CN109628704A - A kind of RH vacuum refining furnace and its building method - Google Patents

A kind of RH vacuum refining furnace and its building method Download PDF

Info

Publication number
CN109628704A
CN109628704A CN201910117309.1A CN201910117309A CN109628704A CN 109628704 A CN109628704 A CN 109628704A CN 201910117309 A CN201910117309 A CN 201910117309A CN 109628704 A CN109628704 A CN 109628704A
Authority
CN
China
Prior art keywords
brick
working lining
circulating pipe
pipe
castable
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910117309.1A
Other languages
Chinese (zh)
Other versions
CN109628704B (en
Inventor
涂方兵
王建华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ruitai Masteel New Material Technology Co ltd
Original Assignee
Anhui Xinhai Environmental Protection New Material Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Xinhai Environmental Protection New Material Co Ltd filed Critical Anhui Xinhai Environmental Protection New Material Co Ltd
Priority to CN201910117309.1A priority Critical patent/CN109628704B/en
Publication of CN109628704A publication Critical patent/CN109628704A/en
Application granted granted Critical
Publication of CN109628704B publication Critical patent/CN109628704B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21CPROCESSING OF PIG-IRON, e.g. REFINING, MANUFACTURE OF WROUGHT-IRON OR STEEL; TREATMENT IN MOLTEN STATE OF FERROUS ALLOYS
    • C21C7/00Treating molten ferrous alloys, e.g. steel, not covered by groups C21C1/00 - C21C5/00
    • C21C7/10Handling in a vacuum

Abstract

The invention discloses a kind of RH vacuum refining furnace and its building methods, belong to the metallurgical external refining masonry technology of resistance to material field.RH vacuum refining furnace mainly includes steel shell, the first insulating brick, the second insulating brick, safe floor castable, working lining wall brick, working lining bottom brick, ramming mass, joint sealing material, circulating pipe, dip pipe.Safe floor substitutes traditional brickwork construction using whole knotting castable, and globality and safety are good;When the temperature distortion of steel shell bottom is repaired, the first insulating brick, the second insulating brick, safe floor castable do not need whole dismountings, long service life;Can be different according to each position melting loss of resistance to material rate, working lining wall brick and safe floor castable thickness are adjusted, resistance to material dosage is reduced;Dip pipe and circulating pipe are an overall structure, are installed using jacking apparatus from bottom, when process replaces dip pipe and circulating pipe, do not need to remove circulating pipe top working lining wall brick, further save resistance to material dosage, reduce costs.

Description

A kind of RH vacuum refining furnace and its building method
Technical field
The invention belongs to the metallurgical external refining masonry technology of resistance to material fields, and in particular, to a kind of RH vacuum refining furnace and Its building method.
Background technique
RH SECONDARY REFINING IN A VACUUM CHAMBER originates from the fifties, and nineteen fifty-seven A Erbeide, company applied for vacuum refining of liquid steel degassing method Technical patent, this is the beginning of vacuum outgas method development, with the exploitation and development of vacuum steel-smelting technology, final RH and VD because For short processing time, the at low cost, mainstream that can largely handle the advantages that molten steel and become vacuum steel-smelting technology, start the seventies With the appearance in sequence casting workshop, RH is because using molten steel in the technology of vacuum tank circulation to reach short processing time, efficiency High, the advantages of capable of being matched with revolving furnace continuous casting and largely used by converter procedure.
Vacuum furnace structure is made of vacuum tank, and a pair of circulating pipe and dip pipe and argon gas pipeline welding.Shell, very It is built into slack tank with refractory brick, circulating pipe and the effective refractory material casting forming of dipping.
When RH vacuum fine is made steel, dip pipe is immersed in ladle tank, molten steel passes through under argon gas promotion from dip pipe is risen Circulating pipe flows into vacuum tank, then flows through decline dip pipe through declining circulating pipe out of vacuum tank, flows back in ladle tank, this true Sky smelts the purity that purpose improves steel, reaches high quality and requires steel.
In existing RH vacuum refining furnace technology, one layer of safe floor is built between vacuum drying oven insulating brick and working lining wall brick Brick, easy to damage in safe floor brick use process, service life is low, and globality poor, and brickwork joint is more, cannot play good protection Property;When newly repairing with process replacement dip pipe, dip pipe first is welded from bottom, then circulating pipe is installed down from top, it is complicated for operation, Large area is needed to remove working lining wall brick simultaneously, circulating pipe could be installed, and material consumption is serious;Vacuum furnace bottom flange distortion or Damage when needing replacing, needs all to remove insulating layer brick, safe floor brick, waste of material is serious.
Summary of the invention
The purpose of the present invention is to provide a kind of RH vacuum refining furnace and its building methods, can reduce RH vacuum refining furnace Refractory consumption improves service life, and mitigates labor intensity when replacement dip pipe and circulating pipe.
The purpose of the present invention can be achieved through the following technical solutions:
A kind of RH vacuum refining furnace flows into or out device including the vacuum furnace device being located above and underlying steel, institute Stating vacuum furnace device includes the steel shell set gradually from outside to inside, the first insulating brick, the second insulating brick, safe floor and working lining Wall brick, the steel shell are the shells of entire RH vacuum melting furnace, and the lower end of the steel shell is fixed with herringbone flange;The steel The inside of shell, which is built, first heat-insulated turn, and the inside of first insulating brick, which is built, the second insulating brick, second insulating brick Inner distance the second insulating brick inner surface 50-60mm at build have working lining wall brick, the second thermal insulation layer and working lining It is filled between wall brick using safe floor castable;
It includes working lining bottom brick, ramming mass, joint sealing material, circulating pipe, dip pipe, the working lining that the steel, which flows into or out device, Bottom brick is built is filled with ramming mass between the side of circulating pipe, the working lining bottom brick and circulating pipe;The circulating pipe it is upper Portion and work wall brick are fitted close, and the dip pipe is built in the lower section of circulating pipe, and the dip pipe and circulating pipe are integral The peripheral clearance of structure, the circulating pipe is filled with joint sealing material;The circulating pipe positioned at left side forms steel with dip pipe and flows into Mouthful, the circulating pipe and dip pipe positioned at right side form steel outflux.
Further, the castable of the safe floor castable is corundum pouring material, and raw material forms critical granularity 5- 8mm pours thickness >=50mm.
Further, the contact surface of the circulating pipe and dip pipe is connected and fixed using ratcheting fashion.
Further, the joint sealing material is corundum material, amount of water 5-6%.
Further, the working lining wall brick, working lining bottom brick are magnesia-spinel brick or magnesite-chrome brick.
A kind of RH vacuum refining furnace building method, includes the following steps:
Step S1, dip pipe and circulating pipe are assembled into an overall structure, dip pipe upper end lining brick and circulating pipe lower end are adopted It is connected and fixed with ratcheting fashion;
Step S2, using jacking apparatus, assembled dip pipe and circulating pipe are installed and is welded and fixed from steel shell bottom On the herringbone flange of steel shell;
Step S3, circulating pipe peripheral clearance is tamped using joint sealing material;
Step S4, the first insulating brick, the second insulating brick and working lining bottom brick are built, is protected between working lining bottom brick and circulating pipe The gap 60-80mm is held, gap is consolidated using ramming mass;
Step S5, working lining wall brick is built, the gap 50-60mm is kept between working lining wall brick and the second insulating brick;
Step S6, working lining wall brick and the gap of the second insulating brick are tamped using corundum safe floor castable, safe floor Castable raw material forms critical granularity 3-5mm, completes overhaul and builds, come into operation after baking, completes the block of RH vacuum melting furnace It builds.
Beneficial effects of the present invention:
1, safe floor is integrally knotted using corundum castable substitutes traditional brickwork construction, and the service life is enhanced about more than once, and just Beautiful castable price is lower than the price of brick, and cost reduces;
2, operational layer brick is first built, then pours safe floor castable, it can be according to the resistance to material use environment in each position and melting loss Rate is different, adjusts working lining wall brick and safe floor castable thickness, saves resistance to material dosage;
3, dip pipe and circulating pipe are fabricated to an overall structure, are installed using jacking apparatus from bottom, process replacement leaching When stain pipe and circulating pipe, does not need to remove circulating pipe top operational layer brick, masonry is also reduced while saving resistance to material dosage Labor intensity.
Detailed description of the invention
In order to facilitate the understanding of those skilled in the art, the present invention will be further described below with reference to the drawings.
Fig. 1 is a kind of structural schematic diagram of RH vacuum refining furnace of the present invention;
Figure label: 1- steel shell, the first insulating brick of 2-, the second insulating brick of 3-, 4- safe floor castable, 5- working lining wall Brick, 6- working lining bottom brick, 7- ramming mass, 8- joint sealing material, 9- circulating pipe, 10- dip pipe, 11- herringbone flange.
Specific embodiment
Technical solution of the present invention is clearly and completely described below in conjunction with embodiment, it is clear that described reality Applying example is only a part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, this field is general Logical technical staff all other embodiment obtained without creative efforts belongs to what the present invention protected Range.
A kind of RH vacuum refining furnace, as shown in Figure 1, including that the vacuum furnace device being located above and underlying steel flow into Device out, vacuum furnace device include the steel shell 1 set gradually from outside to inside, the first insulating brick 2, the second insulating brick 3, safe floor 4, With working lining wall brick 5, steel shell 1 is the shell of entire RH vacuum melting furnace, and the lower end of steel shell 1 is fixed with herringbone flange 11; The inside of steel shell 1, which is built, first heat-insulated turn 2, and the inside of the first insulating brick 2, which is built, the second insulating brick 3, the second insulating brick 3 Building at 3 inner surface 50-60mm of the second insulating brick of inner distance has working lining wall brick 5, second thermal insulation layer 3 and working lining wall brick It is filled between 5 using safe floor castable 4, safe floor castable 4 substitutes traditional brickwork construction using whole knotting castable, Globality and safety are good;Preferably, the castable of safe floor castable 4 is corundum pouring material, and raw material forms critical granularity 5-8mm, good flowing properties pour thickness >=50mm;The building method of working lining wall brick 5, safe floor castable 4 are as follows: first build Working lining wall brick 5, then safe floor castable 4 is poured, it so can be different with melting loss rate according to the resistance to material use environment in each position, The thickness for adjusting working lining wall brick 5 and safe floor castable 4, reduces resistance to material dosage;
When 1 bottom temperature distortion of steel shell is repaired, the castable of safe floor 4 does not need whole dismountings, long service life;
It includes working lining bottom brick 6, ramming mass 7, joint sealing material 8, circulating pipe 9, dip pipe 10, working lining bottom that steel, which flows into or out device, Brick 6 is built is filled with ramming mass 7 between the side of circulating pipe 9, working lining bottom brick 6 and circulating pipe 9;The top of circulating pipe 9 with Working lining 5 is fitted close, and dip pipe 10, which is built, is integral structure, ring in the lower section of circulating pipe 9, dip pipe 10 and circulating pipe 9 Flow tube 9 is connect with the contact surface (the bottom end lining brick of dip pipe 10 upper end lining brick and circulating pipe 9) of dip pipe 10 using ratcheting fashion Fixed, globality is strong;The peripheral clearance of circulating pipe 9 is filled with joint sealing material 8, joint sealing material 8 is corundum material, amount of water 5-6%; Circulating pipe 9 and dip pipe 10 positioned at left side form steel and flow into mouth, and the circulating pipe 9 and dip pipe 10 positioned at right side form steel outflow Mouthful, when RH vacuum fine is made steel, dip pipe 10 is immersed in molten steel color tank, molten steel passes through under argon gas promotion from left side dip pipe 10 It crosses left side circulating pipe 9 to flow into vacuum tank, then flows through right side dip pipe 10 through right side circulating pipe 9 out of vacuum tank, flow back to molten steel It in packet tank, is recycled one time by 30 minutes 260 tons of molten steel, improves the purity of steel, reached high quality and require steel;
Dip pipe 10 and circulating pipe 9 are an overall structure, are installed using jacking apparatus from bottom, process replaces dip pipe 10 and when circulating pipe 9, it does not need to remove 9 top operational layer brick of circulating pipe, further saves resistance to material dosage, reduce into This;
Working lining wall brick 5, working lining bottom brick 6 are magnesia-spinel brick or magnesite-chrome brick;
RH vacuum refining furnace building method, includes the following steps:
Step S1, dip pipe 10 and circulating pipe 9 are assembled into an overall structure, 10 upper end lining brick of dip pipe and circulating pipe 9 Lower end is connected and fixed using ratcheting fashion;
Step S2, using jacking apparatus, assembled dip pipe 10 and circulating pipe 9 are installed and is welded from 1 bottom of steel shell It is fixed on the herringbone flange 11 of steel shell 1;
Step S3,9 peripheral clearance of circulating pipe is tamped using joint sealing material 8;
Step S4, the first insulating brick 2, the second insulating brick 3 and working lining bottom brick 6, working lining bottom brick 6 and circulating pipe 9 are built Between keep the gap 60-80mm, gap is consolidated using ramming mass 7;
Step S5, working lining wall brick 5 is built, the gap 50-60mm is kept between working lining wall brick 5 and the second insulating brick 3;
Step S6, working lining wall brick 5 and the gap of the second insulating brick 3 are tamped using corundum safe floor castable 4, safety Layer 4 raw material of castable forms critical granularity 3-5mm, completes overhaul and builds, come into operation after baking, completes RH vacuum melting furnace It builds;
Wherein, main to replace circulating pipe 9 and dip pipe 10, replacement when being built by laying in RH vacuum refining furnace later period use process It is identical that method and RH vacuum refining furnace repair method entirely, does not need to remove 9 top working lining wall brick 5 of circulating pipe;
1 bottom of steel shell is because heated be deformed, and when repairing and replacing, safe floor castable 4 is not required to remove, and the service life mentions It is high.
Present invention disclosed above preferred embodiment is only intended to help to illustrate the present invention.There is no detailed for preferred embodiment All details are described, are not limited the invention to the specific embodiments described.Obviously, according to the content of this specification, It can make many modifications and variations.These embodiments are chosen and specifically described to this specification, is in order to better explain the present invention Principle and practical application, so that skilled artisan be enable to better understand and utilize the present invention.The present invention is only It is limited by claims and its full scope and equivalent.

Claims (6)

1. a kind of RH vacuum refining furnace, which is characterized in that flowed into including the vacuum furnace device being located above and underlying steel Device out, the vacuum furnace device include the steel shell (1) set gradually from outside to inside, the first insulating brick (2), the second insulating brick (3), safe floor castable (4) and working lining wall brick (5), the steel shell (1) are the shell of entire RH vacuum melting furnace, the steel The lower end of shell (1) is fixed with herringbone flange (11);The inside of the steel shell (1), which is built, to be had first heat-insulated turn (2), and described the The inside of one insulating brick (2), which is built, to be had the second insulating brick (3), the second insulating brick of inner distance (3) of second insulating brick (3) Building at inner surface 50-60mm has working lining wall brick (5), uses between the second thermal insulation layer (3) and working lining wall brick (5) Safe floor castable (4) filling;
It includes working lining bottom brick (6), ramming mass (7), joint sealing material (8), circulating pipe (9), dip pipe that the steel, which flows into or out device, (10), the working lining bottom brick (6) builds between the side of circulating pipe (9), the working lining bottom brick (6) and circulating pipe (9) Filled with ramming mass (7);The top and working lining (5) of the circulating pipe (9) are fitted close, and the dip pipe (10) builds in ring The lower section of flow tube (9), the dip pipe (10) and circulating pipe (9) are integral structure, and the peripheral clearance of the circulating pipe (9) is filled out Filled with joint sealing material (8);Steel is formed positioned at the circulating pipe (9) in left side and dip pipe (10) and flows into mouth, described in right side Circulating pipe (9) and dip pipe (10) form steel outflux.
2. a kind of RH vacuum refining furnace according to claim 1, which is characterized in that the safe floor castable (4) is rigid Beautiful matter castable, raw material form critical granularity 5-8mm, pour thickness >=50mm.
3. a kind of RH vacuum refining furnace according to claim 1, which is characterized in that the circulating pipe (9) and dip pipe (10) contact surface is connected and fixed using ratcheting fashion.
4. a kind of RH vacuum refining furnace according to claim 1, which is characterized in that the joint sealing material (8) is corundum material, Amount of water 5-6%.
5. a kind of RH vacuum refining furnace according to claim 1, which is characterized in that the working lining wall brick (5), working lining Bottom brick (6) is magnesia-spinel brick or magnesite-chrome brick.
6. a kind of RH vacuum refining furnace building method, which comprises the steps of:
Step S1, dip pipe (10) and circulating pipe (9) are assembled into an overall structure, dip pipe (10) upper end lining brick and circulating pipe (9) lower end is connected and fixed using ratcheting fashion;
Step S2, using jacking apparatus, assembled dip pipe (10) and circulating pipe (9) are installed and is welded from steel shell (1) bottom It connects on the herringbone flange (11) for being fixed on steel shell (1);
Step S3, circulating pipe (9) peripheral clearance is tamped using joint sealing material (8);
Step S4, the first insulating brick (2), the second insulating brick (3) and working lining bottom brick (6), working lining bottom brick (6) and circulation are built It manages and keeps the gap 60-80mm between (9), gap is consolidated using ramming mass (7);
Step S5, working lining wall brick (5) are built, the gap 50-60mm is kept between working lining wall brick (5) and the second insulating brick (3);
Step S6, working lining wall brick (5) and the gap of the second insulating brick (3) are tamped using corundum safe floor castable (4), are pacified Holostrome castable (4) raw material forms critical granularity 3-5mm, completes overhaul and builds, come into operation after baking, completes RH vacuum melting The masonry of furnace.
CN201910117309.1A 2019-02-15 2019-02-15 RH vacuum refining furnace and building method thereof Active CN109628704B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910117309.1A CN109628704B (en) 2019-02-15 2019-02-15 RH vacuum refining furnace and building method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910117309.1A CN109628704B (en) 2019-02-15 2019-02-15 RH vacuum refining furnace and building method thereof

Publications (2)

Publication Number Publication Date
CN109628704A true CN109628704A (en) 2019-04-16
CN109628704B CN109628704B (en) 2020-11-17

Family

ID=66065301

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910117309.1A Active CN109628704B (en) 2019-02-15 2019-02-15 RH vacuum refining furnace and building method thereof

Country Status (1)

Country Link
CN (1) CN109628704B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113894923A (en) * 2021-09-30 2022-01-07 营口市瑞福来耐火材料有限公司 Integral forming production method of dip pipe and integral forming dip pipe

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201128745Y (en) * 2007-11-22 2008-10-08 宝山钢铁股份有限公司 Large circulation dip pipe for vacuum degassing device
CN202671581U (en) * 2012-06-14 2013-01-16 鞍钢股份有限公司 Vacuum circulating degassing furnace bottom groove
CN102978345A (en) * 2012-12-24 2013-03-20 武汉钢铁(集团)公司 Low-chrome refractory material RH refining furnace and building method thereof
CN204097510U (en) * 2014-09-30 2015-01-14 洛阳利尔耐火材料有限公司 A kind of RH vacuum refining furnace configuring chromium-free brick
CN205289726U (en) * 2015-12-18 2016-06-08 武汉钢铁(集团)公司 Permanent layer pouring body of improved generation combined type ladle
CN205821375U (en) * 2016-06-29 2016-12-21 中钢集团耐火材料有限公司 A kind of RH refining furnace vacuum chamber task layer structure-improved
CN106623883A (en) * 2016-12-14 2017-05-10 山东钢铁股份有限公司 Integral pouring process for large steel ladle
CN206768167U (en) * 2017-04-24 2017-12-19 洛阳利尔耐火材料有限公司 A kind of masonry construction of RH refining furnaces lower channel

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201128745Y (en) * 2007-11-22 2008-10-08 宝山钢铁股份有限公司 Large circulation dip pipe for vacuum degassing device
CN202671581U (en) * 2012-06-14 2013-01-16 鞍钢股份有限公司 Vacuum circulating degassing furnace bottom groove
CN102978345A (en) * 2012-12-24 2013-03-20 武汉钢铁(集团)公司 Low-chrome refractory material RH refining furnace and building method thereof
CN204097510U (en) * 2014-09-30 2015-01-14 洛阳利尔耐火材料有限公司 A kind of RH vacuum refining furnace configuring chromium-free brick
CN205289726U (en) * 2015-12-18 2016-06-08 武汉钢铁(集团)公司 Permanent layer pouring body of improved generation combined type ladle
CN205821375U (en) * 2016-06-29 2016-12-21 中钢集团耐火材料有限公司 A kind of RH refining furnace vacuum chamber task layer structure-improved
CN106623883A (en) * 2016-12-14 2017-05-10 山东钢铁股份有限公司 Integral pouring process for large steel ladle
CN206768167U (en) * 2017-04-24 2017-12-19 洛阳利尔耐火材料有限公司 A kind of masonry construction of RH refining furnaces lower channel

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
于勇等: "浇注料", 《现代连续铸钢实用手册》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113894923A (en) * 2021-09-30 2022-01-07 营口市瑞福来耐火材料有限公司 Integral forming production method of dip pipe and integral forming dip pipe

Also Published As

Publication number Publication date
CN109628704B (en) 2020-11-17

Similar Documents

Publication Publication Date Title
CN108176844B (en) A kind of device and method for clearing up tundish upper nozzle dross object
CN109628704A (en) A kind of RH vacuum refining furnace and its building method
CN104529485B (en) Two-layer compound refractory material and two-layer compound refractory material ditch cover and its manufacture method and application
CN206572944U (en) A kind of aluminium alloy semi-solid die casting immersion electrical heating pool holding furnace
CN106111970A (en) A kind of device and method being reduced ladle top slag oxidisability by excessive slag method
CN104451008A (en) Construction method for automatically-flowing refractory castable of blast furnace
CN109909460B (en) Production method of ingot mold for ultra-pure special steel
CN114905033B (en) Hot-metal bottle structure with heating function
CN107243623B (en) Steel ladle with vacuum layer
CN213195603U (en) Novel assembled aluminium liquid chute
CN210796513U (en) Blast furnace foundation gas leakage plugging structure
CN114247876A (en) Ladle stuffing sand adding device and method
CN110842183A (en) Steel ladle cover and manufacturing method thereof
CN216192472U (en) Sectional type composite desulfurization spray gun
CN111719037A (en) Method for increasing number of continuous casting furnaces of double-flow plate blank tundish
CN204177202U (en) A kind of refractory brick improving the stove life-span
CN217677614U (en) Corrosion-resistant blast furnace iron runner
CN219425608U (en) Water trough for subcontracting spheroidization
CN215593110U (en) Connection structure of iron flowing groove and side iron adding groove
CN103722156B (en) A kind of casting method of cooling plate provided with steel tube casted in copper base and used for submerged arc furnace
CN209578145U (en) A kind of casting device
CN214977712U (en) Iron ladle repairing structure for casting and building combined blast furnace
CN207188776U (en) Ladle heat insulation steel ladle cover in a kind of steelmaking process
CN220507663U (en) Molten aluminum transfer device of centralized melting furnace
CN212205674U (en) Communicating vessel type electric smelting magnesium oxide smelting cooling device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: A RH vacuum refining furnace and its masonry method

Effective date of registration: 20210204

Granted publication date: 20201117

Pledgee: Anhui Ma'anshan Rural Commercial Bank Co.,Ltd.

Pledgor: ANHUI XINHAI ENVIRONMENTAL PROTECTION NEW MATERIAL Co.,Ltd.

Registration number: Y2021980001029

PE01 Entry into force of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20211103

Granted publication date: 20201117

Pledgee: Anhui Ma'anshan Rural Commercial Bank Co.,Ltd.

Pledgor: ANHUI XINHAI ENVIRONMENTAL PROTECTION NEW MATERIAL Co.,Ltd.

Registration number: Y2021980001029

PC01 Cancellation of the registration of the contract for pledge of patent right
TR01 Transfer of patent right

Effective date of registration: 20231011

Address after: 243000 No.8, dingzhouqiao Road, Yushan District, Maanshan City, Anhui Province

Patentee after: RUITAI MASTEEL NEW MATERIAL TECHNOLOGY Co.,Ltd.

Address before: No. 155 Huxi South Road, Ma'anshan City, Anhui Province, 243000

Patentee before: ANHUI XINHAI ENVIRONMENTAL PROTECTION NEW MATERIAL Co.,Ltd.

TR01 Transfer of patent right