CN109653527A - 一种建筑结构中间层竖向及水平构件置换方法 - Google Patents
一种建筑结构中间层竖向及水平构件置换方法 Download PDFInfo
- Publication number
- CN109653527A CN109653527A CN201811594239.0A CN201811594239A CN109653527A CN 109653527 A CN109653527 A CN 109653527A CN 201811594239 A CN201811594239 A CN 201811594239A CN 109653527 A CN109653527 A CN 109653527A
- Authority
- CN
- China
- Prior art keywords
- channel steel
- horizontal member
- vertical
- middle layer
- building structure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
- E04G23/0218—Increasing or restoring the load-bearing capacity of building construction elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
- E04G23/0218—Increasing or restoring the load-bearing capacity of building construction elements
- E04G23/0222—Replacing or adding wall ties
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Chemical & Material Sciences (AREA)
- Chemical Kinetics & Catalysis (AREA)
- Electrochemistry (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
本发明公开了一种建筑结构中间层竖向及水平构件置换方法,所述中间层竖向及水平构件通过在剪力墙(2)上布置的导力架(1)来进行置换,其特征在于:所述导力架(2)具体布置步骤如下:1)先竖向布置导力架(2),所述导力架包括缀板(4)、双肢槽钢(5)、加劲板(6),所述双肢槽钢(5)上连接有缀板(4),所述双肢槽钢(5)内连接有加劲板(6)。本发明采用导力架设计,通过导力架布置,解决了全部构件的置换问题,具有无需拆除上部结构中质量符合要求的部分,较大降低工程造价,大幅减少施工工程量,减少施工工期,满足业主竣工时间要求,大幅减少拆除的构件,减少建筑垃圾,减少环境污染等优点。
Description
技术领域
本发明涉及一种工具,尤其涉及一种建筑结构中间层竖向及水平构件置换方法。
背景技术
目前,高层住宅施工过程中,当商品混凝土质量不达标时,会造成所供的该批次混凝土构件质量都有问题,结构承载力不满足安全要求,此类情况常有发生,通常采用全部拆除重建的办法处理。但当结构施工到很高的楼层高度,发现下部部分楼层构件质量有问题时,处理起来就很棘手,此时采用全部拆除重建的办法,不仅大大影响建设工期,无法满足业主的交付节点,同时大大增加工程造价,废弃建筑垃圾造成环境污染,对整个工程建设将会造成很多负面问题,如果延期交房,还可能导致小区业主上访,甚至造成社会群体上访事件,影响社会稳定。
发明内容
本发明提供了一种采用导力架设计,通过竖向导力架布置,解决建筑结构中间层竖向及水平构件置换方法。
为解决上述技术问题,本发明提供一种建筑结构中间层竖向及水平构件置换方法,所述中间层竖向及水平构件通过在剪力墙上布置的导力架来进行置换,其特征在于:所述导力架具体布置步骤如下:
1)先竖向布置导力架,在导力架上连接10#槽钢,再在10#槽钢上焊接有短钢筋与缀条,10#槽钢上采用60mm钻头钻有多个钻孔从而在10#槽钢上形成开孔,最后用灌浆料灌实开孔来完成建筑结构中间层竖向构件的置换;
2)之后水平构件置换,通过每一片剪力墙始终保证有一侧楼板固定或一侧部分楼板固定的方法,形成左右前后一隔一棋盘跳跃式置换水平构件。
进一步的,所述10#槽钢与所述短钢筋之间的焊接点形成有围焊层。
进一步的,所述10#槽钢在钻孔前采用钢筋探测仪进行钢筋定位,避免成孔过程对剪力墙墙身钢筋损坏,待缀条与10#槽钢焊接以及10#槽钢腹板收紧后,立即进行灌浆料浇筑。
更进一步的,本发明的方法包括分层分区分段置换方法与拆除一部分等效一部分置换一部分方法,解决了施工期间水平荷载的传递与上部结构的变形问题。
与现有技术相比,本发明的有益效果为:
本发明采用导力架设计,通过先竖向后水平的导力架布置,解决了全部构件的置换问题,具有无需拆除上部结构中质量符合要求的部分,较大降低工程造价,大幅减少施工工程量,减少施工工期,满足业主竣工时间要求,大幅减少拆除的构件,减少建筑垃圾,减少环境污染等优点。
附图说明
图1为本发明置换剪力墙的顺序示意图。
图2为本发明中的导力架布置示意图。
图3为图1中2-2向剖视图。
图4为导力架竖向布置节点放大示意图。
图5为导力架水平布置节点放大示意图。
图6为本发明中的10#槽钢钻孔示意图。
图7为本发明中的10#槽钢采用灌浆料灌实示意图。
图中标号:
1-导力架 2-剪力墙 3-10#槽钢
4-缀板 5-双肢槽钢 6-加劲板
7-短钢筋 8-灌浆料 9-开孔
10-钻孔 11-围焊层。
具形实施方式
下面对结合附图对本发明的较佳实施例作详细阐述,以使本发明的优点和特征能更易于被本领域技术人员理解,从而对本发明的保护范围作出更为清楚明确的界定。
一种建筑结构中间层竖向及水平构件置换方法,如图1中标示的1、2、3、4、5步骤进行分层分区分段置换;
如图2—图7所示,一种建筑结构中间层竖向及水平构件置换方法,所述中间层竖向及水平构件通过在剪力墙2上布置的导力架1来进行置换,所述导力架2具体布置步骤如下:
1)先竖向布置导力架2,在导力架2上连接10#槽钢3,再在10#槽钢3上焊接有短钢筋7与缀条,其10#槽钢3与短钢筋7之间的焊接点形成有围焊层11,10#槽钢3在钻孔前采用钢筋探测仪进行钢筋定位,避免成孔过程对剪力墙墙身钢筋损坏,10#槽钢3上采用60mm钻头钻有多个钻孔10从而在10#槽钢3上形成开孔9,待缀条与10#槽钢3焊接以及10#槽钢3腹板收紧后,立即用灌浆料8灌实开孔9来完成浇筑;
2)之后水平构件置换,通过每一片剪力墙始终保证有一侧楼板固定或一侧部分楼板固定的方法,形成左右前后一隔一棋盘跳跃式置换水平构件。
综上所示,本发明采用导力架设计,通过导力架布置,解决了全部构件的置换问题,具有无需拆除上部质量符合要求的部分,较大降低工程造价,大幅减少施工工程量,减少施工工期,满足业主竣工时间要求,大幅减少拆除的构件,减少建筑垃圾,减少环境污染等优点。
以上所述仅为本发明的较佳实施方式,本发明的保护范围并不以上述实施方式为限,但凡本领域普通技术人员根据本发明所揭示内容所作的等效修饰或变化,皆应纳入权利要求书中记载的保护范围内。
Claims (3)
1.一种建筑结构中间层竖向及水平构件置换方法,所述中间层竖向及水平构件通过在剪力墙(2)上布置的导力架(1)来进行置换,其特征在于:所述导力架(2)具体布置步骤如下:
1)先竖向布置导力架(2),在导力架(2)上连接10#槽钢(3),再在10#槽钢(3)上焊接有短钢筋(7)与缀条,10#槽钢(3)上采用60mm钻头钻有多个钻孔(10)从而在10#槽钢(3)上形成开孔(9),最后用灌浆料(8)灌实开孔(9)来完成建筑结构中间层竖向构件的置换;
2)竖向构件置换完成后,之后水平构件置换,通过每一片剪力墙始终保证有一侧楼板固定或一侧部分楼板固定的方法,形成左右前后一隔一棋盘跳跃式置换水平构件。
2.根据权利要求1所述的一种建筑结构中间层竖向及水平构件置换方法,其特征在于:所述10#槽钢(3)与所述短钢筋(7)之间的焊接点形成有围焊层(11)。
3.根据权利要求1所述的一种建筑结构中间层竖向及水平构件置换方法,其特征在于:所述10#槽钢(3)在钻孔前采用钢筋探测仪进行钢筋定位,避免成孔过程对剪力墙墙身钢筋损坏,待缀条与10#槽钢(3)焊接以及10#槽钢(3)腹板收紧后,立即进行灌浆料浇筑。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811594239.0A CN109653527A (zh) | 2018-12-25 | 2018-12-25 | 一种建筑结构中间层竖向及水平构件置换方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811594239.0A CN109653527A (zh) | 2018-12-25 | 2018-12-25 | 一种建筑结构中间层竖向及水平构件置换方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109653527A true CN109653527A (zh) | 2019-04-19 |
Family
ID=66116717
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811594239.0A Pending CN109653527A (zh) | 2018-12-25 | 2018-12-25 | 一种建筑结构中间层竖向及水平构件置换方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109653527A (zh) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102733429A (zh) * | 2012-06-29 | 2012-10-17 | 广州市胜特建筑科技开发有限公司 | 新修隧道穿越既有建筑物的托换方法及托换系统 |
CN103075020A (zh) * | 2013-02-04 | 2013-05-01 | 广州市胜特建筑科技开发有限公司 | 一种钢托盘支撑传力系统 |
CN103866989A (zh) * | 2013-12-31 | 2014-06-18 | 青建集团股份公司 | 一种竖向结构条形置换加固施工方法 |
CN205348838U (zh) * | 2016-01-22 | 2016-06-29 | 陕西省建筑科学研究院 | 一种剪力墙混凝土置换用支撑装置 |
CN107401232A (zh) * | 2017-08-22 | 2017-11-28 | 天津联鉴建筑质量鉴定检测有限公司 | 一种置换不合格的剪力墙混凝土的托换结构及施工方法 |
-
2018
- 2018-12-25 CN CN201811594239.0A patent/CN109653527A/zh active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102733429A (zh) * | 2012-06-29 | 2012-10-17 | 广州市胜特建筑科技开发有限公司 | 新修隧道穿越既有建筑物的托换方法及托换系统 |
CN103075020A (zh) * | 2013-02-04 | 2013-05-01 | 广州市胜特建筑科技开发有限公司 | 一种钢托盘支撑传力系统 |
CN103866989A (zh) * | 2013-12-31 | 2014-06-18 | 青建集团股份公司 | 一种竖向结构条形置换加固施工方法 |
CN205348838U (zh) * | 2016-01-22 | 2016-06-29 | 陕西省建筑科学研究院 | 一种剪力墙混凝土置换用支撑装置 |
CN107401232A (zh) * | 2017-08-22 | 2017-11-28 | 天津联鉴建筑质量鉴定检测有限公司 | 一种置换不合格的剪力墙混凝土的托换结构及施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
DE112019002113T5 (de) | Struktur zum Senken, Verstärken, Anheben und Nivellieren der Pfahlgründungsplattformstruktur und Bauverfahren dafür | |
CN101899907B (zh) | 钢筋混凝土柱置换加固方法和卸载钢筋混凝土柱负荷装置 | |
CN102383379B (zh) | 一种可调可控的桥墩盖梁加固的工艺方法 | |
CN112343078B (zh) | 一种厂房设备基础精密抬升方法 | |
CN106401207B (zh) | 用于既有建筑增设柱子基础的叠合连接结构及其施工方法 | |
CN106012697A (zh) | 无砟轨道路基高聚物注浆抬升方法 | |
CN108643602A (zh) | 一种适用于混凝土梁柱节点的外包锚钢加固结构 | |
CN204001813U (zh) | 一种既有钢筋混凝土楼板或屋面板加固结构 | |
CN104652293A (zh) | 一种用于加固psc连续箱梁桥的斜拉桥结构及施工方法 | |
CN205444968U (zh) | 一种植筋锚固结构 | |
CN108518084A (zh) | 框架剪力墙结构中剪力墙拆除的附加结构及方法 | |
US11739495B2 (en) | Reinforcing and lifting method and reinforcing and lifting structure for large-scale piers of high-speed rail | |
CN110397305A (zh) | 一种混凝土托换结构及应用其进行缺陷混凝土置换的方法 | |
CN110230314B (zh) | 一种桩基结构及其施工方法 | |
CN206545159U (zh) | 一种道路面层混凝土施工模板 | |
CN109653527A (zh) | 一种建筑结构中间层竖向及水平构件置换方法 | |
CN212742020U (zh) | 一种架空式桩板结构与路堤的过渡段结构 | |
CN201671063U (zh) | 一种施工预制梁用的活动钢底座及其标准节 | |
CN107246037A (zh) | 一种用于桩端砂性土持力层的建筑物纠偏结构及方法 | |
CN107035045A (zh) | 一种预制混凝土双向空心板及其制备方法 | |
CN206562792U (zh) | 用于既有结构加固改造的叠合转换抗扭结构 | |
CN112343105B (zh) | 一种高铁桥墩加固抬升方法 | |
CN113756601B (zh) | 框架柱置换加固施工方法 | |
CN101672020A (zh) | 更换公路桥桥台上板式橡胶支座的钢筋骨架定位法 | |
CN209040151U (zh) | 桩托三层挡土墙结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20190419 |