CN109494616A - A method of electrification connects 35kv zero load lead - Google Patents

A method of electrification connects 35kv zero load lead Download PDF

Info

Publication number
CN109494616A
CN109494616A CN201811527444.5A CN201811527444A CN109494616A CN 109494616 A CN109494616 A CN 109494616A CN 201811527444 A CN201811527444 A CN 201811527444A CN 109494616 A CN109494616 A CN 109494616A
Authority
CN
China
Prior art keywords
tower
electrician
lead
insulation
length
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811527444.5A
Other languages
Chinese (zh)
Inventor
郝京卫
李明
李红新
李启江
李相辉
许崇新
韩培庆
张洪奎
赵阅群
刘波磊
林令臣
闫同
王国栋
周明亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Yantai Power Supply Co of State Grid Shandong Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Yantai Power Supply Co of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Yantai Power Supply Co of State Grid Shandong Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201811527444.5A priority Critical patent/CN109494616A/en
Publication of CN109494616A publication Critical patent/CN109494616A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/02Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables

Abstract

The present invention relates to a kind of 35kV voltage class routes to charge the method for connecing unloaded lead, belongs to transmission of electricity electrification technical field of operation.The following steps are included: 1, scene is surveyed again;2, work permit and kick-off meeting;3, Work tool, material inspection;4, rod-rising tower and extension coaster;5, installing ground line;6, using insulating cord measure in coupling line length;7, coupling line length and installing is started to exchange fire wire clamp in adjustment;8, it adjusts side coupling line length and installs wire clamp of starting to exchange fire;9, it is mutually grounded and charges in removing and connect middle phase zero load lead;10, dismounting both sides, which are mutually grounded and charge, connects both sides mutually unloaded lead;11, tool for transmitting and lower tower.The present invention is safe and reliable, easy to operate, versatile.

Description

A method of electrification connects 35kv zero load lead
Technical field
The present invention relates to a kind of 35kV voltage class routes to charge the method for connecing unloaded lead, belongs to transmission of electricity livewire work skill Art field.
Background technique
Currently, electric transmission line hot-line connects unloaded lead, frequently with the method that extinguishing arc rope connects unloaded lead, since this method needs Biggish electric clearance distance is wanted, using more in 110kV and Above Transmission Lines.
20kV and distribution circuit electric voltage grade below are lower, and electrification connects unloaded lead frequently with insulating glove working system. The operational method needs operating personnel to wear the insulating protection apparatus of relevant voltage grade, in insulation carrying platform (such as insulation bucket arm Vehicle) on perfect insulation masking is carried out to electrical body and grounding body after, then carry out connecing unloaded lead operation.Insulation clothing etc. is exhausted at present Edge safety device is generally used for 20kV and following voltage class route.
35kV voltage class transmission line of electricity often undertakes important role in counties and districts power.With economic development, The case where T link, is more and more in 35kV voltage class.The voltage class route has the higher voltage of transmission line of electricity simultaneously The features such as grade and distribution line Insulation Coordination are low, electric clearance is small, personnel activity's range is smaller, conventional transmission of electricity electrification, which connects, draws The method that method (such as extinguishing arc rope method) and the distribution electrification of line connect lead (such as insulating glove working system) is difficult to meet the voltage Grade connects the needs of unloaded lead, and the method coverage that power failure connects lead is larger, the theory with power grid enterprises' " good service " It is not inconsistent.The research that the whole nation connects unloaded lead to the electrification of 35kV voltage class at present is in space state.
It would therefore be highly desirable to a kind of method that the electrification that can solve above-mentioned technical problem connects 35kv zero load lead occur.
Summary of the invention
It is an object of the invention to solve the shortcomings of the prior art, a kind of safe and reliable, operation letter is provided It is single, the method that versatile electrification connects 35kv zero load lead.
A method of electrification connects 35kv zero load lead, it is characterised in that the following steps are included:
1, scene is surveyed again:
Whether the live temperature and humidity of detection, wind speed meet livewire work condition, check the dual title of route, and whether verification route is in Light condition;
2, work permit and kick-off meeting:
Apply deactivating service line reclosing to traffic department, report job content, projected operating times read out work ticket, carry out Row Signature Confirmation formality;
3, Work tool, material inspection:
The insulating tool and insulating protection apparatus use scene carries out Insulation monitoring;
4, rod-rising tower and extension coaster:
Electrician third carries at insulation transmission rope rod-rising tower to cross-arm on tower, fastens seat belts and backup protection rope, consolidates at cross-arm Set insulation coaster, on tower electrician's first, second wear a full set of insulation clothing, wear insulated shoes, wear insulating glove successively rod-rising tower to appropriate position It sets, accomplishes fluently safety belt and personal backup protection rope;
5, installing ground line:
Three piece-root grafting ground wires are passed to electrician third on tower by insulating cord by ground electrician, on tower electrician third in lead trackside waiting, Three-phase ground line (per single ground line is accordingly used, being forbidden to use the complete ground line of three-phase shortcircuit) is installed, it should be by when installing Proximal and distal, first attaching ground terminal is followed by conductor end;
6, using insulating cord measure in coupling line length:
By insulating bar, (number of patent application: 201711392790.2), insulated lock lever and insulation measurement rope pass through ground electrician Insulation transmission rope passes to electrician's first on tower, and electrician's first send insulation measurement rope one end to main line meter with insulating bar on tower The place that starts to exchange fire is drawn, the other end is hung over the middle phase strain clamp end waiting for drawing nonloaded line of ground connection with insulated lock lever by electrician's second on tower Portion adjusts insulating cord length, until the equidistant requirement for meeting related regulation of the arc sag of insulation measurement rope, and in insulation measurement rope On make a mark;
7, adjustment in coupling line length and install start to exchange fire wire clamp (patent No.: ZL201320117750.8):
Electrician's first removes insulation measurement rope on tower, and according to step 6 mark lengths, on tower, electrician's first, second, which is worked in coordination, adjusts sky Side wire length is carried, if wire length is more than surveyed length, conducting wire is cut off at suitable length with insulation cutter, if lead is long Degree is less than surveyed length and takes suitable length conducting wire then according to length difference, is attached with general wire clamp is pacified, after the completion, in lead end Portion installs the wire clamp for starting to exchange fire, and should be noted that in operating process and keeps enough safe distances with electrical body, will after the completion of operation Lead is fixed on shaft tower appropriate location;
8, it adjusts both sides coupling line length and installs wire clamp of starting to exchange fire:
According to the method for step 6-7, adjusts both sides coupling line length and install wire clamp of starting to exchange fire, after the completion of operation, lead is fixed In shaft tower appropriate location;
9, it is mutually grounded and charges in removing and connect middle phase zero load lead:
Matched insulating bar end is inserted into middle phase zero load lead wire clamp end of starting to exchange fire by electrician's first on tower, and electrician's second makes on tower The cooperation of electrician's first is lockked on lead, with tower by lead to outer support to appropriate location, unloaded lead and electrical body with insulated lock lever 0.6 meter or more of safe distance is kept, is mutually grounded in the dismounting of electrician third on tower, electrician's first, second is worked in coordination on tower, by middle phase On unloaded gage lap to main line;
10, dismounting both sides, which are mutually grounded and charge, connects both sides mutually unloaded lead:
According to the method for step 9, electrification connects both sides mutually unloaded lead;
11, Work tool and lower tower are transmitted:
Work tool used is transferred under tower by insulating cord and checks that object, lower tower are stayed in shaft tower nothing left by electrician on tower.
Preferably, the step 3 further includes checking whether material used (conducting wire, the general wire clamp of peace, wire clamp of starting to exchange fire etc.) closes It is lattice, complete, impact test is carried out to safety belt, if operation shaft tower is cement pole, it is also necessary to carry out to bar tool (climbers etc.) are stepped on Impact test;
Preferably, there are also step 12, steps 12 after the step 11 are as follows: knock off meeting and scene arrangement, the responsible person that works carry out Work comment, and report and be completed to traffic department, cleaning work scene.
The method that invention electrification connects 35kv zero load lead, is the optimal operational method summed up by field operation, has High safety, it is easy to operate, it is versatile the advantages that, application value with higher.
Specific embodiment
The technical scheme in the embodiments of the invention will be clearly and completely described below, it is clear that described implementation Example is only a part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, this field is common Technical staff's every other embodiment obtained without making creative work belongs to the model that the present invention protects It encloses.
Embodiment 1
The method that electrification of the invention connects 35kv zero load lead, comprising the following steps:
1, scene is surveyed again: operating personnel detects live temperature and humidity, whether wind speed meets livewire work condition, and wind-force is greater than 5 grades (10m/s) must not carry out livewire work, and relative humidity is more than 80%, must not carry out livewire work, and work responsible person checks route Dual title, checks the lead other side waiting transformer, voltage transformer has dropped out operation, and breaker (switch) is kept apart It closes (disconnecting link) to have disconnected, route is no ground;
2, work permit and kick-off meeting: work responsible person applies deactivating service line reclosing, report operation to traffic department
Content, projected operating times etc..Work responsible person reads out work ticket, hands over dangerous point and safety notice, operation people Member fulfils Signature Confirmation formality;
3, Work tool, material inspection: operating personnel locks the insulation that scene uses using the insulation resistance meter of 2500V or more
The insulating protections apparatus such as the insulating tools such as bar and insulation clothing carries out Insulation monitoring, and resistance value must not be lower than 700M Ω, check institute Whether material (conducting wire, the general wire clamp of peace, wire clamp of starting to exchange fire etc.) is qualified, complete, carries out visual examination to safety belt and impact tries It tests.If operation shaft tower is cement pole, it is also necessary to carry out impact test to bar tool (climbers etc.) are stepped on;
4, rod-rising tower and hang coaster: on tower electrician third carry insulation transmission rope rod-rising tower to cross-arm at, fasten seat belts and after
Standby protection rope, fixes insulation coaster, electrician's first, second wears a full set of insulation clothing, wears insulated shoes, wears insulation on tower at cross-arm Successively rod-rising tower accomplishes fluently safety belt and personal backup protection rope to appropriate location to gloves.Safety belt and backup protection rope should be distinguished It hangs on the secured component of shaft tower different parts, backup protection rope must not dock use;
5, installing ground line: three piece-root grafting ground wires are passed to electrician third on tower by insulating cord by ground electrician, electrician third on tower
In lead trackside waiting, three-phase ground line is installed.Ground line should use single ground line, be forbidden to use three-phase shortcircuit at Set ground line.The sectional area of ground line is inaccurate to be less than 25mm2.Should from the near to the distant when installing, first attaching ground terminal is followed by conductor end. Ground line should be installed securely, and connection is reliable.Human body must not touch ground line;
6, using insulating cord measure in coupling line length: ground electrician is by insulating bar, insulated lock lever and insulation measurement rope
By insulate transmission rope pass to electrician's first on tower, on tower electrician's first by insulation measurement rope one end with insulating bar send to Main line plan is started to exchange fire place, and the other end is hung over the waiting of ground connection with insulated lock lever and draws the middle mutually resistance to of nonloaded line by electrician's second on tower End is pressed from both sides in bracing cable, adjusts insulating cord length, until the equidistant requirement for meeting related regulation of the arc sag of insulation measurement rope, and exhausted It makes a mark on edge measurement rope;
7, coupling line length and installing is started to exchange fire wire clamp in adjustment: electrician's first removes insulation measurement rope on tower, according to step (6)
Institute's mark lengths, electrician's first, second, which is worked in coordination, on tower adjusts unloaded side wire length.If wire length is more than to survey length Degree then cuts off conducting wire with insulation cutter at suitable length.It is taken suitable if wire length is less than surveyed length according to length difference When length conducting wire, it is attached with general wire clamp is pacified.After the completion, the wire clamp for starting to exchange fire is installed in wire ends, pays attention to line of starting to exchange fire The setting angle of folder should be suitable.It should be noted that keeping enough safe distances with electrical body in operating process.After the completion of operation, it will draw Line is fixed on shaft tower appropriate location;
8, it adjusts both sides coupling line length and installs wire clamp of starting to exchange fire: according to step (6)-(7) method, adjusting both sides phase
Wire length simultaneously installs wire clamp of starting to exchange fire.After the completion of operation, lead is fixed on shaft tower appropriate location.
9, be mutually grounded and charge and connect middle phase zero load lead in removing: electrician's first starts to exchange fire middle phase zero load lead wire clamp on tower End
Portion is inserted into matched insulating bar end, and electrician's second is lockked electrician's first on lead, with tower using insulated lock lever and matched on tower It closes lead to outer support to appropriate location, unloaded lead keeps 0.6 meter or more of safe distance, electrician third on tower with electrical body It is mutually grounded in dismounting.Remove contact line should first tear conductor end open, after disconnect ground terminal.Electrician's first, second is worked in coordination on tower, by middle phase On unloaded gage lap to main line;
10, dismounting both sides, which are mutually grounded and charge, connects both sides mutually unloaded lead: according to the method for step (9), electrification is connect
The unloaded lead of both sides phase;
11, transmit Work tool and lower tower: Work tool used is transferred to inspection shaft tower nothing left under tower by insulating cord by electrician on tower
Stay object, lower tower;
12, knock off meeting and scene arrange.Work responsible person carries out work comment, and reports and be completed to traffic department.Cleaning work It is clear to accomplish that the complete material of work uses up place for scene.
It although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with A variety of variations, modification, replacement can be carried out to these embodiments without departing from the principles and spirit of the present invention by understanding And modification, the scope of the present invention is defined by the appended.

Claims (3)

1. a kind of charge the method for connecing 35kv zero load lead, it is characterised in that the following steps are included:
1), scene is surveyed again:
Whether the live temperature and humidity of detection, wind speed meet livewire work condition, check the dual title of route, and whether verification route is in Light condition;
2), work permit and kick-off meeting:
Apply deactivating service line reclosing to traffic department, report job content, projected operating times read out work ticket, carry out Row Signature Confirmation formality;
3), Work tool, material inspection:
The insulating tool and insulating protection apparatus use scene carries out Insulation monitoring;
4), rod-rising tower and extension coaster:
Electrician third carries at insulation transmission rope rod-rising tower to cross-arm on tower, fastens seat belts and backup protection rope, consolidates at cross-arm Set insulation coaster, on tower electrician's first, second wear a full set of insulation clothing, wear insulated shoes, wear insulating glove successively rod-rising tower to appropriate position It sets, accomplishes fluently safety belt and personal backup protection rope;
5), installing ground line:
Three piece-root grafting ground wires are passed to electrician third on tower by insulating cord by ground electrician, on tower electrician third in lead trackside waiting, Three-phase ground line is installed, when installing should from the near to the distant, and first attaching ground terminal is followed by conductor end;
6), using insulating cord measure in coupling line length:
Insulating bar, insulated lock lever and insulation measurement rope are passed to electrician's first on tower by the transmission rope that insulate by ground electrician, Insulation measurement rope one end is sent with insulating bar to main line plan and is started to exchange fire place by electrician's first on tower, electrician's second insulation lock on tower The other end is hung over the middle phase strain clamp end waiting for drawing nonloaded line of ground connection by bar, adjusts insulating cord length, until insulation The equidistant requirement for meeting related regulation of arc sag of rope is measured, and is made a mark on insulation measurement rope;
7), coupling line length and installing is started to exchange fire wire clamp in adjustment:
Electrician's first removes insulation measurement rope on tower, and according to step 6 mark lengths, on tower, electrician's first, second, which is worked in coordination, adjusts sky Side wire length is carried, if wire length is more than surveyed length, conducting wire is cut off at suitable length with insulation cutter, if lead is long Degree is less than surveyed length and takes suitable length conducting wire then according to length difference, is attached with general wire clamp is pacified, after the completion, in lead end Portion installs the wire clamp for starting to exchange fire, and should be noted that in operating process and keeps enough safe distances with electrical body, will after the completion of operation Lead is fixed on shaft tower appropriate location;
8) it, adjusts both sides coupling line length and installs wire clamp of starting to exchange fire:
According to step 6) -7) method, adjustment both sides coupling line length, which is simultaneously installed, starts to exchange fire wire clamp, and after the completion of operation, lead is consolidated Due to shaft tower appropriate location;
9) it is mutually grounded and charges in, removing and connect middle phase zero load lead:
Matched insulating bar end is inserted into middle phase zero load lead wire clamp end of starting to exchange fire by electrician's first on tower, and electrician's second makes on tower The cooperation of electrician's first is lockked on lead, with tower by lead to outer support to appropriate location, unloaded lead and electrical body with insulated lock lever 0.6 meter or more of safe distance is kept, is mutually grounded in the dismounting of electrician third on tower, electrician's first, second is worked in coordination on tower, by middle phase On unloaded gage lap to main line;
10), dismounting both sides, which are mutually grounded and charge, connects both sides mutually unloaded lead:
According to the method for step 9), electrification connects both sides mutually unloaded lead;
11) Work tool and lower tower, are transmitted:
Work tool used is transferred under tower by insulating cord and checks that object, lower tower are stayed in shaft tower nothing left by electrician on tower.
2. the method that a kind of electrification described in accordance with the claim 1 connects 35kv zero load lead, it is characterised in that the step 3) is also Including checking whether material used is qualified, complete, impact test is carried out to safety belt, if operation shaft tower is cement pole, is also needed Impact test is carried out to bar tool is stepped on.
3. it is described in accordance with the claim 1 it is a kind of charge connect 35kv zero load lead method, it is characterised in that the step 11) it Afterwards there are also step 12), step 12) are as follows: knock off meeting and scene arranges, the responsible person that works carries out work comment, and to traffic department It reports and is completed, cleaning work scene.
CN201811527444.5A 2018-12-13 2018-12-13 A method of electrification connects 35kv zero load lead Pending CN109494616A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811527444.5A CN109494616A (en) 2018-12-13 2018-12-13 A method of electrification connects 35kv zero load lead

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811527444.5A CN109494616A (en) 2018-12-13 2018-12-13 A method of electrification connects 35kv zero load lead

Publications (1)

Publication Number Publication Date
CN109494616A true CN109494616A (en) 2019-03-19

Family

ID=65710202

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811527444.5A Pending CN109494616A (en) 2018-12-13 2018-12-13 A method of electrification connects 35kv zero load lead

Country Status (1)

Country Link
CN (1) CN109494616A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001112131A (en) * 1999-10-04 2001-04-20 Hitachi Cable Ltd Steel tower rebuilding method for aerial transmission limes
CN101640390A (en) * 2009-07-15 2010-02-03 武汉科瑞德电力科技有限公司 Live-wire operation method for lapping drainage wire for 35kV distribution circuit
CN101719640A (en) * 2009-11-05 2010-06-02 齐齐哈尔电业局 Operation method of connecting charged lead with by-pass jumper for 10 kV wire multi-loop on same tower
CN103746315A (en) * 2013-12-30 2014-04-23 江苏省电力公司常州供电公司 Quick hot-line by-pass jumper overlapping operation method for 10kV insulated power distribution line
CN204905748U (en) * 2015-07-07 2015-12-23 国网山东平邑县供电公司 Multi -purpose fastener of starting to exchange fire of live working

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001112131A (en) * 1999-10-04 2001-04-20 Hitachi Cable Ltd Steel tower rebuilding method for aerial transmission limes
CN101640390A (en) * 2009-07-15 2010-02-03 武汉科瑞德电力科技有限公司 Live-wire operation method for lapping drainage wire for 35kV distribution circuit
CN101719640A (en) * 2009-11-05 2010-06-02 齐齐哈尔电业局 Operation method of connecting charged lead with by-pass jumper for 10 kV wire multi-loop on same tower
CN103746315A (en) * 2013-12-30 2014-04-23 江苏省电力公司常州供电公司 Quick hot-line by-pass jumper overlapping operation method for 10kV insulated power distribution line
CN204905748U (en) * 2015-07-07 2015-12-23 国网山东平邑县供电公司 Multi -purpose fastener of starting to exchange fire of live working

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
雷冬云: "《带电作业人员资质认证培训专用教材 配电线路》", 31 March 2012, 中国电力出版社 *

Similar Documents

Publication Publication Date Title
KR101268620B1 (en) System and method for detecting the high impedence ground fault using distribution automation system
CN109633384A (en) A kind of Intelligent insulating line thunder protection on-Line Monitor Device and method
CN207780156U (en) A kind of low-voltage circuit trouble shoot device
CN105676092B (en) Electric substation's power cable insulation level monitoring method and system
CN106356758B (en) 10KV line insulations bar bypasses charged for replacement on-pole switch operational method indirectly
CN101640392A (en) Live-wire operation method for cutting off drainage wire for 35kV distribution circuit
CN101640390A (en) Live-wire operation method for lapping drainage wire for 35kV distribution circuit
CN110120643A (en) A kind of ground potential distribution power circuit uninterrupted operation method
CN112540259A (en) Distribution network disconnection fault identification method and system suitable for intelligent power distribution terminal
CN107294071A (en) The guard method of power distribution network small resistance grounding system and device
CN105353275B (en) A kind of economical 66kV bands multipoint line Fault Locating Method and system
CN103278725A (en) Method for positioning grounding fault during melting of aerial earth wire
CN107329050B (en) Line fault detection method, detection device and detection system
CN109494616A (en) A method of electrification connects 35kv zero load lead
US4796147A (en) Method for detecting voltage losses in a low voltage distribution system
CN110174575B (en) Comprehensive test system and method for induced electricity of power through line along electrified railway
CN107929972A (en) A kind of transmission line high-altitude operating personnel shaft tower fall after rescue mode
CN111208391A (en) Line ground fault finder adopting alternating current and direct current signals and detection method
CN107913479B (en) Inclined rope bridge type rescue method for trapped people on high-voltage transmission line lead tower
CN213337883U (en) Insulation inspection device of closed bus duct
CN108051693A (en) A kind of method of the raising earth fault judgment accuracy based on TAS devices
CN209417200U (en) Earth-leakage monitoring device for non-coal mine 380V low voltage electric network
CN109473905A (en) Distribution uninterrupted operation " 3+1 " insulating bar working system
CN206640093U (en) A kind of multi-functional current safe connection equipment
CN202837471U (en) Low-current grounding system single-phase earth fault wire discrimination device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190319