CN109469263B - Quantitative grouting construction process for steel bar sleeve - Google Patents

Quantitative grouting construction process for steel bar sleeve Download PDF

Info

Publication number
CN109469263B
CN109469263B CN201811297910.5A CN201811297910A CN109469263B CN 109469263 B CN109469263 B CN 109469263B CN 201811297910 A CN201811297910 A CN 201811297910A CN 109469263 B CN109469263 B CN 109469263B
Authority
CN
China
Prior art keywords
grouting
sleeve
quantitative
construction process
base surface
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201811297910.5A
Other languages
Chinese (zh)
Other versions
CN109469263A (en
Inventor
陆近涛
高路恒
钱野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nantong Textile Vocational Technology College
Original Assignee
Nantong Textile Vocational Technology College
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nantong Textile Vocational Technology College filed Critical Nantong Textile Vocational Technology College
Priority to CN201811297910.5A priority Critical patent/CN109469263B/en
Publication of CN109469263A publication Critical patent/CN109469263A/en
Application granted granted Critical
Publication of CN109469263B publication Critical patent/CN109469263B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/16Auxiliary parts for reinforcements, e.g. connectors, spacers, stirrups
    • E04C5/162Connectors or means for connecting parts for reinforcements
    • E04C5/163Connectors or means for connecting parts for reinforcements the reinforcements running in one single direction
    • E04C5/165Coaxial connection by means of sleeves

Abstract

The invention discloses a quantitative grouting construction process for a steel bar sleeve, which comprises the following steps: (1) preparing in the early stage; (2) preparing grouting material: mixing according to a mixing ratio provided by a manufacturer, and adopting warm water or auxiliary cooling measures when the natural temperature is lower than 5 ℃ or higher than 30 ℃; (3) and (3) treatment of a connection base surface: cleaning impurities such as dust and the like on a connection base surface by using an air gun before hoisting the prefabricated part, uniformly spraying water on the base surface to keep a wet state, and brushing a layer of interface agent on the surface of concrete and then carrying out setting grout treatment by using grouting material; (4) grouting operation and grouting amount control: when formal grouting is carried out, a grouting pump is used for grouting the grouting amount determined by the test from the lower opening of the sleeve; (5) and (3) maintaining after grouting: and protecting the connecting area of the components by using the enclosure facilities after grouting is finished. The construction process adopts a quantitative sleeve filling mode, guarantees the quantity and compactness of the slurry in the sleeve in each grouting, and avoids the hidden sleeve quality trouble caused by leakage of bubbles, holes, slurry and other reasons in the sleeve.

Description

Quantitative grouting construction process for steel bar sleeve
Technical Field
The invention relates to a grouting construction process, in particular to a quantitative grouting construction process for a steel bar sleeve.
Background
In the construction of prefabricated building elements, sleeve grouting is a common element connection method. The steel bar sleeve is embedded in a building component, and when the steel bar sleeve is connected with other components, the steel bar sleeve is inserted into the sleeve through embedded steel bars and slurry is poured into the sleeve to form strength so as to realize component connection. The construction quality of the steel bar sleeve is crucial to the performance of the fabricated building structure, grouting construction belongs to a concealed project, and the grouting in the sleeve is difficult to ensure only by observing the grout outlet mode.
Disclosure of Invention
The purpose of the invention is as follows: aiming at the defects in the prior art, the invention provides a quantitative grouting construction process for a steel bar sleeve, which adopts a quantitative sleeve grouting mode to ensure the quantity and compactness of grout in the sleeve at each time of grouting and avoid the hidden danger of sleeve quality caused by bubbles, holes, grout leakage and the like in the sleeve.
The technical scheme is as follows: the invention relates to a quantitative grouting construction process for a steel bar sleeve, which comprises the following steps:
(1) early preparation work: calculating the grouting amount required by one sleeve or one grouting operation according to the specifications of the grouting sleeve and the conveying pipe used for construction;
(2) preparing grouting material: mixing according to a mixing ratio provided by a manufacturer, adopting warm water or an auxiliary cooling measure when the natural temperature is lower than 5 ℃ or higher than 30 ℃, controlling the stirring speed from slow to fast, slowing down the speed for about 90s when the stirring is finished, and continuously stirring in the whole process to reduce the generation of bubbles; the grouting pump is provided with a quantitative control module and a pressure gauge to realize quantitative grouting, and a grouting test is carried out on site to determine the optimal grouting amount;
(3) and (3) treatment of a connection base surface: cleaning impurities such as dust, broken stones and the like at a connection base surface by using an air gun before hoisting the prefabricated part, uniformly spraying water on the base surface to keep a wet state, brushing a layer of interface agent on the surface of concrete, and then carrying out base grouting treatment by using grouting material, wherein the thickness of the base grouting material is 1.0-1.5cm, the base grouting material is fully paved along the long edge of the prefabricated part to form a rectangular shape, and the edge slightly protrudes by about 3-5 mm; before the prefabricated part is hoisted, wetting and brushing an interface agent on the connecting surface of the prefabricated part by using water, keeping the prefabricated part naturally and slowly fall to the connecting surface during hoisting, not shaking the prefabricated part, and after the prefabricated part is installed in place, carrying out one-time smearing on the peripheral seams to enhance the sealing effect;
(4) grouting operation and grouting amount control: when formal grouting is carried out, a grouting pump is used for grouting the grouting amount determined by the test from the lower opening of the sleeve, when the grout overflows from the grout outlet, the grout outlet is incompletely blocked by a rubber plug, about 1/4-area gaps are reserved for exhausting gas, bubbles and holes in the sleeve are eliminated under the action of pressure, and the grout outlet is completely blocked until a preset amount is poured; controlling the time within 45min from the completion of the preparation of the grouting material to the completion of the pouring;
(5) and (3) maintaining after grouting: after grouting is finished, the enclosure facility is used for protecting the connecting area of the components, vibration construction load cannot exist in the adjacent two-layer building structure within 48h, and the temporary support and the enclosure facility are removed after the joint strength reaches 80% of design strength.
Further, the stirring speed of the blade for stirring the grouting material in the step (2) is kept at 110-150 r/mi.
Further, the grouting speed in the step (4) is controlled to be 0.8-1.0L/min.
And (3) further, in the pouring process in the step (4), if slurry leakage at the position of the connecting base surface is found, stopping pouring, caulking by using the PE sponge strip and the polysulfide sealant according to the leakage condition, and continuing the grouting operation after the sealing is in place.
Has the advantages that: the construction process adopts a quantitative sleeve filling mode, guarantees the quantity and compactness of the slurry in the sleeve in each grouting, and avoids the hidden sleeve quality trouble caused by leakage of bubbles, holes, slurry and other reasons in the sleeve.
Detailed Description
The invention will be further illustrated with reference to specific examples:
example 1
A quantitative grouting construction process for a steel bar sleeve comprises the following steps:
(1) early preparation work: calculating the grouting amount required by one sleeve or one grouting operation according to the specifications of the grouting sleeve and the conveying pipe used for construction;
(2) preparing grouting material: mixing according to a mixing ratio provided by a manufacturer, and adopting warm water or auxiliary cooling measures when the natural temperature is lower than 5 ℃ or higher than 30 ℃; the stirring speed of the blades is kept at 110r/mi, the stirring speed is controlled from slow to fast, the speed is slowed down for about 90s when the fast stirring is finished, and the bubbles are reduced by the whole process of continuous stirring; the grouting pump is provided with a quantitative control module and a pressure gauge to realize quantitative grouting, and a grouting test is carried out on site to determine the optimal grouting amount;
(3) and (3) treatment of a connection base surface: cleaning impurities such as dust, broken stones and the like at a connection base surface by using an air gun before hoisting the prefabricated part, uniformly spraying water on the base surface to keep a wet state, brushing a layer of interface agent on the surface of concrete, and then carrying out base grouting treatment by using grouting material, wherein the thickness of the base grouting material is 1.0cm, the base grouting material is fully paved along the long edge of the prefabricated part to form a rectangular shape, and the edge slightly protrudes by about 3 mm; before the prefabricated part is hoisted, wetting and brushing an interface agent on the connecting surface of the prefabricated part by using water, keeping the prefabricated part naturally and slowly fall to the connecting surface during hoisting, not shaking the prefabricated part, and after the prefabricated part is installed in place, carrying out one-time smearing on the peripheral seams to enhance the sealing effect;
(4) grouting operation and grouting amount control: when formal grouting is carried out, a grouting pump is used for grouting the grouting amount determined by the test from the lower opening of the sleeve, the grouting speed is controlled to be 0.8L/min, when the grout overflows from the grout outlet, a rubber plug is used for incompletely plugging the grout outlet, about 1/4-area gaps are reserved for exhausting gas, bubbles and holes in the sleeve are eliminated under the pressure action, and the grout outlet is completely plugged after the preset amount is poured; controlling the time within 45min from the completion of the preparation of the grouting material to the completion of the pouring; if slurry leaks from the connecting base surface in the pouring process, stopping pouring, caulking by using a PE sponge strip and polysulfide sealant according to the leakage condition, and continuing the grouting operation after the sealing is in place;
(5) and (3) maintaining after grouting: after grouting is finished, the enclosure facility is used for protecting the connecting area of the components, vibration construction load cannot exist in the adjacent two-layer building structure within 48h, and the temporary support and the enclosure facility are removed after the joint strength reaches 80% of design strength.
Example 2
A quantitative grouting construction process for a steel bar sleeve comprises the following steps:
(1) early preparation work: calculating the grouting amount required by one sleeve or one grouting operation according to the specifications of the grouting sleeve and the conveying pipe used for construction;
(2) preparing grouting material: mixing according to a mixing ratio provided by a manufacturer, and adopting warm water or auxiliary cooling measures when the natural temperature is lower than 5 ℃ or higher than 30 ℃; the stirring speed of the blades is kept at 150r/mi, the stirring speed is controlled from slow to fast, the speed is slowed down for about 90s when the fast stirring is finished, and the bubbles are reduced by the whole process of continuous stirring; the grouting pump is provided with a quantitative control module and a pressure gauge to realize quantitative grouting, and a grouting test is carried out on site to determine the optimal grouting amount;
(3) and (3) treatment of a connection base surface: cleaning impurities such as dust, broken stones and the like at a connection base surface by using an air gun before hoisting the prefabricated part, uniformly spraying water on the base surface to keep a wet state, brushing a layer of interface agent on the surface of concrete, and then carrying out base grouting treatment by using grouting material, wherein the thickness of the base grouting material is 1.5cm, the base grouting material is fully paved along the long edge of the prefabricated part to form a rectangular shape, and the edge slightly protrudes by about 5 mm; before the prefabricated part is hoisted, wetting and brushing an interface agent on the connecting surface of the prefabricated part by using water, keeping the prefabricated part naturally and slowly fall to the connecting surface during hoisting, not shaking the prefabricated part, and after the prefabricated part is installed in place, carrying out one-time smearing on the peripheral seams to enhance the sealing effect;
(4) grouting operation and grouting amount control: when formal grouting is carried out, a grouting pump is used for grouting the grouting amount determined by the test from the lower opening of the sleeve, the grouting speed is controlled to be 1.0L/min, when the grout overflows from the grout outlet, a rubber plug is used for incompletely plugging the grout outlet, about 1/4-area gaps are reserved for exhausting gas, bubbles and holes in the sleeve are eliminated under the pressure action, and the grout outlet is completely plugged after the preset amount is poured; controlling the time within 45min from the completion of the preparation of the grouting material to the completion of the pouring; if slurry leaks from the connecting base surface in the pouring process, stopping pouring, caulking by using a PE sponge strip and polysulfide sealant according to the leakage condition, and continuing the grouting operation after the sealing is in place;
(5) and (3) maintaining after grouting: after grouting is finished, the enclosure facility is used for protecting the connecting area of the components, vibration construction load cannot exist in the adjacent two-layer building structure within 48h, and the temporary support and the enclosure facility are removed after the joint strength reaches 80% of design strength.
Example 3
A quantitative grouting construction process for a steel bar sleeve comprises the following steps:
(1) early preparation work: calculating the grouting amount required by one sleeve or one grouting operation according to the specifications of the grouting sleeve and the conveying pipe used for construction;
(2) preparing grouting material: mixing according to a mixing ratio provided by a manufacturer, and adopting warm water or auxiliary cooling measures when the natural temperature is lower than 5 ℃ or higher than 30 ℃; the stirring speed of the blades is kept at 130r/mi, the stirring speed is controlled from slow to fast, the speed is slowed down for about 90s when the fast stirring is finished, and the bubbles are reduced by the whole process of continuous stirring; the grouting pump is provided with a quantitative control module and a pressure gauge to realize quantitative grouting, and a grouting test is carried out on site to determine the optimal grouting amount;
(3) and (3) treatment of a connection base surface: cleaning impurities such as dust, broken stones and the like at a connection base surface by using an air gun before hoisting the prefabricated part, uniformly spraying water on the base surface to keep a wet state, brushing a layer of interface agent on the surface of concrete, and then carrying out base grouting treatment by using grouting material, wherein the thickness of the base grouting material is 1.2cm, the base grouting material is fully paved along the long edge of the prefabricated part to form a rectangular shape, and the edge slightly protrudes by about 4 mm; before the prefabricated part is hoisted, wetting and brushing an interface agent on the connecting surface of the prefabricated part by using water, keeping the prefabricated part naturally and slowly fall to the connecting surface during hoisting, not shaking the prefabricated part, and after the prefabricated part is installed in place, carrying out one-time smearing on the peripheral seams to enhance the sealing effect;
(4) grouting operation and grouting amount control: when formal grouting is carried out, a grouting pump is used for grouting the grouting amount determined by the test from the lower opening of the sleeve, the grouting speed is controlled to be 0.9L/min, when the grout overflows from the grout outlet, a rubber plug is used for incompletely plugging the grout outlet, about 1/4-area gaps are reserved for exhausting gas, bubbles and holes in the sleeve are eliminated under the pressure action, and the grout outlet is completely plugged after the preset amount is poured; controlling the time within 45min from the completion of the preparation of the grouting material to the completion of the pouring; if slurry leaks from the connecting base surface in the pouring process, stopping pouring, caulking by using a PE sponge strip and polysulfide sealant according to the leakage condition, and continuing the grouting operation after the sealing is in place;
(5) and (3) maintaining after grouting: after grouting is finished, the enclosure facility is used for protecting the connecting area of the components, vibration construction load cannot exist in the adjacent two-layer building structure within 48h, and the temporary support and the enclosure facility are removed after the joint strength reaches 80% of design strength.
The construction process adopts a quantitative sleeve filling mode, guarantees the quantity and compactness of the slurry in the sleeve in each grouting, and avoids the hidden sleeve quality trouble caused by leakage of bubbles, holes, slurry and other reasons in the sleeve.
Although the present invention has been described with reference to a preferred embodiment, it should be understood that various changes, substitutions and alterations can be made herein without departing from the spirit and scope of the invention as defined by the appended claims.

Claims (4)

1. The quantitative grouting construction process for the steel bar sleeve is characterized by comprising the following steps of: the method comprises the following steps:
(1) early preparation work: calculating the grouting amount required by one sleeve or one grouting operation according to the specifications of the grouting sleeve and the conveying pipe used for construction;
(2) preparing grouting material: mixing according to the mixture ratio provided by a manufacturer, and when the natural temperature is lower than 5 ℃, adopting warm water; when the natural temperature exceeds 30 ℃, an auxiliary cooling measure is adopted, the stirring speed is controlled from slow to fast, the speed is slowed down for 90s when the fast stirring is finished, and the bubbles are reduced by the whole continuous stirring; the grouting pump is provided with a quantitative control module and a pressure gauge to realize quantitative grouting, and a grouting test is carried out on site to determine the optimal grouting amount;
(3) and (3) treatment of a connection base surface: cleaning dust and gravels at the connection base surface by using an air gun before hoisting the prefabricated member, uniformly spraying water on the base surface to keep a wet state, brushing a layer of interface agent on the surface of concrete, and then carrying out base grouting treatment by using grouting material, wherein the thickness of the base grouting material is 1.0-1.5cm, the base grouting material is fully paved along the long edge of the member to form a rectangular shape, and the edge slightly protrudes by 3-5 mm; during hoisting, the component is kept to naturally and slowly fall to the connecting surface without shaking, and after the component is installed in place, one-time smearing and pressing are carried out on the peripheral seams to enhance the sealing effect;
(4) grouting operation and grouting amount control: when formal grouting is carried out, a grouting pump is used for grouting the grouting amount determined by the test from the lower opening of the sleeve, when grout overflows from the grout outlet, the grout outlet is incompletely blocked by a rubber plug, a 1/4-area gap is reserved to remove gas, bubbles and holes in the sleeve are eliminated under the action of pressure, and the grout outlet is completely blocked until a preset amount is poured; controlling the time within 45min from the completion of the preparation of the grouting material to the completion of the pouring;
(5) and (3) maintaining after grouting: after grouting is finished, the enclosure facility is used for protecting the connecting area of the components, vibration construction load cannot exist in the adjacent two-layer building structure within 48h, and the temporary support and the enclosure facility are removed after the joint strength reaches 80% of design strength.
2. The quantitative grouting construction process for the steel sleeve according to claim 1, wherein the grouting construction process comprises the following steps: the stirring speed of the blade stirred by the grouting material in the step (2) is kept at 110-150 r/min.
3. The quantitative grouting construction process for the steel sleeve according to claim 1, wherein the grouting construction process comprises the following steps: and (4) controlling the grouting speed in the pouring process in the step (4) to be 0.8-1.0L/min.
4. The quantitative grouting construction process for the steel sleeve according to claim 1, wherein the grouting construction process comprises the following steps: and (4) if slurry leaks from the connecting base surface in the filling process, suspending filling, caulking by using a PE sponge strip and polysulfide sealant according to the leakage condition, and continuing the grouting operation after the sealing is in place.
CN201811297910.5A 2018-11-02 2018-11-02 Quantitative grouting construction process for steel bar sleeve Active CN109469263B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811297910.5A CN109469263B (en) 2018-11-02 2018-11-02 Quantitative grouting construction process for steel bar sleeve

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811297910.5A CN109469263B (en) 2018-11-02 2018-11-02 Quantitative grouting construction process for steel bar sleeve

Publications (2)

Publication Number Publication Date
CN109469263A CN109469263A (en) 2019-03-15
CN109469263B true CN109469263B (en) 2021-01-08

Family

ID=65672305

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811297910.5A Active CN109469263B (en) 2018-11-02 2018-11-02 Quantitative grouting construction process for steel bar sleeve

Country Status (1)

Country Link
CN (1) CN109469263B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110700589A (en) * 2019-10-22 2020-01-17 武汉合创炬盛科技有限公司 Method for improving compactness of assembly type concrete grouting connection node
CN114250976B (en) * 2022-01-19 2023-04-07 江苏方建质量鉴定检测有限公司 Nondestructive slurry supplementing construction method for realizing slurry return at cavity bottom by using double-cavity compensator

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103726653A (en) * 2014-01-08 2014-04-16 成军 Full-prefabricated structure column steel sleeve cylinder grouting connecting construction method
CN108035493A (en) * 2018-01-31 2018-05-15 合肥建工集团有限公司 A kind of antidetonation assembles half grout sleeve of self-locking
CN108316565A (en) * 2018-04-27 2018-07-24 中民筑友科技投资有限公司 A kind of grout sleeve component
CN108590189A (en) * 2018-05-30 2018-09-28 宁波普利凯建筑科技有限公司 A kind of provisions for grouting and its construction method of prefabricated components

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20100031607A1 (en) * 2008-08-11 2010-02-11 Oliva Michael G Splice System for Fiber-Reinforced Polymer Rebars

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103726653A (en) * 2014-01-08 2014-04-16 成军 Full-prefabricated structure column steel sleeve cylinder grouting connecting construction method
CN108035493A (en) * 2018-01-31 2018-05-15 合肥建工集团有限公司 A kind of antidetonation assembles half grout sleeve of self-locking
CN108316565A (en) * 2018-04-27 2018-07-24 中民筑友科技投资有限公司 A kind of grout sleeve component
CN108590189A (en) * 2018-05-30 2018-09-28 宁波普利凯建筑科技有限公司 A kind of provisions for grouting and its construction method of prefabricated components

Also Published As

Publication number Publication date
CN109469263A (en) 2019-03-15

Similar Documents

Publication Publication Date Title
CN104119101B (en) Cast-in-placely build light foam concrete construction technology
CN109469263B (en) Quantitative grouting construction process for steel bar sleeve
CN108252530B (en) Parapet leakage water repairing process
CN103343655B (en) Wall window construction method
KR100992952B1 (en) Complex waterproofing structure and construction method which use Low melting point polymer modified asphalt Waterproof material and silica sheet
CN108374566B (en) Repairing process for leakage water on back water surface
CN103015721B (en) Leakage prevention construction method of reserved holes in kitchen and toilet
CN209277342U (en) A kind of Novel free tears composite thermal-insulating exterior formwork system open
CN105464243A (en) Thin-layer mortar masonry method for autoclaved aerated accurate blocks
CN109629845A (en) Concrete structure seam areas leakage treatment device and its construction method
CN106760080B (en) Postposition concrete heat-insulating Curtainwall connector and construction method
CN103613339A (en) Special adhering and sealing material for cement-based mosaic tile and preparation and using method thereof
CN110359677A (en) External wall in-situ spraying polyurethane foamed thermal-insulating construction technology
CN104499614A (en) Wall heat-preservation integration point hanging system and mounting method thereof
WO2020004434A1 (en) Concrete reforming method and reforming material
CN104343246B (en) A kind of method of waterproofing and leakage-stopping
CN110409600A (en) Unit-combination type cesspool construction method
CN105545006A (en) HF-3 double-component polysulfide building sealant crack repairing method
CN214462853U (en) Self-healing concrete micro-crack repairing structure
CN105859185B (en) A kind of high-efficiency wall repairing marine glue
CN213539105U (en) A leaking stoppage structure for deep basal pit basement outer wall crack
CN213539598U (en) Z-shaped support mounting device for preventing bearing part from cracking in finished product flue
CN212176341U (en) Side income formula rainwater fill construction structures
CN110528593B (en) Heat-insulation waterproof structure for joint of main body and auxiliary structure top plate of station and construction method
CN115182612B (en) Method for repairing structural cracks without damaging existing decoration layer and waterproof layer

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant