CN109537709A - Tailings Dam closes library system and method, photovoltaic generating system, ecological restoring method - Google Patents
Tailings Dam closes library system and method, photovoltaic generating system, ecological restoring method Download PDFInfo
- Publication number
- CN109537709A CN109537709A CN201811589860.8A CN201811589860A CN109537709A CN 109537709 A CN109537709 A CN 109537709A CN 201811589860 A CN201811589860 A CN 201811589860A CN 109537709 A CN109537709 A CN 109537709A
- Authority
- CN
- China
- Prior art keywords
- library
- barren rock
- beach face
- tailings
- gutter
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims abstract description 53
- 230000006872 improvement Effects 0.000 claims abstract description 50
- 239000011159 matrix material Substances 0.000 claims abstract description 40
- 239000000463 material Substances 0.000 claims abstract description 27
- 238000009395 breeding Methods 0.000 claims abstract description 9
- 230000001488 breeding effect Effects 0.000 claims abstract description 9
- 239000004575 stone Substances 0.000 claims abstract description 6
- 230000008021 deposition Effects 0.000 claims description 86
- 241000196324 Embryophyta Species 0.000 claims description 85
- 239000011435 rock Substances 0.000 claims description 76
- 239000011248 coating agent Substances 0.000 claims description 68
- 238000000576 coating method Methods 0.000 claims description 68
- 239000002689 soil Substances 0.000 claims description 19
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 19
- 239000005416 organic matter Substances 0.000 claims description 14
- 230000008859 change Effects 0.000 claims description 13
- IJGRMHOSHXDMSA-UHFFFAOYSA-N Atomic nitrogen Chemical compound N#N IJGRMHOSHXDMSA-UHFFFAOYSA-N 0.000 claims description 12
- 241000220317 Rosa Species 0.000 claims description 12
- 229910001385 heavy metal Inorganic materials 0.000 claims description 12
- 235000021049 nutrient content Nutrition 0.000 claims description 12
- 238000010248 power generation Methods 0.000 claims description 12
- 241000894007 species Species 0.000 claims description 12
- 238000012360 testing method Methods 0.000 claims description 12
- QJZYHAIUNVAGQP-UHFFFAOYSA-N 3-nitrobicyclo[2.2.1]hept-5-ene-2,3-dicarboxylic acid Chemical compound C1C2C=CC1C(C(=O)O)C2(C(O)=O)[N+]([O-])=O QJZYHAIUNVAGQP-UHFFFAOYSA-N 0.000 claims description 10
- 244000025254 Cannabis sativa Species 0.000 claims description 10
- 239000004021 humic acid Substances 0.000 claims description 10
- 238000012423 maintenance Methods 0.000 claims description 10
- 239000003381 stabilizer Substances 0.000 claims description 10
- 230000005611 electricity Effects 0.000 claims description 9
- 238000009434 installation Methods 0.000 claims description 7
- 240000001592 Amaranthus caudatus Species 0.000 claims description 6
- 235000009328 Amaranthus caudatus Nutrition 0.000 claims description 6
- 241000234642 Festuca Species 0.000 claims description 6
- 240000000950 Hippophae rhamnoides Species 0.000 claims description 6
- 235000003145 Hippophae rhamnoides Nutrition 0.000 claims description 6
- 240000000604 Lespedeza bicolor Species 0.000 claims description 6
- 235000016677 Lespedeza bicolor Nutrition 0.000 claims description 6
- 235000017587 Medicago sativa ssp. sativa Nutrition 0.000 claims description 6
- 241000219830 Onobrychis Species 0.000 claims description 6
- 241001330451 Paspalum notatum Species 0.000 claims description 6
- OAICVXFJPJFONN-UHFFFAOYSA-N Phosphorus Chemical compound [P] OAICVXFJPJFONN-UHFFFAOYSA-N 0.000 claims description 6
- ZLMJMSJWJFRBEC-UHFFFAOYSA-N Potassium Chemical compound [K] ZLMJMSJWJFRBEC-UHFFFAOYSA-N 0.000 claims description 6
- 240000008488 Thlaspi arvense Species 0.000 claims description 6
- 235000008214 Thlaspi arvense Nutrition 0.000 claims description 6
- 229910021536 Zeolite Inorganic materials 0.000 claims description 6
- 235000012735 amaranth Nutrition 0.000 claims description 6
- 239000004178 amaranth Substances 0.000 claims description 6
- BRPQOXSCLDDYGP-UHFFFAOYSA-N calcium oxide Chemical compound [O-2].[Ca+2] BRPQOXSCLDDYGP-UHFFFAOYSA-N 0.000 claims description 6
- 239000000292 calcium oxide Substances 0.000 claims description 6
- ODINCKMPIJJUCX-UHFFFAOYSA-N calcium oxide Inorganic materials [Ca]=O ODINCKMPIJJUCX-UHFFFAOYSA-N 0.000 claims description 6
- 150000001875 compounds Chemical class 0.000 claims description 6
- HNPSIPDUKPIQMN-UHFFFAOYSA-N dioxosilane;oxo(oxoalumanyloxy)alumane Chemical compound O=[Si]=O.O=[Al]O[Al]=O HNPSIPDUKPIQMN-UHFFFAOYSA-N 0.000 claims description 6
- 239000003337 fertilizer Substances 0.000 claims description 6
- 230000007246 mechanism Effects 0.000 claims description 6
- 229910052757 nitrogen Inorganic materials 0.000 claims description 6
- 239000003895 organic fertilizer Substances 0.000 claims description 6
- 229910052698 phosphorus Inorganic materials 0.000 claims description 6
- 239000011574 phosphorus Substances 0.000 claims description 6
- 239000011591 potassium Substances 0.000 claims description 6
- 229910052700 potassium Inorganic materials 0.000 claims description 6
- 238000012545 processing Methods 0.000 claims description 6
- 238000013102 re-test Methods 0.000 claims description 6
- 239000003516 soil conditioner Substances 0.000 claims description 6
- 239000010457 zeolite Substances 0.000 claims description 6
- 244000284012 Vetiveria zizanioides Species 0.000 claims description 5
- 235000007769 Vetiveria zizanioides Nutrition 0.000 claims description 5
- 239000011083 cement mortar Substances 0.000 claims description 5
- 244000052363 Cynodon dactylon Species 0.000 claims description 4
- 241000209082 Lolium Species 0.000 claims description 4
- 240000008013 Phytolacca acinosa Species 0.000 claims description 4
- 235000009076 Phytolacca acinosa Nutrition 0.000 claims description 4
- 230000008569 process Effects 0.000 claims description 4
- 239000000654 additive Substances 0.000 claims description 3
- 230000000996 additive effect Effects 0.000 claims description 3
- 230000002441 reversible effect Effects 0.000 claims description 3
- 239000007787 solid Substances 0.000 claims description 3
- 238000003860 storage Methods 0.000 claims description 3
- 241000258920 Chilopoda Species 0.000 claims 2
- 240000004658 Medicago sativa Species 0.000 claims 2
- 238000004140 cleaning Methods 0.000 claims 1
- 239000004576 sand Substances 0.000 abstract description 2
- 238000000151 deposition Methods 0.000 description 73
- 239000010410 layer Substances 0.000 description 40
- 235000013339 cereals Nutrition 0.000 description 34
- 230000008901 benefit Effects 0.000 description 25
- 239000003795 chemical substances by application Substances 0.000 description 12
- 238000010276 construction Methods 0.000 description 9
- 238000011084 recovery Methods 0.000 description 6
- 230000007613 environmental effect Effects 0.000 description 5
- 230000001360 synchronised effect Effects 0.000 description 5
- 239000002699 waste material Substances 0.000 description 5
- 241000051984 Blepharidachne Species 0.000 description 4
- 241000223782 Ciliophora Species 0.000 description 4
- 241000219823 Medicago Species 0.000 description 4
- 239000002253 acid Substances 0.000 description 4
- 239000000440 bentonite Substances 0.000 description 4
- 229910000278 bentonite Inorganic materials 0.000 description 4
- SVPXDRXYRYOSEX-UHFFFAOYSA-N bentoquatam Chemical compound O.O=[Si]=O.O=[Al]O[Al]=O SVPXDRXYRYOSEX-UHFFFAOYSA-N 0.000 description 4
- 238000010586 diagram Methods 0.000 description 4
- 238000002898 library design Methods 0.000 description 4
- 125000001189 phytyl group Chemical group [H]C([*])([H])/C([H])=C(C([H])([H])[H])/C([H])([H])C([H])([H])C([H])([H])[C@@](C([H])([H])[H])([H])C([H])([H])C([H])([H])C([H])([H])[C@@](C([H])([H])[H])([H])C([H])([H])C([H])([H])C([H])([H])C(C([H])([H])[H])([H])C([H])([H])[H] 0.000 description 4
- 230000008635 plant growth Effects 0.000 description 4
- 238000009331 sowing Methods 0.000 description 4
- 239000002344 surface layer Substances 0.000 description 4
- 238000011161 development Methods 0.000 description 3
- 238000009826 distribution Methods 0.000 description 3
- 238000005065 mining Methods 0.000 description 3
- 241001529246 Platymiscium Species 0.000 description 2
- 239000003513 alkali Substances 0.000 description 2
- 230000015271 coagulation Effects 0.000 description 2
- 238000005345 coagulation Methods 0.000 description 2
- 230000007797 corrosion Effects 0.000 description 2
- 238000005260 corrosion Methods 0.000 description 2
- 239000004615 ingredient Substances 0.000 description 2
- 238000003973 irrigation Methods 0.000 description 2
- 230000002262 irrigation Effects 0.000 description 2
- 229910052751 metal Inorganic materials 0.000 description 2
- 239000002184 metal Substances 0.000 description 2
- 239000000203 mixture Substances 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 238000003823 mortar mixing Methods 0.000 description 2
- 235000016709 nutrition Nutrition 0.000 description 2
- 230000008439 repair process Effects 0.000 description 2
- 241000209056 Secale Species 0.000 description 1
- 235000021307 Triticum Nutrition 0.000 description 1
- 244000098338 Triticum aestivum Species 0.000 description 1
- 230000003321 amplification Effects 0.000 description 1
- 239000004568 cement Substances 0.000 description 1
- 238000005520 cutting process Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000004134 energy conservation Methods 0.000 description 1
- 230000003628 erosive effect Effects 0.000 description 1
- 230000012010 growth Effects 0.000 description 1
- 238000007726 management method Methods 0.000 description 1
- 238000003199 nucleic acid amplification method Methods 0.000 description 1
- 239000002304 perfume Substances 0.000 description 1
- 230000000192 social effect Effects 0.000 description 1
- 235000013599 spices Nutrition 0.000 description 1
- 239000010902 straw Substances 0.000 description 1
- 239000000126 substance Substances 0.000 description 1
- 230000007704 transition Effects 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F5/00—Sewerage structures
- E03F5/04—Gullies inlets, road sinks, floor drains with or without odour seals or sediment traps
-
- A—HUMAN NECESSITIES
- A01—AGRICULTURE; FORESTRY; ANIMAL HUSBANDRY; HUNTING; TRAPPING; FISHING
- A01B—SOIL WORKING IN AGRICULTURE OR FORESTRY; PARTS, DETAILS, OR ACCESSORIES OF AGRICULTURAL MACHINES OR IMPLEMENTS, IN GENERAL
- A01B79/00—Methods for working soil
- A01B79/02—Methods for working soil combined with other agricultural processing, e.g. fertilising, planting
-
- A—HUMAN NECESSITIES
- A01—AGRICULTURE; FORESTRY; ANIMAL HUSBANDRY; HUNTING; TRAPPING; FISHING
- A01G—HORTICULTURE; CULTIVATION OF VEGETABLES, FLOWERS, RICE, FRUIT, VINES, HOPS OR SEAWEED; FORESTRY; WATERING
- A01G17/00—Cultivation of hops, vines, fruit trees, or like trees
- A01G17/005—Cultivation methods
-
- A—HUMAN NECESSITIES
- A01—AGRICULTURE; FORESTRY; ANIMAL HUSBANDRY; HUNTING; TRAPPING; FISHING
- A01G—HORTICULTURE; CULTIVATION OF VEGETABLES, FLOWERS, RICE, FRUIT, VINES, HOPS OR SEAWEED; FORESTRY; WATERING
- A01G22/00—Cultivation of specific crops or plants not otherwise provided for
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B7/00—Barrages or weirs; Layout, construction, methods of, or devices for, making same
- E02B7/02—Fixed barrages
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/20—Securing of slopes or inclines
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02S—GENERATION OF ELECTRIC POWER BY CONVERSION OF INFRARED RADIATION, VISIBLE LIGHT OR ULTRAVIOLET LIGHT, e.g. USING PHOTOVOLTAIC [PV] MODULES
- H02S20/00—Supporting structures for PV modules
- H02S20/30—Supporting structures being movable or adjustable, e.g. for angle adjustment
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A30/00—Adapting or protecting infrastructure or their operation
- Y02A30/60—Planning or developing urban green infrastructure
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/50—Photovoltaic [PV] energy
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P60/00—Technologies relating to agriculture, livestock or agroalimentary industries
- Y02P60/12—Technologies relating to agriculture, livestock or agroalimentary industries using renewable energies, e.g. solar water pumping
Landscapes
- Life Sciences & Earth Sciences (AREA)
- Engineering & Computer Science (AREA)
- Environmental Sciences (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Botany (AREA)
- Mining & Mineral Resources (AREA)
- Civil Engineering (AREA)
- Mechanical Engineering (AREA)
- Paleontology (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Soil Sciences (AREA)
- Health & Medical Sciences (AREA)
- Hydrology & Water Resources (AREA)
- Public Health (AREA)
- Water Supply & Treatment (AREA)
- Photovoltaic Devices (AREA)
Abstract
The invention discloses a kind of Tailings Dams to close library system and method, photovoltaic generating system, ecological restoring method, wherein, it is related to closing Tailings Dam into library system, photovoltaic generating system and restoration of the ecosystem triplicity, the dam body in library is closed by Tailings Dam, deposit the regulation of beach face and drainage system, it recycles discarded stone and tailings is used as and closes library material, photovoltaic generating system is installed in closing library system, CHARACTERISTICS OF TAILINGS SAND matrix is improved as planting matrix and breeding suitable species simultaneously, realize Tailings Dam, rejected ore, goaf, collapse the safety improvement that discarded place has been polluted in decanting zone etc., comprehensive utilization and ecological protection.
Description
Technical field
The present invention relates to the present invention relates to Tailings Dam Treatment process fields, and in particular to a kind of Tailings Dam closes library system and side
Method, photovoltaic generating system, ecological restoring method.
Background technique
Currently, the Tailings Dam in some mines, abandoned mine library, dregs stockyard, goaf, to collapse the large area such as decanting zone idle.
When Tailings Dam closes library improvement at present, ore resources comprehensive utilization in tail library is insufficient.Library is closed to administer and subsequent comprehensive utilization and life safely
State reparation is kept completely separate, or does not carry out comprehensive utilization and restoration of the ecosystem.
Summary of the invention
The present invention is directed at least solve one of the technical problems existing in the prior art.For this purpose, one object of the present invention
It is to propose that a kind of Tailings Dam closes library system, reasonably takes full advantage of the obsolete material of Tailings Dam, saved resource, realize
The safety of Tailings Dam is administered.
The present invention also proposes that a kind of Tailings Dam closes library method, reasonably takes full advantage of the obsolete material of Tailings Dam, saves
Resource, the safety for realizing Tailings Dam are administered.
The present invention also proposes a kind of photovoltaic generating system, realizes the comprehensive utilization that Tailings Dam closes library and photovoltaic power generation.
The present invention also proposes a kind of ecological restoring method, realizes and carries out ecology improvement and recovery after closing library to Tailings Dam;
Or it realizes Tailings Dam and closes the comprehensive utilization of resources that library, photovoltaic power generation and restoration of the ecosystem combine.
The Tailings Dam of embodiment closes library system according to a first aspect of the present invention, comprising:
Beach face coating is deposited, the deposition beach face coating is laid on the deposition beach face using tailings and is formed
Tailings layer;
Dam body, the dam body are disposed around the outside of the deposition beach face coating;The dam body includes outer slope protection layer,
The outer slope protection layer is not produce the slope protection layer that sour barren rock is built into using coarse grain diameter;
Gutter, the gutter include library week gutter and library internal drainage ditch;The library week gutter be looped around it is described
The outside of dam body and adjacent with the dam body;The library internal drainage ditch is located at the deposition beach face coating and the dam body
Surface on, and intersect with library week gutter and be connected to, pass through the convergence gutter row being located on the outside of library week gutter
Out.
The Tailings Dam of embodiment closes library system according to a first aspect of the present invention, and deposition beach face coating is being deposited using tailings
Beach face is laid with, and dam body, which encloses, to be built in the outside of deposition beach face coating, and the outer slope protection layer of dam body is not produced using coarse grain diameter
Sour barren rock is built into, and the surface layer for depositing beach face coating and dam body is equipped with library internal drainage ditch and is connected to library week gutter, passes through position
Convergence gutter discharge on the outside of library week gutter.Any facility for not changing and destroying Tailings Dam not only as a result, also increases
Tailings warehouse dam body regulation, deposition beach face improvement, gutter facility etc., and reasonably take full advantage of the discarded material of Tailings Dam
Material, has saved resource, is conducive to restoration of the ecosystem, closes that library system is safe and reliable, so that the safety for realizing Tailings Dam is administered.
The coarse grain diameter of one embodiment according to a first aspect of the present invention, the outer slope protection layer does not produce sour barren rock
Partial size is greater than 200mm.
One embodiment according to a first aspect of the present invention, the outer slope protection layer with a thickness of 0.4~0.6m.
One embodiment according to a first aspect of the present invention, the gutter are not produce sour mine barren rock and water using fine grain
Gutter made of cement mortar mixing is built.
Further embodiment according to a first aspect of the present invention, the fine grain do not produce sour mine barren rock partial size be 5mm~
60mm。
The Tailings Dam of embodiment closes library method according to a second aspect of the present invention, includes the following steps:
The processing of mine barren rock;According to the physicochemical characteristics of mine barren rock, selection does not produce sour mine barren rock and carries out break process, obtains
Coarse grain diameter does not produce that sour barren rock, fine grain do not produce sour barren rock, middle fine grain does not produce sour barren rock, closes library material as Tailings Dam and uses;
Deposit beach face processing: it is smooth to deposition beach face progress, then it is laid with tailings in deposition beach face, it forms deposition beach face and covers
Layer;
It builds dam body: dam body being built using native stone in the outside of deposition beach face, slope is not produced using coarse grain diameter outside dam body
Sour mine barren rock is built into slope protection layer;
It builds gutter: building library week gutter in dam body outside and with dam body adjacent;In deposition beach face coating
Library internal drainage ditch is built into using fine grain not produce sour barren rock and mix with cement mortar on the surface of dam body, the library internal drainage
Ditch intersects with library week gutter to be connected to, the convergence gutter discharge on the outside of library week gutter.
The tailing of embodiment closes library method according to a second aspect of the present invention, is laid with to form deposition using tailings in deposition beach face
Beach face coating encloses body of building a dam in the outside of deposition beach face coating, and the outer slope protection layer of dam body does not produce acid using coarse grain diameter
Barren rock is built into, and the surface layer for depositing beach face coating and dam body is equipped with library internal drainage ditch and is connected to library week gutter, by being located at
Convergence gutter discharge on the outside of library week gutter.Do not change and destroy any facility of Tailings Dam not only as a result, also increase tail
The regulation of mine library dam body, deposition beach face improvement, gutter facility etc., and reasonably take full advantage of the mine barren rock of Tailings Dam and give up
Tail dropping sand has saved resource as library material is closed, and is conducive to restoration of the ecosystem, so that finally obtained library system of closing is repaired conducive to ecology
It is multiple, securely and reliably.
One embodiment according to a second aspect of the present invention, further comprises the steps of:
The arrangement of PHC concrete prefabricated pipe: multiple PHC coagulations are arranged vertically in deposition beach face covering layer region
Native prefabricated pipe is used for installation photovoltaic component bracket.
Further embodiment according to a second aspect of the present invention further comprises the steps of:
Maintenance constructing road: it according to the deployment scenarios of PHC concrete prefabricated pipe, is used on the deposition beach face coating
Middle fine grain does not produce sour barren rock and builds maintenance road.
One embodiment according to a second aspect of the present invention, the coarse grain diameter do not produce sour barren rock partial size be greater than 200mm,
The fine grain do not produce sour barren rock partial size be 5mm~60mm, the middle fine grain do not produce sour barren rock partial size be 30mm~
100mm。
One embodiment according to a second aspect of the present invention, further comprises the steps of:
Earth material layer is laid with: the earth material layer for being used for planting plants is laid on the deposition beach face coating.
The photovoltaic generating system of embodiment according to a third aspect of the present invention is applied in above-mentioned first aspect any embodiment
Tailings Dam closes in the system of library, comprising:
Multiple PHC concrete prefabricated pipes, multiple PHC concrete prefabricated pipes are linearly spaced apart vertical array, multiple
The PHC concrete prefabricated pipe includes connected lower section prefabricated pipe and upper section prefabricated pipe, and the lower section prefabricated pipe is buried solid in institute
It states in deposition beach face coating, the upper section prefabricated pipe extends vertically upward;
Photovoltaic module support, the photovoltaic module support are fixed on the upper section of multiple PHC concrete prefabricated pipes
In prefabricated pipe;
Photovoltaic module, the photovoltaic module are mounted on the photovoltaic module support.
The photovoltaic generating system of embodiment according to a third aspect of the present invention, since PHC concrete prefabricated pipe is with higher
Support strength, multiple PHC concrete prefabricated pipes can carry photovoltaic module support disposed thereon and be mounted on photovoltaic module branch
The sum of weight of photovoltaic module on frame.Electric energy can be converted light energy by photovoltaic module, is utilized closes library system as a result,
Place carries out photovoltaic power generation, can increase point off supply to bargh's distribution, increase renewable sources of energy ratio, reduce electric cost,
The utilization of resources is abundant.Therefore, the photovoltaic generating system of third aspect present invention embodiment have the advantages that first, do not cut into a mountain,
It is not take up arable land, economizes on resources, build photovoltaic plant using waste land.The second, photovoltaic plant is realized nearby simultaneously close to mining area
Net power supply, electricity, which is marketed one's own products, has consumption advantage, reduces bargh's electric cost.Third, the construction of photovoltaic plant are complete
According to the original geography of Tailings Dam, and with close library design and the synchronous progress of construction, do not change and destroy Tailings Dam not only
Any facility, the also regulation of increase tailings warehouse dam body, deposition beach face improvement, gutter facility etc. realize safety and close library, photovoltaic hair
The comprehensive utilization of electricity.4th, the comprehensive utilization on the idle discarded ground in mine is realized, the environment comprehensive for facilitating Mine land is controlled
Reason.
One embodiment according to a third aspect of the present invention, the photovoltaic module support are the fixed bracket of dip-adjustable type.
One embodiment according to a third aspect of the present invention, the photovoltaic module support include frame and the PHC coagulation
The corresponding multiple columns of native prefabricated pipe, the upper end of multiple columns is connect with the frame, under multiple columns
End is fixed with the upper end of corresponding multiple upper section prefabricated pipes.
Further embodiment according to a third aspect of the present invention, the photovoltaic module support further include very heavy head piece and thousand
Jin top, the very heavy head piece are secured transverse in two PHC concrete prefabricated pipes, and the jack is angularly disposed, institute
The lower end for stating jack is connected on the very heavy head piece, the upper end of the jack hingedly on said frame, Duo Gesuo
The upper end of column is stated with the frame articulation, makes the inclination angle of the frame can with the length by the adjusting jack
It adjusts.
One embodiment according to a third aspect of the present invention further includes inverter and substation, and the substation, which is equipped with, to be become
Depressor, the inverter are connected electrically between the photovoltaic module and the transformer.
Further embodiment according to a third aspect of the present invention, the inverter be connected electrically in the photovoltaic module with it is described
Between transformer specifically: multiple photovoltaic module series connection accumulate a component string, and component string described in multiple groups is collected into one
A header box, multiple header boxs collect into the inverter, and the DC current of input is reverse into three by the inverter
Phase alternating current, and high-voltage electricity is converted by the change device and is sent into electric system.
Further embodiment according to a third aspect of the present invention, the inverter and the substation are arranged in the dam body
Periphery at frame concrete on the basis of.
One embodiment according to a third aspect of the present invention is additionally provided with fine grain in use on the deposition beach face coating
The maintenance road that sour barren rock is built is not produced.
Further embodiment according to a third aspect of the present invention, the middle particulate do not produce sour mine barren rock partial size be 30mm~
100mm。
One embodiment according to a third aspect of the present invention, the concrete in the PHC concrete prefabricated pipe is added with resistance to
The additive of acid and alkali corrosion.
One embodiment according to a third aspect of the present invention, further includes catch basin and water cell, and the catch basin is located at
It is set below the photovoltaic module, for receiving the rainwater flowed down from photovoltaic module and clean water, the catch basin and water storage
Unit connection, so that the water in the catch basin flows into water cell.
The ecological restoring method of embodiment according to a fourth aspect of the present invention is applied in above-mentioned first aspect any embodiment
Tailings Dam closes in the system of library, includes the following steps:
Planting matrix improvement: organic matter, humic acid, metallic stabilizer, soil improvement are added in deposition beach face coating
One or more of agent, water-retaining agent, or the earth material layer for being used for planting plants is directly laid on deposition beach face coating;To changing
Well-founded matter is tested, it is ensured that the pH value and nutrient content of matrix reach the standard of planting technique soil;
Species breeding: according to the physicochemical characteristics of mine barren rock, the plant cultivation of resistance to heavy metal is selected to plant, or/and selected
Impoverishment tolerant plant;
Vegetation plantation: planning as a whole arrangement planting area at the planting matrix of improvement, plants selected species in planting area and plants
Object.
The ecological restoring method of embodiment according to a fourth aspect of the present invention closes library system 100 to Tailings Dam and carries out ecology and repairs
It is multiple, be conducive to the improvement and recovery of closing the ecological environment of library system.
One embodiment according to a fourth aspect of the present invention, the Plant choosing of the resistance to heavy metal ciliate desert-grass, alfalfa, quotient
At least one of land, vetiver, penny cress, three-coloured amaranth and shrub plant;The impoverishment tolerant Plant choosing sainfoin, fescue grass, dog
At least one of root of the tooth, rye grass, paspalum notatum, shrub lespedeza, rose, leapfrog, rose, sea-buckthorn and shrub plant.
One embodiment according to a fourth aspect of the present invention, in the step of testing improvement mechanism, first test kind
PH, organic matter, hydrolyzable nitrogen, available phosphorus and the quick-acting potassium content of phytyl matter, re-test calcium oxide, organic fertilizer, bentonite, zeolite and
Compound fertilizer.
The ecological restoring method of embodiment according to a fifth aspect of the present invention is applied in above-mentioned third aspect any embodiment
In photovoltaic generating system, include the following steps:
Planting matrix improvement: organic matter, humic acid, metallic stabilizer, soil improvement are added in deposition beach face coating
One or more of agent, water-retaining agent, or the earth material layer for being used for planting plants is directly laid on deposition beach face coating;To changing
Well-founded matter is tested, it is ensured that the pH value and nutrient content of matrix reach the standard of planting technique soil;
Species breeding: according to the physicochemical characteristics of mine barren rock, the plant cultivation of resistance to heavy metal is selected to plant, or/and selected
Impoverishment tolerant plant;
Vegetation plantation: planning as a whole arrangement planting area at the planting matrix of improvement, plants selected species in planting area and plants
Object.
The ecological restoring method of embodiment according to a fifth aspect of the present invention closes library system and photovoltaic power generation system in conjunction with Tailings Dam
System carries out restoration of the ecosystem, has the advantage that first, does not cut into a mountain, be not take up arable land, economize on resources and obtain waste land
To realize the reparation of ecological environment.The second, photovoltaic plant realizes grid-connected power supply nearby, electricity, which is marketed one's own products, to be had close to mining area
Consumption advantage reduces bargh's electric cost.The construction of third, photovoltaic plant is completely according to the original geographical shape of Tailings Dam
Gesture, and with close library design and construction it is synchronous progress, do not change and destroy any facility of Tailings Dam not only, also increase tailing dam
The regulation of body 2, deposition beach face improvement, gutter facility etc. realize the comprehensive benefit that safety closes library, photovoltaic power generation and restoration of the ecosystem
With.4th, the comprehensive utilization for realizing the idle discarded ground in mine, facilitates the comprehensive environmental improvement of Mine land.
One embodiment according to a fifth aspect of the present invention, the Plant choosing of the resistance to heavy metal ciliate desert-grass, alfalfa, quotient
At least one of land, vetiver, penny cress, three-coloured amaranth and shrub plant;The impoverishment tolerant Plant choosing sainfoin, fescue grass, dog
At least one of root of the tooth, rye grass, paspalum notatum, shrub lespedeza, rose, leapfrog, rose, sea-buckthorn and shrub plant.
One embodiment according to a fifth aspect of the present invention, in the step of testing improvement mechanism, first test kind
PH, organic matter, hydrolyzable nitrogen, available phosphorus and the quick-acting potassium content of phytyl matter, re-test calcium oxide, organic fertilizer, bentonite, zeolite and
Compound fertilizer.
Additional aspect and advantage of the invention will be set forth in part in the description, and will partially become from the following description
Obviously, or practice through the invention is recognized.
Detailed description of the invention
Above-mentioned and/or additional aspect of the invention and advantage will become from the description of the embodiment in conjunction with the following figures
Obviously and it is readily appreciated that, in which:
Fig. 1 is that the Tailings Dam of first aspect present invention embodiment closes the floor map of library system.
Fig. 2 is the diagrammatic cross-section in Fig. 1 at A-A.
Fig. 3 is the diagrammatic cross-section in Fig. 1 at B-B.
Fig. 4 is the amplification schematic cross-section in gutter in Fig. 1.
Fig. 5 is that the Tailings Dam of second aspect of the present invention embodiment closes the flow diagram of library method.
Fig. 6 is one of equipment component schematic diagram of the photovoltaic generating system of third aspect present invention embodiment.
Fig. 7 is the two of the equipment component schematic diagram of the photovoltaic generating system of third aspect present invention embodiment.
Fig. 8 is the flow diagram of the ecological restoring method of fourth aspect present invention or the 5th aspect embodiment.
Appended drawing reference:
Tailings Dam closes library system 100
Deposit beach face coating 1
The outer slope protection layer 21 of dam body 2
3 library week of gutter gutter 31 library internal drainage ditch 32 converge gutter 33
Earth material layer 4
Photovoltaic generating system 200
5 upper section prefabricated pipe 51 of PHC concrete prefabricated pipe
Very heavy 63 jack 64 of head piece of 6 frame of photovoltaic module support, 61 column 62
Specific embodiment
The embodiment of the present invention is described in detail below, examples of the embodiments are shown in the accompanying drawings, wherein from beginning to end
Same or similar label indicates same or similar element or element with the same or similar functions.Below with reference to attached
The embodiment of figure description is to show routinely, for explaining only the invention, and is not considered as limiting the invention.
The present invention using build novel ecological industrialization mine, Green Mine as target, in line with development of resources with optimize the environment
It combines, comprehensive utilization of resources is combined with environmental protection, improves development of resources economic benefit and ecological environment synchronized construction phase
In conjunction with principle, the Item Sets new energy, waste stone utilization, tailing close library, land, ecological recovery and go sightseeing etc. more
The integrated project in position, the transition of power-assisted tradition old mine enterprise upgrading sufficiently practice energy conservation and environmental protection and Green Development theory, solve part
Employee's re-employment, generates good social effect, ecological effect and economic benefits, has important demonstration meaning.
Tailings Dam according to an embodiment of the present invention is described below with reference to Fig. 1 to Fig. 8 closes library system and method, photovoltaic power generation
System, ecological restoring method.
As shown in Figures 1 to 4, the Tailings Dam of embodiment closes library system 100, including deposition beach according to a first aspect of the present invention
Face coating 1, dam body 2 and gutter 3.Wherein, deposition beach face coating 1 is laid on deposition beach face using tailings and is formed
Tailings layer;Dam body 2 is disposed around the outside of deposition beach face coating 1;Dam body 2 includes outer slope protection layer 21, outer slope protection layer 21
Not produce the slope protection layer that sour barren rock is built into using coarse grain diameter;Gutter 3 includes library week gutter 31 and library internal drainage ditch 32;Library week
Gutter 31 is looped around the outside of dam body 2 and adjacent with dam body 2;Library internal drainage ditch 32 is located at deposition 1 He of beach face coating
On the surface of dam body 2, and intersect with library week gutter 31 and be connected to, by the convergence gutter 33 for being located at 31 outside of library week gutter
Discharge.
Specifically, deposition beach face coating 1 is to be laid on the tailings layer formed on deposition beach face using tailings.As a result,
The tailings discarded at Tailings Dam is taken full advantage of, is economized on resources, restoration of the ecosystem is conducive to.
Dam body 2 is disposed around the outside of deposition beach face coating 1;Dam body 2 includes outer slope protection layer 21, outer slope protection layer 21
Not produce the slope protection layer that sour barren rock is built into using coarse grain diameter.As a result, by setting dam body 2, prevent under deposition beach face coating 1
It collapses.The outer slope protection layer 21 of dam body 2 does not produce sour barren rock using coarse grain diameter and is built into, and on the one hand ensure that dam body 2 will not glide, prevents
The earth flow of dam body 2 loses, so that it is safe and reliable to close library system, is conducive to restoration of the ecosystem;On the other hand, it is also fully utilized by tail library mine
On mine barren rock, saved resource.
Gutter 3 includes library week gutter 31 and library internal drainage ditch 32;Library week, gutter 31 was looped around the outside of dam body 2
And it is adjacent with dam body 2;Library internal drainage ditch 32 be located at deposition beach face coating 1 and dam body 2 surface on, and with library week gutter
31 intersect connection, and the convergence gutter 33 by being located at 31 outside of library week gutter is discharged.It, can as a result, by setting gutter 3
To avoid depositing on beach face coating 1 because rainwater weather generates rainwater ponding, be conducive to restoration of the ecosystem.
The Tailings Dam of embodiment closes library system 100 according to a first aspect of the present invention, and deposition beach face coating 1 is existed using tailings
Deposition beach face is laid with, and dam body 2, which encloses, to be built in the outside of deposition beach face coating 1, and the outer slope protection layer 21 of dam body 2 is using thick
Partial size does not produce sour barren rock and is built into, deposit beach face coating 1 and dam body 2 surface layer be equipped with library internal drainage ditch 32 and with library week gutter
31 connections, the convergence gutter 33 by being located at 31 outside of library week gutter are discharged.Do not change and destroy Tailings Dam not only as a result,
Any facility, the also regulation of increase tailings warehouse dam body 2, deposition beach face improvements, 3 facility of gutter etc., and reasonably sufficiently sharp
With the obsolete material of Tailings Dam, resource has been saved, has been conducive to restoration of the ecosystem, it is safe and reliable to close library system, to realize tailing
The safety in library is administered.
One embodiment according to a first aspect of the present invention, the partial size that the coarse grain diameter of outer slope protection layer 21 does not produce sour barren rock are
Greater than 200mm.Be conducive to sufficiently and reasonably protect dam body 2 not stay sliding using resource as a result,.
One embodiment according to a first aspect of the present invention, outer slope protection layer 21 with a thickness of 0.4~0.6m.As a result, both
Build cost can be taken into account, and can preferably protect dam body 2.
One embodiment according to a first aspect of the present invention, gutter 3 are not produce sour mine barren rock and cement using fine grain
Gutter 3 made of mortar mixing is built.Be conducive to sufficiently and reasonably utilize resource as a result,.
Further embodiment according to a first aspect of the present invention, the partial size that fine grain does not produce sour mine barren rock is 5mm~60mm.
Be conducive to sufficiently and reasonably utilize resource as a result,.
In conjunction with shown in Fig. 1 to Fig. 5, the Tailings Dam of embodiment closes library method according to a second aspect of the present invention, including walks as follows
It is rapid:
S1: the processing of mine barren rock: according to the physicochemical characteristics of mine barren rock, selection does not produce sour mine barren rock and carries out break process,
It obtains coarse grain diameter and does not produce that sour barren rock, fine grain do not produce sour barren rock, middle fine grain does not produce sour barren rock, closing library material as Tailings Dam makes
With;
S2: deposition beach face processing: it is smooth to deposition beach face progress, then it is laid with tailings in deposition beach face, form deposition beach face
Coating 1;
S3: it builds dam body: dam body 2 being built using native stone in the outside of deposition beach face, uses coarse grain diameter on the outer slope of dam body 2
Sour mine barren rock is not produced is built into slope protection layer;
S4: it builds gutter: building library week gutter 31 in 2 outside of dam body and with 2 adjacent of dam body;In deposition beach face
Sour barren rock is not produced mix with cement mortar build into library internal drainage ditch 32, library on the surface of coating 1 and dam body 2 using fine grain
Internal drainage ditch 32 intersects with library week gutter 31 to be connected to, and the convergence gutter 33 positioned at 31 outside of library week gutter is discharged.
The tailing of embodiment closes library method according to a second aspect of the present invention, is laid with to form deposition using tailings in deposition beach face
Beach face coating 1 builds dam body 2 in the outside of deposition beach face coating 1, and the outer slope protection layer 21 of dam body 2 uses coarse grain diameter
It does not produce sour barren rock to be built into, the surface layer for depositing beach face coating 1 and dam body 2 is equipped with library internal drainage ditch 32 and connects with library week gutter 31
Logical, the convergence gutter 33 by being located at 31 outside of library week gutter is discharged.Do not change not only as a result, and destroys appointing for Tailings Dam
What facility, the also regulation of increase tailings warehouse dam body 2, deposition beach face improvement, 3 facility of gutter etc., and reasonably take full advantage of
The mine barren rock of Tailings Dam and discarded tailings have saved resource as library material is closed, and are conducive to restoration of the ecosystem, so that finally obtained close
Library system is conducive to restoration of the ecosystem, securely and reliably.
One embodiment according to a second aspect of the present invention, further comprises the steps of:
The arrangement of S5:PHC concrete prefabricated pipe 5: multiple PHC concrete are arranged vertically in deposition 1 region of beach face coating
Prefabricated pipe 5 is used for installation photovoltaic component bracket 6.As a result, by vertically arranged for installing in deposition 1 region of beach face coating
Multiple PHC concrete prefabricated pipes 5 of photovoltaic module support 6 are conducive to the photovoltaics such as installation photovoltaic component bracket 6 and photovoltaic module hair
Some equipment of electricity can increase point off supply, increase using library system place progress photovoltaic power generation is being closed to bargh's distribution
Add renewable sources of energy ratio, reduces electric cost.
Further embodiment according to a second aspect of the present invention further comprises the steps of:
S6: it maintenance constructing road: according to the deployment scenarios of PHC concrete prefabricated pipe 5, is adopted on deposition beach face coating 1
Sour barren rock is not produced with middle fine grain builds maintenance road.Road is overhauled by setting, is convenient to maintenance photovoltaic apparatus.Overhaul road
Fine grain does not produce sour barren rock and builds in, takes full advantage of mine barren rock resource.
One embodiment according to a second aspect of the present invention, the partial size that coarse grain diameter does not produce sour barren rock is greater than 200mm, particulate
The partial size that diameter does not produce sour barren rock is 5mm~60mm, and the partial size that middle fine grain does not produce sour barren rock is 30mm~100mm.Pass through as a result,
Sour barren rock is not produced by do not produce that sour mine barren rock is broken into different-grain diameter, is classified according to library material requested is closed, sufficiently reasonable benefit
With not producing sour mine barren rock resource.
One embodiment according to a second aspect of the present invention, further comprises the steps of:
S7: earth material layer 4 is laid with: the earth material layer 4 for being used for planting plants is laid on deposition beach face coating 1.Thus, it is possible to
The planting plants in the region for closing library system realize that ecology improves and restores, improve the ecological environment for closing library system.
As shown in Figure 6 to 7, the photovoltaic generating system 200 of embodiment according to a third aspect of the present invention, is applied above-mentioned
The Tailings Dam of one side any embodiment closes in library system 100, including multiple PHC concrete prefabricated pipes 5, photovoltaic module support 6
With photovoltaic module (not shown).Wherein, multiple PHC concrete prefabricated pipes 5 vertical array linearly spaced apart, multiple PHC
Concrete prefabricated pipe 5 includes connected lower section prefabricated pipe (not shown) and upper section prefabricated pipe 51, and lower section prefabricated pipe is buried solid
In deposition beach face coating 1, upper section prefabricated pipe 51 extends vertically upward;Photovoltaic module support 6 is fixed on multiple PHC concrete
In the upper section prefabricated pipe 51 of prefabricated pipe 5;Photovoltaic module is mounted on photovoltaic module support 6.
The photovoltaic generating system 200 of embodiment according to a third aspect of the present invention, due to PHC concrete prefabricated pipe 5 have compared with
High support strength, multiple PHC concrete prefabricated pipes 5 can carry photovoltaic module support 6 disposed thereon and be mounted on photovoltaic
The sum of the weight of photovoltaic module on assembly support 6.Electric energy can be converted light energy by photovoltaic module, is utilized as a result,
It closes library system place and carries out photovoltaic power generation, can increase point off supply to bargh's distribution, increase renewable sources of energy ratio, reduce
Electric cost, the utilization of resources are abundant.Therefore, the photovoltaic generating system 200 of third aspect present invention embodiment has the advantages that
The first, it does not cut into a mountain, is not take up arable land, economizes on resources, building photovoltaic plant using waste land.The second, photovoltaic plant is close to mine
Area realizes grid-connected power supply nearby, and electricity, which is marketed one's own products, has consumption advantage, reduces bargh's electric cost.Third, photovoltaic electric
The construction stood completely according to the original geography of Tailings Dam, and with close library design and the synchronous progress of construction, do not change not only with
Any facility of Tailings Dam is destroyed, also the regulation of increase tailings warehouse dam body, deposition beach face improvement, 3 facility of gutter etc., realizes peace
The comprehensive utilization in fully closed library, photovoltaic power generation.4th, the comprehensive utilization for realizing the idle discarded ground in mine, facilitates Mine land
Comprehensive environmental improvement.
One embodiment according to a third aspect of the present invention, photovoltaic module support 6 are dip-adjustable type photovoltaic module support
6.By using dip-adjustable type photovoltaic module support 6, the adjustable photovoltaic module being mounted on photovoltaic module support 6 inclines
Even if the direction of angle photovoltaic module, so that photovoltaic module direction is in optimum state, such as keeps light vertical with photovoltaic module, obtain
Obtain optimum total power.
One embodiment according to a third aspect of the present invention, photovoltaic module support 6 include the frame for installation photovoltaic component
Frame 61 and multiple columns 62 corresponding with PHC concrete prefabricated pipe 5, the upper end of multiple columns 62 is connect with frame 61, more
The lower end of a column 62 is fixed with the upper end of corresponding multiple upper section prefabricated pipes 51.Wherein, the upper end of 62 columns and frame
Connection type can specifically be fixed using welding or bolt fixing method.Photovoltaic module support 6 will by setting column 62 as a result,
Frame 61 is connected in PHC concrete prefabricated pipe 5, easy installation and reliable by 61 installation photovoltaic component of frame.
Further embodiment according to a third aspect of the present invention, photovoltaic module support 6 further include very heavy head piece 63 and thousand
Jin top 64, very heavy head piece 63 is secured transverse in two PHC concrete prefabricated pipes 5, and jack 64 is angularly disposed, jack 64
Lower end be connected on very heavy head piece 63, the upper end of jack 64 is hinged on frame 61, the upper end of multiple columns 62 with
Frame 61 is hinged, to make the tilt adjustable of frame 61 by the length for adjusting jack 64.It is vertical by the way that frame 61 to be hinged on
On column 62 and the jack of inclined setting 64 and multiple columns 62, with the mandril length for overregulating jack 64, such as same mistake
Hand mode adjusts the mandril length of jack 64, can have and be conveniently adjusted the photovoltaic group that 61 machine of frame is mounted on frame 61
The inclination angle of part makes photovoltaic module towards in optimum position, obtains optimum total power.Here, it needs to illustrate a bit, photovoltaic module
It is maintained at 1.2m or more as far as possible apart from ground level, there are enough growths empty with the plant for ensuring to plant below photovoltaic module
Between.
One embodiment according to a third aspect of the present invention further includes inverter and substation (inverter and substation's figure
In be not shown), substation is equipped with transformer, and inverter is connected electrically between photovoltaic module and transformer.It is same as a result, to cross inverter
The direct current that photovoltaic module inputs can be converted into alternating current, then be converted to the alternating current that inverter inputs by transformer
The alternating current of required specification and output.
Further embodiment according to a third aspect of the present invention, inverter, which is connected electrically between photovoltaic module and transformer, to be had
Body are as follows: multiple photovoltaic module series connection accumulate a component string, and multi-grade module string collects into a header box, and multiple header boxs converge
Collection enters inverter, and the DC current of input is reverse into three-phase alternating current by inverter, and is converted into high-voltage electricity by change device and is sent
Enter electric system.
Further embodiment according to a third aspect of the present invention, inverter and substation are arranged at the periphery of dam body 2
On the basis of frame concrete.Thus, it is possible to avoid Tailings Dam from settling and damage relevant device, such as inverter and substation set
It is standby.
One embodiment according to a third aspect of the present invention, deposit beach face coating 1 on be additionally provided with use in fine grain not
Produce the maintenance road that sour barren rock is built.Road is overhauled by setting, can be convenient to photovoltaic apparatus such as photovoltaic module, photovoltaic group
Part bracket 6 etc. is overhauled.Fine grain does not produce sour barren rock and builds in maintenance road use, and it is useless reasonably to take full advantage of mine
Stone resource.
Further embodiment according to a third aspect of the present invention, middle particulate do not produce sour mine barren rock partial size be 30mm~
100mm.Mine barren rock resource is reasonably taken full advantage of as a result,.
One embodiment according to a third aspect of the present invention, the concrete in PHC concrete prefabricated pipe 5 are added with acid and alkali-resistance
The additive of corrosion.Thus, it is possible to avoid PHC concrete prefabricated pipe 5 be deposited beach face coating 1 acid and alkali substance corruption
Erosion, improves the service life of PHC concrete prefabricated pipe 5.
One embodiment according to a third aspect of the present invention further includes catch basin and water cell (catch basin and water storage list
Member is not shown), catch basin is located at below photovoltaic module and sets, for receiving the rainwater flowed down from photovoltaic module or clean water,
Catch basin is connected to water cell, so that the water in catch basin flows into water cell.Collected by being arranged in the lower section of photovoltaic module
Sink can collect the rainwater flowed down from photovoltaic module or clean water, and be flowed to water cell, to be planted in deposition
The plant of beach covering layer region is watered in due course, and watering mode can be realized using sprinkling irrigation or drip irrigation.Hereby it is achieved that water-saving
It irrigates.
As shown in figure 8, the ecological restoring method of embodiment according to a fourth aspect of the present invention, applies and appoints in above-mentioned first aspect
The Tailings Dam of one embodiment closes in library system 100 (as shown in Figure 1 to Figure 3), includes the following steps:
S11: organic matter, humic acid, metallic stabilizer, soil planting matrix improvement: are added in deposition beach face coating 1
One or more of modifying agent, water-retaining agent, or the earth material layer for being used for planting plants is directly laid on deposition beach face coating 1
4;Improvement planting matrix is tested, it is ensured that the pH value and nutrient content of matrix reach the standard of planting technique soil;
S12: species breeding: according to the physicochemical characteristics of mine barren rock, selecting the plant cultivation of resistance to heavy metal to plant, or/and
Select impoverishment tolerant plant;
S13: vegetation plantation: planning as a whole arrangement planting area at the planting matrix of improvement, plants selected object in planting area
Kind plant.
Specifically, in the planting matrix improvement of step S11, a kind of mode be to deposition beach face coating 1 relatively on
One of organic matter, humic acid, metallic stabilizer, soil conditioner, water-retaining agent or a variety of, example are added in the tailings at position
Such as, a kind of soil conditioner is added, or improve planting matrix simultaneously added with machine matter, humic acid, metallic stabilizer and water-retaining agent
The quality of matter, then improvement planting matrix is tested, it is ensured that the pH value and nutrient content of planting matrix reach planting technique soil
The standard of earth, to be suitable for plant growth;Another middle mode is directly directly to be laid with one layer on deposition beach face coating 1 to be used for
The dope layer of planting plants, then improvement planting matrix is tested, it is ensured that the pH value and nutrient content of planting matrix reach green
Change the standard of planting soil, to be suitable for plant growth.
In terms of the species breeding of step S12, since deposition beach face coating 1 is spread using the discarded tailings of Tailings Dam
If forming, content of beary metal is higher in tailings, and nutritional ingredient needed for plant is barren in tailings, and therefore, it is necessary to select a resistance to huge sum of money
Platymiscium or impoverishment tolerant planting.
It in terms of the vegetation plantation of step S13, rationally chooses seeds, plans as a whole arrangement plantation at the planting matrix of improvement.For
Cultivation is broadcasted sowing using surface or gone to herbaceous plant.It when surface is broadcasted sowing, first scatters seeds, then in surface earthing;When row is planted, first dig
Furrow is sowed in furrow, then in earthing.For perennial shrub plant, planted using cave.
The ecological restoring method of embodiment according to a fourth aspect of the present invention closes library system 100 to Tailings Dam and carries out ecology and repairs
It is multiple, be conducive to the improvement and recovery of closing the ecological environment of library system.
An implementation according to a fourth aspect of the present invention, the Plant choosing of resistance to heavy metal ciliate desert-grass, alfalfa, Phytolacca acinosa, perfume (or spice)
At least one of root grass, penny cress, three-coloured amaranth and shrub plant;Impoverishment tolerant Plant choosing sainfoin, fescue grass, Bermuda grass, rye
At least one of grass, paspalum notatum, shrub lespedeza, rose, leapfrog, rose, sea-buckthorn and shrub plant.As a result, by rationally choosing seeds,
The plant grew well for ensuring to close the plantation of library system, is conducive to the improvement and recovery of closing the ecological environment of library system.
One embodiment according to a fourth aspect of the present invention, in the step of testing improvement mechanism, first test kind
PH, organic matter, hydrolyzable nitrogen, available phosphorus and the quick-acting potassium content of phytyl matter, re-test calcium oxide, organic fertilizer, bentonite, zeolite and
Compound fertilizer.Thus, it is ensured that the pH value and nutrient content of planting matrix reach the standard of planting technique soil, it is raw to be suitable for plant
It is long.
As shown in figure 8, the ecological restoring method of embodiment according to a fifth aspect of the present invention, applies and appoints in the above-mentioned third aspect
In the photovoltaic generating system 200 (as shown in Figure 6 and Figure 7) of one embodiment, include the following steps:
S21: organic matter, humic acid, metallic stabilizer, soil planting matrix improvement: are added in deposition beach face coating 1
One or more of modifying agent, water-retaining agent, or the earth material layer for being used for planting plants is directly laid on deposition beach face coating 1
4;Improvement matrix is tested, it is ensured that the pH value and nutrient content of matrix reach the standard of planting technique soil;
S22: species breeding: according to the physicochemical characteristics of mine barren rock, selecting the plant cultivation of resistance to heavy metal to plant, or/and
Select impoverishment tolerant plant;
S23: vegetation plantation: planning as a whole arrangement planting area at the planting matrix of improvement, plants selected object in planting area
Kind plant.
Specifically, in the planting matrix improvement of step S21, a kind of mode be to deposition beach face coating 1 relatively on
One of organic matter, humic acid, metallic stabilizer, soil conditioner, water-retaining agent or a variety of, example are added in the tailings at position
Such as, a kind of soil conditioner is added, or improve planting matrix simultaneously added with machine matter, humic acid, metallic stabilizer and water-retaining agent
The quality of matter, then improvement planting matrix is tested, it is ensured that the pH value and nutrient content of planting matrix reach planting technique soil
The standard of earth, to be suitable for plant growth;Another middle mode is directly directly to be laid with one layer on deposition beach face coating 1 to be used for
The dope layer of planting plants, then improvement planting matrix is tested, it is ensured that the pH value and nutrient content of planting matrix reach green
Change the standard of planting soil, to be suitable for plant growth.
In terms of the species breeding of step S22, since deposition beach face coating 1 is spread using the discarded tailings of Tailings Dam
If forming, content of beary metal is higher in tailings, and nutritional ingredient needed for plant is barren in tailings, and therefore, it is necessary to select a resistance to huge sum of money
Platymiscium or impoverishment tolerant planting.
It in terms of the vegetation plantation of step S23, rationally chooses seeds, plans as a whole arrangement plantation at the planting matrix of improvement.For
Cultivation is broadcasted sowing using surface or gone to herbaceous plant.It when surface is broadcasted sowing, first scatters seeds, then in surface earthing;When row is planted, first dig
Furrow is sowed in furrow, then in earthing.For perennial shrub plant, planted using cave.
The ecological restoring method of embodiment according to a fifth aspect of the present invention incorporates light while Tailings Dam closes library and administers
Volt power generation, and ecological restoration and management is carried out, realize that seamless connection and comprehensive benefit are maximum.Specifically have the advantage that first,
The reparation for not cutting into a mountain, being not take up arable land, economizing on resources and waste land is made to be achieved ecological environment.The second, photovoltaic plant is tight
Grid-connected power supply nearby is realized in adjacent mining area, and electricity, which is marketed one's own products, has consumption advantage, reduces bargh's electric cost.Third, light
The construction of overhead utility completely according to the original geography of Tailings Dam, and with close library design and the synchronous progress of construction, do not change not only
Become and destroy any facility of Tailings Dam, also the regulation of increase tailings warehouse dam body 2, deposition beach face improvement, 3 facility of gutter etc., it is real
The comprehensive utilization that safety closes library, photovoltaic power generation and restoration of the ecosystem is showed.4th, the comprehensive benefit on the idle discarded ground in mine is realized
With facilitating the comprehensive environmental improvement of Mine land.
One embodiment according to a fifth aspect of the present invention, the Plant choosing of resistance to heavy metal ciliate desert-grass, alfalfa, Phytolacca acinosa,
At least one of vetiver, penny cress, three-coloured amaranth and shrub plant;It is impoverishment tolerant Plant choosing sainfoin, fescue grass, Bermuda grass, black
At least one of wheat straw, paspalum notatum, shrub lespedeza, rose, leapfrog, rose, sea-buckthorn and shrub plant.As a result, by rationally selecting
Kind, it is ensured that the plant grew well for closing the plantation of library system is conducive to the improvement and recovery of closing the ecological environment of library system.
One embodiment according to a fifth aspect of the present invention, in the step of testing improvement mechanism, first test kind
PH, organic matter, hydrolyzable nitrogen, available phosphorus and the quick-acting potassium content of phytyl matter, re-test calcium oxide, organic fertilizer, bentonite, zeolite and
Compound fertilizer.Thus, it is ensured that the pH value and nutrient content of planting matrix reach the standard of planting technique soil, it is raw to be suitable for plant
It is long.
In the description of this specification, reference term " one embodiment ", " some embodiments ", " illustrative examples ",
The description of " example ", " specific example " or " some examples " etc. means specific features described in conjunction with this embodiment or example, knot
Structure, material or feature are included at least one embodiment or example of the invention.In the present specification, to above-mentioned term
Schematic representation may not refer to the same embodiment or example.Moreover, specific features, structure, material or the spy of description
Point can be combined in any suitable manner in any one or more of the embodiments or examples.
Although an embodiment of the present invention has been shown and described, it will be understood by those skilled in the art that: not
A variety of change, modification, replacement and modification can be carried out to these embodiments in the case where being detached from the principle of the present invention and objective, this
The range of invention is defined by the claims and their equivalents.
Claims (27)
1. a kind of Tailings Dam closes library system characterized by comprising
Beach face coating is deposited, the deposition beach face coating is that the tailings formed on the deposition beach face is laid on using tailings
Layer;
Dam body, the dam body are disposed around the outside of the deposition beach face coating;The dam body includes outer slope protection layer, described
Outer slope protection layer is not produce the slope protection layer that sour barren rock is built into using coarse grain diameter;
Gutter, the gutter include library week gutter and library internal drainage ditch;The library week, gutter was looped around the dam body
Outside and adjacent with the dam body;The library internal drainage ditch is located at the table of deposition the beach face coating and the dam body
On face, and intersect with library week gutter and be connected to, is discharged by being located at the convergence gutter on the outside of library week gutter.
2. Tailings Dam according to claim 1 closes library system, which is characterized in that the coarse grain diameter of the outer slope protection layer
The partial size for not producing sour barren rock is greater than 200mm.
3. Tailings Dam according to claim 1 closes library system, which is characterized in that the outer slope protection layer with a thickness of 0.4
~0.6m.
4. Tailings Dam according to claim 1 closes library system, which is characterized in that the gutter is not produced using fine grain
Sour mine barren rock is mixed with cement mortar build made of gutter.
5. Tailings Dam according to claim 4 closes library system, which is characterized in that the fine grain does not produce the grain of sour mine barren rock
Diameter is 5mm~60mm.
6. a kind of Tailings Dam closes library method, which comprises the steps of:
The processing of mine barren rock;According to the physicochemical characteristics of mine barren rock, selection does not produce sour mine barren rock and carries out break process, obtains coarse grain
Diameter does not produce that sour barren rock, fine grain do not produce sour barren rock, middle fine grain does not produce sour barren rock, closes library material as Tailings Dam and uses;
Deposit beach face processing: it is smooth to deposition beach face progress, then it is laid with tailings in deposition beach face, form deposition beach face coating;
It builds dam body: dam body being built using native stone in the outside of deposition beach face, slope does not produce sour mine using coarse grain diameter outside dam body
Barren rock is built into slope protection layer;
It builds gutter: building library week gutter in dam body outside and with dam body adjacent;On deposition beach face coating and dam
Do not produce sour barren rock using fine grain on the surface of body and mixed with cement mortar and build into library internal drainage ditch, the library internal drainage ditch and
Library week gutter intersects connection, the convergence gutter discharge on the outside of library week gutter.
7. Tailings Dam according to claim 6 closes library method, which is characterized in that further comprise the steps of:
The arrangement of PHC concrete prefabricated pipe: multiple PHC concrete are arranged vertically in deposition beach face covering layer region
Prefabricated pipe is used for installation photovoltaic component bracket.
8. Tailings Dam according to claim 7 closes library method, which is characterized in that further comprise the steps of:
Overhaul constructing road: according to the deployment scenarios of PHC concrete prefabricated pipe, used on the deposition beach face coating in carefully
Partial size does not produce sour barren rock and builds maintenance road.
9. Tailings Dam according to claim 6 closes library method, which is characterized in that the coarse grain diameter does not produce the partial size of sour barren rock
For greater than 200mm, the partial size that the fine grain does not produce sour barren rock is 5mm~60mm, and the middle fine grain does not produce the grain of sour barren rock
Diameter is 30mm~100mm.
10. tailing according to claim 6 closes library method, which is characterized in that further comprise the steps of:
Earth material layer is laid with: the earth material layer for being used for planting plants is laid on the deposition beach face coating.
11. a kind of photovoltaic generating system, which is characterized in that the Tailings Dam described in any one of claim 1-5 is applied to close
In the system of library, comprising:
Multiple PHC concrete prefabricated pipes, multiple PHC concrete prefabricated pipes are linearly spaced apart vertical array, multiple described
PHC concrete prefabricated pipe includes connected lower section prefabricated pipe and upper section prefabricated pipe, and the lower section prefabricated pipe is buried solid described heavy
In product beach face coating, the upper section prefabricated pipe extends vertically upward;
Photovoltaic module support, the upper section that the photovoltaic module support is fixed on multiple PHC concrete prefabricated pipes are prefabricated
Guan Shang;
Photovoltaic module, the photovoltaic module are mounted on the photovoltaic module support.
12. photovoltaic generating system according to claim 11, which is characterized in that the photovoltaic module support is tilt adjustable
Formula fixes bracket.
13. photovoltaic generating system according to claim 11, which is characterized in that the photovoltaic module support include frame,
Multiple columns corresponding with the PHC concrete prefabricated pipe, the upper end of multiple columns is connect with the frame, multiple
The lower end of the column is fixed with the upper end of corresponding multiple upper section prefabricated pipes.
14. photovoltaic generating system according to claim 13, which is characterized in that the photovoltaic module support further includes very heavy
Head piece and jack, the very heavy head piece are secured transverse in two PHC concrete prefabricated pipes, and the jack is oblique
To setting, the lower end of the jack is connected on the very heavy head piece, and the upper end of the jack is hinged on the frame
On, the upper end of multiple columns with the frame articulation, makes the frame with the length by the adjusting jack
Tilt adjustable.
15. photovoltaic generating system according to claim 11, which is characterized in that it further include inverter and substation, it is described
Substation is equipped with transformer, and the inverter is connected electrically between the photovoltaic module and the transformer.
16. photovoltaic generating system according to claim 15, which is characterized in that the inverter is connected electrically in the photovoltaic
Between component and the transformer specifically: multiple photovoltaic module series connection accumulate a component string, component described in multiple groups
String collects into a header box, and multiple header boxs collect into the inverter, and the inverter is by the direct current of input
Stream is reverse into three-phase alternating current, and is converted into high-voltage electricity by the change device and is sent into electric system.
17. photovoltaic generating system according to claim 15, which is characterized in that the inverter and substation setting
On the basis of frame concrete at the periphery of the dam body.
18. photovoltaic generating system according to claim 11, which is characterized in that be additionally provided on the deposition beach face coating
Fine grain does not produce the maintenance road that sour barren rock is built in.
19. photovoltaic generating system according to claim 18, which is characterized in that the middle particulate does not produce the grain of sour mine barren rock
Diameter is 30mm~100mm.
20. photovoltaic generating system according to claim 11, which is characterized in that mixed in the PHC concrete prefabricated pipe
Solidifying soil is added with the additive of acid-alkali-corrosive-resisting.
21. photovoltaic generating system described in Arbitrary Term in 1 according to claim 1, which is characterized in that further include catch basin and water storage
Unit, the catch basin is located at below the photovoltaic module and sets, for receiving the rainwater flowed down from photovoltaic module and cleaning
Water, the catch basin are connected to water cell, so that the water in the catch basin flows into water cell.
22. a kind of ecological restoring method, which is characterized in that the Tailings Dam described in any one of claim 1-5 is applied to close
In the system of library, include the following steps:
Planting matrix improvement: organic matter, humic acid, metallic stabilizer, soil conditioner, guarantor are added in deposition beach face coating
One or more of aqua, or the earth material layer for being used for planting plants is directly laid on deposition beach face coating;To improvement base
Matter is tested, it is ensured that the pH value and nutrient content of matrix reach the standard of planting technique soil;
Species breeding: according to the physicochemical characteristics of mine barren rock, the plant cultivation of resistance to heavy metal is selected to plant, or/and selected resistance to poor
Lean plant;
Vegetation plantation: planning as a whole arrangement planting area at the planting matrix of improvement, plants selected species in planting area.
23. ecological restoring method according to claim 22, which is characterized in that the Plant choosing of the resistance to heavy metal centipede
At least one of grass, alfalfa, Phytolacca acinosa, vetiver, penny cress, three-coloured amaranth and shrub plant;The impoverishment tolerant Plant choosing
In sainfoin, fescue grass, Bermuda grass, rye grass, paspalum notatum, shrub lespedeza, rose, leapfrog, rose, sea-buckthorn and shrub plant at least
It is a kind of.
24. ecological restoring method according to claim 22, which is characterized in that in the step of testing improvement mechanism
In, first test PH, organic matter, hydrolyzable nitrogen, available phosphorus and the quick-acting potassium content of planting matrix, it is re-test calcium oxide, organic fertilizer, swollen
Profit soil, zeolite and compound fertilizer.
25. a kind of ecological restoring method, which is characterized in that apply the photovoltaic power generation described in Arbitrary Term in claim 11-21
In system, include the following steps:
Planting matrix improvement: organic matter, humic acid, metallic stabilizer, soil conditioner, guarantor are added in deposition beach face coating
One or more of aqua, or the earth material layer for being used for planting plants is directly laid on deposition beach face coating;To improvement base
Matter is tested, it is ensured that the pH value and nutrient content of matrix reach the standard of planting technique soil;
Species breeding: according to the physicochemical characteristics of mine barren rock, the plant cultivation of resistance to heavy metal is selected to plant, or/and selected resistance to poor
Lean plant;
Vegetation plantation: planning as a whole arrangement planting area at the planting matrix of improvement, plants selected species in planting area.
26. ecological restoring method according to claim 25, which is characterized in that the Plant choosing of the resistance to heavy metal centipede
At least one of grass, alfalfa, Phytolacca acinosa, vetiver, penny cress, three-coloured amaranth and shrub plant;The impoverishment tolerant Plant choosing
In sainfoin, fescue grass, Bermuda grass, rye grass, paspalum notatum, shrub lespedeza, rose, leapfrog, rose, sea-buckthorn and shrub plant at least
It is a kind of.
27. ecological restoring method according to claim 25, which is characterized in that in the step of testing improvement mechanism
In, first test PH, organic matter, hydrolyzable nitrogen, available phosphorus and the quick-acting potassium content of planting matrix, it is re-test calcium oxide, organic fertilizer, swollen
Profit soil, zeolite and compound fertilizer.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811589860.8A CN109537709B (en) | 2018-12-25 | 2018-12-25 | Tailing pond closing system and method, photovoltaic power generation system and ecological restoration method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811589860.8A CN109537709B (en) | 2018-12-25 | 2018-12-25 | Tailing pond closing system and method, photovoltaic power generation system and ecological restoration method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109537709A true CN109537709A (en) | 2019-03-29 |
CN109537709B CN109537709B (en) | 2024-06-14 |
Family
ID=65858037
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811589860.8A Active CN109537709B (en) | 2018-12-25 | 2018-12-25 | Tailing pond closing system and method, photovoltaic power generation system and ecological restoration method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109537709B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110280575A (en) * | 2019-06-20 | 2019-09-27 | 江苏萤火虫环境科技有限公司 | The screening technique of heavy metal pollution arable land surrogate outcomes plant under photovoltaic power generation facility |
Citations (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101992209A (en) * | 2009-08-28 | 2011-03-30 | 中国科学院地理科学与资源研究所 | Bioremediation method for arsenic-containing tailings or waste residue |
CN102041845A (en) * | 2010-11-18 | 2011-05-04 | 中钢集团马鞍山矿山研究院有限公司 | United draining system for effectively lowering seepage lines in fill dam of tailing reservoir |
CN102671908A (en) * | 2011-03-11 | 2012-09-19 | 河北农业大学 | Improvement method for biological environment of tailing pond |
CN104092431A (en) * | 2014-07-02 | 2014-10-08 | 苏州威恩斯光电科技有限公司 | Fixed photovoltaic support with adjustable elevation angle |
CN104711953A (en) * | 2015-02-10 | 2015-06-17 | 太原钢铁(集团)有限公司 | Tailing dam built through barren rock |
CN104831678A (en) * | 2015-01-30 | 2015-08-12 | 王健 | Ecological restoration method for tailing depot reclamation after tailing depot closure |
CN104987260A (en) * | 2015-06-11 | 2015-10-21 | 北京矿冶研究总院 | Ecological restoration matrix for lead-zinc tailing pond and preparation method and application thereof |
CN204928674U (en) * | 2015-08-06 | 2015-12-30 | 华电电力科学研究院 | Build solar photovoltaic power station on tailing storehouse |
CN205352381U (en) * | 2016-01-26 | 2016-06-29 | 河南工程学院 | Beach length real -time supervision platform is done in movable tailing storehouse |
CN108380382A (en) * | 2018-02-05 | 2018-08-10 | 珲春紫金矿业有限公司 | A kind of dry heap of fine tailings is built a dam the heap discharge method being combined with wet row |
CN207727532U (en) * | 2018-01-14 | 2018-08-14 | 袁朝 | A kind of flat type Tailings Dam closes the structure of drainning off floodwaters in library |
CN108668553A (en) * | 2018-04-17 | 2018-10-19 | 桂林理工大学 | A kind of reclamation method suitable for Karst area heavy metal tailings library |
CN208201941U (en) * | 2018-05-04 | 2018-12-07 | 魏德宁 | A kind of tailings warehouse dam body piping improvement slope protection |
CN209523280U (en) * | 2018-12-25 | 2019-10-22 | 中国恩菲工程技术有限公司 | Tailings Dam closes library system and photovoltaic generating system |
-
2018
- 2018-12-25 CN CN201811589860.8A patent/CN109537709B/en active Active
Patent Citations (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101992209A (en) * | 2009-08-28 | 2011-03-30 | 中国科学院地理科学与资源研究所 | Bioremediation method for arsenic-containing tailings or waste residue |
CN102041845A (en) * | 2010-11-18 | 2011-05-04 | 中钢集团马鞍山矿山研究院有限公司 | United draining system for effectively lowering seepage lines in fill dam of tailing reservoir |
CN102671908A (en) * | 2011-03-11 | 2012-09-19 | 河北农业大学 | Improvement method for biological environment of tailing pond |
CN104092431A (en) * | 2014-07-02 | 2014-10-08 | 苏州威恩斯光电科技有限公司 | Fixed photovoltaic support with adjustable elevation angle |
CN104831678A (en) * | 2015-01-30 | 2015-08-12 | 王健 | Ecological restoration method for tailing depot reclamation after tailing depot closure |
CN104711953A (en) * | 2015-02-10 | 2015-06-17 | 太原钢铁(集团)有限公司 | Tailing dam built through barren rock |
CN104987260A (en) * | 2015-06-11 | 2015-10-21 | 北京矿冶研究总院 | Ecological restoration matrix for lead-zinc tailing pond and preparation method and application thereof |
CN204928674U (en) * | 2015-08-06 | 2015-12-30 | 华电电力科学研究院 | Build solar photovoltaic power station on tailing storehouse |
CN205352381U (en) * | 2016-01-26 | 2016-06-29 | 河南工程学院 | Beach length real -time supervision platform is done in movable tailing storehouse |
CN207727532U (en) * | 2018-01-14 | 2018-08-14 | 袁朝 | A kind of flat type Tailings Dam closes the structure of drainning off floodwaters in library |
CN108380382A (en) * | 2018-02-05 | 2018-08-10 | 珲春紫金矿业有限公司 | A kind of dry heap of fine tailings is built a dam the heap discharge method being combined with wet row |
CN108668553A (en) * | 2018-04-17 | 2018-10-19 | 桂林理工大学 | A kind of reclamation method suitable for Karst area heavy metal tailings library |
CN208201941U (en) * | 2018-05-04 | 2018-12-07 | 魏德宁 | A kind of tailings warehouse dam body piping improvement slope protection |
CN209523280U (en) * | 2018-12-25 | 2019-10-22 | 中国恩菲工程技术有限公司 | Tailings Dam closes library system and photovoltaic generating system |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110280575A (en) * | 2019-06-20 | 2019-09-27 | 江苏萤火虫环境科技有限公司 | The screening technique of heavy metal pollution arable land surrogate outcomes plant under photovoltaic power generation facility |
Also Published As
Publication number | Publication date |
---|---|
CN109537709B (en) | 2024-06-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Kangas et al. | Nutrient removal from agricultural drainage water using algal turf scrubbers and solar power | |
CN106358694A (en) | Method for quickly greening stony deserted mountain | |
CN206713664U (en) | Mountain area field water fertilizer drip irrigation system based on solar photovoltaic generating | |
CN107494206A (en) | A kind of intelligent drip-irrigation device and drip irrigation method | |
CN105724226A (en) | Water-saving building elevation greening structure and construction method | |
CN106359019A (en) | Cloud computing based intelligent garden management equipment | |
CN106358477A (en) | Sand discharging and sand controlling system of secondary saline and alkaline land of Hetao irrigation area | |
CN113875344A (en) | Ecological restoration method for coal mine mountain geological environment | |
CN101690460B (en) | Turf substrate produced by construction waste and sludge | |
CN104541641A (en) | Method of thinning, eliminating soil salt and increasing yield by arranging crushed ridge bind drain system | |
CN209523280U (en) | Tailings Dam closes library system and photovoltaic generating system | |
CN107896548A (en) | A kind of method and irrigation system suitable for Karst stony mountain areas steep cliff section ecological management | |
CN109537709A (en) | Tailings Dam closes library system and method, photovoltaic generating system, ecological restoring method | |
CN104663225A (en) | Planting, cultivating and culturing system utilizing territorial air space farmland-building land | |
CN103374904B (en) | Farmland discharging-irrigating patten transformation saves land water-saving method | |
CN204498997U (en) | Solar energy remote control system for irrigation | |
CN205712016U (en) | A kind of ecological trench system of water level real-time monitoring | |
CN206395937U (en) | Intelligent remote monitoring solar direct current is aerated artificial wet land system | |
CN210470287U (en) | Efficient watering, fertilizing and conservation system for mine restoration | |
CN101300943A (en) | Method for treating land desertification | |
CN204510932U (en) | A kind of farmland planting system of five in one | |
CN104737662B (en) | A kind of efficient reclamation method of house site | |
CN104563137B (en) | A kind of heavy grade rock side-slope nursing structure based on rainwater-collecting bag | |
CN209073131U (en) | A kind of automation can adjust the irrigation rig of water spraying time according to temperature | |
CN207022779U (en) | A kind of photovoltaic generation hybrid system integrated with water saving irrigation facility |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant |