CN109472483B - Building site on-site modeling method and system based on BIM (building information modeling) model and aerial photography technology - Google Patents

Building site on-site modeling method and system based on BIM (building information modeling) model and aerial photography technology Download PDF

Info

Publication number
CN109472483B
CN109472483B CN201811293976.7A CN201811293976A CN109472483B CN 109472483 B CN109472483 B CN 109472483B CN 201811293976 A CN201811293976 A CN 201811293976A CN 109472483 B CN109472483 B CN 109472483B
Authority
CN
China
Prior art keywords
site
model
bim
dimensional
engineering
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201811293976.7A
Other languages
Chinese (zh)
Other versions
CN109472483A (en
Inventor
王建军
陈孝强
林广泰
孙辉
郑健
王渝清
班贵生
曾明智
梁承斌
许宗勇
李雍友
吕开明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangxi Road and Bridge Engineering Group Co Ltd
Original Assignee
Guangxi Road and Bridge Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangxi Road and Bridge Engineering Group Co Ltd filed Critical Guangxi Road and Bridge Engineering Group Co Ltd
Priority to CN201811293976.7A priority Critical patent/CN109472483B/en
Publication of CN109472483A publication Critical patent/CN109472483A/en
Application granted granted Critical
Publication of CN109472483B publication Critical patent/CN109472483B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • G06Q10/063114Status monitoring or status determination for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06313Resource planning in a project environment
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T17/00Three dimensional [3D] modelling, e.g. data description of 3D objects
    • G06T17/05Geographic models
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T17/00Three dimensional [3D] modelling, e.g. data description of 3D objects
    • G06T17/20Finite element generation, e.g. wire-frame surface description, tesselation

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Physics & Mathematics (AREA)
  • Human Resources & Organizations (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Geometry (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Marketing (AREA)
  • Software Systems (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • Computer Graphics (AREA)
  • Development Economics (AREA)
  • Computer Hardware Design (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Game Theory and Decision Science (AREA)
  • Educational Administration (AREA)
  • Remote Sensing (AREA)
  • Mathematical Optimization (AREA)
  • Evolutionary Computation (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Primary Health Care (AREA)
  • General Health & Medical Sciences (AREA)
  • Pure & Applied Mathematics (AREA)
  • Mathematical Analysis (AREA)
  • Health & Medical Sciences (AREA)
  • Computational Mathematics (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Biodiversity & Conservation Biology (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention provides a building site on-site modeling method and a building site on-site modeling system based on a BIM (building information modeling) model and an aerial photography technology, wherein the building site on-site modeling method comprises the following steps: 1) acquiring geographic information data of a construction site by using aerial equipment; 2) importing the actual topographic map of the construction site into three-dimensional modeling software to manufacture a three-dimensional simulation model of the actual topographic map of the construction site; 3) building a BIM model of a construction site environment by utilizing modeling software; 4) leading the BIM model into the three-dimensional simulation model obtained in the step 2) after analysis, conversion and weight reduction, and combining the BIM model and the three-dimensional simulation model on the construction site to form an open source system; 5) integrating the open source system obtained in the step 4) with the service system, and then uniformly integrating the system and the service system into an engineering construction informatization management platform for a manager to log in for use. The modeling method can solve the technical problems that the traditional modeling method is poor in universality and cannot realize informatization and intellectualization of engineering construction.

Description

Building site on-site modeling method and system based on BIM (building information modeling) model and aerial photography technology
Technical Field
The invention relates to the technical field of digital modeling, in particular to a construction site on-site modeling method and system based on a BIM (building information modeling) model and an aerial photography technology.
Background
The Building Information Modeling (BIM) is a complete Information model, can integrate engineering Information, processes and resources of engineering projects at different stages in a whole life cycle into one model, and is conveniently used by all engineering participants. The real information of the building is simulated through the three-dimensional digital technology, and information models which are coordinated with each other and have consistent interior are provided for engineering design and construction, so that the models achieve the integration of design and construction, and all specialties work together, thereby reducing the engineering production cost and ensuring that the engineering is finished on time according to quality. The BIM is not simply to integrate digital information but is an application of digital information and can be used for a digital method of design, construction, management. The method supports the integrated management environment of the construction engineering, can obviously improve the efficiency of the construction engineering in the whole process and greatly reduce the risk.
At present, the application based on the BIM and a Geographic Information System (GIS) almost becomes the conventional application of engineering construction companies, and the BIM and GIS can be used as a primary planning design, scheme selection and publicity of engineering projects. The GIS is geographic information under a large scene, covers a wide range but is rough, and cannot achieve the required fineness degree for the geographic information of a specific construction site. Most of traditional BIM and GIS three-dimensional models are simply combined with the BIM and the GIS, open sourcing of model data is not achieved, and requirements of various systems and secondary development are not combined.
Disclosure of Invention
The technical problem to be solved by the invention is as follows: the building site on-site modeling method based on the BIM and the aerial photography technology can solve the technical problems that the traditional modeling method is poor in universality and cannot realize informatization and intellectualization of engineering construction.
The invention solves another technical problem that: a building site on-site modeling system based on a BIM model and an aerial photography technology is provided.
In order to solve the first technical problem, the technical scheme adopted by the invention is as follows: a building site on-site modeling method based on a BIM (building information modeling) model and an aerial photography technology comprises the following steps:
1) acquiring an actual topographic map recorded with geographic information data of a construction site by using aerial equipment;
2) importing an actual topographic map recorded with geographic information data of a construction site into three-dimensional modeling software, performing space-three encryption calculation to generate point cloud data, and making a three-dimensional simulation model of the actual topographic map of the construction site by using the point cloud data;
3) building a BIM model of a construction site environment by utilizing modeling software, wherein the construction site environment comprises buildings, equipment and facilities;
4) the BIM model is analyzed, converted and lightened and then is led into the three-dimensional simulation model in the step 2) to form a three-dimensional model of a project, and the BIM model and the three-dimensional simulation model on the construction site are combined to form an open source system;
5) integrating the open source system obtained in the step 4) with the service system, and then uniformly integrating the system and the service system into an engineering construction informatization management platform for a manager to log in for use.
As a refinement, the three-dimensional modeling software in the step 2) is Smart3D, and the modeling software in the step 3) is Revit.
As an improved way, the open-source system obtained in the step 4) is secondarily developed.
As an improved way, the open source system obtained in the step 4) is combined with a progress monitoring system, and the method comprises the following steps:
s1, building a construction model of the project by using BIM;
s2, accurately dividing the components in the engineering by using BIM;
s3, compiling a progress plan of the component, and importing the divided component information (including manufacturers, transporters, receivers, installers, installation procedures, associated components and the like) into the material management platform in stages according to the progress plan;
s4, the material management platform generates a two-dimensional code of the material, the two-dimensional code comprises all information of the process from production and processing to hoisting completion of the component, and the two-dimensional code always accompanies the component from the production stage to the installation stage and even the operation and maintenance stage;
s5, every time when a program is passed, the relevant responsible person scans the two-dimensional code through the material management APP to confirm whether the two-dimensional code is finished
And S6, synchronizing the data to the BIM three-dimensional model and the component progress system in time, and enabling the client to know the progress of all components in time through the platform.
As an improvement, the open source system obtained in step 4) is combined with a positioning system, and the method comprises the following steps:
s1, setting the position of the positioning base station in the engineering three-dimensional model according to the actual situation;
s2, installing a positioning base station in an actual project according to the position of the positioning base station set in the three-dimensional model of the project, connecting a host computer and an upper computer, debugging personnel on site with a label, and forming a three-dimensional positioning system after debugging is successful;
and S3, the three-dimensional positioning system is combined with the engineering three-dimensional model in a butt joint mode, after the butt joint combination is successful, the real-time positioning condition can be displayed in the engineering three-dimensional model, and the specific three-dimensional position of personnel is displayed in the engineering three-dimensional model so as to arrange the personnel for allocation.
As an improvement, the open-source system obtained in step 5) is combined with a device detection system, and the method comprises the following steps:
s1, recording the use and fault maintenance conditions of all engineering equipment into the engineering construction informatization management platform according to the actual use condition;
s2, the real-time monitoring system of the equipment is incorporated into the engineering construction informatization management platform, and the field condition of the equipment can be known in real time in the platform;
s3 user obtains detailed information of any position equipment and finds out the concrete position of the fault equipment and takes measures in the engineering construction information management platform.
As an improved way, the aerial photographing device is an unmanned aerial vehicle.
To solve the second technical problem: the invention provides a building site on-site modeling system based on a BIM (building information modeling) model and an aerial photography technology, which is formed by the building site on-site modeling method based on the BIM model and the aerial photography technology.
The construction site on-site modeling method has the following technical effects:
1. the construction site three-dimensional model established by acquiring geographic information through aerial photography of the unmanned aerial vehicle is more targeted and finer than that under a GIS large scene, and the arrangement of a construction site and the manufacture of an electronic sand table are facilitated;
2. the BIM model is combined with the construction site model to form a true three-dimensional model of the engineering, so that a manager can know the engineering site condition more intuitively;
3. various BIM model data are subjected to open source processing to form a set of system of construction site field model data based on BIM model data and unmanned aerial vehicle aerial photography technology, and the system is convenient to combine with various systems and carry out secondary development so as to realize informatization and intellectualization of program construction.
The progress monitoring system is combined with the open source model, and the model can display in three dimensions according to the progress filled by field personnel.
The positioning system is combined with the open source model, and the specific three-dimensional position of the personnel can be displayed in the three-dimensional model so as to allocate the personnel in time.
By combining the equipment detection system with the open-source model, detailed information of equipment at any position can be known in the site model of the construction site, and the specific position of the equipment with a fault can be found, so that measures can be taken at the first time.
The field equipment detection system is combined with the open-source model, the area to be checked is selected from the field model of the construction site, and the field monitoring picture of the area can be displayed, so that the construction site management is facilitated.
Drawings
FIG. 1 is a system flow diagram of a building site on-site modeling method based on a BIM model and unmanned aerial vehicle aerial photography;
FIG. 2 is a schematic diagram of a three-dimensional model based component monitoring system;
FIG. 3 is a composition diagram of a real-time employee location system based on three-dimensional visualization;
fig. 4 is a flow chart of the engineering equipment safety monitoring system.
Detailed Description
As shown in fig. 1, a building site on-site modeling method based on a BIM model and an aerial photography technique specifically includes the following steps:
1. utilize unmanned aerial vehicle technique of taking photo by plane to obtain the scene topography picture of building site, the basic technical route is: setting basic parameters (including navigation route, transverse and longitudinal photo overlap rate, flight height, lens inclination and the like) for aerial photography of the unmanned aerial vehicle, and controlling the unmanned aerial vehicle to acquire field topographic data on a construction site.
2. Importing an actual topographic map recorded with geographic information data of a construction site, which is acquired by an unmanned aerial vehicle, into Smart3D three-dimensional modeling software, performing space-three encryption calculation to generate point cloud data, and making a three-dimensional simulation model of the actual topographic map of the construction site by using the point cloud data; importing the topographic picture collected by the unmanned aerial vehicle into Smart3D software, performing air-to-air encryption calculation to generate point cloud data, and making an actual topographic map of an engineering field through the point cloud data.
3. Building BIM models of buildings, equipment, facilities and the like involved in a construction site are established by utilizing modeling software such as Revit and the like.
4. And (4) leading the BIM into the second construction site geographical three-dimensional model after analysis, conversion and weight reduction, and realizing the development of BIM data elements in the process.
5. The BIM model and the three-dimensional model of the construction site are combined to form a set of open source system, so that the integration (the service system comprises a progress monitoring system, an equipment monitoring system, a positioning system, an on-site monitoring system and the like) and the secondary development of the three-dimensional model and the service system are facilitated.
6. And uniformly integrating all the combined systems into an engineering construction informatization platform of an enterprise so as to facilitate login and use of a manager.
As shown in fig. 2, the system formed by the building site on-site modeling method based on the BIM model and the aerial photography technology combines the progress monitoring system with the open source model, and includes the following steps:
s1, building a construction model of the project by using BIM;
s2, accurately dividing the components in the engineering by using BIM;
s3, compiling a progress plan of the component, and importing the divided component information (including manufacturers, transporters, receivers, installers, installation procedures, associated components and the like) into the material management platform in stages according to the progress plan;
s4, the material management platform generates a two-dimensional code of the material, the two-dimensional code comprises all information of the process from production and processing to hoisting completion of the component, and the two-dimensional code always accompanies the component from the production stage to the installation stage and even the operation and maintenance stage;
s5, every time when a program is passed, the relevant responsible person scans the two-dimensional code through the material management APP to confirm whether the two-dimensional code is finished
And S6, synchronizing the data to the BIM three-dimensional model and the component progress system in time, and enabling the client to know the progress of all components in time through the platform. The open-source system model is combined with the field monitoring system, the area to be checked is selected from the field model of the construction site, and the field monitoring picture of the area can be displayed, so that the construction site management is facilitated.
As shown in fig. 3, the open source system model in combination with the positioning system comprises the following steps:
s1, setting the position of the positioning base station in the engineering three-dimensional model according to the actual situation;
s2, installing a positioning base station in an actual project according to the position of the positioning base station set in the three-dimensional model of the project, connecting a host computer and an upper computer, debugging personnel on site with a label, and forming a three-dimensional positioning system after debugging is successful;
and S3, the three-dimensional positioning system is combined with the engineering three-dimensional model in a butt joint mode, after the butt joint combination is successful, the real-time positioning condition can be displayed in the engineering three-dimensional model, and the specific three-dimensional position of personnel is displayed in the engineering three-dimensional model so as to arrange the personnel for allocation.
As shown in fig. 4, the open source system in combination with the device detection system model comprises the following steps:
s1, recording the use and fault maintenance conditions of all engineering equipment into the engineering construction informatization management platform according to the actual use condition;
s2, the real-time monitoring system of the equipment is incorporated into the engineering construction informatization management platform, and the field condition of the equipment can be known in real time in the platform;
s3 user obtains detailed information of any position equipment and finds out the concrete position of the fault equipment and takes measures in the engineering construction information management platform.
The building site on-site modeling method based on the BIM and the aerial photography technology comprises the steps of obtaining geographic data of a building site by the aerial photography technology of an unmanned aerial vehicle, processing the topographic data obtained by the unmanned aerial vehicle by software, establishing a geographic three-dimensional model of the building site, arranging the site of the building site, planning arrangement positions of various buildings, construction facilities and engineering equipment, establishing BIM models of the buildings, the construction facilities and the engineering equipment by the software, importing the BIM models into the geographic three-dimensional model of the building site after analysis, conversion and light weight, achieving import and dynamic updating of three-dimensional scene data elements, combining the BIM models with the terrain model of the building site, enabling data of the models to be open to the outside, and forming a set of model data open source system.
The building site on-site modeling method based on the BIM model and the aerial photography technology has the following characteristics:
1. acquiring very fine geographical information data of a construction site by using unmanned aerial vehicle aerial photography;
2. building BIM models of buildings, engineering equipment, construction facilities and the like in a construction site by utilizing modeling software, building a geographical three-dimensional model of an engineering site by utilizing an unmanned aerial photography technology, and combining the geographical three-dimensional model and the geographical three-dimensional model to form a true three-dimensional model of an engineering;
3. carrying out development on data elements of the BIM and the terrain, and realizing the import and dynamic update of the data elements of the three-dimensional construction site;
4. the BIM and the data model of the construction site reserve ports for the intelligent system, and access of various intelligent systems is facilitated.
It should be apparent that the foregoing description and illustrations are by way of example only and are not intended to limit the present disclosure, application or uses. While the embodiments have been described in the embodiments and illustrated in the drawings, the present invention is not limited by the accompanying drawings and the specific examples described in the embodiments as the best mode presently contemplated for carrying out the teachings of the present invention, and the scope of the present invention is intended to include any embodiments falling within the foregoing description and the appended claims.

Claims (5)

1. A building site on-site modeling method based on a BIM (building information modeling) model and an aerial photography technology is characterized by comprising the following steps:
1) acquiring an actual topographic map recorded with geographic information data of a construction site by using aerial equipment;
2) importing the actual topographic map into three-dimensional modeling software, performing space-three encryption calculation to generate point cloud data, and making a three-dimensional simulation model of the actual topographic map of a construction site by using the point cloud data;
3) building a BIM model of a worksite environment by utilizing modeling software, wherein the worksite environment comprises buildings, equipment and facilities;
4) the BIM model is analyzed, converted and lightened and then is led into the three-dimensional simulation model in the step 2) to form an engineering three-dimensional model, and the BIM model and the three-dimensional simulation model on the construction site are combined to form an open source system;
5) integrating the open source system obtained in the step 4) with a service system, and then uniformly integrating the system and the service system into an engineering construction informatization management platform for a manager to log in for use;
combining the open source system obtained in the step 4) with a progress monitoring system, the method comprises the following steps: s1, building a construction model of the project by using BIM; s2, accurately dividing the components in the engineering by using BIM; s3, compiling a progress plan of the component, and importing the divided component information into the material management platform according to the progress plan and stages; s4, the material management platform generates a two-dimensional code of the material, the two-dimensional code comprises all information of the process from production and processing to hoisting completion of the component, and the two-dimensional code always accompanies the component from the production stage to the installation stage and even the operation and maintenance stage; s5, every time a program is executed, the relevant responsible person scans the two-dimensional code through the material management APP to confirm whether the two-dimensional code is finished or not; s6, synchronizing the data to the BIM three-dimensional model and the component progress system in time, and enabling the client to know the progress conditions of all components in time through the platform;
combining the open source system obtained in step 4) with a positioning system, comprising the steps of: s1, setting the position of the positioning base station in the engineering three-dimensional model according to the actual situation; s2, installing a positioning base station in an actual project according to the position of the positioning base station set in the three-dimensional model of the project, connecting a host computer and an upper computer, carrying a label by personnel to enter a field for debugging, and forming a three-dimensional positioning system after the debugging is successful; s3, the three-dimensional positioning system is butt-jointed and combined with the engineering three-dimensional model, after the butt-joint combination is successful, the real-time positioning condition can be displayed in the engineering three-dimensional model, and the specific three-dimensional position of personnel is displayed in the engineering three-dimensional model to arrange the personnel for allocation
Combining the open source system obtained in step 5) with an equipment detection system, comprising the steps of: s1, recording the use and fault maintenance conditions of all engineering equipment into an engineering construction informatization management platform according to the actual use condition; s2, merging the real-time monitoring system of the equipment into the engineering construction informatization management platform, and knowing the field condition of the equipment in real time in the platform; and S3, the user obtains the detailed information of the equipment at any position on the engineering construction information management platform, finds the specific position of the equipment with the fault and takes measures.
2. The BIM and aerial photography technique-based worksite modeling method of claim 1, wherein the three-dimensional modeling software in step 2) is Smart3D, and the modeling software in step 3) is Revit.
3. The BIM and aerial photography technology-based worksite modeling method of claim 1, wherein the open-source system obtained in step 4) is secondarily developed.
4. The BIM and aerial photography technology-based site modeling method of claim 1, wherein the aerial photography device is an unmanned aerial vehicle.
5. A building site on-site modeling system based on a BIM model and aerial photography techniques, formed by the method of claim 1.
CN201811293976.7A 2018-11-01 2018-11-01 Building site on-site modeling method and system based on BIM (building information modeling) model and aerial photography technology Active CN109472483B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811293976.7A CN109472483B (en) 2018-11-01 2018-11-01 Building site on-site modeling method and system based on BIM (building information modeling) model and aerial photography technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811293976.7A CN109472483B (en) 2018-11-01 2018-11-01 Building site on-site modeling method and system based on BIM (building information modeling) model and aerial photography technology

Publications (2)

Publication Number Publication Date
CN109472483A CN109472483A (en) 2019-03-15
CN109472483B true CN109472483B (en) 2022-03-29

Family

ID=65672445

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811293976.7A Active CN109472483B (en) 2018-11-01 2018-11-01 Building site on-site modeling method and system based on BIM (building information modeling) model and aerial photography technology

Country Status (1)

Country Link
CN (1) CN109472483B (en)

Families Citing this family (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110113571A (en) * 2019-05-07 2019-08-09 合肥芃明科技有限公司 A kind of approaches to IM based on virtual reality and video fusion
CN110189417A (en) * 2019-06-12 2019-08-30 南通四建集团有限公司 A kind of scene and phantom images automatic synchronous method based on UWB and BIM
CN110398982A (en) * 2019-06-21 2019-11-01 万翼科技有限公司 A kind of method for inspecting and system of unmanned plane
CN110428716A (en) * 2019-06-28 2019-11-08 中国一冶集团有限公司 A kind of sand table system based on BIM
CN110517347A (en) * 2019-07-08 2019-11-29 浙江兴土桥梁临时钢结构工程有限公司 A kind of construction project data model environment method for visualizing and its device and application
CN110472375A (en) * 2019-09-18 2019-11-19 中国十七冶集团有限公司 A kind of asymmetric suspension bridge construction management-control method based on BIM
CN111444568A (en) * 2020-03-27 2020-07-24 北京中交京纬公路造价技术有限公司 Engineering monitoring BIM cooperative platform based on Internet of things
CN111460557A (en) * 2020-04-01 2020-07-28 中国十七冶集团有限公司 Danger source safety management method based on three-dimensional live-action modeling and BIM technology
CN111597605B (en) * 2020-04-02 2024-05-31 中国国家铁路集团有限公司 Railway dynamic simulation cockpit system
CN111460668A (en) * 2020-04-02 2020-07-28 齐鲁交通信息集团有限公司 BIM technology-based highway digital simulation modeling method
CN112597578A (en) * 2020-12-25 2021-04-02 中铁第五勘察设计院集团有限公司 Railway construction site positioning management system based on BIM and GIS
CN113704860A (en) * 2021-09-08 2021-11-26 中铁二十局集团第六工程有限公司 Method, equipment and storage medium for building information construction platform of super high-rise building
CN113988647A (en) * 2021-10-29 2022-01-28 上海市浦东新区建设(集团)有限公司 Municipal works wisdom building site management system based on BIM
CN113867407B (en) * 2021-11-10 2024-04-09 广东电网能源发展有限公司 Unmanned plane-based construction auxiliary method, unmanned plane-based construction auxiliary system, intelligent equipment and storage medium
CN115953265A (en) * 2022-12-23 2023-04-11 山东青建智慧建筑科技有限公司 Intelligent building site management platform based on BIM
CN116645088B (en) * 2023-07-27 2023-10-31 中国铁路设计集团有限公司 Urban rail information model component division and electromechanical equipment operation and maintenance method and device

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103295085A (en) * 2012-03-02 2013-09-11 姜海西 Highway engineering three-dimensional office system building method based on Google earth
CN106202723A (en) * 2016-07-10 2016-12-07 北京工业大学 A kind of BIM subway work method
CN107037881A (en) * 2017-03-24 2017-08-11 广西七三科技有限公司 The interactive demonstration method and system of GIS and BIM augmented realities in piping lane, subway work
CN108549963A (en) * 2018-02-22 2018-09-18 北京中建建筑设计院有限公司 Novel construction management method based on BIM information flow standardization
CN108596423A (en) * 2018-03-02 2018-09-28 重庆机电装备技术研究院有限公司 A kind of trackways engineering construction progress msg management method based on BIM

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103295085A (en) * 2012-03-02 2013-09-11 姜海西 Highway engineering three-dimensional office system building method based on Google earth
CN106202723A (en) * 2016-07-10 2016-12-07 北京工业大学 A kind of BIM subway work method
CN107037881A (en) * 2017-03-24 2017-08-11 广西七三科技有限公司 The interactive demonstration method and system of GIS and BIM augmented realities in piping lane, subway work
CN108549963A (en) * 2018-02-22 2018-09-18 北京中建建筑设计院有限公司 Novel construction management method based on BIM information flow standardization
CN108596423A (en) * 2018-03-02 2018-09-28 重庆机电装备技术研究院有限公司 A kind of trackways engineering construction progress msg management method based on BIM

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
无人机遥感在地面目标变化监测中的应用研究;喻静敏等;《电子测量技术》;20180531;第95-98页 *

Also Published As

Publication number Publication date
CN109472483A (en) 2019-03-15

Similar Documents

Publication Publication Date Title
CN109472483B (en) Building site on-site modeling method and system based on BIM (building information modeling) model and aerial photography technology
Martinez et al. UAV integration in current construction safety planning and monitoring processes: Case study of a high-rise building construction project in Chile
JP6284240B2 (en) Structure information provision system
CN109902332A (en) A kind of power matching network system based on Three-dimension
CN111006646B (en) Method for monitoring construction progress based on unmanned aerial vehicle oblique photography measurement technology
CN114077764B (en) Three-dimensional GIS and BIM integration-based temporary modeling type establishment method and application
CN112580939A (en) BIM + GIS technology-based process management system for highway construction
CN105277233A (en) Sky-ground integrated land data acquisition system and method
CN107153744B (en) Underground three-dimensional pipeline decision making system
CN107396046A (en) A kind of stereoscopic monitoring system and method based on the true threedimensional model of oblique photograph
CN109163715B (en) Electric power station selection surveying method based on unmanned aerial vehicle RTK technology
CN114419231B (en) Traffic facility vector identification, extraction and analysis system based on point cloud data and AI technology
CN112800516A (en) Building design system with real-scene three-dimensional space model
CN110660125B (en) Three-dimensional modeling device for power distribution network system
CN112712300A (en) BIM + GIS construction project management system based on B/S information system
Kang et al. Managing construction schedule by telepresence: Integration of site video feed with an active nD CAD simulation
CN110837541A (en) Prefabricated component factory production management system based on GIS + BIM system
CN112381943A (en) Building construction quality monitoring method, system, device and storage medium
CN112257497A (en) Method for supervising line construction by utilizing air-ground fusion true three-dimensional scene
CN116798142A (en) Visual inspection method, system, equipment and storage medium for long bridge
KR20230149237A (en) System for 3D construction project management based on web and GIS and its operation method
US7487070B2 (en) Method for planning a security array of sensor units
CN116644878A (en) Engineering monitoring BIM cooperation platform based on Internet of things
CN105786994A (en) Oil and gas field exploration and development information integration system and method based on geographic information
CN106033623A (en) 3D visualized mass data processing method, apparatus and system thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant