CN109650088A - A kind of foundry formed coke half-finished product collects storing and transporting system and its working method - Google Patents

A kind of foundry formed coke half-finished product collects storing and transporting system and its working method Download PDF

Info

Publication number
CN109650088A
CN109650088A CN201910100454.9A CN201910100454A CN109650088A CN 109650088 A CN109650088 A CN 109650088A CN 201910100454 A CN201910100454 A CN 201910100454A CN 109650088 A CN109650088 A CN 109650088A
Authority
CN
China
Prior art keywords
chute
gathers materials
hydraulic cylinder
finished product
storage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910100454.9A
Other languages
Chinese (zh)
Inventor
李翔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201910100454.9A priority Critical patent/CN109650088A/en
Publication of CN109650088A publication Critical patent/CN109650088A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65GTRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
    • B65G63/00Transferring or trans-shipping at storage areas, railway yards or harbours or in opening mining cuts; Marshalling yard installations
    • B65G63/008Transferring or trans-shipping at storage areas, railway yards or harbours or in opening mining cuts; Marshalling yard installations for bulk material

Landscapes

  • Intermediate Stations On Conveyors (AREA)

Abstract

The present invention relates to a kind of foundry formed coke half-finished products to collect storing and transporting system and its working method, hoisting mechanism including storage and transportation platform and above storage and transportation platform, the hoisting mechanism is at least one and lower section is connected with suspender, the storage and transportation platform is equipped at least one channel that gathers materials, collection system is provided in the channel that gathers materials, the storage and transportation platform is equipped with the storage and transportation area for being located at the channel side that gathers materials and the traffic zone in front of the channel that gathers materials, foundry formed coke half-finished product can be carried out automatically collecting storage and transport using hoisting mechanism and collection system by the present invention, it can reduce artificial, cost is saved, increase safety guarantee.

Description

A kind of foundry formed coke half-finished product collects storing and transporting system and its working method
Technical field
The present invention relates to the technical field that foundry formed coke half-finished product collects storage and transportation, in particular to a kind of foundry formed coke half-finished products Collect storing and transporting system and its working method.
Background technique
Foundry formed coke half-finished product is mainly subject to binder by agitating and heating by molding machine by raw materials such as anchracite duff, coke powders Molding, foundry formed coke half-finished product have that easily broken, temperature is slightly higher, artificially collect that efficiency is extremely low and also personnel be easy scald, Semi-finished product are frangible;200000 tons/year of foundry formed coke half-finished product production systems calculated according to 330 days every year, need semi-finished product daily extremely It is 600 tons few;20% quantity in stock calculated according to production 20 hours daily then to produce 720 tons daily, to produce 36 per hour Ton, 12 hoppers (3 tons/hopper);Often about 5 tons of platform molding machine output (about 3000 pieces) need 8 molding machines while producing; About 50 pieces per minute of every molding machine semi-finished product produced, 3 people is at least needed to be collected simultaneously material bin;So 8 molding machines Production just needs 24 people to be collected simultaneously material bin simultaneously;Therefore it can not be adapted at all with 200,000 tons/year of mechanization production systems.
In the prior art, in order to realize that foundry formed coke half-finished product is collected, the measure of acquisition has: 1, passing through rubber conveyer reality The transport of existing semi-finished product;2, semifinished product warehouse storage, charging hopper are realized by storage;3, fork truck realizes that hopper transports retort. For such collection means of transportation, disadvantage is that: semi-finished product are easily broken not to can guarantee casting formed coke quality, fork truck fortune It is defeated once to transport a hopper, it is necessary at least 4 fork trucks, while it is constant also not can guarantee bucket location, causes to reach Bad lifting, efficiency are extremely low in retort Lift-on/Lift-off System.
Therefore the prior art can not be also adapted with extensive mechanization semi-finished product production system.
Summary of the invention
In order to solve the above technical problem, the present invention provides a kind of using simple, high degree of automation, high-efficient, anti-broken The good foundry formed coke half-finished product of broken effect collects storing and transporting system and its working method.
The technical scheme is that a kind of foundry formed coke half-finished product collects storing and transporting system, including storage and transportation platform and it is located at Hoisting mechanism above storage and transportation platform, the hoisting mechanism is at least one and lower section is connected with suspender, and the storage and transportation platform is set There is at least one channel that gathers materials, collection system is provided in the channel that gathers materials, the storage and transportation platform is equipped with logical positioned at gathering materials The storage and transportation area of road side and the traffic zone in front of the channel that gathers materials.
Preferably, the traffic zone is equipped with the haul track of installation dumper, and the centre of the haul track is equipped with driving The car puller of dumper.
Preferably, the collection system includes the pan feeding rubber conveyer above the channel that gathers materials, the channel that gathers materials Interior to be equipped with the ingredient bracket being located in front of pan feeding rubber conveyer, the ingredient bracket is equipped with the material distribution that can be horizontally slipped Device, the both-side opening of the stock distributor and is hinged with the liftable chute that gathers materials, and the two sides of the ingredient bracket are equipped with Installation collects the track that gathers materials of truck, and aggregate bin is placed on the collection truck, and the centre of the track that gathers materials is equipped with driving and gathers materials The car puller of vehicle.
Preferably, the outlet of the chute that gathers materials is equipped with chute door, and the chute door and the chute that gathers materials are opened the door by chute Hydraulic cylinder connection, the cylinder body of the chute enabling hydraulic cylinder are connect with the supporting plate to gather materials on chute is fixed on, and the chute opens the door The telescopic rod of hydraulic cylinder is connect with chute door.
Preferably, the top with the top of ingredient bracket of the chute that gathers materials are connect by chute lifting hydraulic cylinder, described The cylinder body of chute lifting hydraulic cylinder is connect with ingredient bracket, and the telescopic rod of the chute lifting hydraulic cylinder is connect with the chute that gathers materials.
Preferably, the stock distributor is connect by sliding rail with ingredient bracket, and the stock distributor also passes through distribution Device mobile hydraulic cylinder is connect with ingredient bracket, and the cylinder body of the distributor mobile hydraulic cylinder is connect with ingredient bracket, the distribution The telescopic rod of device mobile hydraulic cylinder is connect with stock distributor.
Preferably, the collection truck includes bottom plate, and the lower section of the bottom plate is equipped with mobile bracket, the mobile bracket installation There is shaft, the both ends of the shaft are provided with and gather materials the idler wheel of track cooperation, and the top of the bottom plate is equipped with positioned at two sides Backplate, the lifting groove being additionally provided with above the bottom plate among two backplates, the two sides of the lifting groove are turned up and are passed through Truck lifting hydraulic cylinder is connect with bottom plate, and the cylinder body of the truck lifting hydraulic cylinder is connect with bottom plate, the truck raise-lower hydraulic The telescopic rod of cylinder is connect with lifting groove.
A kind of foundry formed coke half-finished product collection conveying method, collects storing and transporting system including above-mentioned foundry formed coke half-finished product, Specifically includes the following steps:
Step 1, will be in aggregate bin handling to collection truck by hoisting mechanism;
Step 2 runs pan feeding rubber conveyer, while the chute door of the chute that gathers materials in collection system being closed, by material point Orchestration is mobile to side, and material is added into the chute that gathers materials of side by stock distributor in pan feeding rubber conveyer;
Step 3, it is after material is filled it up in the chute that gathers materials of side, material stock distributor is mobile to the other side, while by one The chute door that side has been filled with the chute that gathers materials is opened, and material, pan feeding rubber conveyer is added in aggregate bin on the collection truck of side Material is added into the chute that gathers materials of the other side by stock distributor;
Step 4 repeats step 2 and step 3, fills until in the wherein aggregate bin of side, rearward by the collection truck of side It is mobile, and aggregate bin is transported to storage area storage or is transported to traffic zone using hoisting mechanism and is directly transported;
Step 5 repeats step 1 to step 4, until material collection storage and transportation finishes.
Preferably, in step 3 and step 4, aggregate bin will gather materials chute afterwards in place will by chute lifting hydraulic cylinder Then material is added to the chute that gathers materials again in the chute that gathers materials decline, the chute that gathers materials will be by truck liter when material is added to aggregate bin Descending liquid cylinder pressure will collect truck and rise drop slot rising, and reduction blanking is poor, as the addition of material gradually declines lifting groove.
Preferably, in step 3 and step 4, after material is filled in aggregate bin, the chute that will gather materials rises.
The beneficial effects of the present invention are:
Foundry formed coke half-finished product can be carried out automatically collecting storage and transport using hoisting mechanism and collection system by the present invention, It can reduce manually, save cost, increased safety guarantee.
Collection system of the invention can reduce the percentage of damage of material, and collection efficiency is high.
Cooperate two chute energy cycle operations of gathering materials using the collection truck of two sides, increase working efficiency, by collection truck The lifting of the height adjustment of lifting groove and the chute that gathers materials can make material keep safe and reliable blanking poor, avoid material broken It is broken.
Detailed description of the invention
Fig. 1 is schematic front view of the invention;
Fig. 2 is floor plan of the invention;
Fig. 3 is the structural schematic diagram of suspender in the present invention;
Fig. 4 is the structural schematic diagram of collection system in the present invention;
Fig. 5 is the structural schematic diagram of the collection truck in collection system;
In figure: 1, gather materials channel;101, car puller;102, gather materials track;2, ingredient bracket;3, pan feeding rubber conveyer;301, Chute lifting hydraulic cylinder;302, distributor mobile hydraulic cylinder;4, stock distributor;5, gather materials chute;501, supporting plate;502, chute Enabling hydraulic cylinder;503, chute door;6, collect truck;601, bottom plate;602, mobile bracket;603, idler wheel;604, backplate;605, expect Vehicle lifting hydraulic cylinder;606, lifting groove;607, weighing balance 607;7, aggregate bin;8, hoisting mechanism;9, suspender;10, storage and transportation platform; 1001, haul track;11, dumper.
Specific embodiment
A specific embodiment of the invention is referring to Fig. 1-5:
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clearly and completely Description, wherein hoisting mechanism 8, stock distributor 4, pan feeding rubber conveyer 3 are existing equipment, herein no longer to existing equipment Specific structure be described, in addition 9 the applicant of suspender of hoisting mechanism 8 is application No. is 2016211520837, titles Disclosure is carried out for a kind of patent of invention of novel quenching hopper Automatic hook block, therefore the structure of suspender 9 is not also being retouched It states.
The technical solution of the present invention is as follows:
A kind of foundry formed coke half-finished product collection storing and transporting system, the hoisting machine including storage and transportation platform 10 and above storage and transportation platform 10 Structure 8, the hoisting mechanism 8 is at least one and lower section is connected with suspender 9, and the storage and transportation platform 10 gathers materials logical equipped at least one Road 1, collection system is provided in the channel 1 that gathers materials, and the storage and transportation platform 10 is equipped with the storage and transportation for being located at 1 side of channel that gathers materials Area and the traffic zone in front of the channel 1 that gathers materials, the traffic zone is equipped with the haul track 1001 of installation dumper 11, described The centre of haul track 1001 is equipped with the car puller 101 of driving dumper 11, and the collection system includes being located to gather materials on channel 1 The pan feeding rubber conveyer 3 of side, the channel 1 that gathers materials is interior to be equipped with the ingredient bracket 2 for being located at 3 front of pan feeding rubber conveyer, institute It states ingredient bracket 2 and the stock distributor 4 that can be horizontally slipped is installed, the both-side opening of the stock distributor 4 and be hinged with can The chute 5 that gathers materials of lifting, the two sides of the ingredient bracket 2 are equipped with the track 102 that gathers materials of installation collection truck 6, the collection truck 6 On be placed with aggregate bin 7, the centre of the track 102 that gathers materials is equipped with the car puller 101 of driving collection truck 6, the chute 5 that gathers materials Outlet be equipped with chute door 503, the chute door 503 with gather materials chute 5 pass through chute enabling hydraulic cylinder 502 connect, it is described to slip The cylinder body of slot enabling hydraulic cylinder 502 is connect with the supporting plate 501 to gather materials on chute 5 is fixed on, the chute enabling hydraulic cylinder 502 Telescopic rod is connect with chute door 503, and the top of the chute 5 that gathers materials and the top of ingredient bracket 2 pass through chute lifting hydraulic cylinder 301 connections, the cylinder body of the chute lifting hydraulic cylinder 301 are connect with ingredient bracket 2, and the chute lifting hydraulic cylinder 301 is stretched Contracting bar is connect with the chute 5 that gathers materials, and the stock distributor 4 is connect by sliding rail with ingredient bracket 2, and the stock distributor 4 is also It is connect by distributor mobile hydraulic cylinder 302 with ingredient bracket 2, the cylinder body and ingredient branch of the distributor mobile hydraulic cylinder 302 Frame 2 connects, and the telescopic rod of the distributor mobile hydraulic cylinder 302 is connect with stock distributor 4, and the collection truck 6 includes bottom plate 601, the lower section of the bottom plate 601 is equipped with mobile bracket 602, and the mobile bracket 602 is equipped with shaft, the both ends of the shaft It is provided with and the idler wheel 603 for the cooperation of track 102 of gathering materials, the top of the bottom plate 601 is described equipped with the backplate 604 positioned at two sides The top of bottom plate 601 is additionally provided with the lifting groove 606 among two backplates 604, and the two sides of the lifting groove 606 are turned up and led to It crosses truck lifting hydraulic cylinder 605 to connect with bottom plate 601, the cylinder body of the truck lifting hydraulic cylinder 605 is connect with bottom plate 601, institute The telescopic rod for stating truck lifting hydraulic cylinder 605 is connect with lifting groove 606.
A kind of foundry formed coke half-finished product collection conveying method, collects storing and transporting system including above-mentioned foundry formed coke half-finished product, Specifically includes the following steps:
Step 1, will be in 7 handling of aggregate bin to collection truck 6 by hoisting mechanism 8;
Step 2 runs pan feeding rubber conveyer 3, while the chute door 503 of the chute 5 that gathers materials in collection system being closed, will Stock distributor 4 is mobile to side, and pan feeding rubber conveyer 3 passes through the admixture into the chute 5 that gathers materials of side of stock distributor 4 Material;
Step 3, it is after material is filled it up in the chute 5 that gathers materials of side, material stock distributor 4 is mobile to the other side, simultaneously will The chute door 503 that side has been filled with the chute 5 that gathers materials is opened, and material, pan feeding glue is added in aggregate bin 7 on the collection truck 6 of side Material is added into the chute 5 that gathers materials of the other side by stock distributor 4 with conveyer 3;
Step 4 repeats step 2 and step 3, fills until in the wherein aggregate bin 7 of side, backward by the collection truck 6 of side Fang Yidong, and aggregate bin 7 is transported to storage area storage or is transported to traffic zone using hoisting mechanism 8 and is directly transported;
Step 5 repeats step 1 to step 4, until material collection storage and transportation finishes.
In step 3 and step 4, aggregate bin 7 will gather materials chute 5 afterwards in place will collection by chute lifting hydraulic cylinder 301 Expect that chute 5 declines, material then is added to the chute 5 that gathers materials again, the chute 5 that gathers materials will pass through truck when material is added to aggregate bin 7 Lifting hydraulic cylinder 605 will collect lifting groove 606 on truck 6 and rise, and reduction blanking is poor, as the addition of material is gradually by lifting groove 606 declines.
In step 3 and step 4, after material is filled in aggregate bin 7, the chute 5 that will gather materials rises.
The present invention can using hoisting mechanism 8 and collection system by foundry formed coke half-finished product carry out automatically collecting storage and Transport can reduce manually, save cost, increase safety guarantee.
Collection system of the invention cooperates two 5 energy cycle operations of chute of gathering materials using the collection truck 6 of two sides, increases work Efficiency can make material keep safety can by the height adjustment of lifting groove 606 and the lifting for the chute 5 that gathers materials on collection truck 6 The blanking leaned on is poor, avoids material broken.

Claims (10)

1. a kind of foundry formed coke half-finished product collects storing and transporting system, the hoisting machine including storage and transportation platform and above storage and transportation platform Structure, it is characterised in that: the hoisting mechanism is at least one and lower section is connected with suspender, and the storage and transportation platform is equipped at least one Gather materials channel, and collection system is provided in the channel that gathers materials, and the storage and transportation platform is equipped with the storage for being located at the channel side that gathers materials Transport area and the traffic zone in front of the channel that gathers materials.
2. foundry formed coke half-finished product according to claim 1 collects storing and transporting system, it is characterised in that: the traffic zone is equipped with The haul track of dumper is installed, the centre of the haul track is equipped with the car puller of driving dumper.
3. foundry formed coke half-finished product according to claim 2 collects storing and transporting system, it is characterised in that: the collection system packet The pan feeding rubber conveyer being located above the channel that gathers materials is included, is equipped with and is located in front of pan feeding rubber conveyer in the channel that gathers materials Ingredient bracket, the ingredient bracket are equipped with the stock distributor that can be horizontally slipped, the both-side opening of the stock distributor and It is hinged with the liftable chute that gathers materials, the two sides of the ingredient bracket are equipped with the track that gathers materials of installation collection truck, described to gather materials Aggregate bin is placed on vehicle, the centre of the track that gathers materials is equipped with the car puller of driving collection truck.
4. foundry formed coke half-finished product according to claim 3 collects storing and transporting system, it is characterised in that: the chute that gathers materials Outlet is equipped with chute door, the chute door with gather materials chute and connect by chute enabling hydraulic cylinder, the chute enabling hydraulic cylinder Cylinder body connect with the supporting plate to gather materials on chute is fixed on, the telescopic rod of the chute enabling hydraulic cylinder is connect with chute door.
5. foundry formed coke half-finished product according to claim 4 collects storing and transporting system, it is characterised in that: the chute that gathers materials Top is connect with the top of ingredient bracket by chute lifting hydraulic cylinder, the cylinder body and ingredient bracket of the chute lifting hydraulic cylinder Connection, the telescopic rod of the chute lifting hydraulic cylinder are connect with the chute that gathers materials.
6. foundry formed coke half-finished product according to claim 5 collects storing and transporting system, it is characterised in that: the stock distributor It is connect by sliding rail with ingredient bracket, the stock distributor also passes through distributor mobile hydraulic cylinder and connect with ingredient bracket, institute The cylinder body for stating distributor mobile hydraulic cylinder is connect with ingredient bracket, and the telescopic rod and material of the distributor mobile hydraulic cylinder distribute Device connection.
7. foundry formed coke half-finished product according to claim 6 collects storing and transporting system, it is characterised in that: the collection truck includes Bottom plate, the lower section of the bottom plate are equipped with mobile bracket, and the mobile bracket is equipped with shaft, the both ends of the shaft be provided with The idler wheel of the track that gathers materials cooperation, the top of the bottom plate are equipped with the backplate positioned at two sides, are additionally provided with and are located above the bottom plate Lifting groove among two backplates, the two sides of the lifting groove are turned up and are connect by truck lifting hydraulic cylinder with bottom plate, described The cylinder body of truck lifting hydraulic cylinder is connect with bottom plate, and the telescopic rod of the truck lifting hydraulic cylinder is connect with lifting groove.
8. a kind of foundry formed coke half-finished product collects conveying method, including foundry formed coke half-finished product as claimed in claim 7 collects storage Fortune system, it is characterised in that: the following steps are included:
Step 1, will be in aggregate bin handling to collection truck by hoisting mechanism;
Step 2 runs pan feeding rubber conveyer, while the chute door of the chute that gathers materials in collection system being closed, by material point Orchestration is mobile to side, and material is added into the chute that gathers materials of side by stock distributor in pan feeding rubber conveyer;
Step 3, it is after material is filled it up in the chute that gathers materials of side, material stock distributor is mobile to the other side, while by one The chute door that side has been filled with the chute that gathers materials is opened, and material, pan feeding rubber conveyer is added in aggregate bin on the collection truck of side Material is added into the chute that gathers materials of the other side by stock distributor;
Step 4 repeats step 2 and step 3, fills until in the wherein aggregate bin of side, rearward by the collection truck of side It is mobile, and aggregate bin is transported to storage area storage or is transported to traffic zone using hoisting mechanism and is directly transported;
Step 5 repeats step 1 to step 4, until material collection storage and transportation finishes.
9. foundry formed coke half-finished product according to claim 8 collects conveying method, it is characterised in that: in step 3 and step In four, aggregate bin will gather materials afterwards in place chute by chute lifting hydraulic cylinder will gather materials chute decline, then again to the chute that gathers materials Material is added, truck rising drop slot will be collected when material is added to aggregate bin in the chute that gathers materials by truck lifting hydraulic cylinder and risen, It is poor to reduce blanking, as the addition of material gradually declines lifting groove.
10. foundry formed coke half-finished product according to claim 9 collects conveying method, it is characterised in that: in step 3 and step In rapid four, after material is filled in aggregate bin, the chute that will gather materials rises.
CN201910100454.9A 2019-01-31 2019-01-31 A kind of foundry formed coke half-finished product collects storing and transporting system and its working method Pending CN109650088A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910100454.9A CN109650088A (en) 2019-01-31 2019-01-31 A kind of foundry formed coke half-finished product collects storing and transporting system and its working method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910100454.9A CN109650088A (en) 2019-01-31 2019-01-31 A kind of foundry formed coke half-finished product collects storing and transporting system and its working method

Publications (1)

Publication Number Publication Date
CN109650088A true CN109650088A (en) 2019-04-19

Family

ID=66121993

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910100454.9A Pending CN109650088A (en) 2019-01-31 2019-01-31 A kind of foundry formed coke half-finished product collects storing and transporting system and its working method

Country Status (1)

Country Link
CN (1) CN109650088A (en)

Citations (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE19731929A1 (en) * 1997-07-24 1999-01-28 Siemens Ag Automatic filling method for loose material transport vehicles
CN2353705Y (en) * 1998-12-09 1999-12-15 河南神火煤电股份有限公司选煤厂 Device for preventing lump-coal from cracking for moving-type automatically proportioning bin
CN104691794A (en) * 2013-12-04 2015-06-10 新昌县儒岙镇诺一机械厂 Quick packing device
CN104803204A (en) * 2015-04-01 2015-07-29 宁波大榭招商国际码头有限公司 Loading and unloading process system for regional container
CN104986582A (en) * 2015-07-17 2015-10-21 武汉电力设备厂 lump coal boxing system and boxing method thereof
CN105692179A (en) * 2016-03-23 2016-06-22 江苏鹏飞集团股份有限公司 Feeding device for garbage treatment
CN205816773U (en) * 2016-07-29 2016-12-21 福建长江工业有限公司 A kind of structure improved low pressure casting splicing car
CN206157092U (en) * 2016-10-31 2017-05-10 李翔 Novel casting formed coke coke quenching cart
CN106794971A (en) * 2014-06-30 2017-05-31 科尼全球公司 Transported by the load for loading processing equipment
CN107054902A (en) * 2017-01-17 2017-08-18 马鞍山钢铁股份有限公司 A kind of transport coke, the train container of coal, the device for discharging supporting with it and Environmental-protection transporting discharge method
CN206550314U (en) * 2017-01-17 2017-10-13 中冶华天工程技术有限公司 A kind of scale collection device that system is heat-fed for strand
CN207109470U (en) * 2017-06-16 2018-03-16 廊坊合力天一机械设备有限公司 The template self-compacting concretes of CRTS III pour device
CN107826708A (en) * 2016-09-15 2018-03-23 南京梅山冶金发展有限公司 Rubber conveyer material flow changes device
CN108016892A (en) * 2017-12-26 2018-05-11 中冶京诚工程技术有限公司 Bulk cargo bin stock system and method
CN108455297A (en) * 2018-02-11 2018-08-28 瑞安市阀门厂 Container-type raw coal storing and transporting system and method
CN209455694U (en) * 2019-01-31 2019-10-01 李翔 A kind of foundry formed coke half-finished product collection storing and transporting system

Patent Citations (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE19731929A1 (en) * 1997-07-24 1999-01-28 Siemens Ag Automatic filling method for loose material transport vehicles
CN2353705Y (en) * 1998-12-09 1999-12-15 河南神火煤电股份有限公司选煤厂 Device for preventing lump-coal from cracking for moving-type automatically proportioning bin
CN104691794A (en) * 2013-12-04 2015-06-10 新昌县儒岙镇诺一机械厂 Quick packing device
CN106794971A (en) * 2014-06-30 2017-05-31 科尼全球公司 Transported by the load for loading processing equipment
CN104803204A (en) * 2015-04-01 2015-07-29 宁波大榭招商国际码头有限公司 Loading and unloading process system for regional container
CN104986582A (en) * 2015-07-17 2015-10-21 武汉电力设备厂 lump coal boxing system and boxing method thereof
CN105692179A (en) * 2016-03-23 2016-06-22 江苏鹏飞集团股份有限公司 Feeding device for garbage treatment
CN205816773U (en) * 2016-07-29 2016-12-21 福建长江工业有限公司 A kind of structure improved low pressure casting splicing car
CN107826708A (en) * 2016-09-15 2018-03-23 南京梅山冶金发展有限公司 Rubber conveyer material flow changes device
CN206157092U (en) * 2016-10-31 2017-05-10 李翔 Novel casting formed coke coke quenching cart
CN107054902A (en) * 2017-01-17 2017-08-18 马鞍山钢铁股份有限公司 A kind of transport coke, the train container of coal, the device for discharging supporting with it and Environmental-protection transporting discharge method
CN206550314U (en) * 2017-01-17 2017-10-13 中冶华天工程技术有限公司 A kind of scale collection device that system is heat-fed for strand
CN207109470U (en) * 2017-06-16 2018-03-16 廊坊合力天一机械设备有限公司 The template self-compacting concretes of CRTS III pour device
CN108016892A (en) * 2017-12-26 2018-05-11 中冶京诚工程技术有限公司 Bulk cargo bin stock system and method
CN108455297A (en) * 2018-02-11 2018-08-28 瑞安市阀门厂 Container-type raw coal storing and transporting system and method
CN209455694U (en) * 2019-01-31 2019-10-01 李翔 A kind of foundry formed coke half-finished product collection storing and transporting system

Similar Documents

Publication Publication Date Title
CN201301134Y (en) Colliery railway quick loading gauge addition device
CN209455694U (en) A kind of foundry formed coke half-finished product collection storing and transporting system
CN201258198Y (en) Dual-purpose car-loading station
CN109650088A (en) A kind of foundry formed coke half-finished product collects storing and transporting system and its working method
CN209616465U (en) A kind of foundry formed coke half-finished product anti-crushing collection system
CN207973126U (en) A kind of mining haul device
CN107054902A (en) A kind of transport coke, the train container of coal, the device for discharging supporting with it and Environmental-protection transporting discharge method
CN109676999A (en) A kind of foundry formed coke half-finished product anti-crushing collection system and its working method
CN209651272U (en) A kind of automatic feeding
CN205701102U (en) A kind of automatic centrifugal oil remover
CN211619404U (en) Railway bulk grain transportation and loading equipment
CN209668337U (en) A kind of coal mine twin-skip divides storage system automatically
CN209802699U (en) Abandoned material recovery system of raw coal sampling machine
CN209754122U (en) Cold-rolled strip steel shearing machine
CN202944893U (en) Vehicle-mounted bulk potato fast automatic discharge screening and soil removing device
CN204161946U (en) Chain type ageing mixture machine
CN207657022U (en) A kind of charger
CN206157092U (en) Novel casting formed coke coke quenching cart
DE3806861C1 (en) Transport installation for hot iron sponge
CN112502768B (en) Mining wisdom conveying system
CN213301822U (en) Unmanned ore inspection sampling device
CN212981330U (en) Double-station movable discharging device
CN215288870U (en) Scrap steel bucket
CN201210013Y (en) Automatic charging device at back of electric furnace
CN210824148U (en) Goods-discharging lifting door of inclined belt conveyor

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 450000 building 65, No. 2, yard 90, Wenhua Road, Jinshui District, Zhengzhou City, Henan Province

Applicant after: Li Xiang

Address before: 476600 Business District 482, Guangming Road, Yongcheng New Town, Shangqiu City, Henan Province

Applicant before: Li Xiang

CB02 Change of applicant information
CB02 Change of applicant information

Address after: No.65, building 2, building 90, Wenhua Road, Jinshui District, Zhengzhou City, Henan Province

Applicant after: Li Xiang

Address before: No.65, building 2, yard 90, Wenhua Road, Jinshui District, Zhengzhou City, Henan Province

Applicant before: Li Xiang

CB02 Change of applicant information