CN109469042A - Seepage-proofing karst cave processing structure for storage yard field area - Google Patents

Seepage-proofing karst cave processing structure for storage yard field area Download PDF

Info

Publication number
CN109469042A
CN109469042A CN201811505890.6A CN201811505890A CN109469042A CN 109469042 A CN109469042 A CN 109469042A CN 201811505890 A CN201811505890 A CN 201811505890A CN 109469042 A CN109469042 A CN 109469042A
Authority
CN
China
Prior art keywords
karst cave
solution cavity
antiseepage
stockyard
underground water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811505890.6A
Other languages
Chinese (zh)
Other versions
CN109469042B (en
Inventor
王河
吴维兴
陶维中
赵谊
程功
刘军涛
谭文超
马俊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Guiyang Engineering Corp Ltd
Original Assignee
PowerChina Guiyang Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Guiyang Engineering Corp Ltd filed Critical PowerChina Guiyang Engineering Corp Ltd
Priority to CN201811505890.6A priority Critical patent/CN109469042B/en
Publication of CN109469042A publication Critical patent/CN109469042A/en
Application granted granted Critical
Publication of CN109469042B publication Critical patent/CN109469042B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Soil Sciences (AREA)
  • Agronomy & Crop Science (AREA)
  • Hydrology & Water Resources (AREA)
  • Lining And Supports For Tunnels (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention provides a karst cave processing structure of an impermeable yard field region, which comprises a reinforced concrete cover plate; the reinforced concrete cover plate covers the concrete cushion layer, the concrete cushion layer is laminated in the reinforcing layer, the bottom of the concrete cushion layer is provided with a karst cave, and the area of the concrete cushion layer is larger than the top opening of the karst cave; the top surfaces of the reinforced concrete cover plate and the reinforced layer are covered with an anti-seepage system; an HDPE pipe penetrates through the anti-seepage system, the reinforced concrete cover plate and the concrete cushion layer and is explored into the karst cave; the underground water draining pipe passes through the strengthening layer. The invention can drain the underground water through the karst cave and the underground water drainage system, effectively solves the problem that the traditional karst cave landfill treatment technology can not discharge the underground water, and avoids the damage of overhigh water level of the underground water to the seepage-proofing system.

Description

A kind of antiseepage stockyard place karst cave treatment structure
Technical field
The present invention relates to a kind of antiseepage stockyard place karst cave treatment structures.
Background technique
Solution cavity is that underground water long-term corrosion in In Limestone Area is formed by the complicated underground space, meets with solution cavity in construction project When, if do not handled in time it, it will increase the risk of entire engineering, or even engineering accident occurs.
Existing Treatment technology of karst cave mainly fills, just for different type of cavern, the embedding material taken and Landfill is different.
(1) traditional treatment method: heavy excavation construction or toward solution cavity grout injection or concrete, this method general duration compared with It is long, costly and be unable to ensure being sufficient filling with for solution cavity.
(2) utilizing works waste soil fills solution cavity: utilizing works waste soil is prepared into bubble composite soil as underground karst cavity Packing material, specific steps include: geological mapping, collapse hole protection, drilling, bore flushing, prepare bubble composite soil, slip casting make Industry etc..This method can guarantee being sufficient filling with for solution cavity.
(3) fill method of different materials is used to different types of solution cavity: first being classified to solution cavity, according to different Type of cavern uses different fill methods.Specific steps include: the method to small-sized solution cavity using backfill clay drilling Gu Bi; Hole is blocked up using slabstone clay to medium-sized solution cavity and builds wall approach, slabstone soil cement pulping method is used for large-scale solution cavity.This method is directed to Different types of solution cavity uses different processing methods, is conducive to save material, shortens construction period, improves construction efficiency.
Existing solution cavity landfill disposal technology, is not able to satisfy the karst cave treatment requirement of antiseepage stockyard place.Firstly, existing Solution cavity landfill disposal technology solution cavity channel is blocked completely after, underground water cannot be drained by solution cavity again, if underground Water water level is excessively high to generate huge jacking force to the seepage control system in antiseepage stockyard, causes the destruction of seepage control system;Secondly, existing Solution cavity landfill disposal technology be not able to satisfy antiseepage stockyard seepage control system laying flatness requirement;Last existing solution cavity landfill Processing technique cannot avoid the differential settlement of solution cavity backfill substance under external force completely, once differential settlement occurs must So cause the destruction of seepage control system.
Summary of the invention
In order to solve the above technical problems, the present invention provides a kind of antiseepage stockyard place karst cave treatment structure, the antiseepage heap Field place karst cave treatment structure can smoothly drain underground water, be able to satisfy the flatness requirement of antiseepage stockyard seepage control system laying, and It is avoided that the differential settlement of solution cavity under external force damages seepage control system.
The present invention is achieved by the following technical programs.
A kind of antiseepage stockyard place provided by the invention karst cave treatment structure, including reinforced concrete cover plate;The reinforcing bar Concrete cover covers on concrete cushion, and concrete mats are laminated in strengthening layer, has solution cavity in concrete cushion bottom and mixes Solidifying soil padding area is greater than the top opening of solution cavity;The reinforced concrete cover plate and strengthening layer top surface are covered with seepage control system;Have HDPE pipe is probeed into across seepage control system, reinforced concrete cover plate, concrete cushion into solution cavity;There is underground water discharge guiding pipe from reinforcing It is crossed in layer.
The solution cavity is divided into shallow karst cavity and latent solution cavity two types, when solution cavity is shallow karst cavity, is filled in solution cavity Backfill sandy gravel.
Backfill sandy gravel compactness in solution cavity is not less than 0.93.
The concrete cushion is C15 concrete, with a thickness of 10cm.
The seepage control system is multilayer, and basal layer, clay protective layer, GCL soil blanket, smooth surface HDPE are up followed successively by from bottom Film, protective layer geotextiles.
The GCL soil blanket specification is 4800g/m2, protective layer geotextiles are filament nonwoven geotextiles, specification 600g/m2
The smooth surface HDPE film specification is 2.0mm, and smooth surface HDPE film carries out local overlap joint across position in HDPE pipe and adopts It is squeezed out and is welded with single weld seam, the lap of splice is not less than 0.5m in the horizontal direction, and vertical direction is not less than 0.7m.
The HDPE that the HDPE pipe is Ф 160 is managed.
The underground water discharge guiding pipe, geotextiles, backfill rubble, backfill clay form underground water guide system, wherein underground Water discharge guiding pipe is passed through from backfill rubble fill part.
The beneficial effects of the present invention are: underground water can be drained by solution cavity and underground water guide system, be had Effect solves the problems, such as that traditional solution cavity landfill disposal technology cannot discharge underground water, and it is excessively high to antiseepage to avoid groundwater level The destruction of system;By the way that reinforced concrete cover plate is arranged on solution cavity top cover layer surface, the existing solution cavity of effective solution is filled out It buries processing technique and is not able to satisfy the problem of antiseepage stockyard seepage control system is laid with flatness requirement, can be avoided solution cavity backfill substance and exist Destruction of the differential settlement generated under external force to seepage control system;Pipe wears the application of membrane technology, wears this antiseepage of film to pipe System weak part has carried out reinforcement, can effectively avoid the leakage of the sewage such as percolate here, have to antiseepage stockyard Great use value.
Detailed description of the invention
Fig. 1 is the structural schematic diagram that the present invention is applied to shallow karst cavity;
Fig. 2 is the structural schematic diagram that the present invention is applied to latent solution cavity;
Fig. 3 is the face A-A cross-sectional view in Fig. 1 and Fig. 2;
Fig. 4 is the thin portion structural schematic diagram of HDPE pipe in Fig. 1 and Fig. 2.
In figure: 1- basement rock, the stratum 2- line of demarcation, 3- strengthening layer, 4- seepage control system, 5- solution cavity, 6- backfill sandy gravel, and 7- is mixed Solidifying soil padding, 8- reinforced concrete cover plate, 9- underground water discharge guiding pipe, 10- geotextiles, 11- backfill rubble, and 12- backfills clay, 13- french drain, 14- smooth surface HDPE film, 15-HDPE pipe, 16- weld seam.
Specific embodiment
Be described further below technical solution of the present invention, but claimed range be not limited to it is described.
A kind of antiseepage stockyard place karst cave treatment structure as shown in Figures 1 to 4, including reinforced concrete cover plate 8;It is described Reinforced concrete cover plate 8 covers on concrete cushion 7, and concrete cushion 7 is pressed in strengthening layer 3, has in 7 bottom of concrete cushion Solution cavity 5 and 7 area of concrete cushion are greater than the top opening of solution cavity 5;The reinforced concrete cover plate 8 and 3 top surface of strengthening layer are covered There is seepage control system 4;There is HDPE pipe 15 to pass through seepage control system 4, reinforced concrete cover plate 8, concrete cushion 7 to probe into solution cavity 5; There is underground water discharge guiding pipe 9 to cross from strengthening layer 3.
The solution cavity 5, which divides, to be filled out in solution cavity 5 for shallow karst cavity and latent solution cavity two types when solution cavity 5 is shallow karst cavity There is backfill sandy gravel 6.
The backfill sandy gravel 6 compactness in solution cavity 5 is not less than 0.93.
The concrete cushion 7 is C15 concrete, with a thickness of 10cm.
The seepage control system 4 is multilayer, and basal layer, clay protective layer, GCL soil blanket, smooth surface are up followed successively by from bottom HDPE film 14, protective layer geotextiles.
The GCL soil blanket specification is 4800g/m2, protective layer geotextiles are filament nonwoven geotextiles, specification 600g/m2
14 specification of smooth surface HDPE film is 2.0mm, and smooth surface HDPE film 14 passes through position in HDPE pipe 15 and carries out local take It connects and single weld seam 16 is used to squeeze out welding, the lap of splice is not less than 0.5m in the horizontal direction, and vertical direction is not less than 0.7m.
The HDPE that the HDPE pipe 15 is Ф 160 manages (SDR13.6).
The underground water discharge guiding pipe 9, geotextiles 10, backfill rubble 11, backfill clay 12 form underground water guide system, Middle underground water discharge guiding pipe 9 is passed through from backfill 11 fill part of rubble.
More generally, the present invention is broadly divided into following several parts: a. solution cavity structure and treatment measures, b. underground water guide System, c. seepage control system, d. pipe wear membranous system.
Wherein:
Solution cavity structure and treatment measures are divided into shallow karst cavity structure and treatment measures and latent solution cavity structure and treatment measures. Wherein, shallow karst cavity structure and treatment measures are by basement rock 1, stratum line of demarcation 2, strengthening layer 3, seepage control system 4, solution cavity 5, Cast-in-situ Piles in Sand-filling Gravel material 6, concrete cushion 7 and reinforced concrete cover plate 8 form;Latent solution cavity structure and treatment measures basement rock 1, stratum line of demarcation 2, middle differentiation layer/strengthening layer 3, seepage control system 4, solution cavity 5, concrete cushion 7 and reinforced concrete cover plate 8 form.
Underground water guide system is made of underground water discharge guiding pipe 9, geotextiles 10, backfill rubble 11, backfill clay 12.
Pipe is worn membranous system and is made of smooth surface HDPE film 14, HDPE pipe 15 and weld seam 16.
It, can be in accordance with the following steps when operation:
1) coating removing is carried out to stratum upper surface a certain range at the top of solution cavity 5 (shallow karst cavity or latent solution cavity), it is right Shallow karst cavity filling backfill sandy gravel 6, successively construct on the basis of coating or backfill sandy gravel 6 concrete cushion 7 and steel Reinforced concrete cover board 8;
2) slope excavation is carried out to underground water guide french drain 13, the laying of geotextiles 10, bottom is successively carried out after excavation The backfill of rubble 11, underground water discharge guiding pipe 9 are laid with, the backfill of upper layer rubble 11, geotextiles 10 suture, backfill clay 12 is filled, wherein 5 top underground water guide system of solution cavity is default when karst cave treatment measure is implemented, and implementation sequence is same as above;
3) on the basis of 5 treatment measures of solution cavity and finished underground water guide system, applying for seepage control system 4 is carried out Work, sequence of construction be followed successively by basal layer roll, clay protective layer be laid with roll, GCL soil blanket be laid with, smooth surface HDPE film 14 be laid with With welding and protective layer geotextile laying;
4) pipe wears HDPE pipe 15 pre-buried, smooth surface HDPE film 14 and DPE pipe 15 in the implementation of 5 treatment measures of solution cavity in membranous system Be welded in seepage control system implementation when smooth surface HDPE film 14 is laid with.
In addition, in the specific implementation, it should also be noted that:
1) reinforced concrete cover plate 7 should should be greater than solution cavity 5 using C25 concrete and Ф 16HRB300 reinforcing bar, coverage area Sideline about 1m;The label of reinforced concrete cover plate 7, the specification of size and reinforcing bar, spacing can be according to practical geological conditions and solution cavity 5 The case where through Structure Calculation is determining or adjustment;
2) supervisor of underground water discharge guiding pipe 9 uses Ф 315HDPE floral tube (SDR13.6), and branch pipe uses Ф 200HDPE floral tube (SDR13.6);20 hole a Ф is opened for every 45 degree in pipe circumferential direction, and the every 12cm in pipe range direction opens 20 hole a Ф, and aperture is using quincunx Arrangement;
3) backfill rubble 11 uses 3~5cm of diameter rubble, and compactness is not less than 0.93;
4) backfill 12 compactness of clay is not less than 0.93, to avoid differential settlement;
5) 13 cross section of french drain is inverted trapezoidal, and bottom width 0.6m, top width 2.1m, a height of 1.5m excavate side The slope gradient is 1:0.5;
6) the basic roadbed of seepage control system 4 is not less than 0.93, to avoid differential settlement;
7) 4 clay protective layer thickness of seepage control system is not less than 60cm, and compactness is not less than 0.93, and it is uneven heavy to avoid Drop.

Claims (9)

1. a kind of antiseepage stockyard place karst cave treatment structure, including reinforced concrete cover plate (8), it is characterised in that: the reinforcing bar Concrete cover (8) covers on concrete cushion (7), and concrete cushion (7) is pressed in strengthening layer (3), in concrete cushion (7) Solution cavity (5) is arranged at bottom and concrete cushion (7) area is greater than the top opening of solution cavity (5);The reinforced concrete cover plate (8) and Strengthening layer (3) top surface is covered with seepage control system (4);There is HDPE pipe (15) to pass through seepage control system (4), reinforced concrete cover plate (8), mix Solidifying soil padding (7) are probeed into solution cavity (5);There is underground water discharge guiding pipe (9) to cross from strengthening layer (3).
2. antiseepage stockyard as described in claim 1 place karst cave treatment structure, it is characterised in that: the solution cavity (5) is divided into shallowly Solution cavity and latent solution cavity two types are buried, when solution cavity (5) are shallow karst cavity, is filled with backfill sandy gravel (6) in solution cavity (5).
3. antiseepage stockyard as claimed in claim 2 place karst cave treatment structure, it is characterised in that: the backfill sandy gravel (6) Compactness is not less than 0.93 in solution cavity (5).
4. antiseepage stockyard as described in claim 1 place karst cave treatment structure, it is characterised in that: the concrete cushion (7) For 15 concrete of C, with a thickness of 10cm.
5. antiseepage stockyard as described in claim 1 place karst cave treatment structure, it is characterised in that: the seepage control system (4) is Multilayer is up followed successively by basal layer, clay protective layer, GCL soil blanket, smooth surface HDPE film (14), protective layer geotextiles from bottom.
6. antiseepage stockyard as claimed in claim 5 place karst cave treatment structure, it is characterised in that: the GCL soil blanket specification is 4800g/m2, protective layer geotextiles are filament nonwoven geotextiles, specification 600g/m2
7. antiseepage stockyard as claimed in claim 5 place karst cave treatment structure, it is characterised in that: the smooth surface HDPE film (14) Specification is 2.0mm, and smooth surface HDPE film (14) is passed through the local overlap joint of position progress in HDPE pipe (15) and squeezed using single weld seam (16) It welds out, the lap of splice is not less than 0.5m in the horizontal direction, and vertical direction is not less than 0.7m.
8. antiseepage stockyard as described in claim 1 place karst cave treatment structure, it is characterised in that: the HDPE pipe (15) is Ф 160 HDPE pipe.
9. antiseepage stockyard as described in claim 1 place karst cave treatment structure, it is characterised in that: the underground water discharge guiding pipe (9), geotextiles (10), backfill rubble (11), backfill clay (12) form underground water guide system, wherein underground water discharge guiding pipe (9) it is passed through from backfill rubble (11) fill part.
CN201811505890.6A 2018-12-10 2018-12-10 Anti-seepage storage yard field karst cave processing structure Active CN109469042B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811505890.6A CN109469042B (en) 2018-12-10 2018-12-10 Anti-seepage storage yard field karst cave processing structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811505890.6A CN109469042B (en) 2018-12-10 2018-12-10 Anti-seepage storage yard field karst cave processing structure

Publications (2)

Publication Number Publication Date
CN109469042A true CN109469042A (en) 2019-03-15
CN109469042B CN109469042B (en) 2024-03-26

Family

ID=65676099

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811505890.6A Active CN109469042B (en) 2018-12-10 2018-12-10 Anti-seepage storage yard field karst cave processing structure

Country Status (1)

Country Link
CN (1) CN109469042B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110886305A (en) * 2019-11-08 2020-03-17 济南轨道交通集团有限公司 Foundation pit water burst layered backfilling and plugging method based on protection karst water channel
CN110886308A (en) * 2019-11-08 2020-03-17 济南轨道交通集团有限公司 Rapid frozen groundwater plugging method based on protection karst water channel
CN110984120A (en) * 2019-12-31 2020-04-10 桂林电子科技大学 Filling structure of shallow-buried non-pressure water-filled karst cave and construction method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6719493B1 (en) * 1999-07-13 2004-04-13 Friedrich Meyer Method and system for encasing an endless, laid pipeline conduit with backfill concrete
CN203742622U (en) * 2013-11-13 2014-07-30 江南水利水电工程公司 Seep-proof component for constructing bearing structure
CN105201001A (en) * 2015-10-10 2015-12-30 中国电建集团贵阳勘测设计研究院有限公司 Composite seepage-proofing structure of large karst cave in karst region and construction method thereof
CN106013178A (en) * 2016-05-25 2016-10-12 河北建设勘察研究院有限公司 Filling method for karst surface collapse of shallow-buried karst area
CN209482289U (en) * 2018-12-10 2019-10-11 中国电建集团贵阳勘测设计研究院有限公司 Seepage-proofing karst cave processing structure for storage yard field area

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6719493B1 (en) * 1999-07-13 2004-04-13 Friedrich Meyer Method and system for encasing an endless, laid pipeline conduit with backfill concrete
CN203742622U (en) * 2013-11-13 2014-07-30 江南水利水电工程公司 Seep-proof component for constructing bearing structure
CN105201001A (en) * 2015-10-10 2015-12-30 中国电建集团贵阳勘测设计研究院有限公司 Composite seepage-proofing structure of large karst cave in karst region and construction method thereof
CN106013178A (en) * 2016-05-25 2016-10-12 河北建设勘察研究院有限公司 Filling method for karst surface collapse of shallow-buried karst area
CN209482289U (en) * 2018-12-10 2019-10-11 中国电建集团贵阳勘测设计研究院有限公司 Seepage-proofing karst cave processing structure for storage yard field area

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110886305A (en) * 2019-11-08 2020-03-17 济南轨道交通集团有限公司 Foundation pit water burst layered backfilling and plugging method based on protection karst water channel
CN110886308A (en) * 2019-11-08 2020-03-17 济南轨道交通集团有限公司 Rapid frozen groundwater plugging method based on protection karst water channel
CN110984120A (en) * 2019-12-31 2020-04-10 桂林电子科技大学 Filling structure of shallow-buried non-pressure water-filled karst cave and construction method thereof
CN110984120B (en) * 2019-12-31 2020-09-25 桂林电子科技大学 Filling structure of shallow-buried non-pressure water-filled karst cave and construction method thereof

Also Published As

Publication number Publication date
CN109469042B (en) 2024-03-26

Similar Documents

Publication Publication Date Title
CN204059124U (en) A kind of sand drain strong rammer grouting behind shaft or drift lining foundation reinforcing structure
CN102433876B (en) Multi-compartment casing composite pile and construction method thereof
CN210104706U (en) Construction structure for treating deep and thick soft foundation by vacuum combined preloading
CN105951711A (en) Enclosing construction method of underground continuous wall of seashore power station
CN101936012B (en) Impermeable membrane anchoring structure at middle part of side slope of abrupt and hard rock side slope single-layer impermeable structure
CN110029690B (en) Percolate leakage detection and collection structure and construction method thereof
CN104499479A (en) Dig-hole pile construction method based on penetration of sand gravel backfilling layer
CN109469042A (en) Seepage-proofing karst cave processing structure for storage yard field area
CN105804007B (en) A kind of reinforced earth quaywall structure based on the soft base of beach
CN112523264B (en) High-steep side slope seepage prevention system and laying method thereof
CN108571000A (en) The construction method of underground water cutting when wearing existing railway under a kind of road of location along the river
CN113174958A (en) Construction method for foundation pit of adjacent road under poor ground condition
CN109594575A (en) A kind of open caisson periphery grouting and reinforcing soil body construction method
CN211421169U (en) Fill side slope gravity type retaining wall reinforced structure
CN108547260A (en) Seepage-proofing treatment structure for reservoir full-reservoir basin in karst region and construction method
CN107687175A (en) The vertical antifouling isolation wall construction of both sides ground local stiffening type and method
CN201424658Y (en) Water leakage detection of underground continuous wall groove seams and block repair device
CN209482289U (en) Seepage-proofing karst cave processing structure for storage yard field area
CN107700521B (en) Building foundation reinforcement underpinning pier and construction method thereof
CN104074195B (en) A kind of method controlling the outer surface subsidence of foundation ditch by horizontal grouting
CN103276717B (en) The method of composite earthwork synthetic materials reinforcement cushion soft soil foundation
CN104480945B (en) A kind of foundation ditch reversed construction method
CN208455573U (en) Karst area reservoir basin seepage prevention processing structure
CN114134920A (en) Post-cast strip advanced sealing construction method
CN212153420U (en) Flexible protection system for treating side slope seepage

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant