CN109487678A - The bridge plate bridge pier connection structure of prefabricated bridge - Google Patents

The bridge plate bridge pier connection structure of prefabricated bridge Download PDF

Info

Publication number
CN109487678A
CN109487678A CN201811513893.4A CN201811513893A CN109487678A CN 109487678 A CN109487678 A CN 109487678A CN 201811513893 A CN201811513893 A CN 201811513893A CN 109487678 A CN109487678 A CN 109487678A
Authority
CN
China
Prior art keywords
pilot hole
bar
bridge
ring cover
clasp joint
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811513893.4A
Other languages
Chinese (zh)
Other versions
CN109487678B (en
Inventor
郑琼华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Ouyue Jiaojian Technology Co Ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202010562476.XA priority Critical patent/CN111676802B/en
Priority to CN201811513893.4A priority patent/CN109487678B/en
Publication of CN109487678A publication Critical patent/CN109487678A/en
Application granted granted Critical
Publication of CN109487678B publication Critical patent/CN109487678B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/04Bearings; Hinges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention relates to a kind of bridge plate bridge pier connection structures of prefabricated bridge, including bridge plate, bridge pier and rubber bar, the lower end surface of bridge plate is equipped with upper pilot hole, lower end surface is equipped with lower pilot hole, the opening of upper pilot hole is equipped with upper pilot hole ring cover and forms pilot hole ring cover, the opening of pilot hole is equipped with lower pilot hole ring cover and forms lower pilot hole ring cover, the upper end of rubber bar is hinged with several extension bars of rising to the bait, lower end is hinged with several lower clasp joint bars, the upper end of rubber bar is threaded through in pilot hole ring cover and rises to the bait extension bar clasp joint on upper pilot hole ring cover, concrete has been poured in upper pilot hole, the lower end of rubber bar is threaded through in lower pilot hole ring cover and lower clasp joint pike pole connects on lower pilot hole ring cover, concrete has been poured in lower pilot hole, gap is equipped between bridge plate and bridge pier.The present invention squeezes the advantages of anti-lateral displacement and antivibration, solves the problems, such as that the vibration isolating effect between existing prefabricated concrete structure interlayer is poor.

Description

The bridge plate bridge pier connection structure of prefabricated bridge
Technical field
The present invention relates to the bridge plate bridge pier connection structures of bridge more particularly to a kind of prefabricated bridge.
Background technique
Bridge construction highway, high-speed railway and overhead road of city construction in be accent, in bridge construction, bridge plate into There are two types of the modes of row construction: one kind is prefabricated construction, and another kind is cast in situs construction.Prefabricated construction, just It is that bridge plate is resolved into cell cube to make in factory or precasting yard, then transports to the cell cube for constituting bridge plate at bridge place simultaneously It is mounted on bridge pier.The advantages of this kind of method for bridge construction, is: bridge pier and bridge plate can parallel construction, the duration is relatively short;Bridge (boat) current under bridge is influenced in process of construction small.It is existing when being attached to prefabricated bridge plate and bridge pier for by concrete into Row pours together, and there are the deficiencies of junction Lateral resisting ability difference for which, have then been changed to pass through company in order to overcome the problems referred above Joint chair is supported between bridge plate and bridge pier, and attachment base is linked together by bolt with bridge plate and bridge pier, although the connection type Overcome the deficiency of anti-lateral displacement effect difference present in concrete binding mode, but there are bolt it is exposed be easy corrosion outside and It damages short so as to cause service life.All there is the deficiency of vibration isolating effect difference in any way.
Summary of the invention
The present invention provides a kind of bridge plate bridge pier connection structures of prefabricated bridge that anti-lateral displacement vibration isolating effect is good, solve existing Prefabricated assembled bridge plate and bridge pier between vibration isolating effect difference problem.
The above technical problem solves by the following technical programs: a kind of bridge plate bridge pier connection structure of prefabricated bridge, packet Include bridge plate and bridge pier, which is characterized in that further include rubber bar, the lower end surface of the bridge plate is equipped with upper pilot hole, described Integrally formed with upper pilot hole ring cover in the opening of upper pilot hole, the lower end surface of the bridge pier is equipped with lower pilot hole, described Integrally formed with lower pilot hole ring cover in the opening of lower pilot hole, the upper end of the rubber bar is hinged with several upper clasp joints Bar, lower end are hinged with several lower clasp joint bars, and the upper end of the rubber bar is threaded through in the upper pilot hole ring cover and institute It states and rises to the bait extension bar clasp joint on upper pilot hole ring cover, poured concrete in the upper pilot hole and the extension bar of rising to the bait is same Bridge plate is fixed together, and the lower end of the rubber bar is threaded through in the lower pilot hole ring cover and the lower clasp joint pike pole It connects on lower pilot hole ring cover, has poured concrete in the lower pilot hole and the lower clasp joint bar is fixed on one with bridge pier It rises, gap is equipped between the bridge plate and bridge pier.Since bridge plate connects by rubber bar with bridge pier and is provided with gap, So that having vibration isolating effect between bridge plate bridge pier.Clasp joint bar and upper and lower clasp joint bar are hinged above and below being arranged, can either Facilitate insertion that can guarantee reliable fixation again and prevent to move up and down, rubber bar is the energy being threaded through in bridge plate and bridge pier It enough effectively prevent translating.Clasp joint bar is cast in concrete, so that will not corrode for metal, is used to play extension The effect in service life.
Preferably, the extension bar of rising to the bait is equipped with upper limit potential head, it is upper fixed that the upper surface of the rubber bar is equipped with Position vertical bar, extension bar clasp joint upper limit potential head when on the upper pilot hole ring cover of rising to the bait, which is located at, rises to the bait extension bar far from upper On the side of pilot hole ring cover, the extension bar of rising to the bait is holded up on described when upper limit potential head is connected on the upper positioning vertical bar Clasp joint bar be downwardly inclined and generate the torque turned downward and extension bar of rising to the bait it is directed downwardly projection be all located on the rubber bar. The convenience for being that rubber bar is assembled together with bridge plate is good.Extension bar of rising to the bait can fall automatically after protruding into upper pilot hole Under.
Preferably, the upper surface of the rubber bar is equipped on upper steel construction end plate, the extension bar of rising to the bait is hinged It is hinged with the rubber bar on the upper steel construction end plate.Easy to connect and good reliability.
Preferably, the upper positioning vertical bar is also connected on the upper steel construction end plate, the upper positioning vertical bar is risen to the bait Extension bar and upper limit potential head are all metal structure.It enables to the concrete being poured into pilot hole and upper positioning vertical bar, rise to the bait Extension bar and upper limit potential head, which link together, constitutes reinforced concrete structure to improve bonding strength, solves interior intracavitary formation reinforcing bar The problem of concrete.
Preferably, being equipped with upper pilot hole sidewall portion reinforced frame, the upper assembly orifice ring in the hole wall of the upper pilot hole Upper hole cover reinforced frame is equipped in shape lid.It can be improved the structural strength of pilot hole.
Preferably, the lower clasp joint bar is equipped with lower limit potential head, it is lower fixed that the lower end surface of the rubber bar is equipped with Position vertical bar, the lower clasp joint pike pole connect lower limit potential head when on the lower pilot hole ring cover and are located at lower clasp joint bar far under On the side of pilot hole ring cover;It is described when the lower clasp joint bar holds up lower limit potential head and is connected on the lower positioning vertical bar The center of gravity of lower clasp joint bar is located across one far from lower positioning vertical bar of the upright plane of hinged shaft of the lower clasp joint bar with rubber bar Side, the projection of lower clasp joint bar upward are all located on the rubber bar;The lower clasp joint bar is ferromagnet, the lower pilot hole Ring cover, which is equipped with, to be adsorbed the lower clasp joint bar and lower clasp joint bar is turned to and is abutted together with lower pilot hole ring cover The permanent magnet of annular.Convenience when rubber bar is assembled together with bridge pier is good.Lower clasp joint bar can protrude into upper dress After distribution on automatic turning to lower pilot hole ring cover.
Preferably, the lower end surface of the rubber bar is equipped on lower steel construction end plate, the lower clasp joint bar is hinged on It is hinged with the rubber bar on the lower steel construction end plate.Easy to connect and good reliability.
Preferably, the upper positioning vertical bar is also connected on the upper steel construction end plate, the upper positioning vertical bar and upper Spacing head is all metal structure.Enable to the concrete being poured into lower pilot hole and lower positioning vertical bar, lower clasp joint bar and under Spacing head, which links together, constitutes reinforced concrete structure to improve bonding strength, solves and forms reinforced concrete in lower pilot hole The problem of soil.
Preferably, the upper pilot hole is equipped with bridge plate portion plug hole and bridge plate portion gas vent, bridge plate portion plug hole Bridge plate upper surface is all penetrated through with bridge plate portion gas vent, the lower pilot hole is equipped with bridge pier portion plug hole and bridge pier portion gas vent.? Convenient and patency is good when casting concrete in upper pilot hole and lower pilot hole.It is not easy to generate bubble in concrete.Bridge plate Portion's plug hole and bridge plate portion gas vent all penetrate through bridge plate upper surface, can construct by platform of bridge plate, convenient when construction.
Preferably, being equipped with upper pilot hole sidewall portion reinforced frame, the lower assembly orifice ring in the hole wall of the lower pilot hole Lower opening cover reinforced frame is equipped in shape lid.It can be improved the structural strength of lower pilot hole.
Preferably, the rubber bar between the upper pilot hole ring cover for interference fit, the rubber branch Strut between the lower pilot hole ring cover for interference fit.It can prevent from going out to flow from upper and lower pilot hole ring cover when slip casting Out.
The present invention has an advantage that can be to carrying out vibration isolation between bridge plate and driving;Lateral resisting ability is good;Metalwork pours It builds in concrete, it is not easy to generate corrosion damage.
Detailed description of the invention
Fig. 1 is the schematic diagram that embodiment one carries out a state when assembled.
Fig. 2 is the schematic diagram that one present invention of embodiment carries out another state when assembled.
Fig. 3 is the schematic diagram of embodiment one.
Fig. 4 is the schematic diagram of embodiment two.
In figure: bridge plate 1, upper pilot hole 11, upper pilot hole ring cover 13, upper pilot hole sidewall portion reinforced frame 14, upper port lid Portion's reinforced frame 15, bridge plate portion plug hole 16, bridge plate portion gas vent 17, bridge pier 2, lower pilot hole 21, lower pilot hole ring cover 23, on Pilot hole sidewall portion reinforced frame 24, lower opening cover reinforced frame 25, bridge pier portion plug hole 26, bridge pier portion gas vent 27, rubber Bar 3, upper steel construction end plate 31, upper positioning vertical bar 311, extension bar 32 of rising to the bait, on ship and resell on another market 321, upper limit potential head 322, lower steel construction end Plate 33, lower positioning vertical bar 331, lower clasp joint bar 34, under ship and resell on another market 341, lower limit potential head 342, by lower clasp joint bar with rubber bar Hinged shaft upright plane S1, annular permanent magnet 35, upper pilot hole Concrete Filled body 36, lower pilot hole Concrete Filled body 37, gap S2.
Specific embodiment
The present invention will be further described below with reference to the accompanying drawings and embodiments.
Embodiment one, referring to figure 1, figure 2 and figure 3, a kind of bridge plate bridge pier connection structure of prefabricated bridge, including bridge plate 1, bridge pier 2 and rubber bar 3.
The lower end surface of bridge plate 1 is equipped with upper pilot hole 11.Integrally formed with upper pilot hole annular in the opening of upper pilot hole Lid 13.Upper pilot hole sidewall portion reinforced frame 14 is equipped in the hole wall of upper pilot hole.Upper hole cover is equipped in upper pilot hole ring cover Reinforced frame 15.Upper pilot hole is equipped with bridge plate portion plug hole 16 and bridge plate portion gas vent 17.Bridge plate portion plug hole and the exhaust of bridge plate portion Hole all penetrates through bridge plate upper surface.
The lower end surface of bridge pier 2 is equipped with lower pilot hole 21.Integrally formed with lower pilot hole annular in the opening of lower pilot hole Lid 23.Upper pilot hole sidewall portion reinforced frame 24 is equipped in the hole wall of lower pilot hole.Lower opening cover is equipped in lower pilot hole ring cover Reinforced frame 25.Lower pilot hole is equipped with bridge pier portion plug hole 26 and bridge pier portion gas vent 27.
Vulcanization is fixed on steel construction end plate 31 on the upper surface of rubber bar 3.On the center of upper steel construction end plate Equipped with upper positioning vertical bar 311.Upper positioning vertical bar 311 is metal structure.Upper steel construction end plate is equipped with several along upper steel construction The circumferentially distributed extension bar 32 of rising to the bait of end plate.Rise to the bait extension bar by above ship and resell on another market 321 be hinged on upper steel construction end plate and with rubber branch Strut is hinged.Extension bar of rising to the bait is metal structure.Extension bar of rising to the bait is equipped with upper limit potential head 322.Upper limit potential head is metal knot Structure.It is separate that extension bar clasp joint when state (i.e.) in Fig. 2 upper limit potential head when on upper pilot hole ring cover of rising to the bait is located at extension bar of rising to the bait On the side of upper pilot hole ring cover.Extension bar of rising to the bait holds up upper limit potential head and is connected to (i.e. shape in Fig. 1 when on positioning vertical bar When state) extension bar of rising to the bait is downwardly inclined and extension bar of rising to the bait projection directed downwardly is all located on the rubber bar, and which makes The extension bar that must rise to the bait generates the torque turned downward.
Vulcanization is fixed on lower steel construction end plate 33 on the lower end surface of rubber bar 3.On the center of lower steel construction end plate Equipped with lower positioning vertical bar 331.Lower positioning vertical bar 331 is metal structure.Lower steel construction end plate is equipped with several along lower steel construction The circumferentially distributed lower clasp joint bar 34 of end plate.Lower clasp joint bar is shipped and resell on another market under 341 to be hinged on lower steel construction end plate with rubber branch Strut is hinged.Lower clasp joint bar is that the ferromagnetic iron material in metal structure is made.Lower clasp joint bar is equipped with lower limit First 342.Lower limit potential head is metal structure.When lower clasp joint bar is overlapped on pilot hole ring cover under when state (i.e.) in Fig. 2 Spacing head is located on side of the lower clasp joint bar far from upper pilot hole ring cover.Lower clasp joint bar hold up upper limit potential head be connected to it is lower fixed The center of gravity of clasp joint bar is located across hinged shaft of the lower clasp joint bar with rubber bar under when state () in Fig. 1 when on the vertical bar of position The side far from lower positioning vertical bar of upright plane S1, the projection of lower clasp joint bar upward are all located on rubber bar.Rubber The upper end of bar is threaded through in pilot hole ring cover.Rubber bar is same as above between pilot hole ring cover as interference fit.Upper dress Pilot hole Concrete Filled body 36 is poured in distribution and the extension bar that will rise to the bait is fixed together with bridge plate.Under rubber bar End is threaded through in lower pilot hole ring cover.Rubber bar between the lower pilot hole ring cover for interference fit.Lower clasp joint Pike pole connects on lower pilot hole ring cover.Lower pilot hole Concrete Filled body 37 is poured in lower pilot hole and lower clasp joint bar is same Bridge pier is fixed together.Gap S2 is equipped between bridge plate and bridge pier.
The process that the present invention is assembled are as follows: the extension bar that makes to rise to the bait is holded up upper limit potential head and is connected on positioning vertical bar, so The upper end of rubber vibration insulating pad is protruded into upper pilot hole through upper pilot hole ring cover afterwards, goes up clasp joint after protruding under gravity Bar overturns and snaps on pilot hole ring cover;Make lower clasp joint bar hold up lower limit potential head to be connected on lower positioning vertical bar, so The lower end of rubber vibration insulating pad is protruded into lower pilot hole through lower pilot hole ring cover afterwards, uses magnetic on the upper surface of bridge pier after protruding into Iron such as magnet are adsorbed and lower clasp joint bar are made to overturn and snap on lower pilot hole ring cover;Through upper pouring hole by concrete In injection in pilot hole, concrete is injected in lower pilot hole through lower pouring hole.
Embodiment two, with the difference of embodiment one are as follows:
Referring to fig. 4, lower pilot hole ring cover is equipped with permanent magnet 35.Rubber bar protrude into after under the action of permanent magnet 35 under Clasp joint bar overturns and snaps on lower pilot hole ring cover.It has been to be adsorbed without artificial separately that magnet and generate overturning, has mentioned Convenience when high construction.

Claims (10)

1. a kind of bridge plate bridge pier connection structure of prefabricated bridge, including bridge plate and bridge pier, which is characterized in that further include rubber Bar, the lower end surface of the bridge plate are equipped with upper pilot hole, integrally formed with upper pilot hole annular in the opening of the upper pilot hole Lid, the lower end surface of the bridge pier are equipped with lower pilot hole, integrally formed with lower pilot hole annular in the opening of the lower pilot hole Lid, the upper end of the rubber bar is hinged with several extension bars of rising to the bait, lower end is hinged with several lower clasp joint bars, the rubber The upper end of bar is threaded through in the upper pilot hole ring cover and the extension bar clasp joint of rising to the bait is on upper pilot hole ring cover, it is described on Concrete has been poured in pilot hole and the extension bar of rising to the bait has been fixed together with bridge plate, and the lower end of the rubber bar is worn In the lower pilot hole ring cover and the lower clasp joint pike pole connects on lower pilot hole ring cover, pours in the lower pilot hole There is concrete and the lower clasp joint bar is fixed together with bridge pier, gap is equipped between the bridge plate and bridge pier.
2. the bridge plate bridge pier connection structure of prefabricated bridge according to claim 1, which is characterized in that set on the extension bar of rising to the bait There is upper limit potential head, the upper surface of the rubber bar is equipped with upper positioning vertical bar, and the extension bar clasp joint of rising to the bait is in the upper dress The upper limit potential head is located at and rises to the bait on side of the extension bar far from upper pilot hole ring cover when on distribution ring cover, the extension bar of rising to the bait Extension bar of rising to the bait described in holding up when upper limit potential head is connected on the upper positioning vertical bar is downwardly inclined and generates the power turned downward Square and extension bar of rising to the bait it is directed downwardly projection be all located on the rubber bar.
3. according to the bridge plate bridge pier connection structure for the prefabricated bridge that claim 2 is stated, which is characterized in that the rubber bar it is upper End face is equipped with upper steel construction end plate, and the extension bar of rising to the bait is hinged on the upper steel construction end plate and with the rubber bar It is hinged.
4. according to the bridge plate bridge pier connection structure for the prefabricated bridge that claim 3 is stated, which is characterized in that the upper positioning vertical bar also connects It connects on the upper steel construction end plate, the upper positioning vertical bar rises to the bait extension bar and upper limit potential head is all metal structure.
5. the bridge plate bridge pier connection structure of prefabricated bridge according to claim 1, which is characterized in that the hole of the upper pilot hole It is equipped with upper pilot hole sidewall portion reinforced frame in wall, is equipped with upper hole cover reinforced frame in the upper pilot hole ring cover.
6. the bridge plate bridge pier connection structure of prefabricated bridge according to claim 1, which is characterized in that set on the lower clasp joint bar There is lower limit potential head, the lower end surface of the rubber bar is equipped with lower positioning vertical bar, and the lower clasp joint pike pole connects in the lower dress The lower limit potential head is located on side of the lower clasp joint bar far from lower pilot hole ring cover when on distribution ring cover;The lower clasp joint bar When holding up lower limit potential head and being connected on the lower positioning vertical bar, the center of gravity of the lower clasp joint bar is located across the lower same rubber of clasp joint bar The side far from lower positioning vertical bar of the upright plane of the hinged shaft of glue support rod, the projection of lower clasp joint bar upward are all located at the rubber On support rod;The lower clasp joint bar is ferromagnet, and the lower pilot hole ring cover, which is equipped with, to be adsorbed the lower clasp joint bar and make Lower clasp joint bar turns to the permanent magnet of the annular with lower pilot hole ring cover abutting together.
7. according to the bridge plate bridge pier connection structure for the prefabricated bridge that claim 6 is stated, which is characterized in that under the rubber bar End face is equipped with lower steel construction end plate, and the lower clasp joint bar is hinged on the lower steel construction end plate and cuts with scissors with the rubber bar It is connected together.
8. according to the bridge plate bridge pier connection structure for the prefabricated bridge that claim 7 is stated, which is characterized in that the upper pilot hole is equipped with bridge Plate portion plug hole and bridge plate portion gas vent, bridge plate portion plug hole and bridge plate portion gas vent all penetrate through bridge plate upper surface, described Lower pilot hole is equipped with bridge pier portion plug hole and bridge pier portion gas vent.
9. the bridge plate bridge pier connection structure of prefabricated bridge according to claim 1, which is characterized in that the hole of the lower pilot hole It is equipped with upper pilot hole sidewall portion reinforced frame in wall, is equipped with lower opening cover reinforced frame in the lower pilot hole ring cover.
10. the bridge plate bridge pier connection structure of prefabricated bridge according to claim 1, which is characterized in that the rubber bar With being interference fit between the upper pilot hole ring cover, the rubber bar was between the lower pilot hole ring cover It is full of cooperation.
CN201811513893.4A 2018-12-11 2018-12-11 Bridge plate and pier connecting structure of prefabricated bridge Active CN109487678B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN202010562476.XA CN111676802B (en) 2018-12-11 2018-12-11 Bridge plate and pier connecting structure of prefabricated bridge
CN201811513893.4A CN109487678B (en) 2018-12-11 2018-12-11 Bridge plate and pier connecting structure of prefabricated bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811513893.4A CN109487678B (en) 2018-12-11 2018-12-11 Bridge plate and pier connecting structure of prefabricated bridge

Related Child Applications (1)

Application Number Title Priority Date Filing Date
CN202010562476.XA Division CN111676802B (en) 2018-12-11 2018-12-11 Bridge plate and pier connecting structure of prefabricated bridge

Publications (2)

Publication Number Publication Date
CN109487678A true CN109487678A (en) 2019-03-19
CN109487678B CN109487678B (en) 2020-08-11

Family

ID=65709833

Family Applications (2)

Application Number Title Priority Date Filing Date
CN202010562476.XA Active CN111676802B (en) 2018-12-11 2018-12-11 Bridge plate and pier connecting structure of prefabricated bridge
CN201811513893.4A Active CN109487678B (en) 2018-12-11 2018-12-11 Bridge plate and pier connecting structure of prefabricated bridge

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN202010562476.XA Active CN111676802B (en) 2018-12-11 2018-12-11 Bridge plate and pier connecting structure of prefabricated bridge

Country Status (1)

Country Link
CN (2) CN111676802B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06221357A (en) * 1993-01-25 1994-08-09 Bridgestone Corp Laminated rubber body lined with rubber
JPH08209626A (en) * 1995-02-07 1996-08-13 Nitta Ind Corp Bridge falling preventing device for bridge
CN102206930A (en) * 2007-02-15 2011-10-05 尹学军 Split type vibration isolating device and application thereof
CN204435219U (en) * 2015-02-09 2015-07-01 中交公路养护工程技术有限公司 A kind of for the shock-absorbing bridge support between bridge pier and bridge
CN107151976A (en) * 2017-06-16 2017-09-12 北京交达铁工科技有限公司 Separate type tenon component, elastoplasticity girder falling stopping means and its installation method
CN108824172A (en) * 2018-09-05 2018-11-16 沈阳建筑大学 Bridge rubber pad limits energy-consuming device

Family Cites Families (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3438404C1 (en) * 1984-10-19 1986-03-06 plattex GmbH, 7853 Steinen Hinge connection
US4574537A (en) * 1985-06-13 1986-03-11 Krieger Steven R Insulated panel and method of constructing same
FR2658874B1 (en) * 1990-02-26 1992-05-15 Roux Marcel IMPROVED JAW DEVICE FOR ASSEMBLING TUBULAR ELEMENTS.
DE19807663A1 (en) * 1998-02-24 1999-09-09 Baur Connection means for releasably connecting a first component and a second component and method for releasing a connection of a first component and a second component
DE29924948U1 (en) * 1999-08-09 2007-01-25 Max Bögl Bauunternehmung GmbH & Co. KG Track way for rail vehicle of magnetic levitation transport system, has rainwater or melted snow drainage troughs preferably defined between exposed part of bracket and upper section of hollow track way beam
JP4486843B2 (en) * 2004-03-31 2010-06-23 スガツネ工業株式会社 Structural material fixing device
ES2249188B1 (en) * 2005-04-11 2006-12-01 Ingenieria De Encofrados Y Servicios, S.L. CLAMP FOR CLAMPING PANELS.
KR101390863B1 (en) * 2012-07-12 2014-05-08 삼성중공업 주식회사 Fixing Apparatus for riser of drilling ship
CN103362062A (en) * 2013-01-08 2013-10-23 韩志群 Connector girder
EP2957780A1 (en) * 2014-06-18 2015-12-23 Helping Hands International Holdings Limited Locking hinge for convertible stand/table
CN104878854A (en) * 2015-04-14 2015-09-02 华南理工大学建筑设计研究院 Prefabricated shear wall horizontal abutted seam buckle welding built-up connection device
CN205443922U (en) * 2016-03-24 2016-08-10 青海省兴利公路桥梁工程公司 Bridge bearing
CN205475739U (en) * 2016-04-01 2016-08-17 金陵科技学院 Can dismantle steel connection structure
CN207332106U (en) * 2017-10-16 2018-05-08 江苏双楼建设集团有限公司 A kind of assembled architecture wallboard with shock-damping structure
CN107620386B (en) * 2017-10-23 2019-08-23 南京百西思建筑科技有限公司 The mounting structure and construction method of shock isolating pedestal in existing building base isolation reinforcement
CN108252512B (en) * 2018-02-08 2018-12-07 杭州富阳锦丰纸业有限公司 A kind of reinforced concrete floor pours case
CN108678179B (en) * 2018-05-17 2019-10-29 福建省惠东建筑工程有限公司 A kind of prefabricated buildings
CN108643365A (en) * 2018-05-17 2018-10-12 曙光建设有限公司 A kind of building cavity type prefabrication and assembly construction building structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06221357A (en) * 1993-01-25 1994-08-09 Bridgestone Corp Laminated rubber body lined with rubber
JPH08209626A (en) * 1995-02-07 1996-08-13 Nitta Ind Corp Bridge falling preventing device for bridge
CN102206930A (en) * 2007-02-15 2011-10-05 尹学军 Split type vibration isolating device and application thereof
CN204435219U (en) * 2015-02-09 2015-07-01 中交公路养护工程技术有限公司 A kind of for the shock-absorbing bridge support between bridge pier and bridge
CN107151976A (en) * 2017-06-16 2017-09-12 北京交达铁工科技有限公司 Separate type tenon component, elastoplasticity girder falling stopping means and its installation method
CN108824172A (en) * 2018-09-05 2018-11-16 沈阳建筑大学 Bridge rubber pad limits energy-consuming device

Also Published As

Publication number Publication date
CN111676802B (en) 2021-09-14
CN109487678B (en) 2020-08-11
CN111676802A (en) 2020-09-18

Similar Documents

Publication Publication Date Title
CN208701729U (en) A kind of offshore wind farm High-Rise Pile Cap Foundation using prefabricated cushion cap
CN109083003A (en) A kind of precast pier pier top connection structure and its construction method
CN207633196U (en) A kind of no anchor bottom bearing plate and band change the arch bridge suspender anchor structure in the interim hole of rope
CN109487678A (en) The bridge plate bridge pier connection structure of prefabricated bridge
CN109594833A (en) Prefabricated concrete structure Interlayer seismic isolation method
CN109487677A (en) The bridge plate bridge pier connection method of prefabricated bridge
CN105863048A (en) Connection structure of prefabricated frame support structure beam column node
CN105442855B (en) A kind of high-precision buried equipment, method of large scale embedded board
US3791154A (en) Mooring structure and method
CN109594832A (en) Prefabricated concrete structure structures with interlayer seismic isolation
CN209523213U (en) Assembled independent foundation
CN204825975U (en) Novel pressure seat well of integral type seals structure
CN206859240U (en) Reduce the device of steel suspended box cofferdam bottoming concrete thickness
KR101784114B1 (en) Holding the founding stone structure
CN215441418U (en) Pier column structure
CN206385526U (en) A kind of highway subgrade broken stone pile
CN208455871U (en) A kind of concrete assembled construction wall
CN209099157U (en) A kind of precast pier pier top connection structure
CN208502395U (en) A kind of fixed precast base of steel structural upright column
CN108951700A (en) The precast assembly bottom plate and its splicing structure and installation method of a kind of same stake connection
CN211872580U (en) Force transmission device between main arch and steel box girder of arch bridge
CN213420898U (en) Safe 5G intelligent street lamp
CN215252991U (en) Anti-seismic angle steel tower iron tower foundation
JPH0349199Y2 (en)
CN217267600U (en) High-strength street lamp ground cage assembly

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20200713

Address after: 325701 yingpanji village, Damen Town, Dongtou District, Wenzhou City, Zhejiang Province

Applicant after: Zhejiang Ouyue Jiaojian Technology Co., Ltd

Address before: 437600 No. 004, Group 8, Xihu Village, Xiapu Town, Tongshan County, Xianning City, Hubei Province

Applicant before: Zheng Qionghua

GR01 Patent grant
GR01 Patent grant