CN109447441A - A kind of probabilistic transient stability methods of risk assessment of consideration new energy unit - Google Patents
A kind of probabilistic transient stability methods of risk assessment of consideration new energy unit Download PDFInfo
- Publication number
- CN109447441A CN109447441A CN201811213071.4A CN201811213071A CN109447441A CN 109447441 A CN109447441 A CN 109447441A CN 201811213071 A CN201811213071 A CN 201811213071A CN 109447441 A CN109447441 A CN 109447441A
- Authority
- CN
- China
- Prior art keywords
- section
- power
- new energy
- failure
- unit
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims abstract description 44
- 230000001052 transient effect Effects 0.000 title claims abstract description 41
- 238000012502 risk assessment Methods 0.000 title claims abstract description 24
- 230000005540 biological transmission Effects 0.000 claims abstract description 32
- 238000011156 evaluation Methods 0.000 claims abstract description 6
- 230000001186 cumulative effect Effects 0.000 claims abstract description 5
- 238000005286 illumination Methods 0.000 claims abstract description 5
- 230000035945 sensitivity Effects 0.000 claims description 7
- 238000004088 simulation Methods 0.000 claims description 5
- 230000008569 process Effects 0.000 claims description 4
- 238000010206 sensitivity analysis Methods 0.000 claims description 4
- 206010063659 Aversion Diseases 0.000 claims description 3
- 230000009471 action Effects 0.000 claims description 3
- 230000001174 ascending effect Effects 0.000 claims description 3
- 230000005611 electricity Effects 0.000 claims description 3
- 238000012163 sequencing technique Methods 0.000 claims description 3
- 230000004888 barrier function Effects 0.000 claims description 2
- 210000004209 hair Anatomy 0.000 claims 1
- 238000011158 quantitative evaluation Methods 0.000 claims 1
- 239000000203 mixture Substances 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 238000013139 quantization Methods 0.000 description 2
- 230000009467 reduction Effects 0.000 description 2
- 239000000243 solution Substances 0.000 description 2
- 238000004458 analytical method Methods 0.000 description 1
- 238000004364 calculation method Methods 0.000 description 1
- 238000004140 cleaning Methods 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000005315 distribution function Methods 0.000 description 1
- 238000005265 energy consumption Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000013277 forecasting method Methods 0.000 description 1
- 239000000446 fuel Substances 0.000 description 1
- 239000005431 greenhouse gas Substances 0.000 description 1
- 238000002347 injection Methods 0.000 description 1
- 239000007924 injection Substances 0.000 description 1
- 230000002265 prevention Effects 0.000 description 1
- 238000004445 quantitative analysis Methods 0.000 description 1
- 230000003068 static effect Effects 0.000 description 1
- 230000002123 temporal effect Effects 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0635—Risk analysis of enterprise or organisation activities
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/06—Energy or water supply
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/80—Management or planning
- Y02P90/82—Energy audits or management systems therefor
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Engineering & Computer Science (AREA)
- Economics (AREA)
- Strategic Management (AREA)
- Theoretical Computer Science (AREA)
- Entrepreneurship & Innovation (AREA)
- Health & Medical Sciences (AREA)
- Marketing (AREA)
- General Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- Tourism & Hospitality (AREA)
- Physics & Mathematics (AREA)
- Public Health (AREA)
- Primary Health Care (AREA)
- Water Supply & Treatment (AREA)
- Development Economics (AREA)
- Educational Administration (AREA)
- General Health & Medical Sciences (AREA)
- Game Theory and Decision Science (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Supply And Distribution Of Alternating Current (AREA)
Abstract
The invention discloses a kind of probabilistic transient stability methods of risk assessment of consideration new energy unit, generate forecast failure based on power grid current operating conditions and carry out Transient Stability Evaluation, identify the corresponding transient state stable key transmission cross-section of the failure;Each new energy power plant power output interval probability is obtained by short-term wind-force, intensity of illumination prediction result, carries out power interval and its probability that probabilistic load flow obtains key transmission cross-section;Increase new energy unit output and assess the severity of failure, by the cumulative risk indicator as failure of section power section operation risk.If the risk indicator of failure is greater than threshold value, preferentially taking under the premise of preferentially guaranteeing new energy power plant power output reduces conventional power unit power output measure, as that cannot meet the requirements, guarantees that risk indicator is less than threshold value by way of limitation new energy power plant power output.The method of the present invention can comprehensively reflect the service condition of system and potential risk and tender spots in discovery system, play the operation potentiality of power grid.
Description
Technical field
The present invention relates to a kind of probabilistic transient stability methods of risk assessment of consideration new energy unit, belong to power train
System field of automation technology.
Background technique
The new cleaning fuels such as wind-powered electricity generation, photovoltaic greatly develop the discharge that can reduce greenhouse gases, save fossil energy
Consumption, but due to new energy power output uncertainty and intermittence, large-scale grid connection brings huge to electric power netting safe running
Big challenge.Consider that new energy probabilistic methods of risk assessment of contributing can comprehensively reflect the service condition of system, and
It was found that potential risk and tender spots in system, the operation potentiality of power grid are further played by preventing pre-control.
Currently, by consider new energy contribute temporal characteristics short-term new energy power forecasting method can provide it is several can
The power output scene of energy and the new energy power output probability of each scene.On quickly decoupling tide model or sensitivity analysis technique basis
On, the probability-distribution function of each state variable can be obtained using the probabilistic load flow of Cumulants method and calculating speed can
To meet application on site requirement, commented comprehensively by the risk indicators such as the out-of-limit probability of each state variable and generation severity of consequence
Estimate system risk.However, the above method is only capable of assessing the static security risk of system, the risk of transient stability is commented
Estimate it needs to be determined that running mode data and carry out time-domain-simulation, if system number containing wind power plant be M, what each wind power plant was estimated
Power output section number is K, then not knowing number of scenes is KMEven if it is temporary only to select a point to carry out each uncertain scene
State stability analysis calculates, and calculation amount is also unable to satisfy the requirement of online risk assessment.
EEAC extended equal area criterion quantitative analysis method can provide nargin and steady on the basis of failure time-domain-simulation
Mould-fixed Clustering information, the stable mode message reflection physical essence of angle stability, a certain angle stability mode correspond to one
A key sections.A kind of patent " identification method of transient state stable key transmission cross-section based on EEAC " (ZL
201611048235.3) the stable mode Clustering information provided based on EEAC utilizes each line in transient stability emulation dynamic process
The power swing amplitude on road, which screens candidate section composition branch, can accurately identify the corresponding pass with the mode by topology search
Key section.Method by finding key sections, can be by the section function of the power of extra-high dimension injection quantity space dimensionality reduction to low-dimensional
Rate space, and then each new energy power plant possible magnanimity of power output is not known into scene composition and is reduced to limited section power sky
Between scene, can satisfy online transient safe and stable risk assessment and prevention and control to effective requirement.
Summary of the invention
Purpose: in order to overcome the deficiencies in the prior art, it is uncertain that the present invention provides a kind of consideration new energy unit
The transient stability methods of risk assessment of property, potential risk and tender spots that can in time in discovery system, can satisfy and answer online
With needs.
Technical solution: in order to solve the above technical problems, the technical solution adopted by the present invention are as follows:
A kind of probabilistic transient stability methods of risk assessment of consideration new energy unit, includes the following steps:
Step 1: model parameter and current operating status based on power grid generate power flow files, stablize file and anticipation event
Hinder set F1, set F1Middle failure sum is N, sets currently processed failure serial number K=1, enters step 2;
Step 2: for set F1Middle k-th failure carries out transient stability quantization according to EEAC extended equal area criterion and comments
Estimate, such as its transient rotor angle stability nargin ηkLess than or equal to transient rotor angle stability nargin threshold value ηmin, then according to the master of EEAC offer
It leads complementation group unit and identifies the corresponding transient state stable key transmission cross-section of the failure;Otherwise, 9 are entered step;
Step 3: setting current time as th, subsequent time t is obtained by short-term wind-force, intensity of illumination prediction resulth+1Each new energy
Source power plant may contribute the probability C in sectionhi,;It enablesRepresent i-th of prediction
New energy power plant is in th+1The possibility power output section at moment, shares KXA section, whereinFor j-th of section, Respectively j-th of section power output lower limit value and power output upper limit value, j-th of section power output+1 section of upper limit value and jth go out
Power lower limit value is equal, then i-th of new energy power plant power output is in sectionProbability be Chi,jIfFor the power output intermediate value of the section bound, then it is believed that i-th of new energy power plant power output is's
Power output interval probability is Chi,j;
Step 4: sensitivity analysis is carried out to the key transmission cross-section of failure K identification, section power sensitivity coefficient is big
It is determined as related new energy power plant in the new energy power plant of threshold value, the section power sensitivity system based on related new energy power plant
Number and power output interval probability carry out probabilistic load flow, obtain power capability section and its probability [(Δ of key transmission cross-section
PLK.1,ChK.1),(ΔPLK.2,ChK.2),…(ΔPLK.M,ChK.M)], wherein Δ PLK.i,ChK.iRespectively i-th of section power area
Between intermediate value and power interval intermediate value probability, corresponding transmission cross-section power interval isFor area
Between lower limit of the power value and upper limit of the power value, M be transmission cross-section power interval sum;
Step 5: factor size being participated according to the leading complementation group unit that EEAC is provided, calculates separately key transmission cross-section phase
The Universal electric distance in new energy power plant bus and Critical Group and remaining group between all generator bus is closed, by related new energy
Source power plant is ranked up according to Universal electric apart from ascending sequence;It is obtained later by ultra-short term generation schedule and load prediction
Conventional power unit and load power are obtained, increases new energy power plant power output in order on this basis until i-th key transmission cross-section
Power reaches the section power section intermediate value, Transient Stability Evaluation is carried out to failure K based on the method for operation after adjustment, according to failure
The severity S of loss load total amount assessment failure afterwardseK.i, thus to obtain the operation risk I in the section power sectionrK.i=SeK.i*
ChK.i;It repeats the above process until section power section quantity reaches maximum value M, by the cumulative work of the risk in each section power section
For the risk indicator of failure K
Step 6: judging the risk indicator I of failure KrKWhether preassigned threshold value I is greater thanrK.th, such as larger than then turn
Enter step 7, is otherwise transferred to step 9;
Step 7: carrying out on-line operation risk-aversion control under the premise of preferentially guaranteeing new energy power plant power output;According to
EEAC provide Critical Group unit participate in factor size, meet system needs be rotated up and down spare capacity constraint under, gradually
The operation risk assessment that Critical Group conventional power unit contributes and carries out each section power section to failure K is reduced, until the wind of failure K
Dangerous index IrKLess than threshold value IrK.th, export conventional power unit and drop power output measure, enter step 9;Such as all Critical Group routine machines
The power output lower limit that group power output is down to permission is still unable to satisfy IrK< IrK.th, then 8 are entered step;
Step 8: the risk indicator I ' of failure K after step 7 reduces conventional power unit power outputrKOn the basis of, it is new by limiting
The mode of energy power plant power output guarantees that risk indicator is less than threshold value;Power capability section and its fortune based on key transmission cross-section
Row risk [(Δ PLK.1,IrK.1),(ΔPLK.2,IrK.2),…(ΔPLK.M,IrK.M)], by calculating formulaAt
Vertical section power section quantity maximum value M', wherein M'< M, obtains maximum allowable section power increment Delta PLK.M', output should
Power limit and conventional power unit drop power output measure enter step 9 as Control Measure;
Step 9:K=K+1 judges K≤N, reenters step 2 in this way, otherwise by the faulty Control Measure of institute
It is incorporated as the Control Measure of final output.
Preferably, the current time thWith subsequent time th+1Between be spaced 15min.
Preferably, the leading complementation group unit provided in the step 5 according to EEAC participates in factor size to pass
Key transmission cross-section correlation new energy power plant sort method is as follows:
5.1.1: institute in related new energy power plant bus and Critical Group and remaining group is calculated separately using formula (1) and (2)
There is the Universal electric distance between generator bus;Wherein, ajThe generator j transient rotor angle stability provided for EEAC participate in because
Son, xi.jFor the electrical distance between generator j bus and related new energy power plant bus i, S is generator number of units in Critical Group,
N is generator number of units in remaining group;
5.1.2: if XKN.i> XKS.i+ Δ X, Δ X are electrical distance threshold value, then it is critical to judge that new energy power plant i belongs to
Group;If XKS.i> XKN.i+ Δ X then judges that new energy power plant i belongs to remaining group;In Critical Group and remaining group respectively according to
XKS.iAnd XKN.iSize is ranked up new energy power plant, obtains related new energy power plant sequencing queue.
Preferably, section power is adjusted to calculative section power section intermediate value side in the step 5
Method is as follows:
5.2.1: conventional power unit and load power are adjusted to ultra-short term generation schedule and predicted load;
5.2.2: going out to try hard to keep by increasing Critical Group new energy power plant power output in order and reducing remaining group's new energy power plant
Power-balance is demonstrate,proved, such as remaining group's new energy power plant's undercapacity is to balance power, then by subtracting according to participation factor size order
Few remainder group's conventional power unit goes out dynamic balance, until reaching i-th of section power section intermediate value.
Preferably, the severity method of failure is assessed such as according to loss load total amount after failure in the step 5
Under:
5.3.1 consider that second defence line security control device and three lines of defence low-frequency and low-voltage subtract in the calculating of failure time-domain-simulation
It carries, disconnection device parsing action modeling, by statistics, failure directly causes load loss, second and third road defence line automatic safety device is cut
Severity index except loss load total amount, as failure.
Preferably, meet the requirements failure risk index by reducing conventional power unit power output in the step 7
Method is as follows:
7.1 participate in factor size according to the Critical Group unit that EEAC is provided, and preferentially reduce according to the big unit of the factor is participated in
Principle, gradually reduce Critical Group conventional power unit and contribute and carry out the operation risk assessment in each section power section to failure K,
Until failure risk index is met the requirements.
The utility model has the advantages that a kind of probabilistic transient stability risk assessment side of consideration new energy unit provided by the invention
Method generates forecast failure collection based on power grid current operating conditions and carries out Transient Stability Evaluation, is only less than to transient stability margin
Threshold value failure carries out risk assessment to meet online calculating speed requirement;On short-term new energy power plant power output fundamentals of forecasting,
Probabilistic load flow is carried out using sensitivity coefficient of the related new energy power plant power output to section power and further speeds up calculating speed
Degree;The severity that size order increases new energy unit output and assesses failure is influenced according on security margin, thus may be used
To obtain relatively conservative section power section operation risk;Reduction is taken under the premise of preferentially guaranteeing new energy power plant power output
Conventional power unit power output measure can satisfy actual motion requirement.Using the method for the present invention, it can comprehensively reflect the operation of system
Condition and potential risk and tender spots in discovery system, play the operation potentiality of power grid.
Detailed description of the invention
Fig. 1 is the flow diagram of the method for the present invention.
Specific embodiment
The present invention will be further explained with reference to the accompanying drawing.
A kind of probabilistic transient stability methods of risk assessment of consideration new energy unit is based on power grid current operating conditions
It generates forecast failure and carries out Transient Stability Evaluation, identify that the failure is corresponding temporarily according to the leading complementation group unit that EEAC is provided
State stablizes key transmission cross-section;Each new energy power plant power output interval probability is obtained by short-term wind-force, intensity of illumination prediction result,
Power interval and its probability that probabilistic load flow obtains key transmission cross-section are carried out on the basis of this;According to security margin
It influences size order to increase new energy unit output and assess the severity of failure, it is possible thereby to obtain relatively conservative section function
Rate section operation risk, by the cumulative risk indicator as failure of section power section operation risk.Such as the risk indicator of failure
Greater than threshold value, preferentially taking under the premise of preferentially guaranteeing new energy power plant power output reduces conventional power unit power output measure, if not
It is able to satisfy requirement and then guarantees that risk indicator is less than threshold value by way of limitation new energy power plant power output.As shown in Figure 1, it has
Steps are as follows for body:
Step 1: model parameter and current operating status based on power grid generate power flow files, stablize file and anticipation event
Hinder set F1, set F1Middle failure sum is N, sets currently processed failure serial number K=1, enters step 2;
Step 2: for set F1Middle k-th failure carries out transient stability quantization according to EEAC extended equal area criterion and comments
Estimate, such as its transient rotor angle stability nargin ηkLess than or equal to transient rotor angle stability nargin threshold value ηmin, then according to the master of EEAC offer
It leads complementation group unit and identifies the corresponding transient state stable key transmission cross-section of the failure;Otherwise, 9 are entered step;
Step 3: setting current time as th, subsequent time t is obtained by short-term wind-force, intensity of illumination prediction resulth+1(usually
After 15min) each new energy power plant may contribute the probability C in sectionhi,j;
It enablesI-th of new energy power plant of prediction is represented in th+1Moment
May contribute section, share KXA section, whereinFor j-th of section,Respectively j-th of section goes out
Power lower limit value and power output upper limit value, j-th section power output upper limit value is equal with+1 section power output lower limit value of jth, then i-th newly
Energy power plant contributes in sectionProbability be Chi,jIfFor going out for the section bound
Power intermediate value, then it is believed that i-th of new energy power plant power output isPower output interval probability be approximately Chi,j;
Step 4: sensitivity analysis is carried out to the key transmission cross-section of failure K identification, section power sensitivity coefficient is big
It is determined as related new energy power plant in the new energy power plant of threshold value, the section power sensitivity system based on related new energy power plant
Number and power output interval probability carry out probabilistic load flow, obtain power capability section and its probability [(Δ of key transmission cross-section
PLK.1,ChK.1),(ΔPLK.2,ChK.2),…(ΔPLK.M,ChK.M)], wherein Δ PLK.i,ChK.iRespectively i-th of section power area
Between intermediate value (increment on current section power level) and power interval intermediate value probability, corresponding transmission cross-section power interval is For section lower limit of the power value and upper limit of the power value, M is transmission cross-section power interval sum;
Step 5: factor size being participated according to the leading complementation group unit that EEAC is provided, calculates separately key transmission cross-section phase
The Universal electric distance in new energy power plant bus and Critical Group and remaining group between all generator bus is closed, by related new energy
Source power plant is ranked up according to Universal electric apart from ascending sequence.It is obtained later by ultra-short term generation schedule and load prediction
Conventional power unit and load power are obtained, increases new energy power plant power output in order on this basis until i-th key transmission cross-section
Power reaches the section power section intermediate value, Transient Stability Evaluation is carried out to failure K based on the method for operation after adjustment, according to failure
The severity S of loss load total amount assessment failure afterwardseK.i, thus to obtain the operation risk I in the section power sectionrK.i=SeK.i*
ChK.i.It repeats the above process until section power section quantity reaches maximum value M, by the cumulative work of the risk in each section power section
For the risk indicator of failure K
Wherein, the leading complementation group unit provided according to EEAC participates in factor size to key transmission cross-section correlation new energy
Power plant's sort method is as follows:
5.1.1: institute in related new energy power plant bus and Critical Group and remaining group is calculated separately using formula (1) and (2)
There is the Universal electric distance between generator bus.Wherein, ajThe generator j transient rotor angle stability provided for EEAC participate in because
Son, xi.jFor the electrical distance between generator j bus and related new energy power plant bus i, S is generator number of units in Critical Group,
N is generator number of units in remaining group.
5.1.2: if XKN.i> XKS.i+ Δ X (Δ X is electrical distance threshold value), then judge that new energy power plant i belongs to and face
Boundary group;If XKS.i> XKN.i+ Δ X then judges that new energy power plant i belongs to remaining group.In Critical Group and remaining group respectively according to
XKS.iAnd XKN.iSize is ranked up new energy power plant, obtains related new energy power plant sequencing queue.
Section power is adjusted as follows to calculative section power section median method:
5.2.1: conventional power unit and load power are adjusted to ultra-short term generation schedule and predicted load;
5.2.2: going out to try hard to keep by increasing Critical Group new energy power plant power output in order and reducing remaining group's new energy power plant
Power-balance is demonstrate,proved, such as remaining group's new energy power plant's undercapacity is to balance power, then by subtracting according to participation factor size order
Few remainder group's conventional power unit goes out dynamic balance, until reaching i-th of section power section intermediate value.
It is as follows according to the severity method for losing load total amount assessment failure after failure:
5.3.1 consider that second defence line security control device and three lines of defence low-frequency and low-voltage subtract in the calculating of failure time-domain-simulation
The modeling of the device actions such as load, off-the-line directly causes load loss, second and third road defence line automatic safety device by counting failure
The loss load total amount such as excision, the severity index as failure.
Step 6: judging the risk indicator I of failure KrKWhether preassigned threshold value I is greater thanrK.th, such as larger than then turn
Enter step 7, is otherwise transferred to step 9;
Step 7: carrying out on-line operation risk-aversion control under the premise of preferentially guaranteeing new energy power plant power output first.Root
According to EEAC provide Critical Group unit participate in factor size, meet system needs be rotated up and down spare capacity constraint under, by
Step reduces the operation risk assessment that Critical Group conventional power unit contributes and carries out each section power section to failure K, until failure K
Risk indicator IrKLess than threshold value IrK.th, export conventional power unit and drop power output measure, enter step 9;Such as all Critical Group routine machines
The power output lower limit that group power output is down to permission is still unable to satisfy IrK< IrK.th, then 8 are entered step;
It is wherein as follows by reducing the method that conventional power unit power output meets the requirements failure risk index:
Factor size is participated according to the Critical Group unit that EEAC is provided, the original preferentially reduced according to the big unit of the participation factor
Then, the operation risk assessment that Critical Group conventional power unit contributes and carries out each section power section to failure K is gradually reduced, until therefore
Barrier risk indicator is met the requirements.
Step 8: the risk indicator I ' of failure K after step 7 reduces conventional power unit power outputrKOn the basis of, it is new by limiting
The mode of energy power plant power output guarantees that risk indicator is less than threshold value;Power capability section and its fortune based on key transmission cross-section
Row risk [(Δ PLK.1,IrK.1),(ΔPLK.2,IrK.2),…(ΔPLK.M,IrK.M)], by calculating formulaAt
Vertical section power section quantity maximum value M', wherein M'< M, obtains maximum allowable section power increment Delta PLK.M', output should
Power limit and conventional power unit drop power output measure enter step 9 as Control Measure;
Step 9:K=K+1 judges K≤N, reenters step 2 in this way, otherwise by the faulty Control Measure of institute
It is incorporated as the Control Measure of final output.
The above is only a preferred embodiment of the present invention, it should be pointed out that: for the ordinary skill people of the art
For member, various improvements and modifications may be made without departing from the principle of the present invention, these improvements and modifications are also answered
It is considered as protection scope of the present invention.
Claims (6)
1. a kind of probabilistic transient stability methods of risk assessment of consideration new energy unit, it is characterised in that: including walking as follows
It is rapid:
Step 1: model parameter and current operating status based on power grid generate power flow files, stablize file and forecast failure collection
Close F1, set F1Middle failure sum is N, sets currently processed failure serial number K=1, enters step 2;
Step 2: for set F1Middle k-th failure carries out transient stability quantitative evaluation according to EEAC extended equal area criterion, such as
Its transient rotor angle stability nargin ηkLess than or equal to transient rotor angle stability nargin threshold value ηmin, then provided according to EEAC leading mutual
It mends group's unit and identifies the corresponding transient state stable key transmission cross-section of the failure;Otherwise, 9 are entered step;
Step 3: setting current time as th, subsequent time t is obtained by short-term wind-force, intensity of illumination prediction resulth+1Each new energy electricity
Factory may contribute the probability C in sectionhi,j;It enablesRepresent i-th of new energy of prediction
Source power plant is in th+1The possibility power output section at moment, shares KXA section, whereinFor j-th of section,
Respectively j-th of section power output lower limit value and power output upper limit value, j-th of section are contributed under+1 section power output of upper limit value and jth
Limit value is equal, then i-th of new energy power plant power output is in sectionProbability be Chi,jIf
For the power output intermediate value of the section bound, then it is believed that i-th of new energy power plant power output isPower output interval probability be
Chi,j;
Step 4: sensitivity analysis being carried out to the key transmission cross-section of failure K identification, section power sensitivity coefficient is greater than door
The new energy power plant of threshold value is determined as related new energy power plant, the section power sensitivity coefficient based on related new energy power plant and
Interval probability of contributing carries out probabilistic load flow, obtains power capability section and its probability [(the Δ P of key transmission cross-sectionLK.1,
ChK.1),(ΔPLK.2,ChK.2),…(ΔPLK.M,ChK.M)], wherein Δ PLK.i,ChK.iIn respectively i-th of section power section
Value and power interval intermediate value probability, corresponding transmission cross-section power interval are For section function
Rate lower limit value and upper limit of the power value, M are transmission cross-section power interval sum;
Step 5: factor size being participated according to the leading complementation group unit that EEAC is provided, it is related new to calculate separately key transmission cross-section
Universal electric distance in energy power plant bus and Critical Group and remaining group between all generator bus, by related new energy electricity
Factory is ranked up according to Universal electric apart from ascending sequence;It is obtained later by ultra-short term generation schedule and load prediction normal
Unit and load power are advised, increases new energy power plant power output in order on this basis until i-th of key transmission cross-section power
The section power section intermediate value is reached, Transient Stability Evaluation is carried out to failure K based on the method for operation after adjustment, according to damaging after failure
Lose the severity S of load total amount assessment failureeK.i, thus to obtain the operation risk I in the section power sectionrK.i=SeK.i*
ChK.i;It repeats the above process until section power section quantity reaches maximum value M, by the cumulative work of the risk in each section power section
For the risk indicator of failure K
Step 6: judging the risk indicator I of failure KrKWhether preassigned threshold value I is greater thanrK.th, such as larger than then it is transferred to step
7, otherwise it is transferred to step 9;
Step 7: carrying out on-line operation risk-aversion control under the premise of preferentially guaranteeing new energy power plant power output;It is mentioned according to EEAC
The Critical Group unit of confession participates in factor size, meet system needs be rotated up and down spare capacity constraint under, gradually reduce and face
Boundary's group's conventional power unit contributes and carries out the operation risk assessment in each section power section to failure K, until the risk indicator of failure K
IrKLess than threshold value IrK.th, export conventional power unit and drop power output measure, enter step 9;Such as all Critical Group conventional power unit power outputs are equal
The power output lower limit for being down to permission is still unable to satisfy IrK< IrK.th, then 8 are entered step;
Step 8: the risk indicator I ' of failure K after step 7 reduces conventional power unit power outputrKOn the basis of, by limiting new energy
The mode of power plant's power output guarantees that risk indicator is less than threshold value;Power capability section and its operation wind based on key transmission cross-section
Danger [(Δ PLK.1,IrK.1),(ΔPLK.2,IrK.2),…(ΔPLK.M,IrK.M)], by calculating formulaIt sets up
Section power section quantity maximum value M', wherein M'< M, obtains maximum allowable section power increment Delta PLK.M', export the power
Limit value and conventional power unit drop power output measure enter step 9 as Control Measure;
Step 9:K=K+1 judges K≤N, reenters step 2 in this way, otherwise merges the faulty Control Measure of institute
Control Measure as final output.
2. a kind of probabilistic transient stability methods of risk assessment of consideration new energy unit according to claim 1,
It is characterized in that: the current time thWith subsequent time th+1Between be spaced 15min.
3. a kind of probabilistic transient stability methods of risk assessment of consideration new energy unit according to claim 1,
Be characterized in that: the leading complementation group unit provided in the step 5 according to EEAC participates in factor size to key transmission cross-section phase
It is as follows to close new energy power plant sort method:
5.1.1: all hairs in related new energy power plant bus and Critical Group and remaining group are calculated separately using formula (1) and (2)
Universal electric distance between motor bus;Wherein, ajThe factor, x are participated in for the generator j transient rotor angle stability that EEAC is providedi.j
For the electrical distance between generator j bus and related new energy power plant bus i, S is generator number of units in Critical Group, and N is remaining
Generator number of units in lower group;
5.1.2: if XKN.i> XKS.i+ Δ X, Δ X are electrical distance threshold value, then judge that new energy power plant i belongs to Critical Group;
If XKS.i> XKN.i+ Δ X then judges that new energy power plant i belongs to remaining group;Respectively according to X in Critical Group and remaining groupKS.i
And XKN.iSize is ranked up new energy power plant, obtains related new energy power plant sequencing queue.
4. a kind of probabilistic transient stability methods of risk assessment of consideration new energy unit according to claim 1,
It is characterized in that: adjusting section power in the step 5 as follows to calculative section power section median method:
5.2.1: conventional power unit and load power are adjusted to ultra-short term generation schedule and predicted load;
5.2.2: guaranteeing function by increasing Critical Group new energy power plant power output in order and reducing remaining group's new energy power plant power output
Rate balance, such as remaining group's new energy power plant's undercapacity is to balance power, then by according to participating in more than factor size order reduces
Lower group's conventional power unit goes out dynamic balance, until reaching i-th of section power section intermediate value.
5. a kind of probabilistic transient stability methods of risk assessment of consideration new energy unit according to claim 1,
It is characterized in that: as follows according to the severity method for losing load total amount assessment failure after failure in the step 5:
5.3.1 consider in the calculating of failure time-domain-simulation second defence line security control device and three lines of defence low-frequency low-voltage load shedding,
Disconnection device parsing action modeling directly causes load loss, second and third road defence line automatic safety device excision damage by counting failure
Lose load total amount, the severity index as failure.
6. a kind of probabilistic transient stability methods of risk assessment of consideration new energy unit according to claim 1,
It is characterized in that: as follows by reducing the method that conventional power unit power output meets the requirements failure risk index in the step 7:
7.1 participate in factor size according to the Critical Group unit that EEAC is provided, the original preferentially reduced according to the big unit of the participation factor
Then, the operation risk assessment that Critical Group conventional power unit contributes and carries out each section power section to failure K is gradually reduced, until therefore
Barrier risk indicator is met the requirements.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811213071.4A CN109447441B (en) | 2018-10-17 | 2018-10-17 | Transient stability risk assessment method considering uncertainty of new energy unit |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811213071.4A CN109447441B (en) | 2018-10-17 | 2018-10-17 | Transient stability risk assessment method considering uncertainty of new energy unit |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109447441A true CN109447441A (en) | 2019-03-08 |
CN109447441B CN109447441B (en) | 2021-12-17 |
Family
ID=65547106
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811213071.4A Active CN109447441B (en) | 2018-10-17 | 2018-10-17 | Transient stability risk assessment method considering uncertainty of new energy unit |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109447441B (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110311419A (en) * | 2019-07-01 | 2019-10-08 | 国电南瑞科技股份有限公司 | New energy based on transient security nargin receives ability and minimum booting appraisal procedure |
CN111950765A (en) * | 2020-07-06 | 2020-11-17 | 四川大川云能科技有限公司 | Probabilistic transient stability prediction method based on stacked noise reduction self-encoder |
CN112036718A (en) * | 2020-08-19 | 2020-12-04 | 国电南瑞科技股份有限公司 | Electric power system safety risk assessment method considering new energy uncertainty |
CN112084663A (en) * | 2020-09-14 | 2020-12-15 | 江苏海洋大学 | Flexible pipeline three-dimensional numerical simulation method based on complex marine environment |
CN113077075A (en) * | 2021-03-15 | 2021-07-06 | 国网宁夏电力有限公司 | New energy uncertainty electric power system safety risk prevention control method and device |
CN113937757A (en) * | 2021-10-09 | 2022-01-14 | 国网安徽省电力有限公司电力科学研究院 | Electromagnetic transient stability control method and device based on energy storage and photovoltaic output |
CN115967126A (en) * | 2022-12-06 | 2023-04-14 | 哈尔滨工业大学 | Online analysis method for new energy cluster output outward-sending risk under natural disasters |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101640418A (en) * | 2009-09-03 | 2010-02-03 | 国网电力科学研究院 | Identification method of transient state stable key transmission cross-section of electric power system fault |
CN101969202A (en) * | 2010-11-23 | 2011-02-09 | 国网电力科学研究院 | Method for recognizing transmission section power limit interval of power system transient stability |
CN103440401A (en) * | 2013-07-31 | 2013-12-11 | 南京南瑞集团公司 | Risk quantitative assessment method for emergency control measure for improving power transmission capacity of power grid |
CN106602548A (en) * | 2016-11-25 | 2017-04-26 | 国电南瑞科技股份有限公司 | EEAC (extended equal area criterion)-based transient stability critical power transmission section identification method |
-
2018
- 2018-10-17 CN CN201811213071.4A patent/CN109447441B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101640418A (en) * | 2009-09-03 | 2010-02-03 | 国网电力科学研究院 | Identification method of transient state stable key transmission cross-section of electric power system fault |
CN101969202A (en) * | 2010-11-23 | 2011-02-09 | 国网电力科学研究院 | Method for recognizing transmission section power limit interval of power system transient stability |
CN103440401A (en) * | 2013-07-31 | 2013-12-11 | 南京南瑞集团公司 | Risk quantitative assessment method for emergency control measure for improving power transmission capacity of power grid |
CN106602548A (en) * | 2016-11-25 | 2017-04-26 | 国电南瑞科技股份有限公司 | EEAC (extended equal area criterion)-based transient stability critical power transmission section identification method |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110311419B (en) * | 2019-07-01 | 2022-09-06 | 国电南瑞科技股份有限公司 | New energy acceptance and minimum startup evaluation method based on transient safety margin |
CN110311419A (en) * | 2019-07-01 | 2019-10-08 | 国电南瑞科技股份有限公司 | New energy based on transient security nargin receives ability and minimum booting appraisal procedure |
CN111950765A (en) * | 2020-07-06 | 2020-11-17 | 四川大川云能科技有限公司 | Probabilistic transient stability prediction method based on stacked noise reduction self-encoder |
CN111950765B (en) * | 2020-07-06 | 2024-04-19 | 四川大川云能科技有限公司 | Probabilistic transient stability prediction method based on stacked noise reduction self-encoder |
CN112036718A (en) * | 2020-08-19 | 2020-12-04 | 国电南瑞科技股份有限公司 | Electric power system safety risk assessment method considering new energy uncertainty |
CN112036718B (en) * | 2020-08-19 | 2022-10-25 | 国电南瑞科技股份有限公司 | Electric power system safety risk assessment method considering new energy uncertainty |
CN112084663A (en) * | 2020-09-14 | 2020-12-15 | 江苏海洋大学 | Flexible pipeline three-dimensional numerical simulation method based on complex marine environment |
CN112084663B (en) * | 2020-09-14 | 2021-03-30 | 江苏海洋大学 | Flexible pipeline test system based on complex marine environment |
CN113077075B (en) * | 2021-03-15 | 2022-05-10 | 国网宁夏电力有限公司 | New energy uncertainty electric power system safety risk prevention control method and device |
CN113077075A (en) * | 2021-03-15 | 2021-07-06 | 国网宁夏电力有限公司 | New energy uncertainty electric power system safety risk prevention control method and device |
CN113937757A (en) * | 2021-10-09 | 2022-01-14 | 国网安徽省电力有限公司电力科学研究院 | Electromagnetic transient stability control method and device based on energy storage and photovoltaic output |
CN115967126A (en) * | 2022-12-06 | 2023-04-14 | 哈尔滨工业大学 | Online analysis method for new energy cluster output outward-sending risk under natural disasters |
CN115967126B (en) * | 2022-12-06 | 2024-03-22 | 哈尔滨工业大学 | Online analysis method for new energy cluster outcoming air supply risk under natural disasters |
Also Published As
Publication number | Publication date |
---|---|
CN109447441B (en) | 2021-12-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109447441A (en) | A kind of probabilistic transient stability methods of risk assessment of consideration new energy unit | |
CN108173293A (en) | Meter and the new energy active power output maximum value on-line calculation method of operation of power networks constraint | |
CN103473393B (en) | A kind of transmission of electricity nargin Controlling model modeling method considering random chance | |
CN105375533B (en) | A kind of independent micro-capacitance sensor operational mode Forecasting Methodology containing wind, light regenerative resource | |
CN103606913B (en) | Distributed hybrid power system power source planning method | |
CN109190792A (en) | A kind of method and system of the configuration of determining Distributed Generation in Distribution System | |
CN102915471A (en) | Wind power disturbance online safety precaution method | |
CN109149562B (en) | Economic dispatching method and device suitable for alternating current-direct current hybrid power grid | |
CN105244920B (en) | Consider the energy-storage system multi objective control method and its system of cell health state | |
CN104463697A (en) | Risk assessment method for power system including large-scale wind power | |
CN106600136A (en) | Electric power section off-limit control efficiency evaluation method | |
CN106099991B (en) | A kind of power grid wind electricity digestion capability appraisal procedure | |
CN109598377A (en) | A kind of alternating current-direct current mixing power distribution network robust planing method based on failure constraint | |
CN110245858A (en) | A kind of micro-capacitance sensor reliability estimation method containing electric automobile charging station | |
CN104319785A (en) | Source flow path electrical subdivision-based wind power system key node identification method | |
CN104779608A (en) | Safe stable on-line additional emergency control method of power system based on off-line strategy | |
CN104505855A (en) | Online evaluation system for grid-connected characteristic of wind power plant | |
CN109217294A (en) | Wind power plant large-scale power grid security assessment method | |
Zhang et al. | Boosting the power grid resilience under typhoon disasters by coordinated scheduling of wind energy and conventional generators | |
CN111049165A (en) | Method and system for energy storage configuration of new energy power system | |
CN104467198A (en) | Electric energy storage system based on online distribution | |
CN101325324B (en) | Anti-icing method for overhead wire based on real time operation mode | |
CN106022594B (en) | Electric system on-line operation safety risk estimating method based on extreme value theory | |
CN107846034A (en) | A kind of energy storage for stabilizing wind power plant climbing rate goes out force control method | |
CN108039728A (en) | Lift the real-time scheduling method of power grid clean energy resource digestion capability |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |