CN109680810A - The switching node and construction method of upper layer steel pipe column and lower layer's reinforced column - Google Patents

The switching node and construction method of upper layer steel pipe column and lower layer's reinforced column Download PDF

Info

Publication number
CN109680810A
CN109680810A CN201910150487.4A CN201910150487A CN109680810A CN 109680810 A CN109680810 A CN 109680810A CN 201910150487 A CN201910150487 A CN 201910150487A CN 109680810 A CN109680810 A CN 109680810A
Authority
CN
China
Prior art keywords
column
steel pipe
upper layer
reinforced
pipe column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910150487.4A
Other languages
Chinese (zh)
Other versions
CN109680810B (en
Inventor
樊健生
高劲洋
聂鑫
陶慕轩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tsinghua University
Original Assignee
Tsinghua University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tsinghua University filed Critical Tsinghua University
Priority to CN201910150487.4A priority Critical patent/CN109680810B/en
Publication of CN109680810A publication Critical patent/CN109680810A/en
Application granted granted Critical
Publication of CN109680810B publication Critical patent/CN109680810B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/30Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts being composed of two or more materials; Composite steel and concrete constructions
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/185Connections not covered by E04B1/21 and E04B1/2403, e.g. connections between structural parts of different material
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Mechanical Engineering (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

The invention discloses the switching nodes and construction method of a kind of upper layer steel pipe column and lower layer's reinforced column, the switching node is the tie point of upper layer steel pipe column and lower layer's reinforced column, the upper layer steel pipe column is inserted into switching node region, the switching node region is connected with reinforced beam in the horizontal direction, in the switching node region, weld annulate lamella in the inside of the upper layer steel pipe column, and the ring flat-plate is equipped with grout hole, at least side in the inner side and outer side of the upper layer steel pipe column is welded with steel pipe peg, T shape bracket is welded on the outside of the upper layer steel pipe column;The T shape bracket includes: the bracket edge of a wing, and the bracket edge of a wing is horizontally extending;Bracket web, the bracket web are located at the bottom on the bracket edge of a wing and extend downwardly;And bracket peg, the bracket peg are located on the bracket web.The stress performance of the switching node of upper layer steel pipe column according to the present invention and lower layer's reinforced column is good and safe and reliable.

Description

The switching node and construction method of upper layer steel pipe column and lower layer's reinforced column
Technical field
The present invention relates to architectural engineerings and composite structure technical field, more particularly, to a kind of upper layer steel pipe column and lower layer's steel The switching node and construction method of reinforced concrete column.
Background technique
In the related technology, in recent years, it is the knot of steel pipe column for reinforced column, top that many building structure, which use bottom, Configuration formula.On top, what kind of the handover position of steel pipe column and lower rebar concrete column, rc-frame-beam should use Switching node construction is always focus of attention.Existing engineering will be often inserted in concrete column under steel pipe, and underthrust depth is one The height of floor.The way is overly conservative although can guarantee safety of structure, more serious to the waste of steel, and constructs Cumbersome difficulty.For this purpose, how to optimize the structure of the switching node on the basis of guaranteeing that stress performance is good, structure is safe and reliable Make, reduce the underthrust length of steel pipe, and make construction become simple and convenient, be such switching node can obtain more preferably develop answer Key.
Summary of the invention
The present invention is directed at least solve one of the technical problems existing in the prior art.For this purpose, one object of the present invention It is to propose that the switching node of a kind of upper layer steel pipe column and lower layer's reinforced column, the stress performance of the switching node are excellent More, securely and reliably and easy for construction.
It is another object of the present invention to the switching nodes for proposing a kind of upper layer steel pipe column and lower layer's reinforced column Construction method.
The switching node of the upper layer steel pipe column Yu lower layer's reinforced column of embodiment according to a first aspect of the present invention, it is described Switching node is the tie point of upper layer steel pipe column and lower layer's reinforced column, and the upper layer steel pipe column is inserted into switching node area In domain, the switching node region is connected with reinforced beam in the horizontal direction, in the switching node region, the upper layer Annulate lamella is welded in the inside of steel pipe column, and the ring flat-plate is equipped with grout hole, in the inner side and outer side of the upper layer steel pipe column At least side is welded with steel pipe peg, and T shape bracket is welded on the outside of the upper layer steel pipe column;Wherein, the T shape bracket packet Include: the bracket edge of a wing, the bracket edge of a wing are horizontally extending;Bracket web, the bracket web are located at the bracket edge of a wing Bottom and extend downwardly;And bracket peg, the bracket peg are located on the bracket web.
The switching node of upper layer steel pipe column and lower layer's reinforced column according to an embodiment of the present invention, by upper layer steel Annulate lamella is welded in the inside of tubing string, and ring flat-plate is equipped with grout hole, is convenient for by grout hole to the switching node regional perfusion Concrete is conducive to improve the stress performance in the switching node region.In addition, by being welded in the outside of upper layer steel pipe column There is T shape bracket, is conducive to improve the reliability that upper layer steel pipe column is connect with lower layer reinforced column as a result, is conducive to improve The intensity and ductility of switching node.
In addition, the switching node of upper layer steel pipe column according to the above embodiment of the present invention and lower layer reinforced column also has There is following additional technical characteristic:
According to some embodiments of the present invention, the bracket edge of a wing and the ring flat-plate are in the radial direction side of the upper layer steel pipe column It is oppositely arranged upwards.
According to some embodiments of the present invention, the bracket web has first side and second side, first side In face and the second side at least one at be equipped with the bracket peg.
Further, the bracket peg is arranged perpendicular to the bracket web, the bracket peg include it is multiple, it is described Multiple bracket pegs are arranged spaced apart along the vertical direction.
According to some embodiments of the present invention, the cross section of the reinforced beam is in rectangle, the upper layer steel pipe column Be inserted into the depth in the switching node region no more than the reinforced beam along the vertical direction on height;On described The bottom of layer steel pipe column and the bottom of the bracket web are located at the same horizontal position.
Further, lower layer's reinforced column includes that multiple columns indulge muscle, and the multiple column indulges muscle along around described The axis direction arranged for interval of reinforced column, the column are indulged muscle and are arranged within the scope of the ailhead of the steel pipe peg.
Further, when the diameter of the upper layer steel pipe column is less than the diameter of lower layer's reinforced column, institute It states column and indulges the outside that muscle is arranged in the upper layer steel pipe column, at this point, the top that the column indulges muscle is only butted on the bracket edge of a wing Bottom;When the diameter of the upper layer steel pipe column is greater than the diameter of lower layer's reinforced column, the column is indulged muscle and is arranged in The inside of the upper layer steel pipe column, at this point, the bottom for being butted on the ring flat-plate is stopped at the top that the column indulges muscle.
Optionally, the reinforced beam includes upper longitudinal bar and muscle is indulged in lower part, and muscle is indulged in the upper longitudinal bar and lower part Setting parallel and spaced apart, the upper longitudinal bar is welded in the top on the bracket edge of a wing, and the inner end of the upper longitudinal bar is stopped Be butted on the outer side surface of the upper layer steel pipe column, the lower part indulge muscle horizontally pass through lower layer's reinforced column and Penetrate through the reinforced beam.
According to some embodiments of the present invention, the grout hole be circular hole or polygonal hole, the grout hole and it is described on Layer steel pipe column coaxial line;In the switching node region, the inside of the upper layer steel pipe column is perfused with the concrete of predetermined altitude, The predetermined altitude is no more than the diameter of the upper layer steel pipe column.
The upper layer steel pipe column of embodiment and the switching node of lower layer reinforced column are applied according to a second aspect of the present invention Work method, includes the following steps: S10: the steel member for the completion that is prefabricated in the factory being transported to construction site and is installed in place;S20: fixed The column of position lower layer reinforced column indulges muscle, binds the first reinforcing bar of lower layer's reinforced column, first reinforced steel bar ring is around institute It states column and indulges muscle and including the multiple of the setting that is spaced along the longitudinal;S30: the upper longitudinal bar of reinforced beam and the bracket edge of a wing are welded It connects, muscle perforated rebar beams of concrete, the second reinforcing bar of assembling reinforcement beams of concrete are indulged in the lower part of reinforced beam;S40: formwork Plate, casting concrete complete construction.
The present invention has the following advantages that compared with the existing technology and protrudes effect: first, efficiently and rapidly realizing upper layer Steel pipe column and lower layer's reinforced column greatly optimize the way of traditional steel pipe underthrust in the conversion in switching node region, It is easy for construction, save material.Second, the setting of steel corbel (such as T shape bracket etc.) can effectively improve upper layer steel pipe column and lower layer The reliability of reinforced column connection, improves the intensity and ductility of switching node.It is adopted third, column indulges muscle with upper layer steel pipe column With indirect power transmission, cumbersome construction brought by being directly connected to is avoided.Fourth, upper layer steel pipe column is to its joint cores concrete With effect of restraint, it is remarkably improved its stress performance.
Additional aspect and advantage of the invention will be set forth in part in the description, and will partially become from the following description Obviously, or practice through the invention is recognized.
Detailed description of the invention
Above-mentioned and/or additional aspect of the invention and advantage will become from the description of the embodiment in conjunction with the following figures Obviously and it is readily appreciated that, in which:
Fig. 1 is the one of the switching node of upper layer steel pipe column according to an embodiment of the invention and lower layer's reinforced column A schematic diagram, wherein the diameter of upper layer steel pipe column is less than the diameter of lower layer's reinforced column;
Fig. 2 is the sectional view of the I-I line along Fig. 1;
Fig. 3 is the sectional view of the II-II line along Fig. 1;
Fig. 4 is the sectional view of the III-III line along Fig. 1;
Fig. 5 is the switching node of upper layer steel pipe column and lower layer's reinforced column in accordance with another embodiment of the present invention One schematic diagram, wherein the diameter of upper layer steel pipe column is greater than the diameter of lower layer's reinforced column;
Fig. 6 is the sectional view of the I-I line along Fig. 5;
Fig. 7 is the sectional view of the II-II line along Fig. 5;
Fig. 8 is the sectional view of the III-III line along Fig. 5.
Appended drawing reference:
The switching node 100 of upper layer steel pipe column and lower layer's reinforced column,
Upper layer steel pipe column 1, lower layer's reinforced column 2, reinforced beam 3, ring flat-plate 4, grout hole 5, steel pipe peg 6, T Shape bracket 7, the bracket edge of a wing 8, bracket web 9, bracket peg 10, column indulge muscle 11, upper longitudinal bar 12, and muscle 13, concrete are indulged in lower part 14。
Specific embodiment
The embodiment of the present invention is described below in detail, examples of the embodiments are shown in the accompanying drawings, wherein from beginning to end Same or similar label indicates same or similar element or element with the same or similar functions.Below with reference to attached The embodiment of figure description is exemplary, and for explaining only the invention, and is not considered as limiting the invention.
Below with reference to the accompanying drawings the conversion of upper layer steel pipe column and lower layer's reinforced column according to an embodiment of the present invention is described Node 100.
Referring to Fig.1 and Fig. 5, the upper layer steel pipe column Yu lower layer's reinforced column of embodiment according to a first aspect of the present invention Switching node 100, the switching node are the tie point of upper layer steel pipe column 1 and lower layer's reinforced column 2, upper layer steel pipe column 1 It can be coaxially disposed with lower layer reinforced column 2, upper layer steel pipe column 1 is inserted into switching node region, the switching node Region is connected with reinforced beam 3 in the horizontal direction.For example, upper layer steel pipe column 1 can extend along the vertical direction, the level Direction is the axially direction perpendicular to the upper layer steel pipe column 1, in the axial direction of upper layer steel pipe column 1, reinforced beam 3 Top can be higher than the top in the switching node region, and the bottom of reinforced beam 3 can be lower than the switching node The lowermost end in region.
In the switching node region, the inside of upper layer steel pipe column 1 can weld annulate lamella 4, and ring flat-plate 4 can be with rounded plate Shape, ring flat-plate 4 can be arranged around the axis direction of upper layer steel pipe column 1, be conducive to the radial direction in upper layer steel pipe column 1 by ring flat-plate 4 Power transmission on direction, and grout hole 5 can be equipped on ring flat-plate 4.Optionally, ring flat-plate 4 can be steel, and grout hole 5 can be to set Round hole at 4 middle part of ring flat-plate is convenient for being conducive to improve institute to the switching node regional perfusion concrete by grout hole 5 State the stress performance in switching node region.Certainly, in some optional examples of the invention, grout hole 5 can be to be located at Polygonal hole or irregularly-shaped hole on ring flat-plate 4 etc., the present invention are not especially limited the shape of grout hole 5, and the shape of grout hole 5 can With the setting of adaptability according to actual needs.
At least side in the inner side and outer side of upper layer steel pipe column 1 is welded with steel pipe peg 6.For example, some optional In example, the inside that can be upper layer steel pipe column 1 is welded with steel pipe peg 6;In some optional examples, it is also possible to upper layer The outside of steel pipe column 1 is welded with steel pipe peg 6;In some optional examples, can also be upper layer steel pipe column 1 inside and Steel pipe peg 6 is welded in outside.The switching node region and concrete are advantageously ensured that by steel pipe peg 6 as a result, Connection reliability.
In some embodiments of the invention, as shown in Figure 1 and Figure 5, the outside of upper layer steel pipe column 1 can be welded with T shape Bracket 7;Wherein, T shape bracket 7 includes: the bracket edge of a wing 8, bracket web 9 and bracket peg 10.
Specifically, the bracket edge of a wing 8 can be horizontally extending;For example, reinforced beam 3 can be along shown in Fig. 1 Horizontal direction extend, the bracket edge of a wing 8 can be extended in the same direction with reinforced beam 3.Bracket web 9 is located at the bracket edge of a wing 8 Bottom, and bracket web 9 can extend downwardly;Bracket peg 10 is located on bracket web 9.As a result, by the conversion T shape bracket 7 is arranged in node region, can effectively improve the reliability that upper layer steel pipe column 1 is connect with lower layer reinforced column 2, have Conducive to the intensity and ductility for improving switching node.
For example, referring to Fig. 3 and Fig. 7, the outside of upper layer steel pipe column 1 can be welded with two T shape brackets 7, it is preferable that two T shape bracket 7, in this way can be with force balance, to be conducive to further mention in the diametrically opposed setting of upper layer steel pipe column 1 The reliability that high upper layer steel pipe column 1 is connect with lower layer reinforced column 2.
Wherein, " peg " belongs to a kind of fastener of high-intensitive rigidity connection, is used in various structural steelworks, in difference Stiff assembly connection function is played in connector.
The switching node 100 of upper layer steel pipe column according to an embodiment of the present invention and lower layer's reinforced column, by upper Annulate lamella 4 is welded in the inside of layer steel pipe column 1, and ring flat-plate 4 is equipped with grout hole 5, is convenient for by grout hole 5 to the switching node Regional perfusion concrete is conducive to improve the stress performance in the switching node region.In addition, by upper layer steel pipe column 1 Outside be welded with T shape bracket 7, be conducive to improve as a result, upper layer steel pipe column 1 connect with lower layer reinforced column 2 it is reliable Property, be conducive to the intensity and ductility that improve switching node.
As shown in Figure 1, according to some embodiments of the present invention, the bracket edge of a wing 8 and ring flat-plate 4 can be in upper layer steel pipe columns 1 It is oppositely arranged in the radial direction.For example, upper layer steel pipe column 1 in the radial direction, the bracket edge of a wing 8 and ring flat-plate 4 opposite can be set It sets;On the axial direction of upper layer steel pipe column 1, ring flat-plate 4 and the bracket edge of a wing 8 are contour.Be conducive in transmitting by ring flat-plate 4 as a result, Layer steel pipe column 1 pulling force in radial directions, to advantageously ensure that upper layer steel pipe column 1 is connect with lower layer reinforced column 2 Reliability.
The invention is not limited thereto, and in some alternative embodiments, the bracket edge of a wing 8 and ring flat-plate 4 can also be in upper layer steel pipes The preset distance that is staggered on the axial direction of column 1 setting.
In conjunction with Fig. 4 and Fig. 8, according to some embodiments of the present invention, bracket web 9 has first side and second side, In first side and second side at least one at be equipped with bracket peg 10.Further, bracket peg 10 can be perpendicular to ox Leg web 9 is arranged, and for bracket peg 10 including multiple, multiple bracket pegs 10 are arranged spaced apart along the vertical direction.For example, some In optional example, it can be and be equipped with bracket peg 10 in first side;In some optional examples, it is also possible to second Side is equipped with bracket peg 10;In some optional examples, it can also be and be equipped with bracket in first side and second side Peg 10.
Referring to Fig. 4 and Fig. 1 is combined, according to some embodiments of the present invention, the cross section of reinforced beam 3 can be in square Shape (such as rectangular), upper layer steel pipe column 1 are inserted into the depth in the switching node region no more than (e.g., less than or equal to) Reinforced beam 3 along the vertical direction on height.It can make the bottom of upper layer steel pipe column 1 and reinforced beam 3 in this way Inner bottom surface is spaced apart, structurally reasonable.Optionally, the bottom of upper layer steel pipe column 1 and the bottom of bracket web 9 can be located at same water Prosposition is set.
Further, referring to Fig. 3 and Fig. 7, lower layer's reinforced column 2 may include that multiple columns indulge muscle 11, and multiple columns are vertical Muscle 11 can indulge the ailhead model that muscle 11 is arranged in steel pipe peg 6 along the axis direction arranged for interval around reinforced column 2, column In enclosing.It is arranged within the scope of the ailhead of steel pipe peg 6 by the way that column is indulged muscle 11 as a result, is conducive to preferably power transmission, to guarantee The stress of upper layer steel pipe column 1 is effectively transferred to column and indulges muscle 11.In addition, column, which indulges muscle 11, uses indirect power transmission with upper layer steel pipe column 1, keep away Exempt to be directly connected to brought cumbersome construction, has simplified work progress.
Further, referring to Fig.1, when the diameter of upper layer steel pipe column 1 is less than the diameter of lower layer's reinforced column 2, Column indulges the outside that muscle 11 is arranged in upper layer steel pipe column 1, at this point, the top that column indulges muscle 11 can only be butted on the bottom on the bracket edge of a wing 8. Referring to Fig. 5, when the diameter of upper layer steel pipe column 1 is greater than the diameter of lower layer's reinforced column 2, column indulges muscle 11 and is arranged in upper layer steel The inside of tubing string 1, at this point, the top that the column indulges muscle 11 can only be butted on the bottom of the ring flat-plate 4.Be conducive to as a result, more preferable Ground power transmission, and different construction requirements can be met.
Optionally, referring to Fig.1 with Fig. 4 (or referring to Fig. 5 and Fig. 8), reinforced beam 3 includes upper longitudinal bar 12 and lower part Vertical muscle 13, the T shape bracket 7 can be located at upper longitudinal bar 12 and lower part is indulged between muscle 13, and muscle 13 is indulged in upper longitudinal bar 12 and lower part Parallel and be spaced apart setting, upper longitudinal bar 12 is welded in the top on the bracket edge of a wing 8, and inner end (such as the top of upper longitudinal bar 12 The side of the center line of the neighbouring upper layer steel pipe column 1 of vertical muscle 12) it is only butted on the outer side surface of upper layer steel pipe column 1, muscle 13 is indulged in lower part Horizontally pass through lower layer's reinforced column 2 and perforated rebar beams of concrete 3.For example, adjacent column indulge muscle 11 it Between have gap, lower part indulge muscle 13 can horizontally pass through the column on lower layer's reinforced column 2 indulge muscle 11 between sky Gap, and lower part indulge muscle 13 in the horizontal direction on length can be with the equal length of reinforced beam 3.
According to some embodiments of the present invention, referring to Fig. 2 and Fig. 6, grout hole 5 can be circular hole or polygonal hole etc., fill It starches hole 5 and upper layer steel pipe column 1 can be with coaxial line;For example, the axis of grout hole 5 can be coaxial with the axis of upper layer steel pipe column 1;When When grout hole 5 is polygon, the axis of the grout hole 5 can be the maximum circumscribed circle of polygon or the axis of minimum inscribed circle Line, this will be understood by one skilled in the art.
In the switching node region, the inside of upper layer steel pipe column 1 is perfused with the concrete 14 of predetermined altitude, described predetermined Height is no more than the diameter of upper layer steel pipe column 1.For example, the height that the inside of upper layer steel pipe column 1 is perfused with concrete 14 can be small In or equal to upper layer steel pipe column 1 diameter.Be conducive to save material as a result, and upper layer steel pipe column 1 is to the switching node The concrete in region has effect of restraint, is remarkably improved its stress performance.
The upper layer steel pipe column of embodiment and the switching node of lower layer reinforced column are applied according to a second aspect of the present invention Work method, includes the following steps: S10: the steel member for the completion that is prefabricated in the factory being transported to construction site and is installed in place;The steel Component includes all components other than concrete;S20: the column of positioning lower layer's reinforced column indulges muscle, binds lower layer's steel First reinforcing bar of reinforced concrete column, first reinforced steel bar ring indulges muscle around the column, and first reinforcing bar may include along vertical To the multiple of setting spaced apart;S30: the upper longitudinal bar of reinforced beam and the bracket edge of a wing are welded, reinforced beam Indulge muscle perforated rebar beams of concrete, the second reinforcing bar of assembling reinforcement beams of concrete in lower part;S40: formwork supporting plate, casting concrete are complete At construction.
The construction method of the switching node of upper layer steel pipe column according to an embodiment of the present invention and lower layer's reinforced column, knot Structure is simple, reasonable stress, and all steel members can be prefabricated in the factory, assembled in situ, can effectively improve holding for switching node Loading capability and anti-seismic performance.
The upper layer steel pipe column 1 of the embodiment of the present invention and the switching node 100 of lower layer's reinforced column 2.The conversion section The top of point uses steel pipe column, and bottom is reinforced column, and switching node horizontal direction is connected with reinforced beam 3.? The bottom of upper layer steel pipe column 1 is welded with T shape bracket 7, and upper layer steel pipe column 1 and T shape bracket 7 are inserted into the coagulation in switching node region In soil.It is uniformly distributed that steel pipe peg 6, the first side of bracket web 9 and second side are welded with inside and outside upper layer steel pipe column 1 It is equipped with bracket peg 10, can guarantee the reliability connected with concrete in this way.On upper layer, ring flat-plate 4 is arranged in the inside of steel pipe column 1 To transmit the pulling force of the upper longitudinal bar 12 of reinforced beam 3, the pouring in order to concrete of grout hole 5 is offered on ring flat-plate 4. The upper longitudinal bar 12 of reinforced beam 3 is welded in the bracket edge of a wing 8, and muscle 13 is indulged along full Liang Guantong in the lower part of reinforced beam 3. The column of lower layer's reinforced column 2 indulges the bottom that muscle 11 extends upwardly to the bracket edge of a wing 8, and the column indulges muscle 11 and is arranged in steel pipe bolt Within the scope of the ailhead of nail 6, guarantee that the stress of upper layer steel pipe column 1 is effectively transferred to column and indulges muscle 11.Upper layer steel pipe column 1 is located at described turn The inside for changing the part on node region can be with concrete perfusion 14, so that the connection of upper layer steel pipe column 1 and concrete 14 is more It is reliable.Upper layer steel pipe column 1, T shape bracket 7, ring flat-plate 4 and peg (including steel pipe peg 6 and bracket peg 10) are in factory It is prefabricated, upper layer steel pipe column 1 is lifted in place when construction, binds the reinforcing bar (such as first reinforcing bar) of lower layer's reinforced column, this It welds afterwards, the reinforcing bar (such as second reinforcing bar) of assembling reinforcement beams of concrete, formwork supporting plate, casting concrete is applied to complete node Work.The switching node 100 of upper layer steel pipe column according to an embodiment of the present invention and lower layer's reinforced column, stress performance is good, Simple structure, it is easy for construction, there is significant technical economic benefit.
The switching node 100 and construction method of upper layer steel pipe column according to an embodiment of the present invention and lower layer's reinforced column Other constitute and operation be all for those of ordinary skills it is known, for example, unmentioned in the application The structure or method of switching node 100 and construction method about upper layer steel pipe column and lower layer's reinforced column is referred to often The mode of rule carries out, and is not detailed herein.
In the description of the present invention, it is to be understood that, term " center ", " longitudinal direction ", " transverse direction ", " length ", " width ", " thickness ", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outside", " axis To ", " radial direction ", the orientation or positional relationship of the instructions such as " circumferential direction " be to be based on the orientation or positional relationship shown in the drawings, be only for Convenient for the description present invention and simplify description, rather than the device or element of indication or suggestion meaning there must be specific side Position is constructed and operated in a specific orientation, therefore is not considered as limiting the invention.
In the description of this specification, reference term " one embodiment ", " some embodiments ", " illustrative examples ", The description of " example ", " specific example " or " some examples " etc. means specific features described in conjunction with this embodiment or example, knot Structure, material or feature are included at least one embodiment or example of the invention.In the present specification, to above-mentioned term Schematic representation may not refer to the same embodiment or example.Moreover, specific features, structure, material or the spy of description Point can be combined in any suitable manner in any one or more of the embodiments or examples.
Although an embodiment of the present invention has been shown and described, it will be understood by those skilled in the art that: not A variety of change, modification, replacement and modification can be carried out to these embodiments in the case where being detached from the principle of the present invention and objective, this The range of invention is defined by the claims and their equivalents.

Claims (10)

1. the switching node (100) of a kind of upper layer steel pipe column and lower layer's reinforced column, the switching node is upper layer steel pipe The tie point of column (1) and lower layer's reinforced column (2), which is characterized in that
The upper layer steel pipe column (1) is inserted into switching node region, and the switching node region is connected with steel in the horizontal direction Concrete Beam Reinforced (3), in the switching node region, annulate lamella (4) are welded in the inside of the upper layer steel pipe column (1), and described Ring flat-plate (4) is equipped with grout hole (5), and at least side in the inner side and outer side of the upper layer steel pipe column (1) is welded with steel pipe bolt It follows closely (6), is welded with T shape bracket (7) on the outside of the upper layer steel pipe column (1);
Wherein, the T shape bracket (7) includes:
The bracket edge of a wing (8), the bracket edge of a wing (8) are horizontally extending;
Bracket web (9), the bracket web (9) are located at the bottom of the bracket edge of a wing (8) and extend downwardly;And
Bracket peg (10), the bracket peg (10) are located on the bracket web (9).
2. the switching node (100) of upper layer steel pipe column according to claim 1 and lower layer's reinforced column, feature exists In the bracket edge of a wing (8) being oppositely arranged in the radial direction in the upper layer steel pipe column (1) with the ring flat-plate (4).
3. the switching node (100) of upper layer steel pipe column according to claim 1 or 2 and lower layer's reinforced column, special Sign is, the bracket web (9) has first side and a second side, in the first side and the second side extremely The bracket peg (10) is equipped at few one.
4. the switching node (100) of upper layer steel pipe column according to claim 3 and lower layer's reinforced column, feature exists In, the bracket peg (10) is arranged perpendicular to the bracket web (9), the bracket peg (10) include it is multiple, it is described more A bracket peg (10) is arranged spaced apart along the vertical direction.
5. the switching node (100) of upper layer steel pipe column according to claim 3 and lower layer's reinforced column, feature exists In the cross section of the reinforced beam (3) is in rectangle, and the upper layer steel pipe column (1) is inserted into the switching node region Interior depth be no more than the reinforced beam (3) along the vertical direction on height;
The bottom of the upper layer steel pipe column (1) and the bottom of the bracket web (9) are located at the same horizontal position.
6. the switching node (100) of upper layer steel pipe column according to claim 5 and lower layer's reinforced column, feature exists In lower layer's reinforced column (2) includes that multiple columns indulge muscle (11), and the multiple column indulges muscle (11) along around the reinforcing bar The axis direction arranged for interval of concrete column (2), the column indulge the ailhead range that muscle (11) is arranged in the steel pipe peg (6) It is interior.
7. the switching node (100) of upper layer steel pipe column according to claim 6 and lower layer's reinforced column, feature exists In,
When the diameter of the upper layer steel pipe column (1) is less than the diameter of lower layer's reinforced column (2), the column indulges muscle (11) it is arranged in the outside of the upper layer steel pipe column (1), at this point, the top that the column indulges muscle (11) is only butted on the bracket edge of a wing (8) bottom;
When the diameter of the upper layer steel pipe column (1) is greater than the diameter of lower layer's reinforced column (2), the column indulges muscle (11) it is arranged in the inside of the upper layer steel pipe column (1), at this point, the top that the column indulges muscle (11) is only butted on the ring flat-plate (4) Bottom.
8. the switching node (100) of upper layer steel pipe column according to claim 6 and lower layer's reinforced column, feature exists In the reinforced beam (3) includes that muscle (13) are indulged in upper longitudinal bar (12) and lower part, and the upper longitudinal bar (12) and lower part are vertical Muscle (13) is parallel and is spaced apart setting, and the upper longitudinal bar (12) is welded in the top of the bracket edge of a wing (8), and the top The outer side surface for being butted on the upper layer steel pipe column (1) is stopped in the inner end of vertical muscle (12), and the lower part is indulged muscle (13) and worn in the horizontal direction Cross lower layer's reinforced column (2) and the perforation reinforced beam (3).
9. the switching node (100) of upper layer steel pipe column according to claim 8 and lower layer's reinforced column, feature exists In, the grout hole (5) be circular hole or polygonal hole, the grout hole (5) and upper layer steel pipe column (1) coaxial line;
In the switching node region, the inside of the upper layer steel pipe column (1) is perfused with the concrete (14) of predetermined altitude, described Predetermined altitude is no more than the diameter of the upper layer steel pipe column (1).
10. a kind of conversion section of upper layer steel pipe column according to claim 1 to 9 and lower layer's reinforced column The construction method of point, which comprises the steps of:
S10: the steel member for the completion that is prefabricated in the factory is transported to construction site and is installed in place;
S20: the vertical muscle of the column of positioning lower layer's reinforced column, the first reinforcing bar of binding lower layer's reinforced column, described first Reinforced steel bar ring is around the vertical muscle of the column and including the multiple of the setting that is spaced along the longitudinal;
S30: the upper longitudinal bar of reinforced beam and the bracket edge of a wing are welded, and muscle perforated rebar is indulged in the lower part of reinforced beam Beams of concrete, the second reinforcing bar of assembling reinforcement beams of concrete;
S40: formwork supporting plate, casting concrete complete construction.
CN201910150487.4A 2019-02-28 2019-02-28 Conversion node of upper steel pipe column and lower reinforced concrete column and construction method Active CN109680810B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910150487.4A CN109680810B (en) 2019-02-28 2019-02-28 Conversion node of upper steel pipe column and lower reinforced concrete column and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910150487.4A CN109680810B (en) 2019-02-28 2019-02-28 Conversion node of upper steel pipe column and lower reinforced concrete column and construction method

Publications (2)

Publication Number Publication Date
CN109680810A true CN109680810A (en) 2019-04-26
CN109680810B CN109680810B (en) 2024-04-09

Family

ID=66197029

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910150487.4A Active CN109680810B (en) 2019-02-28 2019-02-28 Conversion node of upper steel pipe column and lower reinforced concrete column and construction method

Country Status (1)

Country Link
CN (1) CN109680810B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111997263A (en) * 2020-07-29 2020-11-27 中国建筑一局(集团)有限公司 Small-section concrete column and large-section steel structure column conversion structure and construction method
CN112095778A (en) * 2020-09-16 2020-12-18 华侨大学 I-shaped steel structure column-beam connecting piece, column-beam connecting structure and construction method
CN112160414A (en) * 2020-09-29 2021-01-01 中建八局科技建设有限公司 Connecting joint of structural column and structural beam of inverted round steel pipe and construction method thereof
CN112227539A (en) * 2020-10-09 2021-01-15 华侨大学 Double-steel-plate-structure column-beam connecting piece, column-beam connecting structure and construction method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06248698A (en) * 1993-02-23 1994-09-06 Kajima Corp Joint structure of square steel pipe or square steel pipe concrete column and beam
CN201835390U (en) * 2010-09-30 2011-05-18 广东杭萧钢构有限公司 Beam-column rigid connection joint for tubular concrete column
CN106545088A (en) * 2016-11-24 2017-03-29 大象建筑设计有限公司 The switching node and implementation of a kind of upper strata concrete column and lower floor's steel core concrete column
CN106638989A (en) * 2017-02-16 2017-05-10 中国建筑设计院有限公司 Steel pipe column and reinforced concrete column reinforced beam switching node and building comprising same
CN106884478A (en) * 2017-03-17 2017-06-23 中铁工程设计咨询集团有限公司 Top flange insertion post interpolation type composite frame structure connecting node, group frame
CN207647032U (en) * 2017-11-14 2018-07-24 中南建筑设计院股份有限公司 A kind of steel core concrete column embedded column base node of band annular bracket
CN109339251A (en) * 2018-11-21 2019-02-15 福建工程学院 A kind of the switching node structure and its construction method of coupled column
CN209989954U (en) * 2019-02-28 2020-01-24 清华大学 Conversion node of upper steel pipe column and lower floor reinforced concrete column

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06248698A (en) * 1993-02-23 1994-09-06 Kajima Corp Joint structure of square steel pipe or square steel pipe concrete column and beam
CN201835390U (en) * 2010-09-30 2011-05-18 广东杭萧钢构有限公司 Beam-column rigid connection joint for tubular concrete column
CN106545088A (en) * 2016-11-24 2017-03-29 大象建筑设计有限公司 The switching node and implementation of a kind of upper strata concrete column and lower floor's steel core concrete column
CN106638989A (en) * 2017-02-16 2017-05-10 中国建筑设计院有限公司 Steel pipe column and reinforced concrete column reinforced beam switching node and building comprising same
CN106884478A (en) * 2017-03-17 2017-06-23 中铁工程设计咨询集团有限公司 Top flange insertion post interpolation type composite frame structure connecting node, group frame
CN207647032U (en) * 2017-11-14 2018-07-24 中南建筑设计院股份有限公司 A kind of steel core concrete column embedded column base node of band annular bracket
CN109339251A (en) * 2018-11-21 2019-02-15 福建工程学院 A kind of the switching node structure and its construction method of coupled column
CN209989954U (en) * 2019-02-28 2020-01-24 清华大学 Conversion node of upper steel pipe column and lower floor reinforced concrete column

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111997263A (en) * 2020-07-29 2020-11-27 中国建筑一局(集团)有限公司 Small-section concrete column and large-section steel structure column conversion structure and construction method
CN111997263B (en) * 2020-07-29 2021-10-08 中国建筑一局(集团)有限公司 Small-section concrete column and large-section steel structure column conversion structure and construction method
CN112095778A (en) * 2020-09-16 2020-12-18 华侨大学 I-shaped steel structure column-beam connecting piece, column-beam connecting structure and construction method
CN112160414A (en) * 2020-09-29 2021-01-01 中建八局科技建设有限公司 Connecting joint of structural column and structural beam of inverted round steel pipe and construction method thereof
CN112227539A (en) * 2020-10-09 2021-01-15 华侨大学 Double-steel-plate-structure column-beam connecting piece, column-beam connecting structure and construction method

Also Published As

Publication number Publication date
CN109680810B (en) 2024-04-09

Similar Documents

Publication Publication Date Title
CN109680810A (en) The switching node and construction method of upper layer steel pipe column and lower layer's reinforced column
CN104831818B (en) The connecting node of precast reinforced concrete beam and superposed column
CN104963415B (en) A kind of round steel pipe binding type steel concrete column and steel beam joint structure
CN108412128A (en) A kind of connection structure of steel core concrete column
CN102071747A (en) Joint of square steel tube concrete column and reinforced concrete floor and production method thereof
CN109113190A (en) A kind of detachable assembling type beam column of steel structure connection structure
CN106917470A (en) The steel tube confinement concrete-filled rectangular steel tube component and its processing method of a kind of sandwich
CN109707055A (en) The switching node and construction method of upper layer steel pipe column and lower layer's reinforced column
CN106869326B (en) The frame system and construction method that hollow steel tube concrete integral node is constituted
CN107724540A (en) Steel plate shear force wall and the attachment structure and its construction method of steel bar girder floor plates
CN109680809A (en) The switching node and construction method of upper layer steel pipe column and lower layer's reinforced column
CN110424548A (en) A kind of steel core concrete column-arch without beam connecting node and its construction method
CN108265856B (en) Steel plate embedded type PC shear wall splicing node structure
CN106836645A (en) Thin wall concrete post in a kind of prefabricated hollow formula
CN114135000A (en) Assembled beam-column connecting joint partially wrapped with U-shaped steel and construction method thereof
JP2010261270A (en) Composite structure and method for constructing composite structure building
JP2007297861A (en) Joint part structure of bridge pier with pile
CN110630032A (en) Node connecting device for newly adding beam on existing reinforced concrete column beam
CN105040828B (en) A kind of round steel pipe binding type steel concrete column and steel beam joint structure
JP2005155036A (en) Column of building and rigid-frame structure using this column
CN209989954U (en) Conversion node of upper steel pipe column and lower floor reinforced concrete column
CN211286279U (en) Prefabricated section steel concrete column
CN209989955U (en) Conversion node of upper steel pipe column and lower floor reinforced concrete column
CN106869320A (en) Framework and its construction method that coupled column combination beam is constituted
JP2004263501A (en) Beam-column joint structural body

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant