CN109487788A - A kind of pile driving equipment - Google Patents
A kind of pile driving equipment Download PDFInfo
- Publication number
- CN109487788A CN109487788A CN201910009080.XA CN201910009080A CN109487788A CN 109487788 A CN109487788 A CN 109487788A CN 201910009080 A CN201910009080 A CN 201910009080A CN 109487788 A CN109487788 A CN 109487788A
- Authority
- CN
- China
- Prior art keywords
- pile
- pivoted arm
- driving equipment
- equipment according
- clip
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D7/00—Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
- E02D7/02—Placing by driving
- E02D7/06—Power-driven drivers
- E02D7/14—Components for drivers inasmuch as not specially for a specific driver construction
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D13/00—Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
- E02D13/04—Guide devices; Guide frames
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D7/00—Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
- E02D7/02—Placing by driving
- E02D7/06—Power-driven drivers
- E02D7/14—Components for drivers inasmuch as not specially for a specific driver construction
- E02D7/16—Scaffolds or supports for drivers
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
The present invention relates to a kind of pile driving equipments, including the piling equipment being arranged on running gear and running gear, piling equipment includes the pile cover device installed on the support frame and support frame for stand shape arrangement, pile monkey is arranged in the top of pile cover device, clip pile device is provided with below pile cover device, the pile body of prefabricated pile constitutes slide-and-guide cooperation clamped by clip pile device and with clip pile device along vertical direction.Above-mentioned technical proposal provided by the invention can clamp prefabricated pile by the setting of clip pile device, prevent prefabricated pile from swinging when carrying out position or attitude regulation.The pushing of prefabricated pile can be oriented to simultaneously, guarantee the piling of prefabricated pile not sideslip vertically.
Description
Technical field
The present invention relates to pile foundation construction fields, and in particular to a kind of pile driving equipment.
Background technique
Prefabricated pile is squeezed into and forms retaining dam in ground by pile driving equipment, prevents erodsion of stream river levee.Pile driving equipment is mainly adopted
Prefabricated pile is squeezed into ground with hydraulic impact hammer.Prefabricated pile is sling to pre- by pile cover device on pile driving equipment and hook gear
Fixed piling point, since the length of prefabricated pile is larger, for such pile driving equipment during mobile prefabricated pile, prefabricated pile is easy hair
It is raw to shake.Secondly, hydraulic impact hammer squeezes into prefabricated pile in ground internal procedure, it is prefabricated since lower section lacks the guiding of guiding device
Stake is easy to appear offset.
Summary of the invention
The object of the present invention is to provide a kind of pile driving equipment, can be used for solving the above problems.
The technical solution adopted by the present invention is that:
A kind of pile driving equipment, it is characterised in that: including the piling equipment being arranged on running gear and running gear, piling equipment
The pile cover device installed on support frame and support frame including founding shape arrangement, the top of pile cover device are arranged pile monkey, under pile cover device
Side is provided with clip pile device, and the pile body of prefabricated pile is led clamped by clip pile device and with clip pile device along vertical direction composition sliding
To cooperation.
Further embodiment are as follows:
Clip pile device includes left and right two clamping parts positioned opposite, and it is close to each other and separate that driving mechanism adjusts two clamping parts.
Clamping part includes for clamping pile body and constituting the clamping piece being slidably matched with pile body, and clamping piece is mounted on pivoted arm
The other end of one end, pivoted arm is articulated and connected by A articulated shaft and running gear, and pivoted arm is connected with the driving mechanism of its rotation is driven
It connects.
Specific scheme are as follows:
Pivoted arm is horizontally disposed, and A articulated shaft is arranged along vertical direction.
Clamping piece is idler wheel composition, and idler wheel is rotatably installed in the end of pivoted arm, the cord horizontal arrangement of idler wheel.
Clamping piece is guiding wheel composition, and guiding wheel is rotatably installed in the end of pivoted arm, the cord horizontal arrangement of guiding wheel.
Conversion support is arranged in the end of pivoted arm, and conversion support is rotatably installed on pivoted arm, and difference is equipped on conversion support
The clamping piece of structure is clamped to prefabricated pile and is oriented to cooperation by the clamping piece that rotation conversion support adjusts different structure,
The locking member locked to the rotation of conversion support is set on pivoted arm or conversion support.
Pile cover device is that a groove profile part that Open Side Down is constituted.
Spacing between the flute length direction and two clamping parts of groove profile part is consistent, and the groove width of groove profile part is from top to bottom gradually
Increase.
Driving mechanism is that oil cylinder is constituted, and the cylinder body of oil cylinder and running gear are articulated and connected, the piston rod of oil cylinder and pivoted arm
Middle part articulated connection.
Compared with prior art, the technical effect that the present invention has are as follows:
Above-mentioned technical proposal provided by the invention can clamp prefabricated pile by the setting of clip pile device, prevent pre-
Stake processed is swung when carrying out position or attitude regulation.The pushing of prefabricated pile can be oriented to simultaneously, guarantee prefabricated pile
Piling not sideslip vertically.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of pile driving equipment;
Fig. 2 is the assembling schematic diagram of clip pile device;
Fig. 3 is the structural schematic diagram of pile cover device;
The explanation of appended drawing reference is specific as follows:
Running gear -10, support frame -20, hook gear -30, pile monkey -40, clip pile device -50, clamping piece -51, pivoted arm -52,
Driving mechanism -53, pile cover device -60.
Specific embodiment
In order to which objects and advantages of the present invention are more clearly understood, the present invention is carried out with reference to embodiments specific
It is bright.It should be appreciated that following text is only used to describe one or more of specific embodiments of the invention, not to the present invention
The protection scope specifically requested carries out considered critical.
As used in this article, term " parallel ", " vertical " etc. word are not limited to its stringent geometric definition, but
Including reasonable for machining or mankind's error and inconsistency tolerance.
As shown in Figure 1, a kind of pile driving equipment, including the piling equipment being arranged on running gear 10 and running gear 10,
Piling equipment includes the pile cover device 60 installed on the support frame 20 and support frame 20 for stand shape arrangement, the top setting of pile cover device 60
Pile monkey 40(concretely hydraulic impact hammer), the lower section of pile cover device 60 is provided with clip pile device 50, and the pile body of prefabricated pile 100 is pressed from both sides
Stake device 50 is clamped and constitutes slide-and-guide cooperation along vertical direction with clip pile device 50.By the setting of clip pile device 50,
It can clamp prefabricated pile 100, prevent prefabricated pile 100 from swinging when carrying out position or attitude regulation.It simultaneously can
It is oriented to the pushing to prefabricated pile 100, guarantees that the piling of prefabricated pile 100 does not deviate vertically.Here all to can be realized pair
The structure or device of guiding role when the clamping of prefabricated pile 100 and prefabricated pile 100 push belong to the folder of the application restriction
The scope of stake device 50, is not limited to following embodiments being specifically described.
Further embodiment are as follows: clip pile device 50 includes left and right two clamping parts positioned opposite, and two clamping parts can be mutual
It is close and separate.In this way by the separate of two clamping parts of regulation, so that the prefabricated pile 100 that hook gear 30 is sling is able to enter folder
It is clamped between stake device 50, when the prefabricated pile 100 that hook gear 30 is sling is mobile, so that the upper end of prefabricated pile 100 is by top
Pile cover device 60 clamp, the pile body of prefabricated pile 100 founds shape arrangement, and it is close to adjust two clamping parts at this time, presss from both sides to prefabricated pile 100
Tightly, when such subsequent movement prefabricated pile 100 reaches scheduled piling point, prefabricated pile 100 would not shake.In addition, pile monkey
When 40 pushing prefabricated pile 100, clip pile device 50 is oriented to, so that piling will not deviate.
Specifically, clamping part includes for clamping pile body and constituting the clamping piece 51 being slidably matched, clamping piece 51 with pile body
It is mounted on one end of pivoted arm 52, the other end of pivoted arm 52 is articulated and connected by A articulated shaft and running gear 10, pivoted arm 52 and driving
Its driving mechanism 53 rotated is connected.Pivoted arm 52 is horizontally disposed, and A articulated shaft is arranged along vertical direction.Clamping piece 51 is idler wheel
It constitutes, idler wheel is rotatably installed in the end of pivoted arm 52, and the cord horizontal of idler wheel is arranged, as shown in Figure 2.Which is mainly used for pair
Section is that the prefabricated pile 100 of H row is clamped.Clamping piece 51 can also be used as guiding wheel composition, guiding wheel is roller composition, roller
The middle part of wheel is inwardly recessed the clamping of annular and the groove of guiding, and guiding wheel is rotatably installed in the end of pivoted arm 52, guide and guard
The cord horizontal of wheel is arranged.Which is mainly used for clamping the clamping for the prefabricated pile 100 that section is polygon, such as regular hexagon.
It is preferred that conversion support is arranged in the end of pivoted arm 52, conversion support is rotatably installed on pivoted arm 52, is equipped with not on conversion support
Isostructural clamping piece 51, by rotation conversion support adjust different structure clamping piece 51 to prefabricated pile 100 carry out clamping and
Guiding cooperates, and the locking member locked to the rotation of conversion support is arranged on pivoted arm 52 or conversion support.Clamping is different in this way
When the prefabricated pile 100 of model, the clamping piece 51 with regard to adjusting different model is clamped, so that the prefabricated pile 100 of all models is equal
Reliably it can be clamped and be oriented to.
Before slinging the progress clip pile of prefabricated pile 100 due to hook gear 30, prefabricated pile 100 is inclined by shape and slings, and stake
The clamping opening of cap device is straight down, therefore, to be pressed from both sides in order to enable the upper end for the prefabricated pile 100 sling can be fallen into pile cover device
Hold, the groove profile part for setting pile cover device 60 to one Open Side Down is constituted, between the flute length direction and two clamping parts of groove profile part between
Away from being consistent, the groove width of groove profile part is from top to bottom gradually increased, as shown in Figure 3.In this way convenient for skewed prefabricated pile 100
Upper end drops down onto pile cover device 60, and the posture of prefabricated pile 100 can be made gradually to be adjusted to vertical by the guiding of pile cover device 60
Shape arrangement.In addition grip block can be set at the both ends of groove profile part, realizes the reliable retention to prefabricated pile 100.
More specifically, driving mechanism 53 is oil cylinder composition, and the cylinder body and running gear 10 of oil cylinder are articulated and connected, oil cylinder
The middle part of piston rod and pivoted arm 52 is articulated and connected.
In short, the technical solution of above-mentioned offer, reliably can be clamped and be oriented to prefabricated pile 100, be prevented prefabricated
Stake 100 shakes and shifts when pushing when mobile.
The above is only a preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art
For member, without departing from the principle of the present invention, it can also make several improvements and retouch, these improvements and modifications are also answered
It is considered as protection scope of the present invention.
Claims (10)
1. a kind of pile driving equipment, it is characterised in that: including the piling equipment being arranged on running gear and running gear, piling dress
It sets including founding the pile cover device installed on the support frame and support frame that shape is arranged, pile monkey is arranged in the top of pile cover device, pile cover device
Lower section is provided with clip pile device, and the pile body of prefabricated pile constitutes sliding clamped by clip pile device and with clip pile device along vertical direction
Guiding cooperation.
2. pile driving equipment according to claim 1, it is characterised in that: clip pile device includes left and right two clampings positioned opposite
Portion, two clamping parts can be close to each other and separate.
3. pile driving equipment according to claim 2, it is characterised in that: clamping part include for clamp pile body and with pile body structure
At the clamping piece being slidably matched, clamping piece is mounted on one end of pivoted arm, and the other end of pivoted arm is cut with scissors by A articulated shaft and running gear
It connects in succession, pivoted arm is connected with the driving mechanism of its rotation is driven.
4. pile driving equipment according to claim 3, it is characterised in that: pivoted arm is horizontally disposed, and A articulated shaft is along vertical direction cloth
It sets.
5. pile driving equipment according to claim 4, it is characterised in that: clamping piece is idler wheel composition, and idler wheel is rotatably installed in
The end of pivoted arm, the cord horizontal arrangement of idler wheel.
6. pile driving equipment according to claim 4, it is characterised in that: clamping piece is guiding wheel composition, guiding wheel rotation peace
Mounted in the end of pivoted arm, the cord horizontal of guiding wheel is arranged.
7. pile driving equipment according to claim 4, it is characterised in that: conversion support, conversion support is arranged in the end of pivoted arm
It is rotatably installed on pivoted arm, the clamping piece of different structure is equipped on conversion support, different knots are adjusted by rotation conversion support
The clamping piece of structure is clamped to prefabricated pile and is oriented to cooperation, and setting carries out the rotation of conversion support on pivoted arm or conversion support
The locking member of locking.
8. pile driving equipment according to claim 4, it is characterised in that: pile cover device is that a groove profile part that Open Side Down is constituted.
9. pile driving equipment according to claim 4, it is characterised in that: between the flute length direction and two clamping parts of groove profile part
Spacing is consistent, and the groove width of groove profile part is from top to bottom gradually increased.
10. pile driving equipment according to claim 4, it is characterised in that: driving mechanism be oil cylinder constitute, the cylinder body of oil cylinder with
Running gear articulated connection, the piston rod of oil cylinder and the middle part of pivoted arm are articulated and connected.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910009080.XA CN109487788A (en) | 2019-01-04 | 2019-01-04 | A kind of pile driving equipment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910009080.XA CN109487788A (en) | 2019-01-04 | 2019-01-04 | A kind of pile driving equipment |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109487788A true CN109487788A (en) | 2019-03-19 |
Family
ID=65713997
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910009080.XA Pending CN109487788A (en) | 2019-01-04 | 2019-01-04 | A kind of pile driving equipment |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109487788A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110185038A (en) * | 2019-05-29 | 2019-08-30 | 安徽恒坤地基基础工程有限公司 | A kind of piling machine guide and guards |
CN116591164A (en) * | 2023-07-14 | 2023-08-15 | 中冶路桥建设有限公司 | Road bridge construction pile driving device |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101798813A (en) * | 2010-03-18 | 2010-08-11 | 上海振中机械制造有限公司 | Construction method for sinking or pulling concrete preformed pile by using vibrohammer |
WO2012010133A2 (en) * | 2010-06-09 | 2012-01-26 | Schletter Gmbh | Pile driver comprising pile feeders |
CN107476303A (en) * | 2017-10-09 | 2017-12-15 | 李云 | A kind of construction site ringing engine |
CN208023578U (en) * | 2018-02-12 | 2018-10-30 | 周兆弟 | Stake machine |
CN108760388A (en) * | 2018-04-11 | 2018-11-06 | 上海大学 | A kind of unmanned boat petroleum-type water sample automatic acquisition device |
CN209523190U (en) * | 2019-01-04 | 2019-10-22 | 安徽恒坤地基基础工程有限公司 | A kind of pile driving equipment |
-
2019
- 2019-01-04 CN CN201910009080.XA patent/CN109487788A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101798813A (en) * | 2010-03-18 | 2010-08-11 | 上海振中机械制造有限公司 | Construction method for sinking or pulling concrete preformed pile by using vibrohammer |
WO2012010133A2 (en) * | 2010-06-09 | 2012-01-26 | Schletter Gmbh | Pile driver comprising pile feeders |
CN107476303A (en) * | 2017-10-09 | 2017-12-15 | 李云 | A kind of construction site ringing engine |
CN208023578U (en) * | 2018-02-12 | 2018-10-30 | 周兆弟 | Stake machine |
CN108760388A (en) * | 2018-04-11 | 2018-11-06 | 上海大学 | A kind of unmanned boat petroleum-type water sample automatic acquisition device |
CN209523190U (en) * | 2019-01-04 | 2019-10-22 | 安徽恒坤地基基础工程有限公司 | A kind of pile driving equipment |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110185038A (en) * | 2019-05-29 | 2019-08-30 | 安徽恒坤地基基础工程有限公司 | A kind of piling machine guide and guards |
CN110185038B (en) * | 2019-05-29 | 2021-05-11 | 安徽恒坤地基基础工程有限公司 | Guide device for pile driver |
CN116591164A (en) * | 2023-07-14 | 2023-08-15 | 中冶路桥建设有限公司 | Road bridge construction pile driving device |
CN116591164B (en) * | 2023-07-14 | 2023-09-19 | 中冶路桥建设有限公司 | Road bridge construction pile driving device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109487788A (en) | A kind of pile driving equipment | |
CN209523190U (en) | A kind of pile driving equipment | |
CN107954203A (en) | A kind of clamping device applied to LED light kludge | |
CN206476483U (en) | Casting transport mechanism | |
CN209536126U (en) | A kind of simple lifting fixture of adjustable dimension | |
CN205666879U (en) | Intelligence mobile phone scanning appearance device | |
CN110359864A (en) | A kind of workover treatment flexible guiding device and workover operation device | |
DE333542C (en) | hair clipper | |
CN212689899U (en) | Gardens are with novel gardens ladder | |
CN201678364U (en) | Pipeline clamper for pipe crane | |
CN108689129A (en) | A kind of precision die turnover device | |
CN105945837A (en) | Clamping device | |
CN208379588U (en) | Band embraces the ringing engine of clamp device | |
CN207525350U (en) | A kind of anode rod special hanger | |
CN113123715A (en) | Gardens are with novel gardens ladder that stability is good | |
CN205822189U (en) | The angle adjusting mechanism of side folder vibration hammer | |
CN206913167U (en) | A kind of new grab bucket | |
CN220494424U (en) | Chain belt anti-deviation device of double-slider zipper machine | |
CN214362924U (en) | Construction equipment for municipal elevated road and bridge anti-collision wall | |
CN211594865U (en) | Automobile winch capable of adjusting pulling direction of steel cable | |
CN204980778U (en) | Band cramp of steel band elevator | |
CN205711925U (en) | A kind of position and the simple environmental sanitation device of logging | |
CN205799299U (en) | A kind of fast clamp mechanism | |
CN204642084U (en) | A kind of canoe antirolling apparatus on horizontal folding-jib loop wheel machine | |
CN209335465U (en) | A kind of swing holder |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB02 | Change of applicant information | ||
CB02 | Change of applicant information |
Address after: Phase I project 1103, AOZHONG wealth center, 916 Jinzhai South Road, Hefei Economic and Technological Development Zone, Anhui Province Applicant after: ANHUI HENGKUN FOUNDATION BASE ENGINEERING Co.,Ltd. Address before: 230601 Room 903, block B, central city, economic development zone, Hefei City, Anhui Province Applicant before: ANHUI HENGKUN FOUNDATION BASE ENGINEERING Co.,Ltd. |