CN109538265A - Tunnel overlength enlarged footing anchor cable and its method for protecting support - Google Patents

Tunnel overlength enlarged footing anchor cable and its method for protecting support Download PDF

Info

Publication number
CN109538265A
CN109538265A CN201710867944.2A CN201710867944A CN109538265A CN 109538265 A CN109538265 A CN 109538265A CN 201710867944 A CN201710867944 A CN 201710867944A CN 109538265 A CN109538265 A CN 109538265A
Authority
CN
China
Prior art keywords
cable body
enlarged footing
cable
overlength
pole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710867944.2A
Other languages
Chinese (zh)
Inventor
吴占瑞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201710867944.2A priority Critical patent/CN109538265A/en
Publication of CN109538265A publication Critical patent/CN109538265A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D21/00Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
    • E21D21/0026Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection characterised by constructional features of the bolts
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D21/00Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
    • E21D21/008Anchoring or tensioning means

Abstract

The invention discloses a kind of tunnel overlength enlarged footing anchor cables, including overlength cable body, the enlarged footing for being set to the cable body inner end, the Pressure-bearing pads for being coated at the cable body, anchor with the cable body and compress the anchorage of Pressure-bearing pads using the prestressing force of cable body, are set to the cable body outer end for carrying out the hydraulic jack of tensioning to cable body;The enlarged footing can be radially furthered out to form wedge structure along cable body;Branch at the beginning of this anchor cable can greatly reduce the later period changes the number that arch and two linings change, and saves the spending of duration, personnel and goods and materials, accelerates construction speed.

Description

Tunnel overlength enlarged footing anchor cable and its method for protecting support
Technical field
The present invention relates to small-clear-distance tunnel construction field, specifically a kind of tunnel overlength enlarged footing anchor cable and its supporting side Method.
Background technique
High-ground stress Support System in Soft Rock Tunnels country rock after excavation supporting be squeezed and deformed it is strong, cause just branch extensive damage, Gunite concrete cracking, steelframe distortion bad break, abutment wall invade limit etc..And release of the high-ground stress in Support System in Soft Rock Tunnels is one A long-term slow process, causing early period, ready-made two lining constantly cracks in the later period, needs to re-start trimming of doing over again. Therefore, rock crusher, crustal stress are larger and the problems such as deenergized period is long causes constructing tunnel deformation big, and process conversion, scheme become More frequently, construction production is discontinuous, work efficiency is low, serious to perplex constructing aims and construction safety.
It can be good at solving the problems, such as that Support System in Soft Rock Tunnels is squeezed and deformed therefore, it is necessary to one kind, at the beginning of greatly reducing the later period Branch changes the number that arch and two linings change, and saves the spending of duration, personnel and goods and materials, accelerates construction speed, improves enterprise Productivity effect tunnel overlength enlarged footing anchor cable and its method for protecting support.
Summary of the invention
In view of this, providing one kind can be soft to high-ground stress the purpose of the present invention is overcoming defect in the prior art Weak country rock large deformation is effectively controlled;Have the function of resource-effective, environmental protection and energy saving tunnel overlength enlarged footing anchor cables simultaneously.
Tunnel overlength enlarged footing anchor cable of the invention, including overlength cable body, the enlarged footing that is set to the cable body inner end, outer The Pressure-bearing pads of the cable body are placed on, are anchored with the cable body and compresses the anchorage of Pressure-bearing pads using the prestressing force of cable body, set The cable body outer end is placed in for carrying out the hydraulic jack of tensioning to cable body;The enlarged footing can be radially furthered out along cable body Form wedge structure;
Further, the enlarged footing includes center-pole and along circumferentially equally distributed multiple two connection rod sets of center-pole, described Center-pole outer wall is fixed in the inner end of two connection rod sets, and outer end can slide axially along center-pole, and make two connection rod sets by the sliding Expansion outward;
Further, the center-pole sliding outer cover has sliding sleeve, and the outer end of two connection rod set is articulated with the sliding sleeve;
Further, the center-pole is equipped with the stop collar for being limited to the sliding of the sliding;
The invention also discloses a kind of methods for carrying out supporting using overlength enlarged footing anchor cable, comprising the following steps:
S1. scene is provided with multiple test miles sections, in tunnel excavation different time sections, carries out respectively to prestress anchorage cable Rock deformation around hole is observed in tensioning;S2. the anchorage cable stretching best opportunity is obtained according to rock deformation around the hole.
The beneficial effects of the present invention are: increasing anchor cable hole bottom anchoring section using prestressing force overlength enlarged footing anchor cable construction Consolidate range, improve the anchor force and withdrawal resistance of bottom hole, while strengthening the skid resistance of country rock sliding surface, with maintain country rock by Dynamic balance.The wedge shaped structure of enlarged footing anchor cable keeps country rock and first branch structure closely connected, plays self to greatest extent, symbol Close New Austrian Tunneling Method principle deformation controlling for rock surrounding gateways.Using geological drilling rig casing follow-up technology, solves overlength anchor cable construction problem in hole; Two-wire small spacing Support System in Soft Rock Tunnels overlength anchor cable reasonable tensioning opportunity in method for protecting support of the invention reduces double hole construction phases Mutually influence.Double holes influence each other greatly in the construction process, and surrouding rock deformation is not easy to control.Scene is provided with multiple test miles sections, In tunnel excavation different time sections, tensioning is carried out to observe rock deformation around hole to prestress anchorage cable respectively, is finally obtained The anchorage cable stretching best opportunity: leading hole and Hou Hangdong are separated by a plate two lining+interim inverted arch cooperation anchor cable and follow up in time, surrouding rock deformation Good control is obtained.
Detailed description of the invention
The invention will be further described with reference to the accompanying drawings and examples:
Fig. 1 is the structural schematic diagram of anchor cable of the invention;
Fig. 2 is the schematic diagram of enlarged footing of the invention.
Specific embodiment
Fig. 1 is the structural schematic diagram of anchor cable 1 of the invention.Fig. 2 is the schematic diagram of enlarged footing of the invention.The present embodiment Tunnel overlength enlarged footing anchor cable 1 including overlength cable body, the enlarged footing that is set to the cable body inner end, is coated at the cable body Pressure-bearing pads 2 compress the anchorage 4 of Pressure-bearing pads 2 with cable body anchoring and using the prestressing force of cable body, are set to the cable body Outer end is used to carry out cable body the hydraulic jack 3 of tensioning;The enlarged footing can be radially furthered out to form wedge-shaped knot along cable body Structure;It is constructed using prestressing force overlength enlarged footing anchor cable 1 and increases the consolidation range of 1 bottom hole anchoring section of anchor cable, improve bottom hole Anchor force and withdrawal resistance, while the skid resistance of country rock sliding surface is strengthened, to maintain force-bearing of surrounding rock mass to balance.Enlarged footing anchor cable 1 is in Wedge structure keeps country rock and first branch structure closely connected, plays self to greatest extent, meets New Austrian Tunneling Method principle control country rock Deformation.Using geological drilling rig casing follow-up technology, solves 1 construction difficult problem of overlength anchor cable in hole.
In the present embodiment, the enlarged footing includes center-pole 7 and along circumferential equally distributed multiple two connection rod sets of center-pole 7 8, two connection rod sets 8 include two connecting rods being hinged, and 7 outer wall of center-pole is fixed in the inner end of two connection rod set 8, and outer end can It slides axially along center-pole 7, and two expansion outward of connection rod set 8 is made by the sliding, 7 lower end of center-pole is equipped with cone 9, passes through cone Point 9 can reduce the resistance that enlarged footing is pierced into drilling, and circumferentially distributed on the conical surface of cone there are three side wing 10, side wings 10 can be improved the resistance to plucking of enlarged footing.
In the present embodiment, 7 sliding outer cover of center-pole has sliding sleeve 5, and the outer end of two connection rod set 8 is articulated with the cunning Set 5.
In the present embodiment, the center-pole 7 is equipped with the stop collar 6 for being limited to the sliding of the sliding.
The invention also discloses a kind of methods for carrying out supporting using overlength enlarged footing anchor cable 1, comprising the following steps:
S1. scene be provided with multiple test miles sections, in tunnel excavation different time sections, respectively to prestress anchorage cable 1 into Rock deformation around hole is observed in row tensioning;When S2. showing that 1 tensioning of anchor cable is best according to rock deformation around the hole Machine.Two-wire small spacing Support System in Soft Rock Tunnels overlength anchor cable 1 reasonable tensioning opportunity reduces double hole constructions and influences each other.
Finally, it is stated that the above examples are only used to illustrate the technical scheme of the present invention and are not limiting, although referring to compared with Good embodiment describes the invention in detail, those skilled in the art should understand that, it can be to skill of the invention Art scheme is modified or replaced equivalently, and without departing from the objective and range of technical solution of the present invention, should all be covered at this In the scope of the claims of invention.

Claims (5)

1. a kind of tunnel overlength enlarged footing anchor cable, which is characterized in that including overlength cable body, be set to the expansion of the cable body inner end Head, the Pressure-bearing pads for being coated at the cable body, the prestressing force for anchoring with the cable body and utilizing cable body compress the anchor of Pressure-bearing pads Have, be set to the cable body outer end for carrying out the hydraulic jack of tensioning to cable body;The enlarged footing can along cable body it is radial to Outreach open form wedgewise structure.
2. overlength enlarged footing anchor cable in tunnel according to claim 1, it is characterised in that: the enlarged footing include center-pole and Along circumferentially equally distributed multiple two connection rod sets of center-pole, center-pole outer wall is fixed in the inner end of two connection rod set, and outer end can It slides axially along center-pole, and two connection rod sets is unfolded outward by the sliding.
3. overlength enlarged footing anchor cable in tunnel according to claim 2, it is characterised in that: the center-pole sliding outer cover has cunning Set, the outer end of two connection rod set is articulated with the sliding sleeve.
4. overlength enlarged footing anchor cable in tunnel according to claim 3, it is characterised in that: the center-pole is equipped with for institute State the stop collar that the sliding of sliding is limited.
5. a kind of method for carrying out supporting using overlength enlarged footing anchor cable, which comprises the following steps:
S1. scene is provided with multiple test miles sections, in tunnel excavation different time sections, carries out tensioning to prestress anchorage cable respectively To observe rock deformation around hole;
S2. the anchorage cable stretching best opportunity is obtained according to rock deformation around the hole.
CN201710867944.2A 2017-09-22 2017-09-22 Tunnel overlength enlarged footing anchor cable and its method for protecting support Pending CN109538265A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710867944.2A CN109538265A (en) 2017-09-22 2017-09-22 Tunnel overlength enlarged footing anchor cable and its method for protecting support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710867944.2A CN109538265A (en) 2017-09-22 2017-09-22 Tunnel overlength enlarged footing anchor cable and its method for protecting support

Publications (1)

Publication Number Publication Date
CN109538265A true CN109538265A (en) 2019-03-29

Family

ID=65830633

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710867944.2A Pending CN109538265A (en) 2017-09-22 2017-09-22 Tunnel overlength enlarged footing anchor cable and its method for protecting support

Country Status (1)

Country Link
CN (1) CN109538265A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111456784A (en) * 2020-04-20 2020-07-28 北京中矿创新联盟能源环境科学研究院 Constant-resistance anchor cable structure and anchoring method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101476320A (en) * 2009-01-21 2009-07-08 中南大学 Inflation anchor bar
CN102890117A (en) * 2012-02-15 2013-01-23 长江水利委员会长江科学院 Method and device for detecting anchoring quality of long anchor cable
CN203559421U (en) * 2013-10-23 2014-04-23 江苏金海新能源科技有限公司 Prestressed double-rhomboid underreamed anchor
CN107165661A (en) * 2017-06-09 2017-09-15 中铁建大桥工程局集团第五工程有限公司 A kind of high-ground stress weak surrounding rock large deformation tunnel overlength enlarged footing anchor cable construction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101476320A (en) * 2009-01-21 2009-07-08 中南大学 Inflation anchor bar
CN102890117A (en) * 2012-02-15 2013-01-23 长江水利委员会长江科学院 Method and device for detecting anchoring quality of long anchor cable
CN203559421U (en) * 2013-10-23 2014-04-23 江苏金海新能源科技有限公司 Prestressed double-rhomboid underreamed anchor
CN107165661A (en) * 2017-06-09 2017-09-15 中铁建大桥工程局集团第五工程有限公司 A kind of high-ground stress weak surrounding rock large deformation tunnel overlength enlarged footing anchor cable construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
程良奎等: "岩土锚固工程的若干力学概念问题", 《岩石力学与工程学报》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111456784A (en) * 2020-04-20 2020-07-28 北京中矿创新联盟能源环境科学研究院 Constant-resistance anchor cable structure and anchoring method
CN111456784B (en) * 2020-04-20 2021-01-08 北京中矿创新联盟能源环境科学研究院 Constant-resistance anchor cable structure and anchoring method

Similar Documents

Publication Publication Date Title
CN106939600B (en) A kind of hydraulic buckling anchor pole
CN205329688U (en) Resistance -increasing slip casting stock
CN105604057B (en) One kind expands unfolding wing type anchor rod device
CN107524457B (en) Utilize the big stroke combined damper of performance behind material peak
CN104018863A (en) Multi-section-expansion yielding prestress grouting anchor rod and using method thereof
CN203188207U (en) Anchor rod with end portions capable of being expanded
CN110295849A (en) Weathering crushed zone bored grouting method and drilling sub-assembly in shallow rock
CN100593624C (en) Mine using great steel derrick lifting special tool
CN109538265A (en) Tunnel overlength enlarged footing anchor cable and its method for protecting support
CN105649078A (en) Recyclable hydraulic umbrella-shaped soil-squeezing anchor rod
CN107178374A (en) The auxiliary support structure and anterior shield component of double shield tunneling boring rock tunnel development machines
CN109681253A (en) A kind of underground deep wall rock supporting novel anchor rod
CN204492855U (en) Detachable adaptive multistage increases resistance high-strength hollow grouting anchor pile
CN207177903U (en) The auxiliary support structure and anterior shield component of double shield tunneling boring rock tunnel development machines
CN202520344U (en) Anchoring force enhancing device for anchor rod
CN111379581B (en) Deep roadway prestress full-anchor support construction equipment and construction method thereof
CN104061010A (en) Rock anchor rod capable of conducting segmented anchoring
CN203879522U (en) Expansion shell type anchor rod
CN103556635B (en) A kind of Recoverable anchor rod device
CN104612731B (en) Detachable adaptive multistage increases resistance high-strength hollow grouting anchor pile and construction method thereof
CN105040693A (en) End expanding type anti-floating anchor rod
CN105002904B (en) The construction method of installation of end expanding type anti-float anchor rod
CN111894601B (en) Coal seam roadway surrounding rock structure passing geological structure and advanced modification tunneling method thereof
CN104632246B (en) A kind of UNDERGROUND STRUCTURES
CN204532362U (en) A kind of UNDERGROUND STRUCTURES

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190329