CN109610443A - A kind of construction method for collapsibility soil body stake - Google Patents

A kind of construction method for collapsibility soil body stake Download PDF

Info

Publication number
CN109610443A
CN109610443A CN201811635353.3A CN201811635353A CN109610443A CN 109610443 A CN109610443 A CN 109610443A CN 201811635353 A CN201811635353 A CN 201811635353A CN 109610443 A CN109610443 A CN 109610443A
Authority
CN
China
Prior art keywords
stake
stake holes
upper section
holes
poured
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811635353.3A
Other languages
Chinese (zh)
Inventor
周同和
孙文怀
张满中
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201811635353.3A priority Critical patent/CN109610443A/en
Publication of CN109610443A publication Critical patent/CN109610443A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Agronomy & Crop Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention belongs to technical field of building construction, and in particular to a kind of construction method for collapsibility soil body stake comprises the steps of: (1) upper section stake holes: squeezing to form upper section stake holes using static pressure compaction hole forming method;(2) lower section stake holes:, which being drilled using long-spiral drilling machine through upper section, and continues soil rotary drilling downwards removes section drilling, forms stake holes;(3) use pours material and is poured from bottom to top to the designed elevation of stake holes, material solidification to be poured, and forms pile foundation or composite foundation reinforcement.The present invention can be under the small-pitch demand of stake, preparatory batch soil compaction pore-forming pours in batches again, avoid conventional driven cast-in-place pile, static pressure or hammering precast concrete pile, under the same conditions, stake spacing is smaller, and carrying out the soil compaction effect that batch construction is formed leads to the broken pile that construction stake has generated, pile body cracking and other issues.

Description

A kind of construction method for collapsibility soil body stake
Technical field
The invention belongs to technical field of building construction, and in particular to a kind of construction method for collapsibility soil body stake.
Background technique
Static pressure compaction pore-forming production pile foundation is usually used in collapsible loess foundation treatment process, existing static pressure compaction pore-forming There are mainly two types of the methods for making pile foundation, and one is being perfused after immersed tube soil compaction, this method is to use Static pressure pile driver by rounded pencil In shape steel pipe indentation soil, then into pipe concrete perfusion or other at pile material, extract immersed tube in perfusion;Another kind is to use Pile for prestressed pipe is squeezed into and forms pile foundation in soil by the methods of static pressure or hammering.During making multiple pile foundations, when stake spacing The collapsibility that cannot play the role of eliminating soil when larger needs the native stake of otherwise designed construction or lime soil pile with Compaction variables, phase To duration longer higher cost, it is unfavorable for construction fugitive dust improvement;Stake spacing above two method when smaller, during soil compaction The pile foundation for closing on completion of having constructed may be impacted, the pile foundation constructed generates the risks such as broken pile, deviation, cracking, therefore The prior art needs further improve.
Summary of the invention
The purpose of the present invention is to provide a kind of Compaction variables can pour to form pile foundation or compound simultaneously in batches in advance The construction method for the stake of the collapsibility soil body of ground reinforcement.
Based on above-mentioned purpose, the present invention is adopted the following technical scheme that:
A kind of construction method for collapsibility soil body stake, comprises the steps of:
(1) it upper section stake holes: squeezes to form upper section stake holes using static pressure compaction hole forming method;
(2) lower section stake holes:, which being drilled using long-spiral drilling machine through upper section, and continues soil rotary drilling downwards removes section drilling, shape At stake holes;
(3) use pours material and is poured from bottom to top to the designed elevation of stake holes, material solidification to be poured, and forms stake.
Further, the length of the upper section stake holes is greater than collapsibility the thickness of the layer 1-2m.
Further, the horizontal plane of the length direction of the stake holes and ground.
Further, the stake in the step (3) is pile foundation or composite foundation reinforcement.
Use the method for above-mentioned preparation method batch making stake, which is characterized in that comprise the steps of:
(1) several upper section stake holes first are squeezed using static pressure compaction hole forming method;
(2) successively reuse long-spiral drilling machine through upper section drill and continue soil rotary drilling downwards remove section drilling, formation Stake holes;
(3) use pours material and pours several stake holes one by one, and material solidification to be poured forms stake.
The present invention is forming several upper section stake holes using static pressure compaction hole forming method first when batch forms stake holes, due to The length of upper section stake holes is merely greater than collapsibility the thickness of the layer 1-2m, therefore after first upper section stake holes is formed, in adjacent bit When setting production second upper section drilling, since the length of its second upper section drilling is relatively short, to first upper section stake holes Influence is smaller, while the present invention also uses long-spiral drilling machine successively to carry out secondary cutting one by one to several upper section stake holes, drills through down Section drilling, long-spiral drilling machine are not only again corrected the aperture of upper section stake holes, prevent during secondary cutting When making upper section stake holes using static pressure compaction hole forming method, adjacent upper section stake holes interacts the deformation of generation, influences stake holes Size.In addition, using method of the invention can first batch making stake holes, poured in batches, greatly reduce the construction time, Increase working efficiency.
Detailed description of the invention
Fig. 1 is the schematic diagram that Static pressure pile driver is in place in embodiment 1 or embodiment 2;
Fig. 2 is the schematic diagram that upper section stake holes is squeezed in embodiment 1 or embodiment 2;
Fig. 3 is the drill bit that Static pressure pile driver is extracted in embodiment 1 or embodiment 2;
Fig. 4 is the schematic diagram that lower section stake holes is drilled through in embodiment 1 or embodiment 2;
Fig. 5 is the schematic diagram of the revolving process of long-spiral drilling machine in embodiment 1 or embodiment 2;
Fig. 6 is the schematic diagram that the drill bit of long-spiral drilling machine is extracted in embodiment 1 or embodiment 2;
Fig. 7 is the schematic diagram poured in embodiment 1 to stake holes;
Fig. 8 is the schematic diagram that steel reinforcement cage is placed in embodiment 2;
Fig. 9 is the schematic diagram poured in embodiment 2 to stake holes.
Specific embodiment
Embodiment 1:
A kind of construction method for collapsibility soil body stake, comprises the steps of:
(1) it upper section stake holes 1: squeezes to form upper section stake holes 1 using static pressure compaction hole forming method;
(2) lower section stake holes 2:, which being drilled using long-spiral drilling machine through upper section, and continues soil rotary drilling downwards removes section drilling, Form stake holes;
(3) use pours material and is poured from bottom to top to the designed elevation of stake holes, material solidification to be poured, and forms stake.
The length of the upper section stake holes 1 be greater than collapsibility the thickness of the layer 1.5m, the length direction of the stake holes with The horizontal plane on ground.
Using the method for above-mentioned preparation method batch making stake, comprise the steps of:
(1) several upper section stake holes 1 first are squeezed using static pressure compaction hole forming method;
(2) successively reuse long-spiral drilling machine through upper section drill and continue soil rotary drilling downwards remove section drilling, formation Stake holes;
(3) use pours material and pours several stake holes one by one, and material solidification to be poured forms stake.
The static pressure compaction hole forming method is to squeeze upper section stake holes 1 using Static pressure pile driver.
This method can be used for the construction of reinforcement in composite foundation, and the material that pours is plain concrete, cement mortar Deng.
It is first as shown in Figure 1, Static pressure pile driver is in place in work progress, then as shown in Fig. 2, use static pressure compaction hole forming method Squeeze upper section stake holes 1, then as shown in figure 3, extract the drill bit of Static pressure pile driver, then as shown in figure 4, the drill bit of long-spiral drilling machine from upper Section stake holes 1 bottom drills down to lower section stake holes 2, then as shown in figure 5, long-spiral drilling machine revolving process, then as shown in fig. 6, pull out The drill bit of long-spiral drilling machine out, then as shown in fig. 7, stake holes is poured.
Embodiment 2:
A kind of construction method for collapsibility soil body stake, comprises the steps of:
(1) it upper section stake holes 1: squeezes to form upper section stake holes 1 using static pressure compaction hole forming method;
(2) lower section stake holes 2:, which being drilled using long-spiral drilling machine through upper section, and continues soil rotary drilling downwards removes section drilling, Form stake holes;
(3) use pours material and is poured from bottom to top to the designed elevation of stake holes, material solidification to be poured, and forms stake.
The length of the upper section stake holes 1 is greater than collapsibility the thickness of the layer 1m, the length direction and ground of the stake holes The horizontal plane in face.When this method is used for pile foundation construction, in above-mentioned steps (3), steel reinforcement cage need to be added in stake holes, then It is poured.
Use the method for above-mentioned preparation method batch making stake, which is characterized in that comprise the steps of:
(1) several upper section stake holes 1 first are squeezed using static pressure compaction hole forming method;
(2) successively reuse long-spiral drilling machine through upper section drill and continue soil rotary drilling downwards remove section drilling, formation Stake holes;
(3) use pours material and pours several stake holes one by one, and material solidification to be poured forms stake.
The static pressure compaction hole forming method is to squeeze upper section stake holes 1 using Static pressure pile driver.
When this method is used for pile foundation construction, in above-mentioned steps (3), steel reinforcement cage need to be added in stake holes, then poured It builds.
It is first as shown in Figure 1, Static pressure pile driver is in place in work progress, then as shown in Fig. 2, use static pressure compaction hole forming method Squeeze upper section stake holes 1, then as shown in figure 3, extract the drill bit of Static pressure pile driver, then as shown in figure 4, the drill bit of long-spiral drilling machine from upper Section stake holes 1 bottom drills down to lower section stake holes 2, then as shown in figure 5, long-spiral drilling machine revolving process, then as shown in fig. 6, pull out The drill bit of long-spiral drilling machine out, then as described in Example 8, placement steel reinforcement cage is added, stake holes is poured as shown in fig. 9 again.
Embodiment 3:
The embodiment described 3 and the difference of embodiment 1 are that the length of the upper section stake holes 1 is greater than the thickness of collapsibility soil layer 2m is spent, pile bottom post-grouting is carried out by reserved Grouting Pipe.

Claims (5)

1. a kind of construction method for collapsibility soil body stake, which is characterized in that comprise the steps of:
(1) it upper section stake holes: squeezes to form upper section stake holes using static pressure compaction hole forming method;
(2) lower section stake holes:, which being drilled using long-spiral drilling machine through upper section, and continues soil rotary drilling downwards removes section drilling, shape At stake holes;
(3) use pours material and is poured from bottom to top to the designed elevation of stake holes, material solidification to be poured, and forms stake.
2. the construction method according to claim 1 for the stake of the collapsibility soil body, which is characterized in that the upper section stake holes Length be greater than collapsibility the thickness of the layer 1-2m.
3. the construction method according to claim 1 for the stake of the collapsibility soil body, which is characterized in that the length of the stake holes Spend the horizontal plane in direction and ground.
4. the construction method according to claim 1 for the stake of the collapsibility soil body, which is characterized in that the step (3) In stake be pile foundation or composite foundation reinforcement.
5. the method for the preparation method batch making stake using claim 1, which is characterized in that comprise the steps of:
(1) several upper section stake holes first are squeezed using static pressure compaction hole forming method;
(2) successively reuse long-spiral drilling machine through upper section drill and continue soil rotary drilling downwards remove section drilling, formation Stake holes;
(3) use pours material and pours several stake holes one by one, and material solidification to be poured forms stake.
CN201811635353.3A 2018-12-29 2018-12-29 A kind of construction method for collapsibility soil body stake Pending CN109610443A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811635353.3A CN109610443A (en) 2018-12-29 2018-12-29 A kind of construction method for collapsibility soil body stake

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811635353.3A CN109610443A (en) 2018-12-29 2018-12-29 A kind of construction method for collapsibility soil body stake

Publications (1)

Publication Number Publication Date
CN109610443A true CN109610443A (en) 2019-04-12

Family

ID=66015429

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811635353.3A Pending CN109610443A (en) 2018-12-29 2018-12-29 A kind of construction method for collapsibility soil body stake

Country Status (1)

Country Link
CN (1) CN109610443A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002129557A (en) * 2000-10-23 2002-05-09 Tokyo Tokushu Kiso Kogyo:Kk Pile burying method
CN102162246A (en) * 2011-05-18 2011-08-24 中铁西北科学研究院有限公司 Vibration-less compaction method of collapsible loess foundation
CN103790173A (en) * 2014-03-12 2014-05-14 中铁第五勘察设计院集团有限公司 Lime-soil compaction pile and CFG rigid pile combined device and method for disposing collapsible loess
CN203755332U (en) * 2014-03-12 2014-08-06 中铁第五勘察设计院集团有限公司 Device for treating collapsible loess with lime-soil compaction piles and CFG rigid piles combined
CN104988913A (en) * 2015-05-29 2015-10-21 王继忠 Construction method for carrier pile of major diameter long pile
CN106703004A (en) * 2017-03-14 2017-05-24 王继忠 Treatment method for collapsible loess foundation

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002129557A (en) * 2000-10-23 2002-05-09 Tokyo Tokushu Kiso Kogyo:Kk Pile burying method
CN102162246A (en) * 2011-05-18 2011-08-24 中铁西北科学研究院有限公司 Vibration-less compaction method of collapsible loess foundation
CN103790173A (en) * 2014-03-12 2014-05-14 中铁第五勘察设计院集团有限公司 Lime-soil compaction pile and CFG rigid pile combined device and method for disposing collapsible loess
CN203755332U (en) * 2014-03-12 2014-08-06 中铁第五勘察设计院集团有限公司 Device for treating collapsible loess with lime-soil compaction piles and CFG rigid piles combined
CN104988913A (en) * 2015-05-29 2015-10-21 王继忠 Construction method for carrier pile of major diameter long pile
CN106703004A (en) * 2017-03-14 2017-05-24 王继忠 Treatment method for collapsible loess foundation

Similar Documents

Publication Publication Date Title
CN105442605B (en) Extract PHC and be reused in deep foundation pit supporting construction method
CN106930277A (en) A kind of construction of manual-excavation cast-in-place pile method
CN103882869A (en) Inclined supporting pile structure for foundation pit support and construction method thereof
CN206784372U (en) Injection forming club-footed pile
CN105672307A (en) Expanded-base combination end pile bearing foundation
CN206646502U (en) A kind of steel pipe type soil nailing
CN104295112B (en) A kind of reinforced concrete post connects steel core concrete column syndeton and construction method
CN107326898A (en) A kind of cement soil wall interpolation rigidity can adjust drum prefabricated pile supporting construction and its construction method
CN203768914U (en) Foundation pit bracing diagonal support pile structure
CN105507336A (en) Method for forming composite foundation by using dewatering well
CN105821887A (en) Installing method for stand column pile constructed in pebble bed
CN106545008A (en) A kind of cast-in-situ bored pile pile making method
CN202247938U (en) Wedge-shaped foundation bolt preformed hole core formwork device
CN110896644B (en) Grouting consolidation method for full-casing drilling guide precast pile
CN204174955U (en) Reinforced concrete post connects steel core concrete column syndeton
CN109610443A (en) A kind of construction method for collapsibility soil body stake
CN205501998U (en) Expand end combination end -bearing pile basis
CN104480947A (en) Construction method of prestress cast-in-place pile and soil cement pile engagement support
CN206539016U (en) Constructional column pours device
CN205875146U (en) Broken pile's reinforced structure
CN201679450U (en) Bidirectional spiral extruding reaming drill with soil guiding grooves
CN114922172A (en) Anchor rod pile device capable of eliminating negative frictional resistance of collapsible loess and construction method
CN110359449B (en) Post-grouting reinforcement CFG pile manufacturing method for anti-broken pile head
CN107975034B (en) The floating stake ground processing method of hollow preformed pile
CN106223334A (en) The restorative procedure of a kind of broken pile and ruggedized construction thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190412