CN109457951A - Contracture shear wall form frame system and its construction method - Google Patents

Contracture shear wall form frame system and its construction method Download PDF

Info

Publication number
CN109457951A
CN109457951A CN201811316223.3A CN201811316223A CN109457951A CN 109457951 A CN109457951 A CN 109457951A CN 201811316223 A CN201811316223 A CN 201811316223A CN 109457951 A CN109457951 A CN 109457951A
Authority
CN
China
Prior art keywords
contracture
shear wall
poured
wall
bracket
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811316223.3A
Other languages
Chinese (zh)
Other versions
CN109457951B (en
Inventor
徐磊
陈逯浩
陆庆华
张星波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction No 1 Group Co Ltd
Original Assignee
Shanghai Construction No 1 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction No 1 Group Co Ltd filed Critical Shanghai Construction No 1 Group Co Ltd
Priority to CN201811316223.3A priority Critical patent/CN109457951B/en
Publication of CN109457951A publication Critical patent/CN109457951A/en
Application granted granted Critical
Publication of CN109457951B publication Critical patent/CN109457951B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/20Movable forms; Movable forms for moulding cylindrical, conical or hyperbolical structures; Templates serving as forms for positioning blocks or the like
    • E04G11/28Climbing forms, i.e. forms which are not in contact with the poured concrete during lifting from layer to layer and which are anchored in the hardened concrete
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/18Scaffolds essentially supported by building constructions, e.g. adjustable in height supported by cantilevers or other provisions mounted in openings in the building, e.g. window openings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/04Means for fastening, supporting, or bracing scaffolds on or against building constructions
    • E04G5/045Means for fastening, supporting, or bracing scaffolds on or against building constructions for fastening scaffoldings on profiles, e.g. I or H profiles
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

Contracture shear wall form frame system of the invention and its construction method are related to construction equipment technical field.For the problem that the wall of the inside contracture of Super High Core Walls Structure, traditional formwork system can not implement efficient, safe construction.It includes: interior tub bracket, the outer tub support unit one close to contracture shear wall to be poured;Within tub bracket and outer tub support unit one be platform building outstanding anchor scaffold, concrete structure construction for contracture shear wall, and contracture wall climbs columns assemblies, is set at the top of the contracture shear wall poured and can slide along the top beam level of steel platform;Interior tub bracket and inner cylinder the frame body interior tub that constitutes by an active connection support, and interior tub bracket is more than or equal to the vertical projection width of contracture shear wall to be poured along the width in steel platform horizontal extension direction.

Description

Contracture shear wall form frame system and its construction method
Technical field
The present invention relates to construction equipment technical field, in particular to a kind of contracture shear wall form frame system and its construction Method.
Background technique
Currently, high-rise, super high-rise building metamorphosis is increasingly novel, unique, the facade of Core Walls Structure often has inwardly The wall of contracture, and traditional formwork system is often suitable for the construction of vertical wall, the wall that can not be applied to inside contracture is applied Work;Moreover, the appearance of contracture wall often means that the contracture variation of structure, corresponding formwork system also needs to carry out high-altitude It splits, also to the safety of formwork system, more stringent requirements are proposed for this.
Summary of the invention
It can not implement asking for efficient, the inside contracture of safe construction Super High Core Walls Structure wall for traditional formwork system Topic.The object of the present invention is to provide a kind of contracture shear wall form frame system and its construction methods, it is to integrally hoisting steel platform mould The existing structure of frame system split and has been transformed, and improves the utilization rate of material, and the contracture wall added climbs column group Part can guarantee steel platform vertically climbing after the completion of current layer construction, while guaranteeing construction safety, substantially accelerate Construction efficiency.
The technical solution adopted by the present invention to solve the technical problems is: contracture shear wall form frame system, comprising: interior tub Bracket, on the inside of contracture shear wall to be poured;Outer tub support unit one, on the outside of contracture shear wall to be poured; Outstanding anchor scaffold, is platform building with the interior tub bracket and the outer tub support unit one, cuts for the contracture The concrete structure construction of power wall;Contracture wall climbs columns assemblies, is set at the top of the contracture shear wall poured And it can be slided along the top beam level of steel platform;The interior tub bracket and inner cylinder frame body constitute by an active connection interior tub branch Support, and width of the interior tub bracket along steel platform horizontal extension direction is equal to or more than the contracture shear wall to be poured Vertical projection width.
Preferably, contracture wall columns assemblies of climbing include: vertically to be embedded at adjacent two top beams of the steel platform Between lifting beam, and be vertically fixed in the column one that climbs at the top of the lifting beam, the lifting beam by supporting rod and It is installed on four sliding blocks composition of the supporting rod end, the supporting rod is by spaced upper flange, bottom wing Plate, and the longitudinal section rod piece in the shape of an " I " constituted positioned at web between the two, at the top of the supporting rod upper flange Both ends are separately installed with first sliding block, and first sliding block includes setting reeded first pedestal, in the middle part of groove Convex block one is equipped with connecting rod one, and the both ends of the connecting rod one are mounted on idler wheel, supporting rod lower wing plate bottom Both ends are separately installed with second sliding block, and the second sliding block includes setting reeded second pedestal, the convex block in the middle part of groove Two are equipped with connecting rod two, and the both ends of the connecting rod two are mounted on idler wheel, enable the lifting beam along adjacent two The notch of top beam slides.
Preferably, limiting device is also equipped in the lifting beam.
Preferably, the outstanding anchor scaffold includes: the branch for being installed on one top of interior tub bracket and outer tub support unit Frame top beam, the operation platform being layed in above the set cap, and build in the contracture wall foot on the operation platform Hand cradle.
Preferably, connected between the set cap and the contracture shear wall poured by built-in fitting one and skewed horizontal load It connects, the built-in fitting one is embedded in the contracture shear wall poured, one end of the skewed horizontal load and one spiral shell of built-in fitting It tethers and connects or weld, the other end of the skewed horizontal load is connect with the set cap, and the tilt angle of the skewed horizontal load exists Between 30 °~60 °, and one of skewed horizontal load of horizontal interval 4m~6m setting.
Preferably, the interior tub bracket and the outer tub support unit one pass through multiple built-in fittings two and cross-tie Core Walls Structure shear wall with the contracture shear wall poured and positioned at its underpart is connect, and the built-in fitting two, which is embedded in, have been poured Contracture shear wall and in the Core Walls Structure shear wall of its underpart, one end of the cross-tie and two bolt of built-in fitting connect It connects, the other end of the cross-tie is connect with the vertical upright column of the interior tub bracket or the outer tub support unit one.
Preferably, being flexibly connected between said inner tube frame body and the interior tub bracket connects for pin connection or bolt It connects.
Preferably, the vertex angle part of inner cylinder frame body bottom four is equipped with telescopic steel corbel, the interior tub bracket Both ends be respectively provided with a telescopic steel corbel, the close contracture shear wall of the inner cylinder frame body after fractionation end Angle Position two A telescopic steel corbel is supported in the preformed hole of the Core Walls Structure shear wall of vertical non-contracture.
In addition, steps are as follows the present invention also provides a kind of construction method of contracture shear wall form frame system:
S1: it is constructed using integrally hoisting steel platform formwork system to n-th layer below contracture shear wall to be poured;
S2: being promoted to (n+1)th layer for the integrally hoisting steel platform formwork system, tub bracket in reinforcing, described in fractionation Interior tub bracket is flexibly connected with inner cylinder frame body, and removes the inner cylinder frame body close to the safety of contracture shear wall side Net removes the connection of the outer tub support unit one and steel platform close to contracture shear wall side, with the interior tub branch Frame and the outer tub support unit one are that platform in (n+1)th layer of contracture shear wall two sides to be poured sets up (n+1)th layer of outstanding anchor Scaffold is to rely on the template for installing (n+1)th layer of contracture shear wall to be poured, and pour with described (n+1)th layer outstanding anchor scaffold (n+1)th layer of contracture shear wall of construction is built, meanwhile, the Core Walls Structure shear wall of (n+1)th layer of non-contracture of pouring construction climbs contracture wall Rise columns assemblies along steel platform top beam into integrally hoisting steel platform formwork system Slideslip so that the contracture wall climbs Columns assemblies are supported in the (n+1)th layer of contracture shearing coping for having poured completion, repeat the above steps, and successively construction n-th+ 2 ... n+m layers of contracture shear wall, the contracture wall climb columns assemblies along top beam gradually inside Slideslip and be supported in n-th+ 2 ... n+m layers of contracture shears coping, successively completes the concrete pouring construction of contracture shear wall;
S3: the integrally hoisting steel platform formwork system after fractionation continues to climb and pouring construction is located at and has poured contracture Core Walls Structure shear wall above shear wall;
Wherein, n is the natural number more than or equal to 5, and m is the natural number more than or equal to 1.
Preferably, in the step S2, set cap is embedded in inside contracture shear wall with concrete pouring construction.
Effect of the invention is that:
One, contracture shear wall form frame system of the invention, including the interior tub being arranged around contracture shear wall to be poured It bracket, outer tub support unit one, outstanding anchor scaffold and is set at the top of the contracture shear wall poured and can be along steel platform The contracture wall of top beam level sliding climb columns assemblies, encountered in the integrally hoisting steel platform formwork system process of climbing to be poured When the contracture shear wall built, being flexibly connected between interior tub bracket and inner cylinder frame body is dismantled, the interior tub bracket after fractionation Width be equal to or more than contracture shear wall to be poured vertical projection width, within tub bracket and outer tub support unit One is convenient for the concrete pouring construction of contracture shear wall for the outstanding anchor scaffold of platform building;Moreover, being cut in contracture to be poured Power wall top portion setting contracture wall climbs columns assemblies, contracture wall climb columns assemblies can along steel platform top beam inwardly Level sliding enables contracture wall columns assemblies of climbing to be always positioned at the contracture shearing coping that each layer poured, because This, while successively construction contracture shear wall, the Core Walls Structure shear wall of non-contracture can synchronous construction, complete current layer and pour The steel platform of construction can rely on existing climbing system and contracture wall columns assemblies of climbing vertically to climb and pass through and poured Contracture shear wall and non-contracture Core Walls Structure shear wall, the contracture shear wall form frame system is to integrally hoisting steel platform mould bases body The existing structure of system split and has been transformed, and improves the utilization rate of material, and the contracture wall added climbs columns assemblies energy Enough guarantee steel platform vertically climbing after the completion of current layer is constructed, while guaranteeing construction safety, substantially accelerates construction Efficiency.
Two, the construction method of contracture shear wall form frame system of the invention, firstly, in integrally hoisting steel platform formwork system After rising to the contracture shear wall position wait pour, the interior tub bracket and inner cylinder frame body of flexible connection are split, and is torn open Open close to contracture shear wall to be poured outer tub support unit one and steel platform connection, then, within tub bracket and Outer tub support unit one is the outstanding anchor scaffold that platform building is used for contracture shear wall pouring construction, meanwhile, contracture wall is climbed Rising columns assemblies can pour at the top of the contracture shear wall of completion along the inside Slideslip of top beam and being supported in of steel platform, so that The Core Walls Structure shear wall of contracture shear wall and non-contracture can synchronous construction reinstalled after the completion of due-in point of shear wall pours Outer tub support unit two, each layer Core Walls Structure after implementing contracture using the integrally hoisting steel platform formwork system after re-assemblying The construction of shear wall, therefore, construction method of the invention are supported using detachable interior tub, and are combined and can be sheared with contracture The contracture wall of wall change width flexible modulation position climbs columns assemblies, realizes Core Walls Structure contracture shear wall and non-contracture The synchronous construction of Core Walls Structure shear wall substantially accelerate construction efficiency while guaranteeing construction safety.
Detailed description of the invention
Fig. 1 to Fig. 7 is that each step of construction contracture shear wall in one embodiment of contracture shear wall form frame system of the present invention is shown It is intended to;
Fig. 8 is that the contracture wall of one embodiment of contracture shear wall form frame system of the present invention climbs the structural representations of columns assemblies Figure;
Fig. 9 is the A-A cross-sectional view of Fig. 8;
Figure 10 is the structural schematic diagram that the interior tub of one embodiment of contracture shear wall form frame system of the present invention supports;
Figure 11 is the outer tub support of one embodiment of contracture shear wall form frame system of the present invention, interior tub bracket and has poured Connection relationship diagram between contracture shear wall.
Figure label is as follows:
Core Walls Structure shear wall 1;Contracture shear wall 2;Preformed hole 3;
Steel platform 10;Top beam 11;Interior tub support 20;Interior tub bracket 21;Inner cylinder frame body 22;Outer tub support 30; Outer tub support unit 1;Outer tub support unit 2 302;Climbing system 40;Set cap 51;Operation platform 52;It is oblique Support 53;Built-in fitting 1;
Contracture wall climbs columns assemblies 60;Lifting beam 61;Climb column 1;Supporting rod 611;First pedestal 612; Convex block 1;Connecting rod 1;Idler wheel 615;Second pedestal 616;Convex block 2 617;Connecting rod 2 618;
Contracture wall scaffold 55;Built-in fitting 2 212;Cross-tie 211;Telescopic steel corbel 213.
Specific embodiment
The present invention is described in further detail below in conjunction with the drawings and specific embodiments.It should be noted that attached drawing is adopted With very simplified form and using non-accurate ratio, only to facilitate, lucidly aid in illustrating the embodiment of the present invention Purpose.For sake of convenience, "upper" described below, "lower" are consistent with the upper and lower direction of attached drawing, but this can't be this hair The limitation of bright technical solution.
The integrally hoisting steel platform formwork system built for high-rise, Super High includes steel platform 10, support system and climbs System 40 is risen, steel platform 10 extends along 1 cross section of Core Walls Structure shear wall;Support system includes multiple interior tub supports 20 and multiple Outer tub support 30 (is outer tub support 30 positioned at 1 outside of Core Walls Structure shear wall, is positioned at 1 inside of Core Walls Structure shear wall 20), interior tub support 20 and outer tub support 30 are both secured to 10 bottom of steel platform, interior tub under Construction State for interior tub support Support 20 is supported in the preformed hole 3 of Core Walls Structure shear wall 1 by being located at the telescopic steel corbel 213 of its bottom;Climbing system 40 include climbing boots, hydraulic system and the column that climbs being arranged in steel platform 10, and the column that climbs, which is vertically fixed on Core Walls Structure, to be cut The concreting finished surface of power wall 1, climbing boots are set in steel platform 10 and are firmly connected with it, and climbing boots and hydraulic pressure system System connection, integrally hoisting steel platform formwork system realize core by the climbing technology that support system replaces support with climbing system 40 The construction of heart cylinder shear wall 1;Illustrate contracture shear wall form frame system of the invention below with reference to Fig. 4, it includes close to wait pour The inside of contracture shear wall 2 interior tub bracket 21, and the outer tub support unit close to 2 outside of contracture shear wall to be poured 1, within tub bracket 21 and outer tub support unit 1 be the outstanding anchor scaffold of putting up platform, and be set to 2 top of contracture shear wall poured and the columns assemblies that can climb along the contracture wall of the horizontal sliding of top beam 11 of steel platform 10 60;Interior tub bracket 21 and inner cylinder frame body 22 constitute by an active connection interior tub support 20, and interior tub bracket 21 is along steel platform The width W in 10 horizontal extension directions is equal to or more than the vertical projection width of contracture shear wall 2 to be poured;Outstanding anchor scaffold is used In the concrete pouring construction of contracture shear wall 2.
Contracture shear wall form frame system of the invention, including the interior tub branch being arranged around contracture shear wall 2 to be poured Frame 21, outer tub support unit 1, outstanding anchor scaffold and it is set to 2 top of contracture shear wall poured and can be along steel The contracture wall of the horizontal sliding of the top beam 11 of platform 10 climbs columns assemblies 60, climbs in integrally hoisting steel platform formwork system When journey encounters the contracture shear wall 2 wait pour, being flexibly connected between interior tub bracket 21 and inner cylinder frame body 22 is dismantled, is split The width of interior tub bracket 21 afterwards be equal to or more than contracture shear wall 2 to be poured vertical projection width, within tub branch Frame 21 and outer tub support unit 1 are that the outstanding anchor scaffold of platform building is applied convenient for the concreting of contracture shear wall 2 Work;It climbs columns assemblies 60 moreover, contracture wall is arranged at the top of contracture shear wall 2 to be poured, contracture wall climbs column Component 60 can enable contracture wall to climb columns assemblies 60 always along the horizontal sliding inwardly of top beam 11 of steel platform 10 The top of the contracture shear wall 2 poured positioned at each layer, therefore, while successively construction contracture shear wall 2, the core of non-contracture Heart cylinder shear wall 1 can synchronous construction, complete current layer pouring construction steel platform 10 can rely on existing climbing system and The Core Walls Structure shear wall of the contracture shear wall 2 and non-contracture that have poured vertically is climbed and passed through to contracture wall columns assemblies 60 of climbing 1, which split and has been transformed to the existing structure of integrally hoisting steel platform formwork system, improves The utilization rate of material, the contracture wall added columns assemblies 60 of climbing can guarantee steel platform 10 after the completion of current layer construction Vertically climb, while guaranteeing construction safety, substantially accelerate construction efficiency.Contracture shear wall form frame system of the invention It is particularly suitable for the safety with the complicated Core Walls Structure of facade contracture shear wall 2, rapid construction.
As shown in Figure 8 and Figure 9, contracture wall columns assemblies 60 of climbing include: vertically to be embedded at steel platform 10 adjacent two Lifting beam 61 between top beam 11 disposed in parallel, and it is vertically fixed in the column 1 that climbs at 61 top of lifting beam, it is promoted Beam 61 is by supporting rod 611 and is installed on four sliding blocks of 611 end of supporting rod and forms, and supporting rod 611 is by being spaced Upper flange, the lower wing plate of setting, and the rod piece in the shape of an " I " positioned at the longitudinal section that web between the two is constituted, such as Fig. 9 institute Show, the both ends at the top of 611 upper flange of supporting rod are separately installed with first sliding block, and the first sliding block includes being equipped with groove The first pedestal 612, in the grooves the convex block 1 in portion be equipped with connecting rod 1, the both ends of connecting rod 1 are pacified Similar equipped with idler wheel 615, the both ends of 611 lower wing plate bottom of supporting rod are separately installed with second sliding block, and second is sliding Row block includes setting reeded second pedestal 616, and the convex block 2 617 in portion is equipped with connecting rod 2 618, connecting rod in the grooves 2 618 both ends are mounted on idler wheel 615, are set in the notch of two sides top beam 11, are made due to the end vertical of lifting beam 61 Obtaining lifting beam 61 can slide along the notch of adjacent two top beams 11.Therefore, with the layer-by-layer construction of contracture shear wall 2, contracture Wall climbs columns assemblies 60 can be along the gradually inside Slideslip of top beam 11, so that the column 1 that climbs is always in vertical configuration State, to guarantee that the stabilization of steel platform 10 is climbed, realize contracture shear wall 2 and the Core Walls Structure shear wall of non-contracture synchronize apply Work.
More preferably, it is also equipped with limiting device (not shown) in lifting beam 61, climbed columns assemblies in contracture wall After 60 slide into 2 top of contracture shear wall for having poured completion, the positioning for the column 1 that climbs is realized using limiting device, is avoided Subsequent steel platform 10 climb during climb column 1 occur sliding, shifting phenomena, to guarantee that the safety of steel platform 10 is applied Work.Mechanical limiting device mostly uses the structures such as lever, cam, and specific structure and connection relationship are in the prior art Hold, is no longer described in detail.
As shown in figure 11, hanging anchor scaffold includes: to be installed on one 301 top of interior tub bracket 21 and outer tub support unit Set cap 51, be layed in the operation platform 52 of the top of set cap 51, and build in the battered wall on operation platform 52 Body scaffold 55;Using after fractionation interior tub bracket 21 and outer tub support unit 1 be platform building hang anchor scaffold, For the concrete pouring construction of contracture shear wall 2, the existing structure of interior tub support 20 is taken full advantage of, scaffold is simplified Structure improves the utilization rate of material.
Further, as shown in figure 11, above-mentioned set cap 51 passes through built-in fitting 1 and skewed horizontal load 53 and has poured Contracture shear wall 2 be attached, built-in fitting 1 is embedded in the contracture shear wall 2 poured, one end of skewed horizontal load 53 It is bolted or welds with built-in fitting 1, the other end of skewed horizontal load 53 is connect with set cap 51, and skewed horizontal load 53 inclines Rake angle is preferably between 30 °~60 °, and one of skewed horizontal load 53 is arranged in horizontal interval 4m~6m, to guarantee that set cap 51 is steady Surely it is supported in the contracture shear wall 2 poured;Interior tub bracket 21 and outer tub support unit 1 use multiple built-in fittings two 212 and cross-tie 211 connect with the Core Walls Structure shear wall 1 of the non-contracture of the contracture shear wall 2 poured and its underpart, built-in fitting 2 212 are embedded in the Core Walls Structure shear wall 1 of the non-contracture of the contracture shear wall 2 poured and its underpart, horizontally disposed transverse direction One end of pull rod 211 is bolted with built-in fitting 2 212, the other end of cross-tie 211 and interior tub bracket 21 or outer tub The vertical upright column of support unit 1 connects, and cross-tie 211 is set to interior tub bracket 21 second step, the 4th from top to bottom The position of step, the 6th step, outer tub support unit 1 is drawn with interior tub bracket 21 by multiple built-in fittings and laterally as a result, Bar 211 is securely connect with the Core Walls Structure shear wall 1 of the non-contracture of the contracture shear wall 2 poured and its underpart, thus to be subsequent outstanding Building for anchor scaffold provides safe and reliable operating platform.
As shown in Figure 10, inner cylinder frame body 22 (shown in the dotted line wire frame of figure middle and upper part) is a complete frame structure, interior Tub main body 22 bottom four vertex angle part is equipped with telescopic steel corbel 213, interior 21 (figure middle and lower part dotted line wire frame institute of tub bracket Show) be complete frame structure half, the both ends of interior tub bracket 21 are respectively provided with a telescopic steel corbel 213, therefore, this reality The interior tub support 20 for applying example constitutes the frame structure of " 1+0.5 ", the activity between interior tub bracket 21 and inner cylinder frame body 22 It is connected as pin connection or is bolted, fractionation is convenient, fast, reduces overhead welding operation, improves working security;More Good, two telescopic steel corbels 213 of the end Angle Position of the close contracture shear wall 2 of the inner cylinder frame body 22 after fractionation support In the preformed hole 3 of the Core Walls Structure shear wall 1 of vertical non-contracture, to guarantee the interior tub bracket 21 and interior tub master after splitting The stabilization of body 22 is supported in the Core Walls Structure shear wall 1 for having poured completion.Above-mentioned two telescopic steel corbel 213 can be in integrally hoisting steel Platform formwork system starts to enable when construction, can also enable after interior tub supports 20 fractionations.
Illustrate the construction method of contracture shear wall form frame system of the invention in conjunction with Fig. 1 to Fig. 7, contracture is cut in the present embodiment Power wall 2 is located at the (n+1)th to the n-th+6 layer, and steps are as follows for Specific construction:
S1: as shown in Figure 1, constructed the Core Walls Structure shear wall 1 of the non-contracture of each layer using integrally hoisting steel platform formwork system, Until 2 lower section n-th layer of contracture shear wall;
S2: as shown in Fig. 2, integrally hoisting steel platform formwork system is promoted to (n+1)th layer, (n+1)th layer i.e. contracture shearing Layer where 2 bottom of wall reinforces interior tub bracket 21, and the interior tub bracket 21 of fractionation is flexibly connected with inner cylinder frame body 22, and is torn open Except inner cylinder frame body 22 is close to the safety net of 2 side of contracture shear wall, removes the outer tub close to 2 side of contracture shear wall and support The connection of unit 1 and steel platform 10, within tub bracket 21 and outer tub support unit 1 be platform to be poured (n+1)th layer of outstanding anchor scaffold is set up in (n+1)th layer of 2 two sides of contracture shear wall, is to rely on installation to be poured with (n+1)th layer of outstanding anchor scaffold The template for the (n+1)th layer of contracture shear wall 2 built, and (n+1)th layer of contracture shear wall 2 of pouring construction, meanwhile, pouring construction (n+1)th The Core Walls Structure shear wall 1 of the non-contracture of layer climbs contracture wall columns assemblies 60 after concrete reaches the intensity of design requirement Along steel platform 10 top beam 11 into steel platform 10 Slideslip so that contracture wall climbs, columns assemblies 60, which are supported in, has poured At the top of (n+1)th layer of contracture shear wall 2 repeat the above steps as shown in Figures 3 to 5, successively construct n-th+2 ... n+6 layers Contracture shear wall 2, contracture wall columns assemblies 60 of climbing along top beam 11 gradually inside Slideslip and are supported in n-th+2 ... n+6 layers The concrete pouring construction of contracture shear wall 2 is successively completed at the top of contracture shear wall 2;
S3: as shown in fig. 6, the integrally hoisting steel platform formwork system after splitting continues to rise to the n-th+7 layers, and the is built N+7 layers of outstanding anchor scaffold, pouring construction are located at the n-th+7 layers Core Walls Structure shear wall for having poured the 2 non-contracture in top of contracture shear wall 1, it repeats the above steps, pouring construction n-th+8, n+9 layers of Core Walls Structure shear wall 1, as shown in fig. 7, removing the outer of outstanding anchor scaffold Batter hand cradle is cut to 2 top of contracture shear wall, the close contracture of the integrally hoisting steel platform formwork system after fractionation has been poured Outer tub support unit 2 302 is installed in 2 side of power wall, re-assemblies as a complete integrally hoisting steel platform mould bases body System, so that the size of the integrally hoisting steel platform formwork system after re-assemblying adapts to the Core Walls Structure shear wall 1 after contracture, so Afterwards, routinely construction procedure complete contracture after each layer Core Walls Structure shear wall 1 concrete pouring construction.
The construction method of contracture shear wall form frame system of the invention, firstly, being climbed in integrally hoisting steel platform formwork system After rising to 2 position of contracture shear wall wait pour, the interior tub bracket 21 and inner cylinder frame body 22 of flexible connection are split, and The connection for dismantling the outer tub support unit 1 and steel platform 10 close to contracture shear wall 2 to be poured, then, with inner cylinder Frame bracket 21 and outer tub support unit 1 are the outstanding anchor scaffold that platform building is used for 2 pouring construction of contracture shear wall, together When, contracture wall climb columns assemblies 60 can along steel platform 10 the inside Slideslip of top beam 11 and be supported in and poured completion The top of contracture shear wall 2, enables 1 synchronous construction of Core Walls Structure shear wall of contracture shear wall 2 and non-contracture, due-in sub-cut power After the completion of wall 2 pours, outer tub support unit 2 302 is reinstalled, utilizes the integrally hoisting steel platform mould bases after re-assemblying The construction of each layer Core Walls Structure shear wall 1 after system implementation contracture, therefore, construction method of the invention, in detachable Tub support 20, and combine the column group that can climb with the contracture wall of 2 change width flexible modulation position of contracture shear wall Part 60 realizes the synchronous construction of the Core Walls Structure shear wall 1 of Core Walls Structure contracture shear wall 2 and non-contracture, is guaranteeing construction safety Meanwhile substantially accelerating construction efficiency.
In above-mentioned steps S2, according to the difference of 2 tilt angle of contracture shear wall, determines the different fractionation time, as far as possible will Steel platform 10 is promoted to interior 20 outside of tub support with 2 bottom of contracture shear wall to be poured close to outside that is, interior tub support 20 Side and 2 bottom minimum horizontal distance of contracture shear wall to be poured are 10cm, are split in this, as interior tub support 20 critical Point is conducive to the company of interior tub bracket 21 and the contracture shear wall 2 poured after splitting while guaranteeing to climb safe It connects.
In above-mentioned steps S2, the exterior portion positioned at contracture shear wall 2 of outstanding anchor scaffold need to be set up outer with floor construction Enclose protection, and be located at 2 inboard portion of contracture shear wall then can in tub support 20 as protection, it is only necessary in interior tub main body 22 When bottom surmounts the set cap 51 of interior tub bracket 21, exposed inner cylinder frame body 22 is protected.
In above-mentioned steps S2, the set cap 51 across contracture shear wall 2 can be embedded in contracture with concrete pouring construction Inside shear wall 2, to improve the structural strength of interior tub bracket 21, keep it more firm.
Foregoing description is only the description to present pre-ferred embodiments, not to any restriction of the scope of the invention, this hair Any change, the modification that the those of ordinary skill in bright field does according to the disclosure above content, belong to scope of the claims.

Claims (10)

1. contracture shear wall form frame system characterized by comprising
Interior tub bracket, on the inside of contracture shear wall to be poured;
Outer tub support unit one, on the outside of contracture shear wall to be poured;
Outstanding anchor scaffold, is platform building with the interior tub bracket and the outer tub support unit one, is used for the receipts Divide the concrete structure construction of shear wall;
Contracture wall climbs columns assemblies, is set at the top of the contracture shear wall poured and can be along the top of steel platform The sliding of beam level;
The interior tub bracket and inner cylinder the frame body interior tub that constitutes by an active connection support, and the interior tub bracket is along steel platform The width in horizontal extension direction is equal to or more than the vertical projection width of the contracture shear wall to be poured.
2. contracture shear wall form frame system according to claim 1, which is characterized in that the contracture wall climbs column group Part includes: the lifting beam being vertically embedded between adjacent two top beams of the steel platform, and is vertically fixed in the lifting beam The column one that climbs at top, the lifting beam is by supporting rod and is installed on four sliding block groups of the supporting rod end At the supporting rod is to be in by spaced upper flange, lower wing plate, and positioned at the longitudinal section that web between the two is constituted The rod piece of I-shaped, the both ends at the top of the supporting rod upper flange are separately installed with first sliding block, and described first Sliding block include set reeded first pedestal, the convex block one in the middle part of groove be equipped with connecting rod one, the two of the connecting rod one End is mounted on idler wheel, and the both ends of supporting rod lower wing plate bottom are separately installed with second sliding block, and second slides Block includes setting reeded second pedestal, and the convex block two in the middle part of groove is equipped with connecting rod two, and the both ends of the connecting rod two are equal Idler wheel is installed, the lifting beam is slided along the notch of adjacent two top beams.
3. contracture shear wall form frame system according to claim 2, it is characterised in that: be also equipped with limit in the lifting beam Position device.
4. contracture shear wall form frame system according to claim 1, which is characterized in that the outstanding anchor scaffold includes: peace Set cap loaded on interior tub bracket and the top of outer tub support unit one, the construction being layed in above the set cap are flat Platform, and build in the contracture wall scaffold on the operation platform.
5. contracture shear wall form frame system according to claim 4, it is characterised in that: the set cap and the contracture poured It being connected between shear wall by built-in fitting one and skewed horizontal load, the built-in fitting one is embedded in the contracture shear wall poured, One end of the skewed horizontal load is bolted or welds with the built-in fitting one, the other end of the skewed horizontal load and the bracket Top beam connection, the tilt angle of the skewed horizontal load is between 30 °~60 °, and 4m~6m setting in horizontal interval is described oblique together To support.
6. contracture shear wall form frame system according to claim 4, it is characterised in that: the interior tub bracket and described outer Tub support unit one is by multiple built-in fittings two and cross-tie with the contracture shear wall poured and positioned at the core of its underpart The connection of heart cylinder shear wall, the built-in fitting two are embedded in the contracture shear wall poured and the Core Walls Structure shear wall positioned at its underpart Interior, one end of the cross-tie is bolted with the built-in fitting two, the other end of the cross-tie and the interior tub The connection of the vertical upright column of bracket or the outer tub support unit one.
7. contracture shear wall form frame system according to claim 1, it is characterised in that: said inner tube frame body with it is described interior Flexible connection between tub bracket is pin connection or is bolted.
8. contracture shear wall form frame system according to claim 1, it is characterised in that: inner cylinder frame body bottom four Vertex angle part is equipped with telescopic steel corbel, and the both ends of the interior tub bracket are respectively provided with a telescopic steel corbel, after fractionation Two telescopic steel corbels of the end Angle Position of the close contracture shear wall of inner cylinder frame body are supported in the core of vertical non-contracture In the preformed hole of heart cylinder shear wall.
9. the construction method of contracture shear wall form frame system, which is characterized in that steps are as follows:
S1: it is constructed using integrally hoisting steel platform formwork system to n-th layer below contracture shear wall to be poured;
S2: being promoted to (n+1)th layer for the integrally hoisting steel platform formwork system, reinforces interior tub bracket, splits the inner cylinder Frame bracket is flexibly connected with inner cylinder frame body, and removes the inner cylinder frame body close to the safety net of contracture shear wall side, Remove the connection of the outer tub support unit one and steel platform close to contracture shear wall side, with the interior tub bracket and The outer tub support unit one sets up (n+1)th layer of outstanding anchor foot hand in (n+1)th layer of contracture shear wall two sides to be poured for platform Frame is to rely on the template for installing (n+1)th layer of contracture shear wall to be poured, and pour and apply with described (n+1)th layer outstanding anchor scaffold (n+1)th layer of contracture shear wall of work, meanwhile, the Core Walls Structure shear wall of (n+1)th layer of non-contracture of pouring construction climbs contracture wall vertical Column assembly along steel platform top beam into integrally hoisting steel platform formwork system Slideslip, the column so that the contracture wall climbs Modular support shears coping in (n+1)th layer of contracture for having poured completion, repeats the above steps, successively construction n-th+2 ... n+m Layer contracture shear wall, contracture wall columns assemblies of climbing along top beam gradually inside Slideslip and are supported in n-th+2 ... n+m layers Contracture shears coping, successively completes the concrete pouring construction of contracture shear wall;
S3: the integrally hoisting steel platform formwork system after fractionation continues to climb and pouring construction is sheared positioned at contracture has been poured Core Walls Structure shear wall above wall;
Wherein, n is the natural number more than or equal to 5, and m is the natural number more than or equal to 1.
10. construction method according to claim 9, it is characterised in that: in the step S2, set cap is poured with concrete Construction is built to be embedded in inside contracture shear wall.
CN201811316223.3A 2018-11-07 2018-11-07 Formwork system for collecting and dividing shear wall and construction method thereof Active CN109457951B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811316223.3A CN109457951B (en) 2018-11-07 2018-11-07 Formwork system for collecting and dividing shear wall and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811316223.3A CN109457951B (en) 2018-11-07 2018-11-07 Formwork system for collecting and dividing shear wall and construction method thereof

Publications (2)

Publication Number Publication Date
CN109457951A true CN109457951A (en) 2019-03-12
CN109457951B CN109457951B (en) 2024-02-13

Family

ID=65609631

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811316223.3A Active CN109457951B (en) 2018-11-07 2018-11-07 Formwork system for collecting and dividing shear wall and construction method thereof

Country Status (1)

Country Link
CN (1) CN109457951B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114541740A (en) * 2022-01-06 2022-05-27 上海建工一建集团有限公司 Integral steel platform formwork equipment for inclined wall construction and construction method thereof
CN115306152A (en) * 2022-10-12 2022-11-08 上海建工一建集团有限公司 Large-inclination-angle inclined wall folding and separating jacking type steel platform construction device and method
CN115306136A (en) * 2022-10-12 2022-11-08 上海建工一建集团有限公司 Inclined wall eversion climbing type steel platform construction device and method
WO2023240815A1 (en) * 2022-06-13 2023-12-21 上海建工一建集团有限公司 Implementation scaffold for inclined wall and method for using same
WO2023240813A1 (en) * 2022-06-13 2023-12-21 上海建工一建集团有限公司 Steel platform deformation construction structure and method for construction of sloping wall of core tube

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA2394057A1 (en) * 2001-08-20 2003-02-20 Matthew Russell Methods and apparatus for building tall vertical structures
WO2013185277A1 (en) * 2012-06-11 2013-12-19 浙江省建工集团有限责任公司 Constructing method for concrete cylinder of construction steel bar of high-rise steel structure
CN103741947A (en) * 2014-01-17 2014-04-23 上海建工集团股份有限公司 Tube-frame-supporting type hydraulic climbing integral steel platform formwork truss layer construction method
CN103967277A (en) * 2014-05-21 2014-08-06 中国建筑第八工程局有限公司 Construction method of super-high-rise core tube inclined shear wall
CN206289963U (en) * 2016-06-02 2017-06-30 中国建筑第八工程局有限公司 For the climbing form system of section Core tube construction
CN209620571U (en) * 2018-11-07 2019-11-12 上海建工一建集团有限公司 Contracture shear wall form frame system

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA2394057A1 (en) * 2001-08-20 2003-02-20 Matthew Russell Methods and apparatus for building tall vertical structures
WO2013185277A1 (en) * 2012-06-11 2013-12-19 浙江省建工集团有限责任公司 Constructing method for concrete cylinder of construction steel bar of high-rise steel structure
CN103741947A (en) * 2014-01-17 2014-04-23 上海建工集团股份有限公司 Tube-frame-supporting type hydraulic climbing integral steel platform formwork truss layer construction method
CN103967277A (en) * 2014-05-21 2014-08-06 中国建筑第八工程局有限公司 Construction method of super-high-rise core tube inclined shear wall
CN206289963U (en) * 2016-06-02 2017-06-30 中国建筑第八工程局有限公司 For the climbing form system of section Core tube construction
CN209620571U (en) * 2018-11-07 2019-11-12 上海建工一建集团有限公司 Contracture shear wall form frame system

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
曾智宏等: "上海世贸国际广场核心筒自升式钢平台施工系统" *
白宝军;郭应林;许超;刘鹏;张健康;程鹏;张积杰;: "基于智能集成平台的核心筒斜墙段施工关键技术研究与应用" *
龚剑;李鹏;扶新立;刘伟;: "上海环球金融中心核心筒结构施工中格构柱支撑式整体自升钢平台脚手模板系统施工技术" *

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114541740A (en) * 2022-01-06 2022-05-27 上海建工一建集团有限公司 Integral steel platform formwork equipment for inclined wall construction and construction method thereof
WO2023240815A1 (en) * 2022-06-13 2023-12-21 上海建工一建集团有限公司 Implementation scaffold for inclined wall and method for using same
WO2023240813A1 (en) * 2022-06-13 2023-12-21 上海建工一建集团有限公司 Steel platform deformation construction structure and method for construction of sloping wall of core tube
CN115306152A (en) * 2022-10-12 2022-11-08 上海建工一建集团有限公司 Large-inclination-angle inclined wall folding and separating jacking type steel platform construction device and method
CN115306136A (en) * 2022-10-12 2022-11-08 上海建工一建集团有限公司 Inclined wall eversion climbing type steel platform construction device and method
CN115306152B (en) * 2022-10-12 2022-12-16 上海建工一建集团有限公司 Large-inclination-angle inclined wall folding and separating jacking type steel platform construction device and method
CN115306136B (en) * 2022-10-12 2022-12-16 上海建工一建集团有限公司 Inclined wall eversion climbing type steel platform construction device and method
WO2024077880A1 (en) * 2022-10-12 2024-04-18 上海建工一建集团有限公司 Inclining jacking-type steel platform construction apparatus and method for inclining walls having large inclination angle
WO2024077879A1 (en) * 2022-10-12 2024-04-18 上海建工一建集团有限公司 Climbing type steel platform construction device and method for outward-inclined wall

Also Published As

Publication number Publication date
CN109457951B (en) 2024-02-13

Similar Documents

Publication Publication Date Title
CN109457951A (en) Contracture shear wall form frame system and its construction method
CN209620571U (en) Contracture shear wall form frame system
CN102661039A (en) Drum frame supporting power built-in integrated jacking steel platform formwork system and construction method
CN106437130A (en) Inner roof external climbing type formwork construction platform for super high-rise building construction
CN209482679U (en) Tub brace type integral steel platform suitable for sloping core construction
CN109457931A (en) Tub brace type integral steel platform and its construction method suitable for sloping core construction
CN100365237C (en) Autolifting type variable-shape diassembllable integrated lifting steel plateform system and construction method thereof
CN106812328B (en) The whole two step lifting construction methods of string prestressed steel structure rack with hanging layer
CN102912996B (en) Steel tube concrete column high-altitude construction safety protection system
CN109457930A (en) Integrally hoisting steel platform and its construction method for irregular wall construction
CN109057321B (en) Integral steel platform mould bases super large bearing capacity attached wall system and construction method
CN104947926A (en) Core tube inner tank upper formwork system hard protection device and construction method thereof
CN108360380A (en) A kind of bridge pier column construction operation platform and its construction method
CN108331336A (en) The integrated lifting steel plateform system and its construction method of floor synchronous construction
CN202954552U (en) Steel tube concrete column high-altitude construction safety protection system
CN102767282B (en) Assembly-type high-formwork construction method for cantilever of oversized special-shaped conversion layer
CN107419746A (en) A kind of mobile formwork system and its construction method
CN110042743A (en) The hydraulic climbing die block system of twin legged thin wall hollow pier with synchronize climb construction technology
CN107130521B (en) A kind of dell precipice section large-section beam Bailey truss hoisting die construction method
CN106522541B (en) A kind of template suspension centre spandrel girder of steel platform and the hanging method of template system
CN209482678U (en) Integrally hoisting steel platform for irregular wall construction
CN203034799U (en) Tower hoist standard knot bearing overhead support formwork steel platform structure
CN205329640U (en) " T " supports symmetrical sliding formwork construction structures
CN209211877U (en) Steel platform of climbing support device
CN208734045U (en) Monoblock type mould bases for Super High fission conjoined composite structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant