CN109488340A - Advanced pouch pre-pouring grout passes rapidly through the construction method in high prominent down-hole goaf - Google Patents

Advanced pouch pre-pouring grout passes rapidly through the construction method in high prominent down-hole goaf Download PDF

Info

Publication number
CN109488340A
CN109488340A CN201811649735.1A CN201811649735A CN109488340A CN 109488340 A CN109488340 A CN 109488340A CN 201811649735 A CN201811649735 A CN 201811649735A CN 109488340 A CN109488340 A CN 109488340A
Authority
CN
China
Prior art keywords
pipe
grouting
pouch
goaf
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811649735.1A
Other languages
Chinese (zh)
Inventor
黄东超
吴铭
郝万海
武江海
张红涛
孙鹏翔
王冲
杨红波
张延年
高飞
高志兴
张文山
罗飞宇
李文超
李洋
常涛
李书豪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Pingmei Shenma Construction and Engineering Group Co Ltd
Original Assignee
Pingmei Shenma Construction and Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Pingmei Shenma Construction and Engineering Group Co Ltd filed Critical Pingmei Shenma Construction and Engineering Group Co Ltd
Priority to CN201811649735.1A priority Critical patent/CN109488340A/en
Publication of CN109488340A publication Critical patent/CN109488340A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/003Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D15/00Props; Chocks, e.g. made of flexible containers filled with backfilling material
    • E21D15/005Props; Chocks, e.g. made of flexible containers filled with backfilling material characterised by the material
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D15/00Props; Chocks, e.g. made of flexible containers filled with backfilling material
    • E21D15/02Non-telescopic props
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D21/00Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
    • E21D21/0026Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection characterised by constructional features of the bolts

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The present invention relates to the construction methods that a kind of advanced pouch pre-pouring grout passes rapidly through high prominent down-hole goaf, the pressure of grouting pump can be passed through, cement grout is injected into pouch by Grouting Pipe, can roadway excavation contours profiles at cylindric concrete column, the top plate and two of supporting and reinforced roadway helps country rock, one layer of sealing, stable carrying shell are formed digging country rock around tunnel in advance, simultaneously, lap segment can play the role of advance anchor bolt again, to reach increase rock mass from the steady time, the self-stable ability of excavation face surrounding rock body is improved, the purpose of the loose deformation in stratum is limited.

Description

Advanced pouch pre-pouring grout passes rapidly through the construction method in high prominent down-hole goaf
Technical field
The present invention relates to the technical field that coal mine roadway excavates, in particular to a kind of advanced pouch pre-pouring grout passes rapidly through height The construction method in prominent down-hole goaf.
Background technique
Cheng Qian is crossed to what coal resources were exploited, needs to be designed as the exploitation preparation tunnel of entire exploiting field service, under In the work progress in one mining level exploitation preparation tunnel, the case where often encountering the goaf for passing through a mining level.
Due to goaf slump determination in bad order, slump Surrounding Rock Strength is low, excavates easily landslide, roof accident occurs, together When height dash forward that gas bearing capacity in mine goaf is high, and gas density, gas pressure come and go, very unfavorable to constructing.
Summary of the invention
In order to solve the above technical problem, the present invention provides a kind of advanced pouch pre-pouring grouts to pass rapidly through high prominent down-hole The construction method in goaf.
The technical scheme is that a kind of advanced pouch pre-pouring grout passes rapidly through the construction in high prominent down-hole goaf Method, comprising the following steps:
(1) path for excavating tunnel, section shape and size are determined;
(2) pipe canopy pipe makes: taking welded still pipe as Grouting Pipe, the tail end of the Grouting Pipe is processed into tip of a branch closing, described Inlet pipe of the starting point connection caliber of Grouting Pipe less than Grouting Pipe, Grouting Pipe tail portion setting injected hole, the one of the inlet pipe Side is provided with the exhaust pipe for being welded on Grouting Pipe side, using the cylindric pouch of air duct fabric production diameter 1m, one end of pouch Stock inlet is set, and pouch is protruded into from stock inlet in the tail portion of the Grouting Pipe, and pouch, the capsule are also protruded into the tail portion of the exhaust pipe Air in bag is discharged and is wrapped in Grouting Pipe;
(3) drill: along the excavation tunnel top drill pipe canopy pipe jack determined, pipe canopy pipe jack is excavating tunnel over top It is evenly arranged;
(4) insertion tube canopy pipe: by the tail portion insertion tube canopy pipe jack for the pipe canopy pipe made, inlet pipe and exhaust pipe are stayed in outside Face;
(5) slip casting: grouting equipment uses coal Pneumatic injection pump for mine, and the slurries of slip casting are the mixed serum of cement and waterglass, Grouting pressure is 1-2MPa;
(6) tunnelling: preceding 2/3rds length of the Grouting Pipe in pipe canopy pipe jack is inserted into as driving section, rear one third Length is lap segment, and the length of lap segment is not less than 1.5m, and driving section excavation is finished tunnel along given route and is excavated Driving;
(7) roadway support: carrying out supporting for the tunnel tunneled in tunneling process, and supporting carries out again after using U29 gold bracket Gunite;
(8) it circulation construction: repeats step (3)-step (7), until passing through goaf completely.
Preferably, in step (7) a metallic, grouting behind shaft or drift lining is carried out after carrying out gunite, is vertically bored to the side wall for excavating tunnel Hole carries out slip casting.
Preferably, it when carrying out grouting behind shaft or drift lining, drills by row, long injected hole and short injected hole are set every arrangement.
Preferably, the Grouting Pipe uses DN40 welded still pipe, and the diameter of the pipe canopy pipe jack is not less than 55mm.
Preferably, the head setting screw thread and connecting valve of the exhaust pipe, the outside lateral bend in the tail portion of the exhaust pipe.
Preferably, the slurry outlet setting of the Grouting Pipe is 10mm, the slurry outlet in tail portion, the diameter of the slurry outlet Quantity be no less than 5, the distance between slurry outlet described in every two be 200mm.
Preferably, the section for excavating tunnel is arch.
The beneficial effects of the present invention are:
Advanced pouch pre-pouring grout of the invention passes rapidly through the construction method in high prominent down-hole goaf, can pass through grouting pump Cement grout is injected pouch by Grouting Pipe by pressure, can roadway excavation contours profiles at cylindric concrete column, supporting and The top plate of reinforced roadway and two helps country rock, forms one layer of sealing, stable carrying shell digging country rock around tunnel in advance.
Meanwhile lap segment can play the role of advance anchor bolt again, thus reach increase rock mass from the steady time, improve and excavate The self-stable ability of face surrounding rock body limits the purpose of the loose deformation in stratum.
The present invention solves the supporting problem that goaf is crossed in equipment road, the spilling of the toxic and harmful gas of close the goaf, Guarantee construction safety.
The construction method is safe and reliable, and strong operability, speed of application is fast, can provide guarantee for the operation in the face of adopting.
Detailed description of the invention
Fig. 1 is construction sectional view of the invention;
Fig. 2 is pipe canopy pipe layout drawing;
Fig. 3 is the structural schematic diagram of pipe canopy pipe;
Fig. 4 is grouting behind shaft or drift lining schematic diagram;
A is long hole slip casting schematic diagram in Fig. 4;
B is short-bore slip casting schematic diagram in Fig. 4;
Fig. 5 is the observation curve table of one of survey station;
Fig. 6 is the observation curve table of another survey station;
In figure: 1. excavate tunnels, 2. goafs, 3. driving sections, 4. lap segments, 5. pipe canopy pipes, 51. Grouting Pipes, 52. inlet pipes, 53. exhaust pipe, 54. pouches, 6. long injected holes, 7. short injected holes.
Specific embodiment
A specific embodiment of the invention is referring to Fig. 1-4:
A kind of advanced pouch pre-pouring grout passes rapidly through the construction method in high prominent down-hole goaf, picture 1-4, including following step It is rapid:
(1) path for excavating tunnel 1, section shape and size are determined, the section for excavating tunnel 1 is arch;
(2) pipe canopy pipe 5 makes: taking DN40 welded still pipe as Grouting Pipe 51, the diameter of 5 jack of pipe canopy pipe is not less than 55mm, the tail end of the Grouting Pipe 51 are processed into tip of a branch closing, and the starting point connection caliber of the Grouting Pipe 51 is less than Grouting Pipe Injected hole is arranged in 51 inlet pipe 52,51 tail portion of Grouting Pipe, and the side of the inlet pipe 52, which is provided with, is welded on 51 side of Grouting Pipe The exhaust pipe 53 in face, the head setting screw thread and connecting valve of the exhaust pipe 53, the outside lateral bending in tail portion of the exhaust pipe 53 Song, the slurry outlet setting of the Grouting Pipe 51 is in tail portion, and the diameter of the slurry outlet is 10mm, and the quantity of the slurry outlet is many In 5, the distance between slurry outlet described in every two is 200mm, and the cylindric pouch 54 of diameter 1m is made of air duct fabric, Stock inlet is arranged in one end of pouch 54, and pouch 54, the tail of the exhaust pipe 53 are protruded into from stock inlet in the tail portion of the Grouting Pipe 51 Portion also protrudes into pouch 54, and the air in the pouch 54 is discharged and is wrapped in Grouting Pipe 51;
(3) drill: along 1 top drill pipe canopy pipe of excavation tunnel, 5 jack determined, 5 jack of pipe canopy pipe is excavating 1 top of tunnel Top is evenly arranged;
(4) insertion tube canopy pipe 5: by 5 jack of tail portion insertion tube canopy pipe for the pipe canopy pipe 5 made, inlet pipe 52 and exhaust pipe 53 It is left outside;
(5) slip casting: grouting equipment uses coal Pneumatic injection pump for mine, and the slurries of slip casting are the mixed serum of cement and waterglass, Grouting pressure is 1-2MPa;
(6) tunnelling: preceding 2/3rds length of the Grouting Pipe 51 in 5 jack of pipe canopy pipe is inserted into as driving section 3, three points latter One of length be lap segment 4, the length of lap segment 4 is not less than 1.5m, along given route will tunnel the excavation of section 3 finish tunnel into Row excavates driving;
(7) roadway support: carrying out supporting for the tunnel tunneled in tunneling process, and supporting carries out again after using U29 gold bracket Gunite carries out grouting behind shaft or drift lining after carrying out gunite, when carrying out grouting behind shaft or drift lining, drills by row, long injected hole 6 and short slip casting Hole 7 is set every arrangement, carries out slip casting to the side wall vertical drilling for excavating tunnel 1;
(8) circulation construction: repeating step (3)-step (7), until passing through goaf 2 completely.
The own 15-15060 air way high position lane equipment in No. two exploiting fields Jing Jiwu of eight mines that my unit is constructed passes through goaf 2 Using construction method of the invention, goaf 2 is crossed within construction 30 days in the original plan, it is practical by using 54 slurry injection technique of pipe canopy pouch It construction time only 10 days, saves for 2/3 time, while 200,000 yuan of the cost of labor moon can be saved, reduce maintenance cost about 1,620,000 Member.
In order to examine construction effect of the invention, 2 survey stations are established to tunnel across 2 sections of goaf excavating tunnel 1 The deformation on country rock surface carries out observation in 2 months, and the observation curve table of one of survey station is to see Fig. 5, the sight of another survey station It surveys curve table and sees Fig. 6;It can be seen that the tunnel prop after constructing 40 days using construction method of the invention by Fig. 5,6 System has given full play to support action, preferably controls the country rock of equipment road goaf section.

Claims (7)

1. the construction method that a kind of advanced pouch pre-pouring grout passes rapidly through high prominent down-hole goaf, which is characterized in that including Following steps:
(1) path for excavating tunnel, section shape and size are determined;
(2) pipe canopy pipe makes: taking welded still pipe as Grouting Pipe, the tail end of the Grouting Pipe is processed into tip of a branch closing, described Inlet pipe of the starting point connection caliber of Grouting Pipe less than Grouting Pipe, Grouting Pipe tail portion setting injected hole, the one of the inlet pipe Side is provided with the exhaust pipe for being welded on Grouting Pipe side, using the cylindric pouch of air duct fabric production diameter 1m, one end of pouch Stock inlet is set, and pouch is protruded into from stock inlet in the tail portion of the Grouting Pipe, and pouch, the capsule are also protruded into the tail portion of the exhaust pipe Air in bag is discharged and is wrapped in Grouting Pipe;
(3) drill: along the excavation tunnel top drill pipe canopy pipe jack determined, pipe canopy pipe jack is excavating tunnel over top It is evenly arranged;
(4) insertion tube canopy pipe: by the tail portion insertion tube canopy pipe jack for the pipe canopy pipe made, inlet pipe and exhaust pipe are stayed in outside Face;
(5) slip casting: grouting equipment uses coal Pneumatic injection pump for mine, and the slurries of slip casting are the mixed serum of cement and waterglass, Grouting pressure is 1-2MPa;
(6) tunnelling: preceding 2/3rds length of the Grouting Pipe in pipe canopy pipe jack is inserted into as driving section, rear one third Length is lap segment, and the length of lap segment is not less than 1.5m, and driving section excavation is finished tunnel along given route and is excavated Driving;
(7) roadway support: carrying out supporting for the tunnel tunneled in tunneling process, and supporting carries out again after using U29 gold bracket Gunite;
(8) it circulation construction: repeats step (3)-step (7), until passing through goaf completely.
2. advanced pouch pre-pouring grout according to claim 1 passes rapidly through the construction method in high prominent down-hole goaf, It is characterized by: in step (7) a metallic, carry out grouting behind shaft or drift lining after carrying out gunite, to excavate the side wall vertical drilling in tunnel into Row slip casting.
3. advanced pouch pre-pouring grout according to claim 2 passes rapidly through the construction method in high prominent down-hole goaf, It is characterized by: drilling by row, long injected hole and short injected hole are set every arrangement when carrying out grouting behind shaft or drift lining.
4. advanced pouch pre-pouring grout according to claim 3 passes rapidly through the construction method in high prominent down-hole goaf, It is characterized by: the Grouting Pipe uses DN40 welded still pipe, the diameter of the pipe canopy pipe jack is not less than 55mm.
5. advanced pouch pre-pouring grout according to claim 4 passes rapidly through the construction method in high prominent down-hole goaf, It is characterized by: the head setting screw thread and connecting valve of the exhaust pipe, the outside lateral bend in the tail portion of the exhaust pipe.
6. advanced pouch pre-pouring grout according to claim 5 passes rapidly through the construction method in high prominent down-hole goaf, It is characterized by: the slurry outlet setting of the Grouting Pipe, in tail portion, the diameter of the slurry outlet is 10mm, the number of the slurry outlet Amount no less than 5, the distance between slurry outlet described in every two is 200mm.
7. advanced pouch pre-pouring grout according to claim 6 passes rapidly through the construction method in high prominent down-hole goaf, It is characterized by: the section for excavating tunnel is arch.
CN201811649735.1A 2018-12-30 2018-12-30 Advanced pouch pre-pouring grout passes rapidly through the construction method in high prominent down-hole goaf Pending CN109488340A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811649735.1A CN109488340A (en) 2018-12-30 2018-12-30 Advanced pouch pre-pouring grout passes rapidly through the construction method in high prominent down-hole goaf

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811649735.1A CN109488340A (en) 2018-12-30 2018-12-30 Advanced pouch pre-pouring grout passes rapidly through the construction method in high prominent down-hole goaf

Publications (1)

Publication Number Publication Date
CN109488340A true CN109488340A (en) 2019-03-19

Family

ID=65713627

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811649735.1A Pending CN109488340A (en) 2018-12-30 2018-12-30 Advanced pouch pre-pouring grout passes rapidly through the construction method in high prominent down-hole goaf

Country Status (1)

Country Link
CN (1) CN109488340A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110067573A (en) * 2019-04-26 2019-07-30 西和县中宝矿业有限公司 A kind of quick improvement and the construction method for passing through the crushed zone that caved in
CN114033453A (en) * 2021-11-25 2022-02-11 西安科技大学 Coal face goaf roof treatment method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3808714A1 (en) * 1988-03-16 1989-10-05 Westhaus Karl Heinz Prof Dr In Method of constructing a tunnel, in particular a traffic tunnel, and shield driving machine for carrying out the method
CN106149677A (en) * 2015-04-16 2016-11-23 中铁二院工程集团有限责任公司 High-pressure water-enriched goaf grouting reinforcement means
CN106988755A (en) * 2017-05-10 2017-07-28 中铁五局集团第五工程有限责任公司 A kind of tunnel portal weak surrounding rock section overlength pipe shed construction method
CN107524166A (en) * 2017-08-31 2017-12-29 中交第四航务工程局有限公司 A kind of grouting bag and application method
CN208040348U (en) * 2018-04-04 2018-11-02 郑州鑫安矿山机械配件有限公司 Slip casting bag pocket type hole packer

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3808714A1 (en) * 1988-03-16 1989-10-05 Westhaus Karl Heinz Prof Dr In Method of constructing a tunnel, in particular a traffic tunnel, and shield driving machine for carrying out the method
CN106149677A (en) * 2015-04-16 2016-11-23 中铁二院工程集团有限责任公司 High-pressure water-enriched goaf grouting reinforcement means
CN106988755A (en) * 2017-05-10 2017-07-28 中铁五局集团第五工程有限责任公司 A kind of tunnel portal weak surrounding rock section overlength pipe shed construction method
CN107524166A (en) * 2017-08-31 2017-12-29 中交第四航务工程局有限公司 A kind of grouting bag and application method
CN208040348U (en) * 2018-04-04 2018-11-02 郑州鑫安矿山机械配件有限公司 Slip casting bag pocket type hole packer

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
卢海军: "管棚囊袋注浆超前支护技术在巷道过采空区中的应用", 《煤炭科学技术》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110067573A (en) * 2019-04-26 2019-07-30 西和县中宝矿业有限公司 A kind of quick improvement and the construction method for passing through the crushed zone that caved in
CN114033453A (en) * 2021-11-25 2022-02-11 西安科技大学 Coal face goaf roof treatment method
CN114033453B (en) * 2021-11-25 2023-05-30 西安科技大学 Goaf roof treatment method for coal face

Similar Documents

Publication Publication Date Title
CN108661643B (en) It a kind of coal working face end adopts return channel and cuts top release shield lane method
CN101408106B (en) Small tube shed pre-grouting method
CN103306687B (en) Soft rock tunnel long cantilever horizontal jet grouting Deformation control construction method
CN103835729B (en) Deep distance roadway surrounding rock pre grouting from the surface reinforcement process
CN107701188A (en) One kind cuts top destressing method for the mined out side static state spalling of gob side entry driving thin coal pillar
CN110878696B (en) Method for reinforcing surrounding rock of tunnel section at junction of upper soft and lower hard stratum shield method and mine method
CN103334770A (en) Construction method of superhigh water pressure water-affluent crushed zones of long-large counter-slope tunnels
CN105927243B (en) A kind of underground country rock tomography suspension device and method for protecting support
CN112253115B (en) Near-horizontal coal seam roadway type cemented filling mining method
CN106223897B (en) A kind of broken coal petrography deep hole segmenting slip casting method of fully-mechanized mining working
CN105673040A (en) Bearing system of deep well high-stress roadway surrounding rock enhanced support and application of bearing system
CN106522981B (en) Pass through the method for protecting support in goaf tunnel
CN109184747A (en) A kind of method for protecting support of Deep Soft Rock Tunnel
CN103321235A (en) Composite soil nailing wall slope support method
CN104500070A (en) Continuous coal mining machine paste filling mining method
CN102518470A (en) Method for preventing and controlling water by using freezing pipes in annular water intercepting tunnel
CN106014443B (en) A kind of method of the Floor Heave in Roadway for preventing gob side entry retaining and wall sliding
CN109488329A (en) A kind of broken water drenching country rock administering method of Deep Soft Rock Tunnel large deformation
CN109488340A (en) Advanced pouch pre-pouring grout passes rapidly through the construction method in high prominent down-hole goaf
CN106837382A (en) A kind of subway tunnel country rock pre grouting from the surface reinforcement process
CN103993881A (en) Long-wall roadway type cemented filling mining method
CN112127899B (en) Method for consolidation grouting of conglomerate stratum tunnel arch ring
CN109184752A (en) A kind of coal mine supporting construction and its method for protecting support for passing through old kiln goaf
CN115853579A (en) Coal mine filling and mining cooperative carbon dioxide solid storage system and method
CN112174616B (en) Underground consolidation material and method for loose coal rock mass in small kiln damage area

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190319