CN109469303A - A kind of the precast support device and its installation method of achievable Fast Installation for building - Google Patents

A kind of the precast support device and its installation method of achievable Fast Installation for building Download PDF

Info

Publication number
CN109469303A
CN109469303A CN201811634570.0A CN201811634570A CN109469303A CN 109469303 A CN109469303 A CN 109469303A CN 201811634570 A CN201811634570 A CN 201811634570A CN 109469303 A CN109469303 A CN 109469303A
Authority
CN
China
Prior art keywords
inner cylinder
supporting leg
bottom plate
annular bottom
support device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811634570.0A
Other languages
Chinese (zh)
Other versions
CN109469303B (en
Inventor
刘洪波
菅浩然
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yellow River Conservancy Technical Institute
Original Assignee
Yellow River Conservancy Technical Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yellow River Conservancy Technical Institute filed Critical Yellow River Conservancy Technical Institute
Priority to CN201811634570.0A priority Critical patent/CN109469303B/en
Publication of CN109469303A publication Critical patent/CN109469303A/en
Application granted granted Critical
Publication of CN109469303B publication Critical patent/CN109469303B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/15Scaffolds primarily resting on the ground essentially comprising special means for supporting or forming platforms; Platforms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/02Scaffold feet, e.g. with arrangements for adjustment

Abstract

The invention discloses the precast support devices and its installation method of a kind of achievable Fast Installation for building, the technical issues of solution is that current workbench is built and makes all to be using simple bracket, but this bracket is too simple, encounters bad fixation when slope, is easy to happen inclination.The present invention includes pedestal and supporting leg, supporting leg is equipped with supporting surface, the pedestal includes outer ring and inner cylinder, and the inner cylinder includes several arc panels, and outer ring includes annular bottom plate and annular cover plate, annular bottom plate and annular cover plate are interlocked, the annular bottom plate top is equipped with T-slot, is connected between arc panel and annular bottom plate by connecting rod, and described connecting rod one end is fixed on arc panel, the other end is equipped with baffle, baffle is put in T-slot, and spring is arranged on baffle.The present invention uses prefabricated mode, shifts to an earlier date the components such as prefabricated pedestal and inner cylinder, support plate in factory, only need to simply install after arriving at the destination, the durable bracket built far more than snacks.

Description

A kind of the precast support device and its installation method of achievable Fast Installation for building
Technical field
The present invention relates to building fields, and in particular to a kind of precast support device of achievable Fast Installation for building and its Installation method.
Background technique
In building field, worker much needs to conduct a field operation, especially field construction when, need building bracket Or workbench.But field is with a varied topography, topography is changeable, it is difficult to guarantee that the ground of building platform is smooth.At present Workbench build and make all to be using simple bracket, but this bracket is too simple, encounters bad fixation when slope, is easy Run-off the straight influences job schedule;Also have and carry out cement again after carrying out Land leveling work at the scene and the modes such as pour building work Make platform, but this method is excessively complicated, needs more people to prepare in advance and carries a large amount of tools, wasting manpower and material resources.
Summary of the invention
The technical problem to be solved by the present invention is to current workbench build make all be using simple bracket, but it is this Bracket is too simple, encounters bad fixation when slope, is easy to happen inclination, influences job schedule, and it is simple to provide a kind of structure, makes With the precast support device and its installation method of convenient achievable Fast Installation for building.
In order to solve the above technical problems, the present invention adopts the following technical solutions: one kind achievable Fast Installation for building Precast support device, including pedestal and supporting leg, supporting leg are equipped with supporting surface, and the pedestal includes outer ring and inner cylinder, described Inner cylinder includes several arc panels, and the outer ring includes annular bottom plate and annular cover plate, and annular bottom plate and annular cover plate are engaged It closes, the annular bottom plate top is equipped with T-slot, is connected between arc panel and annular bottom plate by connecting rod, the connecting rod one End is fixed on arc panel, the other end is equipped with baffle, and baffle is put in T-slot, spring is arranged on baffle, spring one end is fixed On arc panel, the other end is attached on the inner wall of annular bottom plate.
The inner cylinder top is equipped with silk cap, and silk cap medial surface is threadedly engaged with inner cylinder lateral surface.
The outer surface of the supporting leg and the inner surface of inner cylinder are threadedly engaged;The leading flank of the leg outer surface screw thread is Inclined-plane, trailing flank be face directly or the gradient be less than leading flank inclined-plane.
The T-slot includes inside groove and channel slot, and the outer diameter of spring is greater than the internal diameter of channel slot.
The width of the inside groove is greater than the width of baffle.
It is equipped with tapered rod below the annular bottom plate, the side wall of annular bottom plate is equipped with T-type hole, on the tapered rod Portion is equipped with T forming head, and the Internal periphery in T-type hole is matched with the outer profile of T forming head.
A kind of installation method of the precast support device of achievable Fast Installation for building, comprising the following steps: 1. install Tapered rod: it by tapered rod on outer ring, exerts a force to outer ring, tapered rod is squeezed into ground;2. installing supporting leg: when supporting leg is installed, Supporting leg is inserted directly into inner cylinder;3. screwing on a cap: silk cap being moved to inner cylinder top, silk cap is twisted on the inner cylinder;4. adjusting Highly: after silk cap is twisted, supporting leg being twisted as needed outward, be adjusted to the height of needs.
Step is 2. before the supporting leg insertion inner cylinder, and in a state of nature, when supporting leg is inserted into inner cylinder, arc panel is backward for spring Mobile, spring is compressed;After supporting leg is inserted into inner cylinder, recoil of spring makes arc panel be merged into inner cylinder.
The present invention uses prefabricated mode, shifts to an earlier date the components such as prefabricated pedestal and inner cylinder, support plate in factory, reaches purpose It only need to simply be installed behind ground, the durable bracket built far more than snacks, it is simple to connect installation process, is suitable for big portion Divide temporarily building for workbench;It can remove, reuse, save the cost when leaving.
Detailed description of the invention
Fig. 1 is cross-sectional structure schematic diagram of the present invention;
Fig. 2 is schematic diagram of base structure of the present invention;
Fig. 3 is pedestal partial enlargement structural representation of the present invention;
Fig. 4 is annular bottom plate surface structure schematic diagram of the present invention;
Fig. 5 is annular bottom plate lower surface configuration schematic diagram of the present invention;
Fig. 6 is the structural schematic diagram that tapered rod of the present invention matches place with annular bottom plate.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, those of ordinary skill in the art are obtained every other under that premise of not paying creative labor Embodiment shall fall within the protection scope of the present invention.
As shown in Figures 1 to 6, a kind of precast support device of achievable Fast Installation for building, including pedestal 1 and supporting leg 2, supporting leg 2 is equipped with supporting surface 3, and the pedestal 1 includes outer ring 11 and inner cylinder 12, and the inner cylinder 12 includes several arcs Shape plate 121, the outer ring 11 include annular bottom plate 15 and annular cover plate 16, and annular bottom plate 15 and annular cover plate 16 are interlocked, 15 top of annular bottom plate is equipped with T-slot 111, is connected between arc panel 121 and annular bottom plate 15 by connecting rod 13, described 13 one end of connecting rod be fixed on arc panel 121, the other end is equipped with baffle 131, baffle 131 puts in T-slot 111, baffle 131 On be arranged with spring 14,14 one end of spring is fixed on arc panel 121, the other end is attached on the inner wall of annular bottom plate 15.
12 top of inner cylinder is equipped with silk cap 16, and 16 medial surface of silk cap is threadedly engaged with 12 lateral surface of inner cylinder.Silk cap 16 It covers on supporting leg 2, and can be move freely on supporting leg 2, after supporting leg 2 is installed in place on inner cylinder 12, silk cap is screwed in interior On cylinder 12, prevent from loosening between several arc panels of inner cylinder.
The outer surface of the supporting leg 2 and the inner surface of inner cylinder 12 are threadedly engaged;The front side of 2 outer surface thread of supporting leg Face 21 is inclined-plane, trailing flank 22 be face directly or the gradient be less than leading flank 11 inclined-plane.When installation, first supporting leg 2 is inserted directly into interior In cylinder, supporting leg 2 struts several arc panels of inner cylinder, and supporting leg extends to inner cylinder bottom, simple and fast, is at this moment screwed in silk cap 16 On inner cylinder, supporting leg is turned to proper height upwards further according to needs.
The T-slot 111 includes inside groove 1111 and channel slot 1112, and the outer diameter of spring 14 is greater than the interior of channel slot 1112 Diameter.Spring 14 cannot go deep into channel slot 1112.
The precast support device of achievable Fast Installation for building according to claim 4, it is characterised in that: described The width of inside groove 1111 is greater than the width of baffle 131.Guarantee that baffle has certain activity space but not taken off in inside groove 1111 Inside groove 1111 out.
Tapered rod 17 is equipped with below the annular bottom plate 15, the side wall of annular bottom plate 15 is equipped with T-type hole 112, described 17 top of tapered rod be equipped with T forming head 171, the Internal periphery in T-type hole 112 matches with the outer profile of T forming head 171.It, will when installation Then tapered rod 17 is squeezed into ground out of side promotes outer ring T-type hole 112 by tapered rod 17.The setting of tapered rod 17 just as Several claws of outer ring firmly fix outer ring on the ground.It does not need to dig pit on the ground, supporting leg is embedded in ground by buried depth etc. On face, workload is substantially reduced.
A kind of installation method of the precast support device of achievable Fast Installation for building, comprising the following steps: 1. install Tapered rod 17: it by tapered rod 17 on outer ring 11, exerts a force to outer ring, tapered rod 17 is squeezed into ground;2. installing supporting leg: supporting leg When installation, supporting leg is inserted directly into inner cylinder 12;3. screwing on a cap 16: silk cap being moved to 12 top of inner cylinder, silk cap 16 is twisted On the inner cylinder;4. adjusting height: after silk cap 16 is twisted, as needed twisting supporting leg outward, be adjusted to the height of needs.
Step is 2. before the supporting leg insertion inner cylinder, spring in a state of nature, when supporting leg is inserted into inner cylinder, arc panel 121 It moves backward, spring is compressed;After supporting leg is inserted into inner cylinder, recoil of spring makes arc panel 121 be merged into inner cylinder.

Claims (8)

1. a kind of precast support device of achievable Fast Installation for building, it is characterised in that: including pedestal (1) and supporting leg (2), Supporting leg (2) is equipped with supporting surface (3), and the pedestal (1) includes outer ring (11) and inner cylinder (12), the inner cylinder (12) packet Several arc panels (121) are included, the outer ring (11) includes annular bottom plate (15) and annular cover plate (16), annular bottom plate (15) It is interlocked with annular cover plate (16), the annular bottom plate (15) top is equipped with T-slot (111), arc panel (121) and annular bottom It is connected between plate (15) by connecting rod (13), the connecting rod (13) one end is fixed on arc panel (121), the other end is equipped with gear Plate (131), baffle (131) put in T-slot (111), are arranged on baffle (131) spring (14), spring (14) one end is fixed On arc panel (121), the other end is attached on the inner wall of annular bottom plate (15).
2. the precast support device of achievable Fast Installation for building according to claim 1, it is characterised in that: described Inner cylinder (12) top is equipped with silk cap (16), and silk cap (16) medial surface is threadedly engaged with inner cylinder (12) lateral surface.
3. the precast support device of achievable Fast Installation for building according to claim 1, it is characterised in that: described The outer surface of supporting leg (2) and the inner surface of inner cylinder (12) are threadedly engaged;The leading flank (21) of supporting leg (2) outer surface thread is Inclined-plane, trailing flank (22) be face directly or the gradient be less than leading flank (11) inclined-plane.
4. the precast support device of achievable Fast Installation for building according to claim 1, it is characterised in that: described T-slot (111) includes inside groove (1111) and channel slot (1112), and the outer diameter of spring (14) is greater than the internal diameter of channel slot (1112).
5. the precast support device of achievable Fast Installation for building according to claim 4, it is characterised in that: in described The width of slot (1111) is greater than the width of baffle (131).
6. the precast support device of achievable Fast Installation for building according to claim 4, it is characterised in that: described Tapered rod (17) are equipped with below annular bottom plate (15), the side wall of annular bottom plate (15) is equipped with T-type hole (112), the taper Bar (17) top is equipped with T forming head (171), and the Internal periphery of T-type hole (112) is matched with the outer profile of T forming head (171).
7. a kind of installation method of the precast support device of achievable Fast Installation for building, it is characterised in that: including following step It is rapid: tapered rod (17) 1. being installed: by tapered rod (17) on outer ring (11), exerting a force to outer ring, tapered rod (17) is squeezed into ground Face;2. installing supporting leg: when supporting leg is installed, supporting leg being inserted directly into inner cylinder (12);3. screwing on a cap (16): silk cap is moved to Inner cylinder (12) top twists silk cap (16) on the inner cylinder;4. adjust height: after silk cap (16) is twisted, as needed by supporting leg to It is outer to twist, it is adjusted to the height of needs.
8. the installation method of the precast support device of achievable Fast Installation for building according to claim 7, feature Be: step is 2. before the supporting leg insertion inner cylinder, spring in a state of nature, when supporting leg is inserted into inner cylinder, arc panel (121) to After move, spring is compressed;After supporting leg is inserted into inner cylinder, recoil of spring makes arc panel (121) be merged into inner cylinder.
CN201811634570.0A 2018-12-29 2018-12-29 Prefabricated supporting device capable of realizing rapid installation for building and installation method thereof Active CN109469303B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811634570.0A CN109469303B (en) 2018-12-29 2018-12-29 Prefabricated supporting device capable of realizing rapid installation for building and installation method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811634570.0A CN109469303B (en) 2018-12-29 2018-12-29 Prefabricated supporting device capable of realizing rapid installation for building and installation method thereof

Publications (2)

Publication Number Publication Date
CN109469303A true CN109469303A (en) 2019-03-15
CN109469303B CN109469303B (en) 2024-03-12

Family

ID=65676909

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811634570.0A Active CN109469303B (en) 2018-12-29 2018-12-29 Prefabricated supporting device capable of realizing rapid installation for building and installation method thereof

Country Status (1)

Country Link
CN (1) CN109469303B (en)

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20040077623A (en) * 2004-08-16 2004-09-04 김석윤 Pipe fixing system
CN101649679A (en) * 2008-08-15 2010-02-17 李世源 Height regulating device of support frame for building
CN104493971A (en) * 2014-12-12 2015-04-08 武汉工程大学 Artificial rock core casting mold with supporting mechanism
CN206971679U (en) * 2017-05-25 2018-02-06 胡瑞国 A kind of safe anti-falling scaffold
CN207263174U (en) * 2017-04-10 2018-04-20 广东孛特勘测设计有限公司 A kind of engineering mapping surveying instrument positioner
CN207332351U (en) * 2017-07-12 2018-05-08 北京众享智选科技有限公司 A kind of novel building ergonomic support device
CN207420003U (en) * 2017-11-18 2018-05-29 广东东森金属门窗有限公司 A kind of new scaffold Tiebar structure for civil construction project
CN207847031U (en) * 2018-02-08 2018-09-11 山东国建工程集团有限公司 A kind of supporting rack of construction site portable scaffold
CN208025082U (en) * 2018-02-08 2018-10-30 林新海 A kind of mapping auxiliary device
CN208158321U (en) * 2018-05-25 2018-11-27 江西力玛机电科技有限公司 A kind of motor damping device
CN208294055U (en) * 2018-05-09 2018-12-28 永春县品冠科技有限公司 A kind of scaffold firm banking convenient for fixing and having anticollision effect
CN209413254U (en) * 2018-12-29 2019-09-20 黄河水利职业技术学院 A kind of precast support device of achievable Fast Installation for building

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20040077623A (en) * 2004-08-16 2004-09-04 김석윤 Pipe fixing system
CN101649679A (en) * 2008-08-15 2010-02-17 李世源 Height regulating device of support frame for building
CN104493971A (en) * 2014-12-12 2015-04-08 武汉工程大学 Artificial rock core casting mold with supporting mechanism
CN207263174U (en) * 2017-04-10 2018-04-20 广东孛特勘测设计有限公司 A kind of engineering mapping surveying instrument positioner
CN206971679U (en) * 2017-05-25 2018-02-06 胡瑞国 A kind of safe anti-falling scaffold
CN207332351U (en) * 2017-07-12 2018-05-08 北京众享智选科技有限公司 A kind of novel building ergonomic support device
CN207420003U (en) * 2017-11-18 2018-05-29 广东东森金属门窗有限公司 A kind of new scaffold Tiebar structure for civil construction project
CN207847031U (en) * 2018-02-08 2018-09-11 山东国建工程集团有限公司 A kind of supporting rack of construction site portable scaffold
CN208025082U (en) * 2018-02-08 2018-10-30 林新海 A kind of mapping auxiliary device
CN208294055U (en) * 2018-05-09 2018-12-28 永春县品冠科技有限公司 A kind of scaffold firm banking convenient for fixing and having anticollision effect
CN208158321U (en) * 2018-05-25 2018-11-27 江西力玛机电科技有限公司 A kind of motor damping device
CN209413254U (en) * 2018-12-29 2019-09-20 黄河水利职业技术学院 A kind of precast support device of achievable Fast Installation for building

Also Published As

Publication number Publication date
CN109469303B (en) 2024-03-12

Similar Documents

Publication Publication Date Title
CN104264883A (en) Concrete slab reserved hole structure and construction method thereof
CN104278840A (en) Decorating bare concrete construction method and split bolt hole die for same
CN209413254U (en) A kind of precast support device of achievable Fast Installation for building
CN205089345U (en) Anchor rope is put by pressure equipment
CN109469303A (en) A kind of the precast support device and its installation method of achievable Fast Installation for building
CN203878941U (en) Ground-mounted lifting rod device
CN102653947B (en) Underground embedded steel component limiting straightening construction method
CN203499212U (en) Hoisting structure for curved aluminum circular tube
WO2018086509A1 (en) Methods for mounting and erecting mechanical constant-resistance single prop
CN211194387U (en) Prefabricated bent cap grout bellows positioner
CN204061461U (en) EXPANSION ANCHOR BOLTS embedded part
CN203961171U (en) Without the full glass console mode of column handrail base
CN206971931U (en) A kind of prefabricated assembled isolated column
CN205330172U (en) A formwork support device that is used for wall body corner position to be under construction
CN206681375U (en) Thrust block installation system
CN215629931U (en) Spray anchor supporting device for constructional engineering construction
CN204152205U (en) Decoration exposed concrete construction method split bolt punch die used
CN204458719U (en) A kind of EXPANSION ANCHOR BOLTS effectively can avoiding getting loose
CN216142458U (en) Independent strutting arrangement of post-cast strip of adjustable support height
CN218747525U (en) Hang convenient instrument of muscle installation
CN218633079U (en) Electric wire strutting arrangement is faced to building
CN216516828U (en) Triangular overhanging support base for slip form
CN220100722U (en) Quality control structure for steel structure building construction
CN215291024U (en) Rainwater hopper with adjustable installation height
CN217631371U (en) Building embedded part

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant