CN213539105U - A leaking stoppage structure for deep basal pit basement outer wall crack - Google Patents

A leaking stoppage structure for deep basal pit basement outer wall crack Download PDF

Info

Publication number
CN213539105U
CN213539105U CN202022005628.4U CN202022005628U CN213539105U CN 213539105 U CN213539105 U CN 213539105U CN 202022005628 U CN202022005628 U CN 202022005628U CN 213539105 U CN213539105 U CN 213539105U
Authority
CN
China
Prior art keywords
grouting
layer
leaking stoppage
filling groove
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202022005628.4U
Other languages
Chinese (zh)
Inventor
李骏毅
李金洋
唐颖
罗志斌
李洋
张智
吴辉
金文渊
谭沙奇
李倩
李琼霞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Jiangong No11 Building Engineering Co ltd
Chongqing Construction Engineering Group Co Ltd
Original Assignee
Chongqing Jiangong No11 Building Engineering Co ltd
Chongqing Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing Jiangong No11 Building Engineering Co ltd, Chongqing Construction Engineering Group Co Ltd filed Critical Chongqing Jiangong No11 Building Engineering Co ltd
Priority to CN202022005628.4U priority Critical patent/CN213539105U/en
Application granted granted Critical
Publication of CN213539105U publication Critical patent/CN213539105U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Building Environments (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

The utility model provides a be used for fissured leaking stoppage structure of deep basal pit basement outer wall relates to the technical field of the fissured leaking stoppage construction of wall body, and it is used for forming the seal of airtight cavity with the filling groove including fixing in the filling groove, installs the slip casting mouth that runs through its both sides on the seal, and it has the grout blanket that is used for restoreing the fracture to fill between the tank bottom in seal and filling groove. The grouting nozzle is embedded in the closed layer, so that the work of taking out the grouting nozzle is reduced, and the construction period is shortened.

Description

A leaking stoppage structure for deep basal pit basement outer wall crack
Technical Field
The utility model relates to a technical field of the fissured leaking stoppage construction of wall body especially relates to a be used for fissured leaking stoppage structure of deep basal pit basement outer wall.
Background
The reinforced concrete building is easy to crack, and under the condition that the building cracks cannot be eliminated, the influence of the building cracks on the building function and the attractiveness is reduced, the reduction of the structural safety caused by the building cracks is avoided, and the reinforcement is particularly important for the treatment of the existing cracks.
The construction mode of the prior art is to use a gel waterproof material for plugging, and after plugging is finished, a water stopping needle head needs to be removed, so that the construction period is long.
SUMMERY OF THE UTILITY MODEL
Aiming at the defects in the prior art, the scheme provides the leaking stoppage structure for the outer wall cracks of the basement of the deep foundation pit, and the leaking stoppage structure has the effect of saving the construction period.
According to the utility model discloses an embodiment, a leaking stoppage structure for deep basal pit basement outer wall crack, including fixing the seal that is used for forming airtight cavity with the filling groove in the filling groove, install the slip casting mouth that runs through its both sides on the seal, it has the grout blanket that is used for restoreing the crack to fill between the tank bottom of seal and filling groove.
By the technical scheme, the sealing layer seals the filling groove to form a closed cavity so as to bear the grouting pressure higher than the normal atmospheric pressure during grouting; the grouting nozzle is formed on the closed layer, and the grouting nozzle is directly plugged after grouting is completed, so that the erasing process is reduced, the construction time is shortened, and the whole construction period is shortened.
Preferably, the grouting nozzle comprises a grouting pipe and a positioning plate arranged on the grouting pipe, and the length direction of the grouting pipe is perpendicular to the main plane of the positioning plate.
Through above technical scheme, when the construction, in order to reduce the possibility that can't form airtight cavity with filling in the seam when preparation closed bed, the hose has been preset at the tank bottom of filling the groove, and the locating plate is used for butt location hose, reduces the possibility that the hose takes place to shift when preparation closed bed.
Preferably, one side of the sealing layer close to the notch of the filling groove is covered with a waterproof layer.
Through above technical scheme, the waterproof layer is used for reducing the possibility that flowing water such as rainwater outside the wall body permeates the airtight layer and flows into the building wall body.
Preferably, the closed layer is made of LB-8 quick-hardening cement.
By adopting the technical scheme, the forming time of the closed layer can be shortened by adopting the quick-drying cement, and the construction period is further shortened.
Preferably, the grouting layer is made of LB-7 neoprene latex polymer cement slurry.
Through the technical scheme, the cement paste enables the structure of the scheme to have higher waterproofness, and the possibility that running water or seepage water enters the inside of the wall body is further reduced.
Preferably, the waterproof layer is made of LB-21 epoxy emulsion daub.
Through the technical scheme, compared with the common waterproof material, the waterproof material has higher waterproof property.
Compared with the prior art, the utility model discloses one of following beneficial effect has at least:
1. the grouting nozzle and the structure arranged in the sealing layer reduce the work of dismantling the grouting nozzle after grouting is finished, and shorten the construction period;
2. the closed layer made of the quick-hardening cement can be formed more quickly, so that the construction period is further shortened;
3. the use of a waterproof filler layer and an outermost waterproof layer provides the structure with improved waterproof properties.
Drawings
FIG. 1 is a schematic overall structure of the present application;
fig. 2 is a structural schematic diagram of the installation relationship between the grouting nozzle and the hose.
In the above drawings: 1. a sealing layer; 2. a grouting nozzle; 21. a grouting pipe; 22. positioning a plate; 3. grouting layer; 4. a waterproof layer; 5. a wall body; 51. filling the groove; 6. a hose.
Detailed Description
The technical solution of the present invention will be further explained with reference to the accompanying drawings and embodiments.
A leaking stoppage structure for a crack of an outer wall of a basement of a deep foundation pit refers to fig. 1 and comprises a sealing layer 1 fixed at an opening of a filling groove 51 and a grouting nozzle 2 arranged on the sealing layer 1, wherein the sealing layer 1 and the filling groove 51 form a closed cavity so as to bear high-pressure slurry.
The sealing layer 1 is made of LB-8 quick-hardening cement purchased in the market, so that the forming speed of the sealing layer 1 is higher, and the construction period is shortened. The grouting nozzle 2 comprises a grouting pipe 21 and a positioning plate 22 arranged on the grouting pipe 21, the positioning plate 22 is positioned on one side of the grouting pipe 21 close to the bottom of the filling groove 51, when the sealing layer 1 is manufactured by sealing and plastering, the grouting nozzle 2 is installed stably, and the grouting nozzle 2 is formed on the sealing layer 1.
The sealing layer 1 and the filling groove 51 are filled with high-pressure slurry to form a grouting layer 3, the grouting layer 3 is LB-7 neoprene latex polymer cement slurry, the LB-7 neoprene latex polymer cement slurry is prepared by uniformly mixing LB-7 neoprene latex cement slurry waterproof agents purchased from the market and cement slurry in a certain proportion, the cement slurry has the repairing effect and the waterproof property, the possibility that water on the outer side of the wall body permeates into the wall body is reduced, and the wall body can be better protected.
The waterproof layer 4 is laid on one side, far away from the grouting layer 3, of the sealing layer 1, the waterproof layer 4 is made of LB-21 epoxy emulsion daub purchased through the market, the waterproof material has better waterproofness, and the cost performance of the plugging structure is higher on the premise that waterproof conditions are guaranteed.
The application relates to a construction principle of a leaking stoppage structure for a deep foundation pit basement outer wall crack, which comprises the following steps: referring to fig. 2, a filling groove 51 is formed in the inner joint of the wall 5 along the length direction of the crack, and the filling groove 51 has a V-shaped cross section to clean concrete residues in the filling groove.
Laying the hose 6 at the bottom of the filling groove 51 along the length direction of the filling groove 51, installing a plurality of grouting nozzles 2 in the filling groove 51 at intervals, and sealing and smearing by using quick-setting cement to form a closed layer 1; when the sealing layer 1 is formed, the hose 6 is drawn out, the sealing layer 1 and the filling groove 51 form a closed cavity, and the end part of the grouting pipe 21 close to the positioning plate 22 is abutted against the hose 6 when the grouting nozzle 2 is installed, so that the grouting nozzle 2 is ensured to be communicated with the closed cavity.
The grouting nozzle 2 is communicated with a high-pressure grouting machine, high-pressure LB-7 neoprene latex polymer cement slurry is injected into the closed cavity to form a grouting layer 3, and due to the fact that the capillary cracks of the wall body are communicated with the filling groove 51, fillers enter the capillary cracks under high pressure, and the reinforcing effect of the crack positions of the wall body is good.
And after the sealed cavity is filled with the grout, the high-pressure grouting machine is disconnected, and the grouting nozzle 2 is bent and sealed, so that the possibility of the backflow of the grout in the cavity is reduced.
The waterproof layer 4 is coated on the outer side of the sealing layer 1, so that the sealing structure has higher waterproof performance.
When the sealing layer 1 is manufactured, a certain distance can be reserved between the sealing layer 1 and the notch of the filling groove 51, so that the filling plane height can be adjusted for leveling during secondary filling.
Finally, although the present invention has been described in detail with reference to the preferred embodiments, it should be understood by those skilled in the art that the present invention can be modified or replaced by other means without departing from the spirit and scope of the present invention, which should be construed as limited only by the appended claims.

Claims (6)

1. The utility model provides a leak stoppage structure for deep basal pit basement outer wall crack which characterized in that: the crack repairing device comprises a sealing layer (1) which is fixed in a filling groove (51) and used for forming a closed cavity with the filling groove (51), grouting nozzles (2) penetrating through two sides of the sealing layer (1) are installed on the sealing layer (1), and a grouting layer (3) used for repairing cracks is filled between the sealing layer (1) and the bottom of the filling groove (51).
2. The leaking stoppage structure for the cracks of the outer wall of the basement of the deep foundation pit as claimed in claim 1, is characterized in that: the grouting nozzle (2) comprises a grouting pipe (21) and a positioning plate (22) arranged on the grouting pipe (21), and the length direction of the grouting pipe (21) is perpendicular to the main plane of the positioning plate (22).
3. The leaking stoppage structure for the cracks of the outer wall of the basement of the deep foundation pit as claimed in claim 1, is characterized in that: and a waterproof layer (4) covers one side of the closed layer (1) close to the notch of the filling groove (51).
4. The leaking stoppage structure for the cracks of the outer wall of the basement of the deep foundation pit as claimed in claim 1, is characterized in that: the sealing layer (1) is made of LB-8 quick-hardening cement.
5. The leaking stoppage structure for the cracks of the outer wall of the basement of the deep foundation pit as claimed in claim 1, is characterized in that: the grouting layer (3) is made of LB-7 neoprene latex polymer cement slurry.
6. The leaking stoppage structure for the cracks of the outer wall of the basement of the deep foundation pit as claimed in claim 3, is characterized in that: the waterproof layer (4) is made of LB-21 epoxy emulsion daub.
CN202022005628.4U 2020-09-14 2020-09-14 A leaking stoppage structure for deep basal pit basement outer wall crack Expired - Fee Related CN213539105U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022005628.4U CN213539105U (en) 2020-09-14 2020-09-14 A leaking stoppage structure for deep basal pit basement outer wall crack

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022005628.4U CN213539105U (en) 2020-09-14 2020-09-14 A leaking stoppage structure for deep basal pit basement outer wall crack

Publications (1)

Publication Number Publication Date
CN213539105U true CN213539105U (en) 2021-06-25

Family

ID=76492063

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022005628.4U Expired - Fee Related CN213539105U (en) 2020-09-14 2020-09-14 A leaking stoppage structure for deep basal pit basement outer wall crack

Country Status (1)

Country Link
CN (1) CN213539105U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113958148A (en) * 2021-11-15 2022-01-21 广东科顺修缮建筑技术有限公司 Groove for repairing cracks of back pressure water leakage and grooving process and application thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113958148A (en) * 2021-11-15 2022-01-21 广东科顺修缮建筑技术有限公司 Groove for repairing cracks of back pressure water leakage and grooving process and application thereof

Similar Documents

Publication Publication Date Title
CN108517899A (en) Mouth high-pressure grouting leak stopping processing method is buried in the leakage drilling of deep basal pit diaphram wall
CN108166517B (en) Well sealing method and well sealing device for super high-rise high-water pressure deep well dewatering well
CN205557856U (en) Leakage structure is prevented at building expansion joint
CN109629845A (en) Concrete structure seam areas leakage treatment device and its construction method
CN213539105U (en) A leaking stoppage structure for deep basal pit basement outer wall crack
CN109853629A (en) A kind of sole plate anti-seepage construction method, architecture construction platform
CN110952644B (en) Leakage detection and leakage stoppage integrated device and process method thereof
CN207959289U (en) Structure is repaired in a kind of leak for basement post-pouring zone position
CN207846696U (en) A kind of compound leak stopping system
CN111271084B (en) Tunnel crown arch structure repairing method and repairing structure
CN212153450U (en) Waterproof structure of underground comprehensive pipe gallery deformation joint
CN109235668A (en) Residential building curtain wall and wall crack plugging structure
CN209958531U (en) Deformation joint leakage repairing structure
CN111779303A (en) Grouting plugging construction method
CN217107046U (en) Corrugated steel plate self-plugging structure for highway tunnel transverse passage
CN215367399U (en) Waterproof structure and construction equipment of unilateral formwork of basement side wall
CN214940041U (en) Water leakage prevention structure of diaphragm wall
CN210946855U (en) Plugging device for dewatering well
CN108755776A (en) A kind of underground structure bottom plate leak Integrated Processing Unit and its processing method
CN111156033B (en) Tunnel inverted arch structure repairing method
KR102166830B1 (en) Cross section recovery method using polymer mortar with excellent separation resistance in water by improving water tightness and material separation by including hard calcium carbonate and natural high performance thickener Xanthan gum and polymer mortar composition
CN211080323U (en) Leaking stoppage structure of deformation joint of communication port of basement
CN1900438A (en) Construction body for repairing underground building cracks and its method
CN207959290U (en) A kind of leakage maintaining structure for basement construction seam position
CN113503056A (en) Building deformation joint leakage maintenance method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210625