CN109629814A CN201910024983.5A CN201910024983A CN109629814A CN 109629814 A CN109629814 A CN 109629814A CN 201910024983 A CN201910024983 A CN 201910024983A CN 109629814 A CN109629814 A CN 109629814A
Authority
CN
China
Prior art keywords
frame
platform
wind
electricity generation
powered electricity
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910024983.5A
Other languages
Chinese (zh)
Inventor
于春生
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Cooper (tianjin) Science And Technology Ltd
Cooper Tianjin Technology Co Ltd
Original Assignee
Cooper (tianjin) Science And Technology Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Cooper (tianjin) Science And Technology Ltd filed Critical Cooper (tianjin) Science And Technology Ltd
Priority to CN201910024983.5A priority Critical patent/CN109629814A/en
Publication of CN109629814A publication Critical patent/CN109629814A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • E04G3/30Mobile scaffolds; Scaffolds with mobile platforms suspended by flexible supporting elements, e.g. cables
    • E04G3/32Hoisting devices; Safety devices
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/001Safety or protective measures against falling down relating to scaffoldings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/04Means for fastening, supporting, or bracing scaffolds on or against building constructions
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/08Scaffold boards or planks
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/14Railings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • E04G2003/286Mobile scaffolds; Scaffolds with mobile platforms mobile vertically

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Wind Motors (AREA)

Abstract

The present invention relates to a kind of wind-powered electricity generation concrete tower mounting platforms.Including superposed revolving platform device and positioned at the slewing supporting device of lower part;Revolving platform device includes the slewing frame being made of base circle frame, top annular frame and multiple longitudinal girts between the two, is equipped with upper central frame in center;Discrete four fixed fences are equipped at the edge of top annular frame, are equipped with platform door in the side of each fixed fence;Further include four groups of platform outside tracks being mounted in slewing frame, is mounted on scaling platform in every group platform outside track;Driving assembly is installed in the bottom of upper central frame;Slewing supporting device includes the middle frame of rectangle, is equipped with the first triangle outer framework and the second triangle outer framework in the two sides of middle frame;Lower central frame is equipped in the center of middle frame;Three groups of centralising devices are installed in braced frame.Structure of the invention design is reasonable, can satisfy major diameter wind-power tower installation requirement.

Description

A kind of wind-powered electricity generation concrete tower mounting platform
Technical field
The invention belongs to wind power construction equipment technical field more particularly to a kind of wind-powered electricity generation concrete tower mounting platforms.
Background technique
Wind energy is clean energy resource with fastest developing speed in renewable energy, and most large-scale development and commercialized development The generation mode of prospect.China is wind energy resources big country, according to preresearch estimates, for 50 meters of height, and the available wind energy in land Resource is about 60-100GW, and offshore wind energy resource is about 10-20GW, occupies third place in the world.It can be seen that being dragon with wind-power electricity generation The cleaner power sources form of head realizes that energy development is environmentally friendly, sustainable development and two for improving China's power supply architecture Aoxidizing carbon emission reduction has important strategic position.
Wind-power tower is extremely difficult when building due to highly higher, and after building, to internal repairerment and maintenance Also very inconvenient.Due to the tapered column structure of tower, internal diameter can reduce with height casting, in the work people of inside processing Member, when a lower height of, it may appear that the case where reaching tower inner wall, and if increasing the diameter of platform, and it can be in tower Cylinder upper position blocks.In terms of fixation, existing tower build platform can in the case where guaranteeing plateau levels area of section, The internal diameter of different tower positions is adapted to by the fixation kit realization of extension, but still not can solve operation distance not Enough problems.Furthermore existing tower barrel platform cannot rotate, and operating personnel needs constantly to walk and move on platform, increase Add the security risk of operation.
Therefore, it by being researched and developed to wind-power tower mounting platform, obtains one kind and is built suitable for current wind power facility If mounting platform, promote the efficiency of blower concrete tower installation and to reduce the risk of construction be the work urgently carried out Make.Simultaneously as its tower diameter of the blower of different size is different, and blower fan tower barrel is from bottom to top under normal conditions Its diameter is gradually reduced, therefore so-called mounting platform should have adaptive ability in this project, to guarantee the safety of operation And the versatility of complete machine.
A kind of " rotating platform built for tower " is disclosed in the specification of Chinese invention patent CN207348429U, It include lifting fixed part, rotating part, operation part in structure, rotating part is fixed on the upper end of lifting fixed part, makees The upper end of rotating part is fixed in industry part, is rotatablely connected between operation part and lifting fixed part by rotating part.It should The patentee of patent is all the applicant of this patent, and product disclosed in above-mentioned patent is the early production of our company, is being tied Structure is formal, this product is only applicable to the installation and maintenance of the lesser wind-power tower of internal diameter, due to Telescopic guardrail, revolving platform Etc. design factor, cause the usage scenario of mounting platform limited, be not able to satisfy the continuous of major diameter wind-power tower especially Installation exercise requirement.Therefore, it is necessary to the structures to mounting platform to optimize to meet above-mentioned requirements.
Summary of the invention
The present invention be solve technical problem present in well-known technique and provide it is a kind of it is reasonable in design, can satisfy it is big The wind-powered electricity generation concrete tower mounting platform of diameter wind-power tower installation requirement.
The technical scheme adopted by the present invention to solve the technical problems existing in the known art is that a kind of wind-powered electricity generation concrete Tower mounting platform includes superposed revolving platform device and the slewing supporting device positioned at lower part;Revolving platform device packet The slewing frame being made of base circle frame, top annular frame and multiple longitudinal girts between the two is included, in slewing frame Center is equipped with upper central frame, and a plurality of radiation is equipped between upper central frame and base circle frame and top annular frame Bar;It is laid on top annular frame and platform floors is installed, be equipped with discrete four fixed fences at the edge of top annular frame, Platform door is equipped in the side of each fixed fence;It further include four groups of platform outside tracks being mounted in slewing frame, every Scaling platform is mounted in group platform outside track;Driving assembly is installed in the bottom of upper central frame;Slewing supporting device Middle frame including rectangle is equipped with the first triangle outer framework and the second triangle outer framework, three in the two sides of middle frame Constitute the braced frame of regular hexagon;It is equipped with lower central frame in the center of middle frame, at lower central frame and middle part It is equipped with multiple reinforcing rods between frame, is equipped with multiple reinforcements in the inside of both the first triangle outer framework, the second triangle outer framework Bar;Three groups of centralising devices are installed in braced frame, every group of centralising device includes two centering components of opposite direction setting.
The advantages and positive effects of the present invention are: the present invention provides a kind of wind-powered electricity generation concrete towers reasonable in design Mounting platform, by setting slewing supporting device in the technical program, provides compared with existing tower mounting platform for complete machine Stable revolving support function.By being provided with multiple fixed fences, platform door and the revolving platform device of scaling platform, A stable standing operation platform is provided for operator.Scaling platform can radially stretch horizontally outward, therefore grasp Author can reach farther operating distance on scaling platform.By the way that multiple groups centralising device is arranged on revolving support platform, It enables this mounting platform stablize the position in blower fan tower barrel inside center by centralising device during the work time and reduces shaking, mention Risen platform it is mobile when stability, improve the safety of operator.By setting slewing supporting device by two triangles The middle frame of outer framework and a rectangle constitutes and is arranged inside three reinforcing rod, by setting revolving platform device the bottom of by Portion's ring frame, top annular frame and multiple longitudinal girts between the two constitute and radiation are arranged at middle part, directly improve The structural strength of slewing supporting device and revolving platform device.
Preferably: scaling platform includes under(-)chassis, is equipped with front guardrail in the outer end of under(-)chassis;In under(-)chassis The left and right sides be equipped with the inner orbit of C-type steel structure, internal trolley is installed in the two sides of under(-)chassis, internal trolley is along place Inner orbit rolls movement, and outer idler wheel is equipped on the outside of inner orbit, and platform outside track rolling of the outer idler wheel along place is moved;? Rack gear is installed below under(-)chassis, telescope motor is additionally provided on slewing frame, is installed on the motor shaft of telescope motor There is the driving gear being engaged with rack.
Preferably: being laid at the middle part of under(-)chassis and platform pedal is installed, set up between the middle part of two inner orbits It is equipped with to set up between the first laminate of platform, inside and the second laminate of platform is installed.
Preferably: in front, the middle part of guardrail is equipped with crossbeam, is equipped with front panel in the lower section of crossbeam, also sets on crossbeam There is storage box.
Preferably: driving assembly includes the ring gear for being mounted on central frame bottom, further includes turning motor, in revolution electricity Driving gear with ring gear engaged transmission is installed on the motor shaft of machine;At the top of lower central frame and the bottom of upper central frame Slip is installed between portion and takes electrical component, turning motor takes electrical component to be electrically connected with slip.
Preferably: centering component includes the flexible outer sleeve being fixed in braced frame, is set in flexible outer sleeve There is telescopic boom, the spring in tensional state is equipped between the inner end of telescopic boom and the middle part of flexible outer sleeve inner wall; Universal wheel is also equipped in the outer end of telescopic boom.
Preferably: it further include auxiliary security component, auxiliary security component includes the support rod for being fixed on telescopic boom outer end, Multiple rope otic placodes with connecting hole are equipped at the top of support rod, pulling rope is fixed with by pin shaft on rope otic placode Rope is equipped with hook in the outer end of rope for traction;Multiple hangers are additionally provided in the side of support rod, is equipped on hanger and is taken for personnel With the retinue operating stick for operating the hook.
Preferably: the upper end of upper central frame is extended upwardly to the position contour with fixed fence by the surface of top annular frame It sets, constitutes the hand steered center rest of personnel.
Preferably: pedestals, pedestals and base circle frame and top are equipped on the outside of each fixed fence Ring frame is fixedly connected with;Being equipped in the upper end of pedestals can be with the lifting rotating end of lateral rotation.
Detailed description of the invention
Fig. 1 is overall structure diagram of the invention;
Fig. 2 is the structural schematic diagram of revolving platform device in Fig. 1;
Fig. 3 is the structural schematic diagram of scaling platform in Fig. 2;
Fig. 4 is the structural schematic diagram of slewing supporting device in Fig. 1;
Fig. 5 is the structural schematic diagram of centering component in 4.
In figure:
1, revolving platform device;
1-1, longitudinal girt;1-2, base circle frame;1-3, top annular frame;1-4, scaling platform;1-4-1, front guardrail; 1-4-2, front panel;1-4-3, platform pedal;1-4-4, the first laminate of platform;1-4-5, laminate installation part;1-4-6, platform Second laminate;1-4-7, inner orbit;1-4-8, outer idler wheel;1-4-9, under(-)chassis;1-4-10, rack gear;1-5, telescope motor;1- 6, driving assembly;1-7, platform floors;1-8, platform outside track;1-9, upper central frame;1-10, platform door;1-11, fixation are enclosed Column;1-12, pedestals;1-13, storage box;
2, slewing supporting device;
2-1, rope for traction;2-2, the first triangle outer framework;2-3, lower central frame;2-4, middle frame;2-5, centering Component;2-5-1, hanger;2-5-2, retinue operating stick;2-5-3, rope otic placode;2-5-4, support rod;2-5-5, universal wheel;2- 5-6, telescopic boom;2-5-7, flexible outer sleeve;2-6, the second triangle outer framework.
Specific embodiment
In order to further understand the content, features and effects of the present invention, hereby lifting following embodiment, detailed description are as follows:
Referring to Figure 1, wind-powered electricity generation concrete tower mounting platform of the invention includes superposed 1 He of revolving platform device Slewing supporting device 2 positioned at lower part, wherein revolving platform device 1 turns round movement in the top of slewing supporting device 2, for operation Person provides a rotatably stable standing platform, and slewing supporting device 2 provides slewing supporting device as a pedestal.
Refer to Fig. 2 and Fig. 3, it will thus be seen that revolving platform device 1 includes by base circle frame 1-2, top annular frame 1- The slewing frame that 3 and multiple longitudinal girt 1-1 between the two are constituted is equipped with upper central frame in the center of slewing frame 1-9 is equipped with a plurality of radiation between upper central frame 1-9 and base circle frame 1-2 and top annular frame 1-3, increases in this way The structural strength of the entirety of revolving platform device 1 is added.
It is laid on top annular frame 1-3 and platform floors 1-7 is installed, formed and completely put down for what operator stood Face.Platform floors 1-7 can be made with the enough metal plates of selecting structure intensity, plank etc., using bolt etc. and top annular frame 1-3 is fixedly connected with radiation.Discrete four fixed fence 1-11 are equipped at the edge of top annular frame 1-3, each solid The side for determining fence 1-11 is equipped with platform door 1-10.It further include four groups of platform outside track 1-8 being mounted in slewing frame, Scaling platform 1-4 is mounted in every group platform outside track 1-8.This mounting platform is suitable for the wind-power tower mounting ring of major diameter Border enables the top of revolving platform device 1 sufficiently anti-by fence by the way that fixed fence 1-11 and platform door 1-10 is arranged at top Shield, platform door 1-10 enter the channel inside revolving platform device 1 for operator as multiple.Scaling platform 1-4 can edge Radial direction is flexible, and operator stands and carries out practical operation on scaling platform 1-4.As shown in the figure, four groups of scaling platforms Quartile is set at 90 ° intervals between each other in four direction, that is to say, that can have four behaviour on this revolving platform device 1 simultaneously Make personnel in four direction while working.
In order to promote the safety of operator, it is equipped with pedestals 1-12 on the outside of each fixed fence 1-11, Pedestals 1-12 and base circle frame 1-2 and top annular frame 1-3 are fixedly connected with;It is equipped in the upper end of pedestals 1-12 It can be with the lifting rotating end of lateral rotation.When scaling platform 1-4 stretches out certain distance, since bottom lacks fulcrum, therefore tie Structure and intensity are tested, it may occur however that the accidents such as unstability.At this point it is possible to which stretching for rotating end and this side will be lifted using rope The 1-4 connection of contracting platform promotes the stability of scaling platform 1-4 during the work time.
In the present embodiment, scaling platform 1-4 includes under(-)chassis 1-4-9, before the outer end of under(-)chassis 1-4-9 is equipped with The width of portion guardrail 1-4-1, front guardrail 1-4-1 are equal on revolving platform device 1 by fixed fence 1-11 and platform door 1-10 The width of gained notch after occupancy, in this way after scaling platform 1-4 is retracted, each front guardrail 1-4-1 and each fixed fence 1- Complete circular fence is collectively formed in 11 and platform door 1-10.
The inner orbit 1-4-7 of C-type steel structure is equipped at left and right sides of under(-)chassis 1-4-9, in under(-)chassis 1-4-9 Two sides internal trolley is installed, inner orbit 1-4-7 rolling of the internal trolley along place is moved.It is installed in the outside of inner orbit 1-4-7 There is outer idler wheel 1-4-8, platform outside track 1-8 rolling of the outer idler wheel 1-4-8 along place is moved.In the lower section of under(-)chassis 1-4-9 Rack gear 1-4-10 is installed, telescope motor 1-5 is additionally provided on slewing frame, is equipped on the motor shaft of telescope motor 1-5 The driving gear engaged with rack gear 1-4-10.Under the driving effect of telescope motor 1-5, rack gear 1-4-10 drives under(-)chassis 1- 4-9 is moved radially, it can be seen that scaling platform 1-4 is two-stage stretching structure, and under(-)chassis 1-4-9 is first along inner orbit 1-4-7 Mobile, inner orbit 1-4-7 is moved along platform outside track 1-8 later, and the flexible mode of such two-stage improves scaling platform 1-4 Distance of stretch out and draw back, be more advantageous to major diameter wind-power tower internal operation work.
In the present embodiment, it is laid at the middle part of under(-)chassis 1-4-9 and platform pedal 1-4-3 is installed, in two inner orbits It sets up to be equipped with to set up between the first laminate of platform 1-4-4, inside between the middle part of 1-4-7 and the second laminate of platform 1-4- is installed 6, as seen from the figure, both platform the first laminate 1-4-4 and platform second layer plate 1-4-6 pass through two groups of laminate installation part 1-4-5 It is installed on inner orbit 1-4-7, laminate installation part 1-4-5 is inverted U-shaped shape, is obtained using sheet metal compression moulding, platform Both first laminate 1-4-4 and platform second layer plate 1-4-6 are erected at inner orbit 1-4- by the laminate installation part 1-4-5 of two sides On 7, then know when scaling platform 1-4 telescopic moving, platform the first laminate 1-4-4 and platform second layer plate 1-4-6 also can It moves a certain distance in radial directions, the continuous level stood for operator is constituted together with platform pedal 1-4-3.
In the present embodiment, in front, the middle part of guardrail 1-4-1 is equipped with crossbeam, is equipped with front panel 1-4- in the lower section of crossbeam 2, to promote safety (avoid operator from standing too outer and fall), storage box 1-13 are additionally provided on crossbeam, is needed in operation Tool wanted etc. can be put into storage box 1-13, convenient for taking.
Driving assembly 1-6 is installed for driving 1 rotary motion of revolving platform device in the bottom of upper central frame 1-9. In order to guarantee the stability of this mounting platform driving, the bottom of upper central frame 1-9 should be equipped with shaft, in lower central frame 2-3 Inside be equipped with bearing, the shaft of revolving platform device 1 and the bearing fit of slewing supporting device.
Refer to Fig. 4 and Fig. 5, it will thus be seen that slewing supporting device 2 includes the middle frame 2-4 of rectangle, in middle frame The two sides of 2-4 are equipped with the first triangle outer framework 2-2 and the second triangle outer framework 2-6, and three constitutes the support frame of regular hexagon Frame.It is equipped with lower central frame 2-3 in the center of middle frame 2-4, between lower central frame 2-3 and middle frame 2-4 Equipped with multiple reinforcing rods, multiple reinforcing rods are equipped in the inside of both the first triangle outer framework 2-2, the second triangle outer framework 2-6. Molding seperated in this way carries out the mode of assembly and connection again, both ensure that the convenience of processing, and had in turn ensured whole device structure Intensity.
Three groups of centralising devices are installed in braced frame, every group of centralising device includes two centerings of opposite direction setting Component 2-5, each centering component 2-5 correspond to a direction (six direction altogether) of slewing supporting device (regular hexagon).
Refer to Fig. 5, it will thus be seen that centering component 2-5 includes the flexible outer sleeve 2- being fixed in braced frame 5-7 is equipped with telescopic boom 2-5-6 in flexible outer sleeve 2-5-7, inner end and flexible outer sleeve 2- in telescopic boom 2-5-6 The spring in tensional state is equipped between the middle part of 5-7 inner wall, that is, in its natural state, the elastic force that spring provides forces Telescopic boom 2-5-6 is in the state stretched out, and six centering component 2-5 are held out against from six direction to middle part, realizes revolution branch The centering (stablizing slewing supporting device 2 in the center of wind-power tower) of support arrangement 2;In the outer of telescopic boom 2-5-6 End is also equipped with universal wheel 2-5-5, and when telescopic boom 2-5-6 sufficiently stretches out, universal wheel 2-5-5 is held out against in wind-power tower On inner wall.
In the present embodiment, driving assembly 1-6 includes the ring gear for being mounted on the bottom central frame 1-9, further includes revolution electricity Machine is equipped with the driving gear with ring gear engaged transmission, under the driving of turning motor, ring gear on the motor shaft of turning motor Drive the entire revolution of revolving platform device 1 rotation.Between the top of lower central frame 2-3 and the bottom of upper central frame 1-9 Slip is installed and takes electrical component, turning motor takes electrical component to be electrically connected with slip.Power supply line is connected to the cunning of lower central frame 2-3 Line takes on electrical component, and in the revolution rotation process of revolving platform device 1, slip takes electrical component to take electricity and supply electric energy and turns round Motor.
It further include auxiliary security component, auxiliary security component includes the support rod 2- for being fixed on the outer end telescopic boom 2-5-5 5-4 is equipped with multiple rope otic placode 2-5-3 with connecting hole at the top of support rod 2-5-4, leads on rope otic placode 2-5-3 It crosses pin shaft and is fixed with rope for traction 2-1, be equipped with hook in the outer end of rope for traction 2-1.In the mistake of this mounting platform lifting moving Cheng Zhong is reached in the pre-buried hanging ring that first each hook can be hooked on inner wall of wind-power tower drum behind designated position, this installation in this way Platform (such as hanging broken cable extreme case) when losing the power of lifting suddenly, out of control will not fall, ensure that peace Quan Xing.
For the ease of carrying out hooking operation to hook, in the present embodiment, multiple extensions are additionally provided in the side of support rod 2-5-4 Frame 2-5-1 is equipped on hanger 2-5-1 and takes the retinue operating stick 2-5-2 for operating the hook for personnel.Need to operate hook When, operator removes retinue operating stick 2-5-2, and the hook of pendency is hooked in the front end of retinue operating stick 2-5-2, retinue is grasped Make bar 2-5-2 and raise realization to the operation of the hooking of tower inner wall, the operation for winning hook is also consistent.
In the present embodiment, the upper end of upper central frame 1-9 is extended upwardly to by the surface of top annular frame 1-3 encloses with fixation Column 1-11 contour position constitutes the hand steered center rest of personnel.During revolving platform device 1 slowly rotates, operation Personnel should stand in the position as close as possible apart from upper central frame 1-9, and it is hand steered help steady, avoid falling.It can from figure Out, lead to danger in order to avoid the foot of operator is inserted into upper central frame 1-9, in the present embodiment, in upper central frame A corral baffle is arranged in the bottom of 1-9.

Claims (9)

1. a kind of wind-powered electricity generation concrete tower mounting platform, it is characterized in that: including superposed revolving platform device (1) and being located at The slewing supporting device (2) of lower part;
Revolving platform device (1) includes by base circle frame (1-2), top annular frame (1-3) and between the two multiple vertical The slewing frame that strut (1-1) is constituted is equipped with upper central frame (1-9) in the center of slewing frame, in upper central frame A plurality of radiation is equipped between (1-9) and base circle frame (1-2) and top annular frame (1-3);At top annular frame (1-3) Upper laying is equipped with platform floors (1-7), is equipped with discrete four fixed fence (1- at the edge of top annular frame (1-3) 11), platform door (1-10) is equipped in the side of each fixed fence (1-11);Further include four groups to be mounted in slewing frame Platform outside track (1-8) is mounted on scaling platform (1-4) in every group platform outside track (1-8);In upper central frame (1- 9) bottom is equipped with driving assembly (1-6);
Slewing supporting device (2) includes the middle frame (2-4) of rectangle, is equipped with the one or three in the two sides of middle frame (2-4) Angle outer framework (2-2) and the second triangle outer framework (2-6), three constitute the braced frame of regular hexagon;At middle frame (2-4) Center be equipped with lower central frame (2-3), between lower central frame (2-3) and middle frame (2-4) be equipped with it is multiple add Strong bar is equipped with multiple reinforcing rods in the inside of both the first triangle outer framework (2-2), the second triangle outer framework (2-6);It is supporting Three groups of centralising devices are installed, every group of centralising device includes two centering components (2-5) of opposite direction setting in frame.
2. wind-powered electricity generation concrete tower mounting platform as described in claim 1, it is characterized in that: scaling platform (1-4) includes bottom Frame (1-4-9) is equipped with front guardrail (1-4-1) in the outer end of under(-)chassis (1-4-9);In under(-)chassis (1-4-9) The left and right sides is equipped with the inner orbit (1-4-7) of C-type steel structure, is equipped with internal trolley in the two sides of under(-)chassis (1-4-9), interior Inner orbit (1-4-7) of the idler wheel along place, which rolls, to be moved, and outer idler wheel (1-4-8) is equipped on the outside of inner orbit (1-4-7), outside Platform outside track (1-8) of the idler wheel (1-4-8) along place, which rolls, to be moved;Rack gear is installed below under(-)chassis (1-4-9) (1-4-10) is additionally provided with telescope motor (1-5) on slewing frame, is equipped on the motor shaft of telescope motor (1-5) and tooth The driving gear of item (1-4-10) engagement.
3. wind-powered electricity generation concrete tower mounting platform as claimed in claim 2, it is characterized in that: in under(-)chassis (1-4-9) Portion is laid with and is equipped with platform pedal (1-4-3), sets up between the middle part of two inner orbits (1-4-7) and is equipped with platform first layer It is set up between plate (1-4-4), inside and the second laminate of platform (1-4-6) is installed.
4. wind-powered electricity generation concrete tower mounting platform as claimed in claim 2, it is characterized in that: in front guardrail (1-4-1) Portion is equipped with crossbeam, is equipped with front panel (1-4-2) in the lower section of crossbeam, storage box (1-13) is additionally provided on crossbeam.
5. wind-powered electricity generation concrete tower mounting platform as described in claim 1, it is characterized in that: driving assembly (1-6) includes installation Ring gear in the bottom upper central frame (1-9), further includes turning motor, is equipped on the motor shaft of turning motor and nibbles with ring gear Close the driving gear of transmission;Slip is installed between the top of lower central frame (2-3) and the bottom of upper central frame (1-9) Electrical component is taken, turning motor takes electrical component to be electrically connected with slip.
6. wind-powered electricity generation concrete tower mounting platform as described in claim 1, it is characterized in that: centering component (2-5) includes installation Fixed flexible outer sleeve (2-5-7) on the support frame, is equipped with telescopic boom (2-5-6) in flexible outer sleeve (2-5-7), The bullet in tensional state is equipped between the inner end of telescopic boom (2-5-6) and the middle part of flexible outer sleeve (2-5-7) inner wall Spring;Universal wheel (2-5-5) is also equipped in the outer end of telescopic boom (2-5-6).
7. wind-powered electricity generation concrete tower mounting platform as claimed in claim 6, it is characterized in that: further include auxiliary security component, it is auxiliary Helping security component includes the support rod (2-5-4) for being fixed on the outer end telescopic boom (2-5-6), at the top of support rod (2-5-4) Equipped with multiple rope otic placodes (2-5-3) with connecting hole, rope for traction is fixed with by pin shaft on rope otic placode (2-5-3) (2-1) is equipped with hook in the outer end of rope for traction (2-1);Multiple hanger (2-5- are additionally provided in the side of support rod (2-5-4) 1) it, is equipped on hanger (2-5-1) and takes the retinue operating stick (2-5-2) for operating the hook for personnel.
8. wind-powered electricity generation concrete tower mounting platform as described in any one of claim 1 to 7, it is characterized in that: upper central frame (1- 9) upper end is extended upwardly to the position contour with fixed fence (1-11) by the surface of top annular frame (1-3), constitutes personnel Hand steered center rest.
9. wind-powered electricity generation concrete tower mounting platform as described in any one of claim 1 to 7, it is characterized in that: being enclosed in each fixation It is equipped on the outside of column (1-11) pedestals (1-12), pedestals (1-12) and base circle frame (1-2) and top annular Frame (1-3) is fixedly connected with;Being equipped in the upper end of pedestals (1-12) can be with the lifting rotating end of lateral rotation.
CN201910024983.5A 2019-01-11 2019-01-11 A kind of wind-powered electricity generation concrete tower mounting platform Pending CN109629814A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910024983.5A CN109629814A (en) 2019-01-11 2019-01-11 A kind of wind-powered electricity generation concrete tower mounting platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910024983.5A CN109629814A (en) 2019-01-11 2019-01-11 A kind of wind-powered electricity generation concrete tower mounting platform

Publications (1)

Publication Number Publication Date
CN109629814A true CN109629814A (en) 2019-04-16

Family

ID=66061752

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910024983.5A Pending CN109629814A (en) 2019-01-11 2019-01-11 A kind of wind-powered electricity generation concrete tower mounting platform

Country Status (1)

Country Link
CN (1) CN109629814A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110203858A (en) * 2019-06-24 2019-09-06 山东电力建设第三工程有限公司 Extendible dynamic formula job platform in heat absorption tower
CN111593167A (en) * 2020-06-19 2020-08-28 东风汽车有限公司 Slag removing system of large smelting furnace
CN111980867A (en) * 2020-08-04 2020-11-24 上海市机电设计研究院有限公司 Offset type diameter-changing device for telescopic section of wind power tower drum hoisting construction platform
CN112065025A (en) * 2020-09-08 2020-12-11 安徽泗州拖拉机制造有限公司 Outdoor control mechanism acting on indoor lifter and use method thereof
CN112372078A (en) * 2020-11-04 2021-02-19 芜湖天航重工股份有限公司 Auxiliary processing device for welding wind power tower cylinder
CN112901421A (en) * 2019-12-03 2021-06-04 新疆金风科技股份有限公司 Installation device and installation method of tower drum accessory

Citations (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201395931Y (en) * 2009-02-24 2010-02-03 臧世厚 Combined hanging basket for installing elevators
CN102080446A (en) * 2011-02-18 2011-06-01 中国水利水电第七工程局成都水电建设工程有限公司 Lifting platform for shaft construction
JP2011111869A (en) * 2009-11-30 2011-06-09 Asahi Gakuen Group:Kk Scaffold platform elevating structure in construction scaffolding
CN201990453U (en) * 2011-04-26 2011-09-28 湖南星邦重工有限公司 Two-stage telescopic platform applied to scissor type aerial working platform
CN202007523U (en) * 2011-02-18 2011-10-12 中国水利水电第七工程局成都水电建设工程有限公司 Construction lifting platform of shaft
CN102828609A (en) * 2012-09-24 2012-12-19 中国建筑股份有限公司 Overhanging-type mobile blanking platform for building construction
CN202924532U (en) * 2012-11-26 2013-05-08 甘肃建投装备制造有限公司 External lifter for wind electricity tower drum
KR101299618B1 (en) * 2012-05-25 2013-08-27 박인정 Elastic twisted outdoor fitness equipment
CN103419900A (en) * 2013-08-26 2013-12-04 天津修船技术研究所 Propeller inner bore centering device
CN204510843U (en) * 2015-03-24 2015-07-29 河北盛卓建筑设备制造有限公司 A kind of attaching lifting discharging platform lower support and upper double pull rod structure
CN204589814U (en) * 2015-05-04 2015-08-26 湖南鼎珩智能机械有限公司 Bridge inspection vehicle automatic telescopic platform
CN105253827A (en) * 2015-11-03 2016-01-20 太仓联洲机械设备有限公司 Pneumatic three-dimensional lifting operation platform
CN107673266A (en) * 2017-10-09 2018-02-09 苏州大方特种车股份有限公司 Bi-directional expansion hoistable platform and tunnel cleaning vehicle
CN207003637U (en) * 2017-12-01 2018-02-13 卢宗鸿 A kind of telescopic movable platform
CN207111144U (en) * 2017-07-06 2018-03-16 廊坊景隆重工机械有限公司 A kind of scaling platform and apply its Anchor Care drill carriage
CN207348429U (en) * 2017-07-24 2018-05-11 库珀(天津)科技有限公司 The rotating platform built for tower
CN207892778U (en) * 2017-11-03 2018-09-21 大唐东北电力试验研究所有限公司 Wind turbines tower assembled inside formula lift work platform
CN209482685U (en) * 2019-01-11 2019-10-11 库珀(天津)科技有限公司 A kind of wind-powered electricity generation concrete tower mounting platform

Patent Citations (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201395931Y (en) * 2009-02-24 2010-02-03 臧世厚 Combined hanging basket for installing elevators
JP2011111869A (en) * 2009-11-30 2011-06-09 Asahi Gakuen Group:Kk Scaffold platform elevating structure in construction scaffolding
CN102080446A (en) * 2011-02-18 2011-06-01 中国水利水电第七工程局成都水电建设工程有限公司 Lifting platform for shaft construction
CN202007523U (en) * 2011-02-18 2011-10-12 中国水利水电第七工程局成都水电建设工程有限公司 Construction lifting platform of shaft
CN201990453U (en) * 2011-04-26 2011-09-28 湖南星邦重工有限公司 Two-stage telescopic platform applied to scissor type aerial working platform
KR101299618B1 (en) * 2012-05-25 2013-08-27 박인정 Elastic twisted outdoor fitness equipment
CN102828609A (en) * 2012-09-24 2012-12-19 中国建筑股份有限公司 Overhanging-type mobile blanking platform for building construction
CN202924532U (en) * 2012-11-26 2013-05-08 甘肃建投装备制造有限公司 External lifter for wind electricity tower drum
CN103419900A (en) * 2013-08-26 2013-12-04 天津修船技术研究所 Propeller inner bore centering device
CN204510843U (en) * 2015-03-24 2015-07-29 河北盛卓建筑设备制造有限公司 A kind of attaching lifting discharging platform lower support and upper double pull rod structure
CN204589814U (en) * 2015-05-04 2015-08-26 湖南鼎珩智能机械有限公司 Bridge inspection vehicle automatic telescopic platform
CN105253827A (en) * 2015-11-03 2016-01-20 太仓联洲机械设备有限公司 Pneumatic three-dimensional lifting operation platform
CN207111144U (en) * 2017-07-06 2018-03-16 廊坊景隆重工机械有限公司 A kind of scaling platform and apply its Anchor Care drill carriage
CN207348429U (en) * 2017-07-24 2018-05-11 库珀(天津)科技有限公司 The rotating platform built for tower
CN107673266A (en) * 2017-10-09 2018-02-09 苏州大方特种车股份有限公司 Bi-directional expansion hoistable platform and tunnel cleaning vehicle
CN207892778U (en) * 2017-11-03 2018-09-21 大唐东北电力试验研究所有限公司 Wind turbines tower assembled inside formula lift work platform
CN207003637U (en) * 2017-12-01 2018-02-13 卢宗鸿 A kind of telescopic movable platform
CN209482685U (en) * 2019-01-11 2019-10-11 库珀(天津)科技有限公司 A kind of wind-powered electricity generation concrete tower mounting platform

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110203858A (en) * 2019-06-24 2019-09-06 山东电力建设第三工程有限公司 Extendible dynamic formula job platform in heat absorption tower
CN112901421A (en) * 2019-12-03 2021-06-04 新疆金风科技股份有限公司 Installation device and installation method of tower drum accessory
CN111593167A (en) * 2020-06-19 2020-08-28 东风汽车有限公司 Slag removing system of large smelting furnace
CN111980867A (en) * 2020-08-04 2020-11-24 上海市机电设计研究院有限公司 Offset type diameter-changing device for telescopic section of wind power tower drum hoisting construction platform
CN111980867B (en) * 2020-08-04 2021-11-02 上海市机电设计研究院有限公司 Offset type diameter-changing device for telescopic section of wind power tower drum hoisting construction platform
CN112065025A (en) * 2020-09-08 2020-12-11 安徽泗州拖拉机制造有限公司 Outdoor control mechanism acting on indoor lifter and use method thereof
CN112372078A (en) * 2020-11-04 2021-02-19 芜湖天航重工股份有限公司 Auxiliary processing device for welding wind power tower cylinder
CN112372078B (en) * 2020-11-04 2022-09-20 芜湖天航重工股份有限公司 Auxiliary processing device for welding wind power tower cylinder

Similar Documents

Publication Publication Date Title
CN109629814A (en) A kind of wind-powered electricity generation concrete tower mounting platform
CN201999649U (en) Movable tower crane
CN203064069U (en) Dynamic climbing device of tower
JP5719975B2 (en) Wind energy turbine shell station
CN204848019U (en) Cantilever crane
CN209482685U (en) A kind of wind-powered electricity generation concrete tower mounting platform
CN106089575A (en) There is the Anti-Typhoon ocean wind power generation platform of folding blade
CN203295110U (en) Detection platform for blades of wind tower barrel
CN208327235U (en) A kind of building machinery hoistable platform convenient for adjusting
CN209482686U (en) A kind of revolving platform device of wind-powered electricity generation concrete tower mounting platform
CN209482684U (en) A kind of slewing frame device of wind-powered electricity generation concrete tower mounting platform
CN206645735U (en) A kind of engineering arrangement for crane machinery arm assembly of high security
CN207078954U (en) Cable type drive device
CN204474193U (en) A kind of Pillar-fixing Type Slewing Crane
CN107476560B (en) Wind power tower construction platform and method
CN103306218A (en) Bottom width overhaul hanging basket of bridge
CN204922762U (en) Improved generation street lamp convenient to it is folding
CN209503282U (en) It is a kind of for welding the rotary workbench of wind power foundation tower
CN209482683U (en) A kind of centralising device of wind-powered electricity generation concrete tower mounting platform
CN212832684U (en) Self-propelled combined lifting multifunctional aerial work platform truck
CN208716716U (en) Wind-power electricity generation installs loop wheel machine
CN203452004U (en) Bottom width overhaul hanging basket of bridge
CN104037661B (en) A kind of all direction multifunctional power transmission and transformation installation, repairing auxiliary device
CN106639609A (en) Tower frame convenient to install and maintain
CN206091254U (en) Whole construction scaffold frame of track formula of climbing

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 300000 No. 20, Hongxing Road, cuihuangkou Town, Wuqing District, Tianjin

Applicant after: Cooper new energy Co.,Ltd.

Address before: 301700 102-8, No. 56, Laiyu Road, huanghuadian Town, Wuqing District, Tianjin

Applicant before: COOPER (TIANJIN) TECHNOLOGY CO.,LTD.

CB02 Change of applicant information
RJ01 Rejection of invention patent application after publication

Application publication date: 20190416