CN109598075A - A kind of test macro and method of the power information equipment based on dynamic load - Google Patents

A kind of test macro and method of the power information equipment based on dynamic load Download PDF

Info

Publication number
CN109598075A
CN109598075A CN201811502105.1A CN201811502105A CN109598075A CN 109598075 A CN109598075 A CN 109598075A CN 201811502105 A CN201811502105 A CN 201811502105A CN 109598075 A CN109598075 A CN 109598075A
Authority
CN
China
Prior art keywords
information equipment
power information
load
testing
adjustment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811502105.1A
Other languages
Chinese (zh)
Inventor
闫龙川
俞学豪
白东霞
李莉敏
赵子岩
陈智雨
何永远
高德荃
李君婷
王颖
李枫
马丽
张晓亮
张林锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Information and Telecommunication Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Information and Telecommunication Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Information and Telecommunication Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201811502105.1A priority Critical patent/CN109598075A/en
Publication of CN109598075A publication Critical patent/CN109598075A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Engineering & Computer Science (AREA)
  • Theoretical Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Physics & Mathematics (AREA)
  • Economics (AREA)
  • Health & Medical Sciences (AREA)
  • General Physics & Mathematics (AREA)
  • General Engineering & Computer Science (AREA)
  • Human Resources & Organizations (AREA)
  • Evolutionary Computation (AREA)
  • Computer Hardware Design (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Geometry (AREA)
  • Marketing (AREA)
  • Primary Health Care (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

This application provides a kind of power information device test system and method based on dynamic load, system includes: testing and control server, for every the first preset time, generate an adjustment of load emulator command, and adjustment of load emulator command is sent to loaded server, and the adjustment of load emulator command generated every time is different;Loaded server, the adjustment of load emulator command generated every time according to testing and control server, adjusts separately the load run in power information equipment;Equipment is acquired, the electricity consumption data after the adjustment of load for running in each power information equipment, when acquisition power information equipment operation;Control server is tried, is also used to obtain electricity consumption data when the primary power information equipment is run from acquisition equipment every the second preset time, and test report is generated according to the electricity consumption data got.In this application, the test to power information equipment under different operation loads can be completed in the above manner, guarantee test result more comprehensively, accurately.

Description

A kind of test macro and method of the power information equipment based on dynamic load
Technical field
This application involves technical field of electric power, in particular to the test system of a kind of power information equipment based on dynamic load System and method.
Background technique
Electric power data center is electric system important component, is the important base of power grid enterprises' production, operation and management Infrastructure.Electric power data center is deployed with a large amount of power information equipment, electricity consumption data (e.g., the voltage, electricity of power information equipment Stream, power) operation directly affect the operational safety and service quality at electric power data center, therefore in order to guarantee power information The operational safety of equipment can be tested (e.g., electricity consumption characteristic test) to power information equipment in advance.
But how power information equipment is tested, accurate analysis system loading condition and electricity consumption situation become and ask Topic.
Summary of the invention
In order to solve the above technical problems, the embodiment of the present application provides a kind of survey of power information equipment based on dynamic load Test system and method guarantee that test result is more complete to reach the test completed to power information equipment under different operation loads The purpose in face, technical solution are as follows:
A kind of test macro of the power information equipment based on dynamic load, comprising: testing and control server, load services Device and acquisition equipment;
The testing and control server, for generating an adjustment of load emulator command, concurrently every the first preset time Send the adjustment of load emulator command to the loaded server, and the adjustment of load emulator command generated every time is different;
The loaded server, according to the adjustment of load emulator command that the testing and control server generates every time, respectively The load run in adjustment power information equipment;
The acquisition equipment, after the adjustment of load for being run in each power information equipment, described in acquisition Electricity consumption data when power information equipment is run;
The testing and control server is also used to obtain primary institute from the acquisition equipment every the second preset time The electricity consumption data when operation of power information equipment is stated, and test report is generated according to the electricity consumption data got.
Preferably, the testing and control server is also used to: generating data and curves according to the electricity consumption data got.
Preferably, the testing and control server, is also used to: the test report inquiry request of response user's input, inquiry Corresponding test report is simultaneously shown.
Preferably, the acquisition equipment are as follows: remote power supply manager.
Preferably, the testing and control server is also used to control the remote power supply manager to the power information Target power module for power supply in equipment, to the power module in the power information equipment in addition to the target power module Power-off, and whether detect the target power module normal to the power supply of the power information equipment.
A kind of test method of the power information equipment based on dynamic load, comprising:
Testing and control server generates an adjustment of load emulator command every the first preset time, and sends described negative Adjustment emulator command is carried to loaded server, and the adjustment of load emulator command generated every time is different;
The loaded server, according to the adjustment of load emulator command that the testing and control server generates every time, respectively The load run in adjustment power information equipment;
Equipment is acquired, after the adjustment of load run in each power information equipment, acquires the power information Electricity consumption data when equipment is run;
The testing and control server obtains the primary electric power every the second preset time from the acquisition equipment Electricity consumption data when information equipment is run, and test report is generated according to the electricity consumption data got.
Preferably, the method also includes:
The testing and control server generates data and curves according to the electricity consumption data got.
Preferably, the method also includes:
The testing and control server, the test report inquiry request of response user's input, inquires corresponding test report And it shows.
Preferably, the acquisition equipment are as follows: remote power supply manager.
Preferably, the method also includes:
The testing and control server controls the remote power supply manager to the target electricity in the power information equipment Source module power supply, powers off the power module in the power information equipment in addition to the target power module, and detect institute It is whether normal to the power supply of the power information equipment to state target power module.
Compared with prior art, the application has the beneficial effect that
In this application, testing and control server generates an adjustment of load emulator command every the first preset time, and Adjustment of load emulator command is sent to loaded server, loaded server adjusts power information according to adjustment of load emulator command The load run in equipment realizes the dynamic adjustment of the load run in power information equipment, adjusts operation load in dynamic On the basis of, electricity consumption data when acquisition equipment acquisition power information equipment is run is realized to the electric power under different operation loads The acquisition of the electricity consumption data of information equipment guarantees that collected electricity consumption data is richer.Based on this, since power information equipment is transported Electricity consumption data when row can reflect the operating condition of power information equipment, therefore testing and control server can be from acquisition equipment Electricity consumption data when the middle power information equipment operation obtained under different operation loads, and according to the different operation loads got Under electricity consumption data, generate the lower test report of different operation loads, complete to power information equipment in the case where different operations load Test, guarantee test result more comprehensively.
Detailed description of the invention
In order to more clearly explain the technical solutions in the embodiments of the present application, make required in being described below to embodiment Attached drawing is briefly described, it should be apparent that, the drawings in the following description are only some examples of the present application, for For those of ordinary skill in the art, without any creative labor, it can also be obtained according to these attached drawings His attached drawing.
Fig. 1 is that a kind of logical construction of the test macro of the power information equipment provided by the present application based on dynamic load is shown It is intended to;
Fig. 2 is a kind of schematic diagram of data and curves provided by the present application;
Fig. 3 is a kind of schematic diagram of test software framework provided by the present application;
Fig. 4 is a kind of flow chart of the test method of the power information equipment provided by the present application based on dynamic load;
Fig. 5 is another flow chart of the test method of the power information equipment provided by the present application based on dynamic load;
Fig. 6 is another flow chart of the test method of the power information equipment provided by the present application based on dynamic load.
Specific embodiment
Below in conjunction with the attached drawing in the embodiment of the present application, technical solutions in the embodiments of the present application carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of embodiments of the present application, instead of all the embodiments.It is based on Embodiment in the application, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall in the protection scope of this application.
The embodiment of the present application discloses a kind of test macro of power information equipment based on dynamic load, comprising: test Control server, loaded server and acquisition equipment;The testing and control server, for generating every the first preset time Adjustment of load emulator command, and the adjustment of load emulator command is sent to the loaded server;The load services Device, for adjusting the load run in power information equipment according to the adjustment of load emulator command;The acquisition equipment is used After the adjustment of load run in the power information equipment, electricity consumption number when power information equipment operation is acquired According to;The testing and control server is also used to every the second preset time, and the primary electric power is obtained from the acquisition equipment Electricity consumption data when information equipment is run, and test report is generated according to the electricity consumption data got.It in this application, can be complete The test of pairs of power information equipment, and guarantee test result more comprehensively.
Next it is situated between to the test macro of the power information equipment disclosed in the embodiment of the present application based on dynamic load It continues, referring to Figure 1, the test macro of power information equipment includes: that testing and control server 11, loaded server 12 and acquisition are set Standby 13.
The testing and control server 11, for generating an adjustment of load emulator command every the first preset time, and The adjustment of load emulator command is sent to the loaded server 12, and each not phase of the adjustment of load emulator command generated every time Together.
Testing and control server 11 can generate corresponding adjustment of load emulator command according to test request.
First preset time can according to need carry out flexible setting.
The loaded server 12, the adjustment of load emulation for generating every time according to the testing and control server 11 refer to It enables, adjusts separately the load run in power information equipment.
Since the adjustment of load emulator command generated every time is different, loaded server 12 is controlled according to the test The adjustment of load emulator command that control server 11 generates every time, after adjusting separately the load run in power information equipment, electric power The load run on information equipment is different.
The acquisition equipment 13 after the adjustment of load for running in each power information equipment, acquires institute State the electricity consumption data when operation of power information equipment.
After the adjustment of load that acquisition equipment 13 is run in each power information equipment, power information equipment is acquired Electricity consumption data when operation, it is ensured that collect electricity consumption data when power equipment is run under the load of different operations, make to adopt Electricity consumption data when the power equipment operation collected is richer.
In the present embodiment, electricity consumption data when acquisition equipment 13 can run collected power information equipment is stored in In database, loss of data is avoided.
The testing and control server 11 is also used to obtain one from the acquisition equipment 13 every the second preset time Electricity consumption data when the secondary power information equipment is run, and test report is generated according to the electricity consumption data got.
Second preset time can according to need carry out flexible setting.
Testing and control server 11 generates test report according to the electricity consumption data got, may include: that basis is got Electricity consumption data generate power information equipment the test report with electrical characteristics.
The case where electricity consumption data when acquiring equipment 13 and run collected power information equipment is stored to database Under, testing and control server 11 can obtain the electricity consumption data when operation of power information equipment from database.
In this application, testing and control server 11 generates an adjustment of load emulator command every the first preset time, And adjustment of load emulator command is sent to loaded server 12, loaded server 12 is according to adjustment of load emulator command, adjustment electricity The load run in force information equipment realizes the dynamic adjustment of the load run in power information equipment, in dynamic adjustment fortune On the basis of row load, acquisition equipment 13 acquires the electricity consumption data when operation of power information equipment, realizes and loads to different operations Under power information equipment electricity consumption data acquisition, guarantee that collected electricity consumption data is richer.Based on this, since electric power is believed Electricity consumption data when breath equipment operation can reflect the operating condition of power information equipment, therefore testing and control server 11 can be with Obtain electricity consumption data when the lower power information equipment operation of different operation loads from acquisition equipment 13, and according to getting Electricity consumption data under difference operation load generates the test report under different operation loads, completes to power information equipment not With the test under operation load, guarantee test result more comprehensively.
More fully test result can provide accurately for the planning management of the power information equipment at electric power data center Data guidance, provides data foundation for the option of power information equipment, so that electric power data center can choose best performance Power information equipment improves the safety and efficiency of system operation.Also, more fully test result can be analyzed more accurately The loading condition and electricity consumption situation of system.
In another embodiment of the application, the function of above-mentioned testing and control server 11 is extended, specifically such as Under:
The testing and control server 11, can be also used for: generate data and curves according to the electricity consumption data got.
It is to be understood that being used to reflect the curve of the variation tendency of electricity consumption data, power as shown in Figure 2 becomes data and curves Change curve.
Specifically, according to the process that the electricity consumption data that gets generates data and curves may include: using the time as horizontal axis, with Power is the longitudinal axis, draws the change trend curve of electricity consumption data.
Data and curves are generated according to the electricity consumption data got, can more intuitively reflect the variation tendency of electricity consumption data.
In another embodiment of the application, the function of above-mentioned testing and control server 11 is extended, after extension Testing and control server 11 can be also used for:
The test report inquiry request for responding user's input, inquires corresponding test report and shows.
Testing and control server 11 can provide a user friendly user interface, and user can initiate on a user interface Corresponding request, such as test report inquiry request.Test controller server is in the test report inquiry for receiving user's input After request, the test report inquiry request of response user's input is inquired corresponding test report and is shown.
Certainly, testing and control server 11 can also provide back-stage management interface, can be gone through in back-stage management interface History inquires (e.g., query history test report or historical data curve), (e.g., test report generates, modification is surveyed for test report management Examination report) and user management in any one and it is a variety of.
In another embodiment of the application, above-mentioned acquisition equipment 13 is introduced, is specifically as follows but does not limit to In: remote power supply manager (ReachctrlPower, intelligent PDU).
Remote power supply manager is set by acquisition equipment 13, can more easily collect the electricity of power information equipment The electricity consumption datas such as stream, voltage and power.
Remote power supply manager based on previous embodiment introduction, in another embodiment of the application, to above-mentioned survey The function of examination control server 11 is extended, specific as follows:
Testing and control server 11, can be also used for:
The remote power supply manager is controlled to the target power module for power supply in the power information equipment, to the electricity Power module power-off in force information equipment in addition to the target power module, and the target power module is detected to described Whether the power supply of power information equipment is normal.
It should be noted that target power module can be testing and control server 11 from the power supply in power information equipment It is chosen in module, or power information equipment chooses itself from each power module, and active reporting To testing and control server 11.
Testing and control server 11 controls the remote power supply manager to the target power in the power information equipment Module for power supply powers off the power module in the power information equipment in addition to the target power module, and described in detection Whether target power module is normal to the power supply of the power information equipment, realizes to power module in power information equipment Test guarantees the power supply of power information equipment to adjust the power module in power information equipment for power supply according to test result Normally, it operates normally.
In this application, the test macro for the power information equipment based on dynamic load that foregoing individual embodiments are introduced The software architecture that the test carried out relies on may refer to Fig. 3, as shown in figure 3, WEB service layer can provide user interface with after Platform administration interface realizes automatic test, data and curves generation, test report generation, server admin, user management, history number It is investigated that asking;Data analysis layer can provide data storage, data set calculating, data report and data filing;Data storage layer can Data storage is carried out to provide database;Equipment acquisition layer can provide long-range control (e.g., power module in power information equipment Long-range control), timing acquiring, PDU equipment management and safety verification.
Next the test method of the power information equipment to provided by the present application based on dynamic load is introduced, hereafter The test method for the power information equipment based on dynamic load introduced and the power information based on dynamic load described above The test macro of equipment can correspond to each other reference.
Fig. 4 is referred to, the test method of power information equipment may include:
Step S11, testing and control server generates an adjustment of load emulator command, concurrently every the first preset time Send the adjustment of load emulator command to loaded server.
Wherein, the adjustment of load emulator command generated every time is different.
Step S12, the described loaded server, the adjustment of load emulation generated every time according to the testing and control server refer to It enables, adjusts separately the load run in power information equipment.
Step S13, equipment is acquired, after the adjustment of load run in each power information equipment, described in acquisition Electricity consumption data when power information equipment is run.
Step S14, the described testing and control server obtains primary every the second preset time from the acquisition equipment Electricity consumption data when the power information equipment is run, and test report is generated according to the electricity consumption data got.
In another embodiment of the application, the survey of another the power information equipment based on dynamic load is expanded Method for testing refers to Fig. 5, may include:
Step S21, testing and control server generates an adjustment of load emulator command, concurrently every the first preset time Send the adjustment of load emulator command to loaded server.
Wherein, the adjustment of load emulator command generated every time is different.
Step S22, the described loaded server, the adjustment of load emulation generated every time according to the testing and control server refer to It enables, adjusts separately the load run in power information equipment.
Step S23, equipment is acquired, after the adjustment of load run in each power information equipment, described in acquisition Electricity consumption data when power information equipment is run.
Step S24, the described testing and control server obtains primary every the second preset time from the acquisition equipment Electricity consumption data when the power information equipment is run, and test report is generated according to the electricity consumption data got.
Step S25, the described testing and control server generates data and curves according to the electricity consumption data got.
In another embodiment of the application, the survey of another the power information equipment based on dynamic load is provided Method for testing refers to Fig. 6, may include:
Step S31, testing and control server generates an adjustment of load emulator command, concurrently every the first preset time Send the adjustment of load emulator command to loaded server.
Wherein, the adjustment of load emulator command generated every time is different.
Step S32, the described loaded server, the adjustment of load emulation generated every time according to the testing and control server refer to It enables, adjusts separately the load run in power information equipment.
Step S33, equipment is acquired, after the adjustment of load run in each power information equipment, described in acquisition Electricity consumption data when power information equipment is run.
Step S34, the described testing and control server obtains primary every the second preset time from the acquisition equipment Electricity consumption data when the power information equipment is run, and test report is generated according to the electricity consumption data got.
Step S35, the described testing and control server, the test report inquiry request of response user's input, inquiry are corresponding Test report is simultaneously shown.
In another embodiment of the application, above-mentioned acquisition equipment is introduced, is specifically as follows: remote power supply pipe Manage device.
In the case where acquiring equipment is remote power supply manager, the test method of the power information equipment shown in Fig. 4 is also It may comprise steps of:
The testing and control server controls the remote power supply manager to the target electricity in the power information equipment Source module power supply, powers off the power module in the power information equipment in addition to the target power module, and detect institute It is whether normal to the power supply of the power information equipment to state target power module.
It should be noted that all the embodiments in this specification are described in a progressive manner, each embodiment weight Point explanation is the difference from other embodiments, and the same or similar parts between the embodiments can be referred to each other. For device class embodiment, since it is basically similar to the method embodiment, so being described relatively simple, related place ginseng See the part explanation of embodiment of the method.
Finally, it is to be noted that, herein, relational terms such as first and second and the like be used merely to by One entity or operation are distinguished with another entity or operation, without necessarily requiring or implying these entities or operation Between there are any actual relationship or orders.Moreover, the terms "include", "comprise" or its any other variant meaning Covering non-exclusive inclusion, so that the process, method, article or equipment for including a series of elements not only includes that A little elements, but also including other elements that are not explicitly listed, or further include for this process, method, article or The intrinsic element of equipment.In the absence of more restrictions, the element limited by sentence "including a ...", is not arranged Except there is also other identical elements in the process, method, article or apparatus that includes the element.
For convenience of description, it is divided into various units when description apparatus above with function to describe respectively.Certainly, implementing this The function of each unit can be realized in the same or multiple software and or hardware when application.
As seen through the above description of the embodiments, those skilled in the art can be understood that the application can It realizes by means of software and necessary general hardware platform.Based on this understanding, the technical solution essence of the application On in other words the part that contributes to existing technology can be embodied in the form of software products, the computer software product It can store in storage medium, such as ROM/RAM, magnetic disk, CD, including some instructions are used so that a computer equipment (can be personal computer, server or the network equipment etc.) executes the certain of each embodiment of the application or embodiment Method described in part.
Above the test macro to a kind of power information equipment based on dynamic load provided herein and method into It has gone and has been discussed in detail, specific examples are used herein to illustrate the principle and implementation manner of the present application, the above implementation The explanation of example is merely used to help understand the present processes and its core concept;Meanwhile for the general technology people of this field Member, according to the thought of the application, there will be changes in the specific implementation manner and application range, in conclusion this explanation Book content should not be construed as the limitation to the application.

Claims (10)

1. a kind of test macro of the power information equipment based on dynamic load characterized by comprising testing and control service Device, loaded server and acquisition equipment;
The testing and control server, for generating an adjustment of load emulator command, and send institute every the first preset time Adjustment of load emulator command is stated to the loaded server, and the adjustment of load emulator command generated every time is different;
The loaded server is adjusted separately according to the adjustment of load emulator command that the testing and control server generates every time The load run in power information equipment;
The acquisition equipment after the adjustment of load for running in each power information equipment, acquires the electric power Electricity consumption data when information equipment is run;
The testing and control server is also used to every the second preset time, and the primary electricity is obtained from the acquisition equipment Electricity consumption data when force information equipment is run, and test report is generated according to the electricity consumption data got.
2. system according to claim 1, which is characterized in that the testing and control server is also used to: according to getting Electricity consumption data generate data and curves.
3. system according to claim 1, which is characterized in that the testing and control server is also used to: response user is defeated The test report inquiry request entered is inquired corresponding test report and is shown.
4. system according to claim 1, which is characterized in that the acquisition equipment are as follows: remote power supply manager.
5. system according to claim 4, which is characterized in that the testing and control server is also used to control described remote Journey power supervisor is described to removing in the power information equipment to the target power module for power supply in the power information equipment Power module power-off except target power module, and detect power supply of the target power module to the power information equipment It is whether normal.
6. a kind of test method of the power information equipment based on dynamic load characterized by comprising
Testing and control server generates an adjustment of load emulator command every the first preset time, and sends the load and adjust Whole emulator command is to loaded server, and the adjustment of load emulator command generated every time is different;
The loaded server is adjusted separately according to the adjustment of load emulator command that the testing and control server generates every time The load run in power information equipment;
Equipment is acquired, after the adjustment of load run in each power information equipment, acquires the power information equipment Electricity consumption data when operation;
The testing and control server obtains the primary power information every the second preset time from the acquisition equipment Electricity consumption data when equipment is run, and test report is generated according to the electricity consumption data got.
7. according to the method described in claim 6, it is characterized in that, the method also includes:
The testing and control server generates data and curves according to the electricity consumption data got.
8. according to the method described in claim 6, it is characterized in that, the method also includes:
The testing and control server, the test report inquiry request of response user's input, inquires corresponding test report and opens up Show.
9. according to the method described in claim 6, it is characterized in that, the acquisition equipment are as follows: remote power supply manager.
10. according to the method described in claim 9, it is characterized in that, the method also includes:
The testing and control server controls the remote power supply manager to the target power mould in the power information equipment Block power supply, powers off the power module in the power information equipment in addition to the target power module, and detect the mesh Whether the power supply for marking power information equipment described in electric power source pair of module is normal.
CN201811502105.1A 2018-12-10 2018-12-10 A kind of test macro and method of the power information equipment based on dynamic load Pending CN109598075A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811502105.1A CN109598075A (en) 2018-12-10 2018-12-10 A kind of test macro and method of the power information equipment based on dynamic load

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811502105.1A CN109598075A (en) 2018-12-10 2018-12-10 A kind of test macro and method of the power information equipment based on dynamic load

Publications (1)

Publication Number Publication Date
CN109598075A true CN109598075A (en) 2019-04-09

Family

ID=65962027

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811502105.1A Pending CN109598075A (en) 2018-12-10 2018-12-10 A kind of test macro and method of the power information equipment based on dynamic load

Country Status (1)

Country Link
CN (1) CN109598075A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113363995A (en) * 2021-05-21 2021-09-07 福建星云电子股份有限公司 Power load management and control method, system, equipment and medium
CN114167753A (en) * 2021-12-02 2022-03-11 中联重科股份有限公司 Drilling machine energy-saving control semi-physical simulation test method, system and storage medium
CN115208807A (en) * 2022-09-14 2022-10-18 中兴系统技术有限公司 POE switch test system and method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103399496A (en) * 2013-08-20 2013-11-20 中国能源建设集团广东省电力设计研究院 Massive real-time data load simulation testing cloud platform for smart power grid, and testing method of cloud platform
CN103926552A (en) * 2014-04-14 2014-07-16 国家电网公司 Electricity utilization information collecting simulation testing platform
CN106597947A (en) * 2016-12-23 2017-04-26 国网浙江宁波市鄞州区供电公司 Substation equipment test method and system, server and tester

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103399496A (en) * 2013-08-20 2013-11-20 中国能源建设集团广东省电力设计研究院 Massive real-time data load simulation testing cloud platform for smart power grid, and testing method of cloud platform
CN103926552A (en) * 2014-04-14 2014-07-16 国家电网公司 Electricity utilization information collecting simulation testing platform
CN106597947A (en) * 2016-12-23 2017-04-26 国网浙江宁波市鄞州区供电公司 Substation equipment test method and system, server and tester

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113363995A (en) * 2021-05-21 2021-09-07 福建星云电子股份有限公司 Power load management and control method, system, equipment and medium
CN113363995B (en) * 2021-05-21 2023-12-05 福建星云电子股份有限公司 Power utilization load control method, system, equipment and medium
CN114167753A (en) * 2021-12-02 2022-03-11 中联重科股份有限公司 Drilling machine energy-saving control semi-physical simulation test method, system and storage medium
CN115208807A (en) * 2022-09-14 2022-10-18 中兴系统技术有限公司 POE switch test system and method
CN115208807B (en) * 2022-09-14 2022-12-30 中兴系统技术有限公司 POE switch test system and method

Similar Documents

Publication Publication Date Title
CN109598075A (en) A kind of test macro and method of the power information equipment based on dynamic load
Hong et al. Fast frequency response for effective frequency control in power systems with low inertia
CN108399114B (en) System performance testing method and device and storage medium
CN110311812B (en) Network analysis method, device and storage medium
CN103248535B (en) A kind of cloud system method of testing and device
KR100964300B1 (en) A dispatcher training simulation system
CN106375420A (en) System and method for intelligently monitoring server cluster based on load balancing
CN109145362A (en) A kind of power network modeling method and system
CN102393726B (en) Method for evaluating performance of AGC (automatic gain control) controller of thermal power unit
US11082323B2 (en) Fault monitoring in a utility supply network
EP2325968A1 (en) Tuning a power oscillation damping unit
KR20200040949A (en) Apparatus for testing performance of energy storage system and method thereof
GB2546118A (en) Fault monitoring by assessing spatial distribution of queries in a utility supply network
CN107633352A (en) The method and apparatus of specification task flow
Liu et al. System restoration navigator: A decision support tool for system restoration
CN104618166A (en) Application service deployment method, device and system
Sharma et al. Advanced techniques of power system restoration and practical applications in transmission grids
Wiegel et al. Smart Energy System Control Laboratory–a fully-automated and user-oriented research infrastructure for controlling and operating smart energy systems
CN108701423A (en) Visual estimations indicator and emulating server with event difference
CN108701422A (en) The emulating server for the visual alarm for indicating modeling event difference can be sent to computing device
CN102904769A (en) Test method and test equipment for monitoring systems
KR101963847B1 (en) Frequency regulation event simulation method and frequency regulation event simulation server
CN104702463A (en) Method, device and system for bypass testing of multiple machine rooms
CN105335266B (en) Method for determining the failure of tested equipment
CN112799949A (en) Model optimization method, device, system and equipment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190409

RJ01 Rejection of invention patent application after publication