CN109667427A - A kind of beam steel bar colligation constructing structure and construction method - Google Patents

A kind of beam steel bar colligation constructing structure and construction method Download PDF

Info

Publication number
CN109667427A
CN109667427A CN201811637854.5A CN201811637854A CN109667427A CN 109667427 A CN109667427 A CN 109667427A CN 201811637854 A CN201811637854 A CN 201811637854A CN 109667427 A CN109667427 A CN 109667427A
Authority
CN
China
Prior art keywords
beam steel
bar
steel
support rod
constructing structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811637854.5A
Other languages
Chinese (zh)
Inventor
吴文林
孙松尧
金玉林
岳齐贤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NINGBO MCC20 CONSTRUCTION CO Ltd
China MCC20 Group Corp Ltd
Original Assignee
NINGBO MCC20 CONSTRUCTION CO Ltd
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NINGBO MCC20 CONSTRUCTION CO Ltd, China MCC20 Group Corp Ltd filed Critical NINGBO MCC20 CONSTRUCTION CO Ltd
Priority to CN201811637854.5A priority Critical patent/CN109667427A/en
Publication of CN109667427A publication Critical patent/CN109667427A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/12Mounting of reinforcing inserts; Prestressing
    • E04G21/122Machines for joining reinforcing bars
    • E04G21/123Wire twisting tools

Abstract

The present invention provides a kind of beam steel bar colligation constructing structure and construction methods, belong to technical field of building construction;It solves in existing construction method the technical problem that beam steel bar colligation is inconvenient, difficulty is big;The technical solution of the present invention is as follows: a kind of beam steel bar colligation constructing structure, including lifting bracket, there are two and be respectively arranged at both ends above beam forms;Lifting member is connect with lifting bracket top movable;Support rod has more and laterally setting, and more support rods are axially uniformly layed on beam forms, and support rod is used to support the beam steel of pre- binding;After the completion of beam steel is bound in advance, support rod can remove beam forms, and lifting member can connect with pre- binding beam steel and hang in pre- binding beam steel in beam forms;The invention has the benefit that each components can be made and be assembled at the construction field (site), and overall structure is simpler in this constructing structure, makes, is very easy to use, cost is relatively low.

Description

A kind of beam steel bar colligation constructing structure and construction method
Technical field
The invention belongs to technical field of building construction, it is related to a kind of beam steel bar colligation constructing structure and construction method.
Background technique
In present architectural engineering, beam steel bar colligation is usually to carry out after beam forms is built.After template is built, in mould Reinforcing bar is bound in the range of the reserved concrete collar tie beam of plate.It is errorless by inspection after the completion of reinforcing bar binding work, it can be with Directly start the pouring construction of concrete.
This improving bud grafting is more traditional, can directly start pouring for concrete, but actual mechanical process after binding In, the binding work that reinforcing bar is carried out in casting position is reserved in long and narrow template, construction personnel causes since operating space is narrow Difficulty of construction increases, and the binding node of beam steel is inconvenient to handle, and causes to bind quality reduction, the duration is delayed, in addition, narrow Small space carries out binding operation and safety accident easily occurs, and construction safety coefficient is lower, and construction personnel cannot ensure safely.
In conclusion in order to solve above-mentioned construction method, need to design that a kind of binding is convenient, difficulty The higher beam steel bar colligation constructing structure of small and safety coefficient and construction method.
Summary of the invention
A kind of binding is convenient, difficulty is small the purpose of the present invention is in view of the above-mentioned problems existing in the prior art, proposing and The higher beam steel bar colligation constructing structure of safety coefficient.
Object of the invention can be realized by the following technical scheme: a kind of beam steel bar colligation constructing structure, including
Lifting bracket, there are two and be respectively arranged at both ends above beam forms;
Lifting member is connect with lifting bracket top movable;
Support rod has more and laterally setting, and more support rods are axially uniformly layed on beam forms, the support rod It is used to support the beam steel of pre- binding;
After the completion of beam steel is bound in advance, the support rod can remove beam forms, and lifting member can be with pre- binding beam steel It connects and hangs in pre- binding beam steel in beam forms.
In a kind of above-mentioned beam steel bar colligation constructing structure, the lifting bracket includes
Vertical bar, there is two and vertically spaced apart setting, and two vertical bars are respectively arranged at beam forms two sides;
Cross bar is horizontally disposed with and is connected respectively with two vertical bar upper ends, and the cross bar is located above beam forms, lifting member and Cross bar is movably connected;
Brace has two groups, and every group of two braces are obliquely installed and are connected respectively with the two opposite outer wall of vertical bar.
In a kind of above-mentioned beam steel bar colligation constructing structure, the vertical bar is made of fashioned iron, and the cross bar is by I-steel branch Support, the vertical bar and cross bar are welded to connect.
In a kind of above-mentioned beam steel bar colligation constructing structure, the lifting member is by chain block and coupled steel wire Rope composition.
In a kind of above-mentioned beam steel bar colligation constructing structure, the support rod is made of round steel pipe.
Another object of the present invention is in view of the above-mentioned problems existing in the prior art, it is convenient, difficult to propose a kind of binding Spend the higher beam steel bar colligation construction method of small and safety coefficient.
Object of the invention can be realized by the following technical scheme: a kind of beam steel bar colligation construction method, including following Step:
S1, a lifting bracket is respectively placed at endpoint a quarter in the beam form board ends set up;
S2, the equidistant laterally disposed support rod above the beam forms set up;
S3, beam bottom longitudinal reinforcement is laid on support rod;
S4, installation stirrup, and bound with beam longitudinal reinforcement, complete the binding of beam steel;
S5, beam steel is tied up with wirerope immediately below lifting bracket and is reliably connected with chain block;
S6, chain block is pulled, beam steel is sling, steel reinforcement cage lower support bar is removed;
S7, chain block is reversely pulled, beam steel is slowly transferred to predetermined position;
S8, wirerope is removed, lifting bracket is moved at next construction.
Compared with prior art, the invention has the following advantages:
1, in this constructing structure, each components can be made and be assembled at the construction field (site), and overall structure is simpler It is single, it makes, is very easy to use, cost is relatively low.
2, this construction method carries out beam steel bar colligation outside beam forms, after binding, then passes through lifting member for beam Reinforcing bar is integrally hung in beam forms, so that the assembling reinforcement in narrow space is avoided, simpler, beam steel bar colligation matter of constructing Amount is high, high-efficient, substantially reduces the construction period, while also improving the safety of construction personnel.
Detailed description of the invention
Fig. 1 is floor map of the invention
Fig. 2 is the front elevation view of lifting bracket in the present invention.
Fig. 3 is the side elevational view of lifting bracket in the present invention.
In figure, 10, lifting bracket;11, vertical bar;12, cross bar;13, brace;20, lifting member;21, chain block;22, steel Cord;30, support rod;40, beam forms.
Specific embodiment
Following is a specific embodiment of the present invention in conjunction with the accompanying drawings, technical scheme of the present invention will be further described, However, the present invention is not limited to these examples.
As shown in Figure 1, a kind of beam steel bar colligation constructing structure of the present invention, including lifting bracket 10, lifting member 20 and support Bar 30.
There are two lifting brackets 10 and is respectively arranged at 40 top both ends of beam forms, 10 top of lifting member 20 and lifting bracket It is flexibly connected, support rod 30 has more and laterally setting, and more support rods 30 are axial to be uniformly layed on beam forms 40, the branch Strut 30 is used to support the beam steel of pre- binding, and after the completion of beam steel is bound in advance, the support rod 30 can remove beam forms 40, When work, lifting member 20 is connect with the beam steel bound in advance, pre- binding beam steel can be sling and realize pre- tie up by lifting member 20 It pricks beam steel vertical shift and hangs in pre- binding beam steel in beam forms 40.
The present invention is used cooperatively by lifting bracket 10, lifting member 20 and 30 three of support rod, can be outside beam forms 40 Support rod 30 on beam steel is bound in advance, after band beam steel bar colligation, then the beam that will be bound in advance by lifting member 20 Reinforcing bar is hung in beam forms 40, and entire fit structure is comparatively simple, practical, and operation is very easy.
On the basis of the said structure, the present invention is further improved it.
As shown in Figure 2 and Figure 3, the lifting bracket 10 includes vertical bar 11, cross bar 12 and brace 13, vertical bar 11 have two and Vertically spaced apart setting, two vertical bars 11 are respectively arranged at 40 two sides of beam forms, cross bar 12 be transversely and horizontally set and respectively with two vertical bars 11 upper ends are connected, and the cross bar 12 is located at 40 top of beam forms, and lifting member 20 is movably connected with cross bar 12, and brace 13 has two groups, Every group of two braces 13 are obliquely installed and are connected respectively with the two opposite outer wall of vertical bar 11, and entire 10 structure of lifting bracket is by three A component is constituted, and structure is simple, easy for installation, and vertical bar 11 is for undertaking vertical load, and cross bar 12 is for transmitting load, brace 13 are used to support vertical bar 11 and cross bar 12, play the role of stablizing entire lifting bracket 10.
Further, the vertical bar 11 is made of fashioned iron, and the cross bar 12 is by I-shaped bracing members, the vertical bar 11 and cross bar 12 are welded to connect, and fashioned iron and I-steel are construction site common used material, can be on the spot using fashioned iron and I-steel as raw material Materials, so that the production of lifting bracket 10 is very simple and at low cost.
Further, the lifting member 20 is made of chain block 21 and coupled wirerope 22, chain block 21 with the common lifting means of wirerope 22, facilitate realizations, it is convenient to use.
Further, the support rod 30 is made of round steel pipe, and round steel pipe is also the common profile in construction site, can It gathers materials on the spot on building sites, it is easy to use, at low cost.
A kind of beam steel bar colligation construction method, comprising the following steps:
S1, a lifting bracket is respectively placed at endpoint a quarter in the beam form board ends set up;
S2, the equidistant laterally disposed support rod above the beam forms set up;
S3, beam bottom longitudinal reinforcement is laid on support rod;
S4, installation stirrup, and bound with beam longitudinal reinforcement, complete the binding of beam steel;
S5, beam steel is tied up with wirerope immediately below lifting bracket and is reliably connected with chain block;
S6, chain block is pulled, beam steel is sling, steel reinforcement cage lower support bar is removed;
S7, chain block is reversely pulled, beam steel is slowly transferred to predetermined position;
S8, wirerope is removed, lifting bracket is moved at next construction.
The construction method carries out beam steel bar colligation outside beam forms, after binding, then passes through lifting member for joist steel Muscle is integrally hung in beam forms, so that the assembling reinforcement in narrow space is avoided, simpler, beam steel bar colligation quality of constructing It is high, high-efficient, the construction period is substantially reduced, while also improving the safety of construction personnel.
Specific embodiment described herein is only an example for the spirit of the invention.The neck of technology belonging to the present invention The technical staff in domain can make various modifications or additions to the described embodiments or replace by a similar method In generation, however, it does not deviate from the spirit of the invention or beyond the scope of the appended claims.

Claims (6)

1. a kind of beam steel bar colligation constructing structure, including
Lifting bracket, there are two and be respectively arranged at both ends above beam forms;
Lifting member is connect with lifting bracket top movable;
Support rod has more and laterally setting, and more support rods are axially uniformly layed on beam forms, and the support rod is used for Support the beam steel bound in advance;
After the completion of beam steel is bound in advance, the support rod can remove beam forms, and lifting member can be connect with pre- binding beam steel And pre- binding beam steel is hung in beam forms.
2. a kind of beam steel bar colligation constructing structure according to claim 1, it is characterised in that: the lifting bracket includes
Vertical bar, there is two and vertically spaced apart setting, and two vertical bars are respectively arranged at beam forms two sides;
Cross bar is horizontally disposed with and is connected respectively with two vertical bar upper ends, and the cross bar is located above beam forms, lifting member and cross bar It is movably connected;
Brace has two groups, and every group of two braces are obliquely installed and are connected respectively with the two opposite outer wall of vertical bar.
3. a kind of beam steel bar colligation constructing structure according to claim 2, it is characterised in that: the vertical bar is by fashioned iron system At the cross bar is welded to connect by I-shaped bracing members, the vertical bar and cross bar.
4. a kind of beam steel bar colligation constructing structure according to claim 1, it is characterised in that: the lifting member is by pulling calabash Reed and coupled wirerope composition.
5. a kind of beam steel bar colligation constructing structure according to claim 1, it is characterised in that: the support rod is by circular steel Pipe is made.
6. a kind of beam steel bar colligation construction method, comprising the following steps:
S1, a lifting bracket is respectively placed at endpoint a quarter in the beam form board ends set up;
S2, the equidistant laterally disposed support rod above the beam forms set up;
S3, beam bottom longitudinal reinforcement is laid on support rod;
S4, installation stirrup, and bound with beam longitudinal reinforcement, complete the binding of beam steel;
S5, beam steel is tied up with wirerope immediately below lifting bracket and is reliably connected with chain block;
S6, chain block is pulled, beam steel is sling, steel reinforcement cage lower support bar is removed;
S7, chain block is reversely pulled, beam steel is slowly transferred to predetermined position;
S8, wirerope is removed, lifting bracket is moved at next construction.
CN201811637854.5A 2018-12-29 2018-12-29 A kind of beam steel bar colligation constructing structure and construction method Pending CN109667427A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811637854.5A CN109667427A (en) 2018-12-29 2018-12-29 A kind of beam steel bar colligation constructing structure and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811637854.5A CN109667427A (en) 2018-12-29 2018-12-29 A kind of beam steel bar colligation constructing structure and construction method

Publications (1)

Publication Number Publication Date
CN109667427A true CN109667427A (en) 2019-04-23

Family

ID=66147453

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811637854.5A Pending CN109667427A (en) 2018-12-29 2018-12-29 A kind of beam steel bar colligation constructing structure and construction method

Country Status (1)

Country Link
CN (1) CN109667427A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112324153A (en) * 2020-11-05 2021-02-05 中国二十二冶集团有限公司 A reinforcement auxiliary device for job site
CN113775183A (en) * 2021-10-20 2021-12-10 中国十七冶集团有限公司 Assembled adjustable beam steel bar binding bracket for building construction and use method thereof
CN114309366A (en) * 2021-12-28 2022-04-12 中国建筑土木建设有限公司 Automatic arrangement equipment and automatic arrangement method for reinforcing steel bars for beam yard

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104481151A (en) * 2014-11-05 2015-04-01 北京崇建工程有限公司 Beam steel framework and beam column connecting part stirrup binding method
CN204456908U (en) * 2015-02-05 2015-07-08 中国建筑第四工程局有限公司 A kind of heavy beam equipment
CN204552119U (en) * 2015-03-31 2015-08-12 武汉建工集团股份有限公司 A kind of beam ledges founds binding device
CN108862081A (en) * 2018-06-26 2018-11-23 五冶集团上海有限公司 A kind of chain block crane boom and the application in the adjusting of beam steel protective layer thickness
CN210105328U (en) * 2018-12-29 2020-02-21 浙江二十冶建设有限公司 Roof beam reinforcement construction structures

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104481151A (en) * 2014-11-05 2015-04-01 北京崇建工程有限公司 Beam steel framework and beam column connecting part stirrup binding method
CN204456908U (en) * 2015-02-05 2015-07-08 中国建筑第四工程局有限公司 A kind of heavy beam equipment
CN204552119U (en) * 2015-03-31 2015-08-12 武汉建工集团股份有限公司 A kind of beam ledges founds binding device
CN108862081A (en) * 2018-06-26 2018-11-23 五冶集团上海有限公司 A kind of chain block crane boom and the application in the adjusting of beam steel protective layer thickness
CN210105328U (en) * 2018-12-29 2020-02-21 浙江二十冶建设有限公司 Roof beam reinforcement construction structures

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112324153A (en) * 2020-11-05 2021-02-05 中国二十二冶集团有限公司 A reinforcement auxiliary device for job site
CN113775183A (en) * 2021-10-20 2021-12-10 中国十七冶集团有限公司 Assembled adjustable beam steel bar binding bracket for building construction and use method thereof
CN114309366A (en) * 2021-12-28 2022-04-12 中国建筑土木建设有限公司 Automatic arrangement equipment and automatic arrangement method for reinforcing steel bars for beam yard
CN114309366B (en) * 2021-12-28 2023-12-08 中国建筑土木建设有限公司 Automatic arrangement equipment and method for reinforcing steel bars for beam field

Similar Documents

Publication Publication Date Title
CN100545363C (en) Structure conversion layer type steel concrete girder mould suspension construction method
CN109667427A (en) A kind of beam steel bar colligation constructing structure and construction method
CN104153587B (en) A kind of built with ribbed bricks body of wall assembly construction method
CN103935911B (en) Tower crane attached wall supporting construction and construction method thereof
CN107476470A (en) Steel pipe built in assembled and GFRP pipe regeneration concrete compound shear walls and its construction method
CN109537851A (en) A kind of method for prefabricating of assembled pipe well
CN101659082A (en) System for integral binding and integral hoisting of steel bar framework of box beam and construction method thereof
CN105863253A (en) Integral formwork-supporting type asynchronous casting stairwell wall column formwork supporting system and construction method
CN104175398B (en) Make the mold and method of prefabricated case beam framework of steel reinforcement
CN107254933A (en) The high-rise single through hole precast shear wall of assembled and its assembling structure and construction method
CN207714310U (en) A kind of lowering device for reinforcing cage
CN205348761U (en) Basement does not have reinforced structure of no basic lift of installation on back board
CN207436503U (en) Efficient construction of precast floorslab hangs membrane module
CN206844444U (en) A kind of steel bar girder concrete hollow building roof based on non-dismantling formwork
CN106639328B (en) Concrete beam steel reinforcement framework construction device and construction method
CN210597882U (en) Lattice type steel reinforced concrete combined column beam column node
CN105370027B (en) The construction method of steel supporting platform structure is integrally lifted in high-rise hanging structure
CN201511439U (en) System for integrally binding and hoisting box girder steel reinforcement framework
CN104164882A (en) Construction method for building support structural beam foundation on slope and structure thereof
CN208294079U (en) A kind of detachable set shaped steel formwork concrete operating platform
CN202401026U (en) Construction equipment for installing flue elbow pipe through pulley lifting
CN210105328U (en) Roof beam reinforcement construction structures
CN211473348U (en) Scaffold wall connecting piece
CN109469083B (en) Foundation beam reinforcement cage assembling system and construction method thereof
CN209066488U (en) A kind of mass concrete invert reinforcing steel support system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
CB02 Change of applicant information

Address after: 315 800 Pearl River Road 429 Xindan Street, Beilun District, Ningbo City, Zhejiang Province

Applicant after: Zhejiang 20 Smelter Construction Co.,Ltd.

Applicant after: CHINA MCC20 GROUP Corp.,Ltd.

Address before: 315 800 Pearl River Road 429 Xindan Street, Beilun District, Ningbo City, Zhejiang Province

Applicant before: NINGBO MCC 20 CONSTRUCTION Co.,Ltd.

Applicant before: CHINA MCC20 GROUP Corp.,Ltd.

CB02 Change of applicant information
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190423

RJ01 Rejection of invention patent application after publication