data does not meet audit regulation, is suspectable data, therefore be marked as asking Data are inscribed, the secondary audit of auditor is facilitated.
It can be seen that device provided by the embodiments of the present application realizes the audit of the digitlization to engineering project data, by setting in advance Determine audit regulation table, makes to turn compliance audit in solid audit work and audited by computer generation, and auditor only needs to veritify The corresponding objective evidence of problem data, audit work amount greatly reduce, and also improve while mitigating auditor's operating pressure The efficiency of audit.
It is apparent to those skilled in the art that for convenience and simplicity of description, the module of foregoing description Specific work process, can refer to corresponding processes in the foregoing method embodiment, details are not described herein.
The embodiment of the present application also provides a kind of computer readable storage medium, for storing program code, the program code Turn appointing in fixed assets number auditing method for executing a kind of project under construction described in each embodiment of preceding method It anticipates a kind of embodiment.
The description of the present application and term " first " in above-mentioned attached drawing, " second ", " third ", " the 4th " etc. are (if deposited ) it is to be used to distinguish similar objects, without being used to describe a particular order or precedence order.It should be understood that use in this way Data are interchangeable under appropriate circumstances, so that embodiments herein described herein for example can be in addition to illustrating herein Or the sequence other than those of description is implemented.In addition, term " includes " and " having " and their any deformation, it is intended that Cover it is non-exclusive include, for example, containing the process, method, system, product or equipment of a series of steps or units need not limit In step or unit those of is clearly listed, but may include be not clearly listed or for these process, methods, produce The other step or units of product or equipment inherently.
It should be appreciated that in this application, " at least one (item) " refers to one or more, and " multiple " refer to two or two More than a."and/or" indicates may exist three kinds of relationships, for example, " A and/or B " for describing the incidence relation of affiliated partner It can indicate: only exist A, only exist B and exist simultaneously tri- kinds of situations of A and B, wherein A, B can be odd number or plural number.Word Symbol "/" typicallys represent the relationship that forward-backward correlation object is a kind of "or"." at least one of following (a) " or its similar expression, refers to Any combination in these, any combination including individual event (a) or complex item (a).At least one of for example, in a, b or c (a) can indicate: a, b, c, " a and b ", " a and c ", " b and c ", or " a and b and c ", and wherein a, b, c can be individually, can also To be multiple.
In several embodiments provided herein, it should be understood that disclosed device and method can pass through it Its mode is realized.For example, the apparatus embodiments described above are merely exemplary, for example, the division of the unit, only Only a kind of logical function partition, there may be another division manner in actual implementation, such as multiple units or components can be tied Another system is closed or is desirably integrated into, or some features can be ignored or not executed.Another point, it is shown or discussed Mutual coupling, direct-coupling or communication connection can be through some interfaces, the INDIRECT COUPLING or logical of device or unit Letter connection can be electrical property, mechanical or other forms.
The unit as illustrated by the separation member may or may not be physically separated, aobvious as unit The component shown may or may not be physical unit, it can and it is in one place, or may be distributed over multiple In network unit.It can select some or all of unit therein according to the actual needs to realize the mesh of this embodiment scheme 's.
It, can also be in addition, each functional unit in each embodiment of the application can integrate in one processing unit It is that each unit physically exists alone, can also be integrated in one unit with two or more units.Above-mentioned integrated list Member both can take the form of hardware realization, can also realize in the form of software functional units.
If the integrated unit is realized in the form of SFU software functional unit and sells or use as independent product When, it can store in a computer readable storage medium.Based on this understanding, the technical solution of the application is substantially The all or part of the part that contributes to existing technology or the technical solution can be in the form of software products in other words It embodies, which is stored in a storage medium, including some instructions are used so that a computer Equipment (can be personal computer, server or the network equipment etc.) executes the complete of each embodiment the method for the application Portion or part steps.And storage medium above-mentioned includes: USB flash disk, mobile hard disk, read-only memory (full name in English: Read-Only Memory, english abbreviation: ROM), random access memory (full name in English: Random Access Memory, english abbreviation: RAM), the various media that can store program code such as magnetic or disk.
The above, above embodiments are only to illustrate the technical solution of the application, rather than its limitations;Although referring to before Embodiment is stated the application is described in detail, those skilled in the art should understand that: it still can be to preceding Technical solution documented by each embodiment is stated to modify or equivalent replacement of some of the technical features;And these It modifies or replaces, the spirit and scope of each embodiment technical solution of the application that it does not separate the essence of the corresponding technical solution.

Claims (10)

1. a kind of project under construction turns fixed assets number auditing method characterized by comprising the initial value of default N is 1,
S1: according to the audit demand got, from being transferred in database and the associated number of trial engineering in the audit demand It is believed that breath;
S2: the N articles audit regulation is read from default audit regulation table;
S3: it is extracted and the associated Audit data of the N articles audit regulation from the data information;
S4: sentencing formula according to the logic in the N articles audit regulation, calculates corresponding described the N articles using the Audit data and examines Count the logic operation result of rule;
S5: if the logic operation result is very, the Audit data to be labeled as problem data;
S6: the N for keeping N+1 new judges the audit regulation the item whether new N is greater than in the default audit regulation table Number, if it is not, the S2 is returned to, if so, terminating.
2. a kind of project under construction according to claim 1 turns fixed assets number auditing method, which is characterized in that described After S5 further include:
Described problem data are output to audit issues inventory.
3. a kind of project under construction according to claim 1 turns fixed assets number auditing method, which is characterized in that described After S5 further include:
Described problem data are graphically associated with the N articles audit regulation and export display.
4. according to power to go 1 described in a kind of project under construction turn fixed assets number auditing method, which is characterized in that it is described S1 is specifically included:
According to the audit demand got, transfers from goods and materials database, financial database and project database and examined with described The associated data information of trial engineering in meter demand.
5. a kind of project under construction according to claim 1 turns fixed assets number auditing method, which is characterized in that described After S1 further include:
The data information is screened, invalid data is removed.
6. a kind of project under construction according to claim 5 turns fixed assets number auditing method, which is characterized in that described The data information is screened, after removal invalid data further include:
The data information is exported to display in the form of wide table.
7. a kind of project under construction turns fixed assets number audit device characterized by comprising
Module is reset, the initial value for presetting N is 1;
Data transfer module, for according to the audit demand that gets, from transferred in database in the audit demand to Examine the associated data information of engineering;
Read module, for reading the N articles audit regulation from default audit regulation table;
Extraction module, for being extracted and the associated Audit data of the N articles audit regulation from the data information;
Logical operation module utilizes Audit data calculating pair for sentencing formula according to the logic in the N articles audit regulation Answer the logic operation result of the N articles audit regulation;
Mark module, if being very, the Audit data to be labeled as problem data for the logic operation result;
Cycle criterion module, the N for keeping N+1 new, judges whether the new N is greater than the default audit regulation table In audit regulation item number, if it is not, return to the S2, if so, terminating.
8. a kind of project under construction according to claim 7 turns fixed assets number audit device, which is characterized in that also wrap It includes:
Audit issues inventory generation module, for described problem data to be output to audit issues inventory.
9. a kind of project under construction according to claim 7 turns fixed assets number audit device, which is characterized in that also wrap It includes:
Chart generating module, for described problem data to be graphically associated with and exported with the N articles audit regulation Display.
10. a kind of computer readable storage medium, which is characterized in that the computer readable storage medium is for storing program generation Code, said program code require the described in any item projects under construction of 1-6 to turn fixed assets number auditing party for perform claim Method.
CN201811475736.9A 2018-12-04 2018-12-04 A kind of project under construction turns fixed assets number auditing method and device Pending CN109598484A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811475736.9A CN109598484A (en) 2018-12-04 2018-12-04 A kind of project under construction turns fixed assets number auditing method and device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811475736.9A CN109598484A (en) 2018-12-04 2018-12-04 A kind of project under construction turns fixed assets number auditing method and device

Publications (1)

Publication Number Publication Date
CN109598484A true CN109598484A (en) 2019-04-09

Family

ID=65961046

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811475736.9A Pending CN109598484A (en) 2018-12-04 2018-12-04 A kind of project under construction turns fixed assets number auditing method and device

Country Status (1)

Country Link
CN (1) CN109598484A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110532302A (en) * 2019-08-30 2019-12-03 广西电网有限责任公司南宁供电局 Auditing method, system and readable storage medium storing program for executing
CN111709651A (en) * 2020-06-18 2020-09-25 江西财经职业学院 Digital auditing method and device for converting construction project into fixed asset
CN112884442A (en) * 2021-03-01 2021-06-01 广东铭太信息科技有限公司 Audit monitoring data acquisition method and system based on audit model
CN113052547A (en) * 2020-12-30 2021-06-29 宁波东海蓝帆科技有限公司 Capital transfer management method and management system for construction project in petrochemical industry
CN115794803A (en) * 2023-01-30 2023-03-14 北京至臻云智能科技有限公司 Engineering audit problem monitoring method and system based on big data AI technology
CN117541173A (en) * 2023-10-31 2024-02-09 青矩技术股份有限公司 Forensic sheet generation method, forensic sheet generation device, forensic sheet generation equipment and computer-readable storage medium

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20060248591A1 (en) * 2005-05-02 2006-11-02 Christopher Day Information security auditing and incident investigation system
CN103049708A (en) * 2012-12-27 2013-04-17 华为技术有限公司 Audit configuration method and audit configuration system for database
CN107506383A (en) * 2017-07-25 2017-12-22 中国建设银行股份有限公司 A kind of audit data processing method and computer equipment

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20060248591A1 (en) * 2005-05-02 2006-11-02 Christopher Day Information security auditing and incident investigation system
CN103049708A (en) * 2012-12-27 2013-04-17 华为技术有限公司 Audit configuration method and audit configuration system for database
CN107506383A (en) * 2017-07-25 2017-12-22 中国建设银行股份有限公司 A kind of audit data processing method and computer equipment

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110532302A (en) * 2019-08-30 2019-12-03 广西电网有限责任公司南宁供电局 Auditing method, system and readable storage medium storing program for executing
CN110532302B (en) * 2019-08-30 2024-01-19 广西电网有限责任公司南宁供电局 Audit method, system and readable storage medium
CN111709651A (en) * 2020-06-18 2020-09-25 江西财经职业学院 Digital auditing method and device for converting construction project into fixed asset
CN113052547A (en) * 2020-12-30 2021-06-29 宁波东海蓝帆科技有限公司 Capital transfer management method and management system for construction project in petrochemical industry
CN112884442A (en) * 2021-03-01 2021-06-01 广东铭太信息科技有限公司 Audit monitoring data acquisition method and system based on audit model
CN112884442B (en) * 2021-03-01 2024-05-03 广东铭太信息科技有限公司 Audit monitoring data acquisition method and system based on audit model
CN115794803A (en) * 2023-01-30 2023-03-14 北京至臻云智能科技有限公司 Engineering audit problem monitoring method and system based on big data AI technology
CN117541173A (en) * 2023-10-31 2024-02-09 青矩技术股份有限公司 Forensic sheet generation method, forensic sheet generation device, forensic sheet generation equipment and computer-readable storage medium

Similar Documents

Publication Publication Date Title
CN109598484A (en) A kind of project under construction turns fixed assets number auditing method and device
CN103154991B (en) Credit risk is gathered
US8170998B2 (en) Methods, systems, and computer program products for estimating accuracy of linking of customer relationships
US9075848B2 (en) Methods, systems, and computer program products for generating data quality indicators for relationships in a database
CN109754200A (en) Bill of material management method, apparatus and computer readable storage medium
CN104636338B (en) A kind of data cleansing storage method for the monitoring of value-added tax negative and positive ticket
CN107688591A (en) A kind of actuarial treating method and apparatus
CN108711104A (en) Physical assets information flow method, apparatus and equipment based on block chain
CN109815480B (en) Data processing method and device and storage medium
CN106651575A (en) Data processing method and device
CN108062632A (en) Methods of risk assessment and device, equipment and storage medium
CN106951913A (en) The method for carrying out data exchange, cloud platform and system
Aksoy et al. Artificial intelligence in computer-aided auditing techniques and technologies (CAATTs) and an application proposal for auditors
Hu Predicting and improving invoice-to-cash collection through machine learning
Kumar et al. Achieving market segmentation from B2B insurance client data using RFM & K-Means Algorithm
Du et al. Automated fashion size normalization
CN110458581A (en) Merchant business turnover abnormal recognition methods and device
Huang et al. A framework for analyzing the US coin supply chain
CN108763233A (en) The method and apparatus of the identification of doubtful fake products commodity and classification based on big data
CN112053217A (en) Financial valuation statement generation method and device
Jericevich et al. Comparing the market microstructure between two South African exchanges
JP6279782B1 (en) Information processing terminal, information processing method, and program
CN112633936A (en) Supplier hidden cost prediction method, supplier hidden cost prediction device, server and storage medium
Khan et al. Computer-aided process planning in prismatic shape die components based on Standard for the Exchange of Product model data
Purohit et al. Data mining, applications and knowledge discovery

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190409