CN109469068A - A kind of rich water soft stratum excavation of foundation pit and Support Method - Google Patents

A kind of rich water soft stratum excavation of foundation pit and Support Method Download PDF

Info

Publication number
CN109469068A
CN109469068A CN201811300191.8A CN201811300191A CN109469068A CN 109469068 A CN109469068 A CN 109469068A CN 201811300191 A CN201811300191 A CN 201811300191A CN 109469068 A CN109469068 A CN 109469068A
Authority
CN
China
Prior art keywords
excavation
foundation pit
soil
steel
pit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811300191.8A
Other languages
Chinese (zh)
Inventor
姚志雄
吴波
臧万军
赵振伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian University of Technology
Original Assignee
Fujian University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujian University of Technology filed Critical Fujian University of Technology
Priority to CN201811300191.8A priority Critical patent/CN109469068A/en
Publication of CN109469068A publication Critical patent/CN109469068A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/18Restraining of underground water by damming or interrupting the passage of underground water by making use of sealing aprons, e.g. diaphragms made from bituminous or clay material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ
    • E02D5/187Bulkheads or similar walls made solely of concrete in situ the bulkheads or walls being made continuously, e.g. excavating and constructing bulkheads or walls in the same process, without joints

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The invention discloses a kind of rich water soft stratum excavation of foundation pit and Support Methods, comprising: step 1) applies high-pressure rotary jet grouting pile or deep cement-mixed pile;Step 2 excavates bonding layer foundation pit;Step 3) carries out advanced deep hole curtain-grouting;Step 4) preliminary bracing, loopful are applied in the upright excavation face of foundation pit, and preliminary bracing includes being laid with steel mesh and gunite concrete;Step 5) welds together the exposed tube head of Grouting Pipe with steel mesh, forms combined supporting;Remaining core soil in advance in rapid 6) excavation pit;Support system is arranged in step 7);Step 8) is monitored building enclosure stress, deformation, and monitoring measurement result is normal, then carries out excavation and the supporting operation of subsequent cycle, repeats step 2-step 7).The present invention can make the deep big foundation pit excavation under the conditions of rich water soft stratum achieve the effect that good Deformation control and water seepage prevention, and base pit stability is good, and environment influence is small, and construction risk is small, and comprehensive benefit is high.

Description

A kind of rich water soft stratum excavation of foundation pit and Support Method
Technical field
The present invention relates to Pit under Complicated Geological Conditions excavation and support method more particularly to a kind of rich water soft stratum bases Hole excavate and with infiltration control method.
Background technique
With level of urbanization fast development, city can utilize land resource growing tension, rational exploitation and utilization city Down space resource has become inexorable trend.And base pit engineering is often the engineerings such as large-scale construction engineering, railway traffic engineering, municipal administration Important feature form.Base pit engineering is related to engineering geology, infiltration mechanics, construction technology and monitoring technology etc., comprehensive strong;And The features such as stronger tau-effect of base pit engineering, environmental effect, region, construction risk is very big.Especially rich water soft stratum Condition brings extreme difficulty to underground engineering construction, so base pit engineering is often the main projects of entire construction project.
Urban groundwater is abundant, and mostly soft stratum, excavates in this stratum, and not controlling often such as will appear hole Phenomena such as wall large deformation, bottom heave, water burst, causes Important Project accident.Deep big foundation pit in city underground engineering is often tight Adjacent various important buildings, narrow space, it is clear that excavated without condition slope.Tunneling boring vertical cut is such as carried out, due to stress The factors such as release and soft soil creep, foundation pit deformation is big, and stability is poor.Traditional method for protecting support have soil nail wall, campshed bored concrete pile, Lower diaphragm wall etc., these method for protecting support do not carry out pre-reinforcement to the foundation pit surrounding soil body, mostly use bored concrete pile or interlocking pile, This inevitably will cause some adjacent studs lower parts and is not engaged strictly and leads to leak, and support rigidity deficiency also can inevitably generate compared with Large deformation jeopardizes the safety of base pit engineering and neighboring buildings.It is especially complex to some geological conditions such as rich water soft stratum, adopt It is preferable with diaphram wall support rigidity, but construction of diaphragm wall difficulty is big, even with trough plate type diaphram wall, such as Construction method is improper also cannot to be inevitably aligned in the appearance of adjacent wall section and lead to leak, and this method is costly.
Summary of the invention
The purpose of the present invention is to propose to a kind of rich water soft stratum base pit engineering excavation and Support Methods, can effectively control Foundation pit deformation and underground water leakage processed guarantees that rich water soft stratum base pit engineering safety, quick, low cost are excavated.
For achieving the above object, the technical scheme is that a kind of rich water soft stratum excavation of foundation pit with combine Method for protecting support, comprising the following steps:
Step 1) vertically applies high-pressure rotary jet grouting pile or deep cement-mixed pile in Rock And Soil on the outside of the excavation of foundation pit line, reaches design Depth, formation bonding layer is gone along with sb. to guard him and water-stop curtain;
Step 2 excavates bonding layer foundation pit using provided core soil method, forms the small foundation pit in two sides;
Step 3) is drilled on the outside of the water-stop curtain obliquely using excavation pit space in Rock And Soil, and Grouting Pipe is put into drilling It is interior, advanced deep hole curtain-grouting is carried out, is formed and reinforces Rock And Soil;
Step 4) preliminary bracing, loopful are applied in the upright excavation face of foundation pit, form closed flexible support layer, preliminary bracing packet It includes and is laid with steel mesh and gunite concrete;
Step 5) welds together the exposed tube head of Grouting Pipe with steel mesh, forms combined supporting;
Remaining core soil in advance in step 6) excavation pit;
Support system is arranged in step 7), sets including the circumferential steel purlin being arranged on relative closure Rock And Soil outer wall and interval The steel being placed in circumferential steel purlin is to the steel diagonal brace for supportting and being fixedly installed on closing two adjoining outer walls of Rock And Soil;
Step 8) to building enclosure stress, deformation be monitored, monitoring measurement result is normal, then carry out subsequent cycle excavation and Supporting operation repeats step 2-step 7).
Further, in the step 7), circumferential steel purlin, steel use fashioned iron to the steelframe of support and steel diagonal brace Steelframe.
The beneficial effects of the present invention are:
(1) sealing and deformation control effect are good.Vertical high-pressure rotary jet grouting pile or deep cement-mixed pile are applied in advance, in rich water weakness It can effectively be prevented on the outside of foundation pit in Groundwater infiltration foundation pit under formation condition, water-stagnating effect is good.Pass through bonding layer water-stop curtain, deep hole The combined supporting that curtain-grouting, preliminary bracing and support system are formed, significantly improves the overall stiffness of building enclosure, can effectively control Soft soil foundation pit deformation processed, and foundation pit water-stagnating effect can be obviously improved.
(2) overall stiffness is big, stability is good.Advance support is applied, advance support and preliminary bracing form whole stress knot Structure;Preliminary bracing flexible can not only play preferable Stress relief and excessive deformation occurs for control Rock And Soil, but also can achieve The purpose of effective water seepage prevention, guarantees integral stability of foundation pit.
(3) strong applicability.This method is adaptable to various complicated geologicals and hydrogeology, and control deformation effect is good, prevents Infiltration water-stagnating effect is good, and base pit stability is good, and effect on environment is small, and construction risk is small, has very strong applicability.
(4) comprehensive benefit is high.The deep big foundation pit of proposition is layered provided core soil method excavation and combined supporting side from top to bottom Method, the section excavation that becomes larger are light section excavation, increase base pit stability, reduce construction risk;Support Method is alternatively Lower diaphragm wall, work efficiency height, reliable in quality, environment influence small, good economy performance, and comprehensive benefit is high.
Detailed description of the invention
Fig. 1 is rich water soft stratum base pit engineering combined retaining structure floor map;
Fig. 2 is the sectional schematic diagram of rich water soft stratum base pit engineering combined retaining structure;
Fig. 3 is the partial enlargement diagram of A in Fig. 2;
Fig. 4 is that rich water soft stratum excavation of foundation pit and Support Method apply bonding layer water-stop curtain schematic diagram;
Fig. 5 is rich water soft stratum excavation of foundation pit and Support Method excavation pit first floor schematic diagram;
Fig. 6 is that rich water soft stratum excavation of foundation pit and Support Method apply advanced deep hole curtain-grouting schematic diagram;
Fig. 7 is that rich water soft stratum excavation of foundation pit and Support Method apply the signal of excavation pit vertical surface preliminary bracing Figure;
Fig. 8 is that rich water soft stratum excavation of foundation pit and Support Method excavate foundation pit core soil body schematic diagram;
Fig. 9 is rich water soft stratum excavation of foundation pit and Support Method setting support system schematic diagram;
Component and corresponding label in attached drawing: high-pressure rotary jet grouting pile or deep cement-mixed pile 1, advanced deep hole curtain-grouting 2, just Phase supporting 3, gunite concrete 4, steel mesh 5, circumferential steel purlin 6, steel are to support 7, remaining core soil in advance 8, small foundation pit 9, steel Diagonal brace 10.
Specific embodiment
Below in conjunction with attached drawing, technical scheme in the embodiment of the invention is clearly and completely described.
As shown in Figs. 1-2, a kind of rich water soft stratum base pit engineering combined retaining structure, including high-pressure rotary jet grouting pile or deep layer Cement mixing pile 1, advanced deep hole curtain-grouting 2, preliminary bracing 3 and support system, support system include circumferential steel purlin 6, Steel is to support 7, steel diagonal brace 10.
Excavation of foundation pit and Support Method, comprising the following steps:
As shown in figure 4, step 1) vertically applies high-pressure rotary jet grouting pile or deep-cement stirring on the outside of the excavation of foundation pit line in Rock And Soil Stake 1 reaches projected depth, and formation bonding layer is gone along with sb. to guard him and water-stop curtain;
As shown in figure 5, step 2 excavates bonding layer foundation pit using provided core soil method, the small foundation pit 9 in two sides is formed;
As shown in fig. 6, step 3) is drilled on the outside of the water-stop curtain obliquely using excavation pit space in Rock And Soil, by slip casting Pipe is put into drilling, carries out advanced deep hole curtain-grouting 2, is formed and is reinforced Rock And Soil;
As shown in fig. 7, step 4) preliminary bracing 3, loopful is applied in the upright excavation face of foundation pit, forms closed flexible support Layer, preliminary bracing include being laid with steel mesh 5 and gunite concrete 4;
Step 5) welds together the exposed tube head of Grouting Pipe with steel mesh 5, forms combined supporting;
As shown in figure 8, remaining core soil in advance 8 in step 6) excavation pit;
As shown in figure 9, support system is arranged in step 7), including the circumferential steel purlin being arranged on relative closure Rock And Soil outer wall 6, and the steel that is arranged at intervals in circumferential steel purlin 6 to support 7 and is fixedly installed on closing two adjoining outer walls of Rock And Soil Steel diagonal brace 10;Circumferential steel purlin 6, steel use profile steel frame to the steelframe of support 7 and steel diagonal brace 10;
Step 8) to building enclosure stress, deformation be monitored, monitoring measurement result is normal, then carry out subsequent cycle excavation and Supporting operation repeats step 2-step 7).
Rich water soft stratum excavation of foundation pit of the present invention and Support Method, by water-stop curtain, deep hole curtain-grouting, just The combined supporting that phase supporting and support system are formed, alternatively descends diaphragm wall, avoids because construction method is improper in adjacent wall section Seepy question caused by appearance cannot be aligned, can be obviously improved foundation pit water-stagnating effect, effectively control soft soil foundation pit deformation, have Work efficiency height, reliable in quality, environment influence the high feature of small, good economy performance, comprehensive benefit.
Described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.Based on the present invention In embodiment, every other implementation obtained by those of ordinary skill in the art without making creative efforts Example, belongs to the scope of the present invention.

Claims (2)

1. a kind of rich water soft stratum excavation of foundation pit and Support Method, which comprises the following steps:
Step 1) vertically applies high-pressure rotary jet grouting pile or deep cement-mixed pile in Rock And Soil on the outside of the excavation of foundation pit line, reaches design Depth, formation bonding layer is gone along with sb. to guard him and water-stop curtain;
Step 2 excavates bonding layer foundation pit using provided core soil method, forms the small foundation pit in two sides;
Step 3) is drilled on the outside of the water-stop curtain obliquely using excavation pit space in Rock And Soil, and Grouting Pipe is put into drilling It is interior, advanced deep hole curtain-grouting is carried out, is formed and reinforces Rock And Soil;
Step 4) preliminary bracing, loopful are applied in the upright excavation face of foundation pit, form closed flexible support layer, preliminary bracing packet It includes and is laid with steel mesh and gunite concrete;
Step 5) welds together the exposed tube head of Grouting Pipe with steel mesh, forms combined supporting;
Remaining core soil in advance in step 6) excavation pit;
Support system is arranged in step 7), sets including the circumferential steel purlin being arranged on relative closure Rock And Soil outer wall and interval The steel being placed in circumferential steel purlin is to the steel diagonal brace for supportting and being fixedly installed on closing two adjoining outer walls of Rock And Soil;
Step 8) to building enclosure stress, deformation be monitored, monitoring measurement result is normal, then carry out subsequent cycle excavation and Supporting operation repeats step 2-step 7).
2. a kind of rich water soft stratum excavation of foundation pit as described in claim 1 and Support Method, which is characterized in that described In step 7), circumferential steel purlin, steel use profile steel frame to the steelframe of support and steel diagonal brace.
CN201811300191.8A 2018-11-02 2018-11-02 A kind of rich water soft stratum excavation of foundation pit and Support Method Pending CN109469068A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811300191.8A CN109469068A (en) 2018-11-02 2018-11-02 A kind of rich water soft stratum excavation of foundation pit and Support Method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811300191.8A CN109469068A (en) 2018-11-02 2018-11-02 A kind of rich water soft stratum excavation of foundation pit and Support Method

Publications (1)

Publication Number Publication Date
CN109469068A true CN109469068A (en) 2019-03-15

Family

ID=65672641

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811300191.8A Pending CN109469068A (en) 2018-11-02 2018-11-02 A kind of rich water soft stratum excavation of foundation pit and Support Method

Country Status (1)

Country Link
CN (1) CN109469068A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110185044A (en) * 2019-06-17 2019-08-30 中铁上海设计院集团有限公司 A kind of foundation pit side-wall Stress relief system for deep caving ground
CN110258606A (en) * 2019-06-26 2019-09-20 中国电建集团成都勘测设计研究院有限公司 Projecting wall encloses well construction
US20240076848A1 (en) * 2022-09-06 2024-03-07 Fucai HUA Method for constructing large-span station with two-wing open type half-cover excavation and half-reverse construction

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103147444A (en) * 2013-03-24 2013-06-12 中铁二院工程集团有限责任公司 Foundation pit enclosure structure capable of realizing supporting while excavating and foundation pit excavating method
CN105178326A (en) * 2015-06-03 2015-12-23 福建工程学院 Water stop method for upper-soft and lower-hard water-rich stratum foundation pit engineering retaining structure

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103147444A (en) * 2013-03-24 2013-06-12 中铁二院工程集团有限责任公司 Foundation pit enclosure structure capable of realizing supporting while excavating and foundation pit excavating method
CN105178326A (en) * 2015-06-03 2015-12-23 福建工程学院 Water stop method for upper-soft and lower-hard water-rich stratum foundation pit engineering retaining structure

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110185044A (en) * 2019-06-17 2019-08-30 中铁上海设计院集团有限公司 A kind of foundation pit side-wall Stress relief system for deep caving ground
CN110185044B (en) * 2019-06-17 2023-12-12 中铁上海设计院集团有限公司 Foundation pit side wall stress adjustment system for deep unstable stratum
CN110258606A (en) * 2019-06-26 2019-09-20 中国电建集团成都勘测设计研究院有限公司 Projecting wall encloses well construction
US20240076848A1 (en) * 2022-09-06 2024-03-07 Fucai HUA Method for constructing large-span station with two-wing open type half-cover excavation and half-reverse construction
US11959243B2 (en) * 2022-09-06 2024-04-16 Beijing Urban Construction Design & Development Group Co., Limited Method for constructing large-span station with two-wing open type half-cover excavation and half-reverse construction

Similar Documents

Publication Publication Date Title
CN106013052B (en) The construction method of steel sheet pile and open caisson Combined type underground garage parking
CN109026064B (en) Construction method for large-span multi-arch tunnel with semi-bright and semi-dark
CN111335327B (en) Deep anchor pile supporting system and construction method thereof
CN105240024B (en) A kind of method of parallel shield method enlarging construction subway station
CN101270579B (en) Foundation pit guard method for expansion construction from deep foundation pit to shallow foundation pit
CN108343071A (en) A kind of foundation pit supporting construction and construction method of steel sheet pile combined deposited pile
CN105002913A (en) Strongly-permeable stratum deep foundation pit bottom sealing water stopping structure and construction method thereof
CN207063982U (en) Mechanical assistance sealing Station structure in a kind of pilot tunnel
CN109469068A (en) A kind of rich water soft stratum excavation of foundation pit and Support Method
CN105525619A (en) Occlusive pipe curtain for bored tunnel in water-rich stratum and construction method of occlusive pipe curtain
CN105370289A (en) Ultra-long shallow-buried excavation construction method for existing pipeline in complex environment
CN109403333A (en) A kind of soft lower hard water rich strata deep basal pit reversed construction method
CN107964971B (en) A kind of precipitation method of the subway station using the construction of PBA engineering method
CN103572764A (en) Watertight structure for retaining wall of ultra-deep manually excavated pile and construction method thereof
CN105240023B (en) A kind of method of Curve Pipe Jacking supporting construction enlarging shield-tunneling construction subway station
CN111101540B (en) Construction method for passing existing electric power tunnel on open cut tunnel
CN212104116U (en) Deep anchor pile supporting system
CN111350193A (en) Open type foundation pit supporting method
CN214738189U (en) Bucket waterproof curtain and hole digging pile supporting structure of water-rich sand layer
CN111878119B (en) Subway tunnel ballast bed pipe piece wall post-grouting method
CN212202085U (en) Close-adhesion type open-and-underground excavation combined subway station structure
CN212612517U (en) Micro steel pipe pile composite supporting structure for deep foundation pit in limited space
CN114622574A (en) Water-rich cast-fill deep foundation pit water-intercepting excavation supporting method and supporting device
CN108019211B (en) Water-intercepting curtain in pilot tunnel of water-rich sandy pebble stratum and construction method thereof
CN113832982A (en) External support construction method for subway deep foundation pit

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190315