CN109442096A - Drawing device and its construction method in a kind of PCCP pipeline - Google Patents

Drawing device and its construction method in a kind of PCCP pipeline Download PDF

Info

Publication number
CN109442096A
CN109442096A CN201811645062.2A CN201811645062A CN109442096A CN 109442096 A CN109442096 A CN 109442096A CN 201811645062 A CN201811645062 A CN 201811645062A CN 109442096 A CN109442096 A CN 109442096A
Authority
CN
China
Prior art keywords
pccp pipeline
chain
pccp
drawing device
hangers
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811645062.2A
Other languages
Chinese (zh)
Inventor
刘伟群
韩晋国
侯波
李涛
黄凌春
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Jingshui Construction Group Co Ltd
Original Assignee
Beijing Jingshui Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Jingshui Construction Group Co Ltd filed Critical Beijing Jingshui Construction Group Co Ltd
Priority to CN201811645062.2A priority Critical patent/CN109442096A/en
Publication of CN109442096A publication Critical patent/CN109442096A/en
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/06Accessories therefor, e.g. anchors
    • F16L1/09Accessories therefor, e.g. anchors for bringing two tubular members closer to each other
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66FHOISTING, LIFTING, HAULING OR PUSHING, NOT OTHERWISE PROVIDED FOR, e.g. DEVICES WHICH APPLY A LIFTING OR PUSHING FORCE DIRECTLY TO THE SURFACE OF A LOAD
    • B66F19/00Hoisting, lifting, hauling or pushing, not otherwise provided for

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Structural Engineering (AREA)
  • Sewage (AREA)

Abstract

The present invention relates to drawing devices in a kind of PCCP pipeline, including internal crossbeam, outer transverse beams and chain block, the seam crossing between adjacent PCCP pipeline is arranged in the internal crossbeam, the outermost end of PCCP pipeline to be installed is arranged in the outer transverse beams, and the chain block is arranged between internal crossbeam and outer transverse beams.The present invention has the advantages that structure is simple and convenient to operate.

Description

Drawing device and its construction method in a kind of PCCP pipeline
Technical field
The present invention relates to the technical fields of PCCP Pipe installing, more particularly, to drawing device in a kind of PCCP pipeline and its apply Work method.
Background technique
Prestressed concrete cylinder pipe (Prestressed Concrete Cylinder Pipe, write a Chinese character in simplified form PCCP) refers to Ring orientation prestress steel wire, then the cement mortar protective course of the densification of spray on it are wound on high-strength concrete tube core with steel cylinder And manufactured water-supply-pipe.It is the composite pipe being made of sheet metal, high tensile steel wire and concrete, it is abundant and synthetically sends out The tension of steel, resistance to compression, the corrosion resistance of easily sealing and concrete are waved, with high leakproofness, high intensity and high-impermeable Characteristic.
It draws in equipment hand jack and tries to stop people from fighting each other in traditional PCCP Pipe installing, stress large arm force applying device is very heavy manually Top, when pipeline is moved to away from the 100~200mm of bellmouth for having installed pipeline, with wood lump supporting pad between two pipes, every preparation After the completion, the support pad lumps of wood is removed, carrying out interior draw makes to move in parallel slowly to tubulature, until installation gap as defined in reaching.Tradition Manual hydraulic jack pipe laying, jack operator needs at least six people, and since the PCCP of internal diameter 3.8m is managed Road weighs 70t, pipeline outer wall and tube seat Basement surge as f=0.28~0.30, and installer's labor intensity is very big, is easy Fatigue is not reinforced monitoring, and Pipe installing quality can not be effectively ensured.
It is a kind of for big that existing Chinese Patent Application No. for reference has been the patent disclosure of CN201620988162.5 Equipment is installed in the hydraulic interior drawing of type PCCP Pipe installing.Including the first support device, the second support device and hydraulic interior drawing device, The hydraulic interior drawing installation equipment further includes four connection steel discs, each of connection steel disc connection steel disc described in two of them One end be respectively articulated with the piston rod of the hydraulic cylinder one end, the other ends of described two connection steel discs hinged described the One end of one support beam, each of other two described connection steel disc connection steel disc is respectively articulated with the hydraulic cylinder The piston rod of the other end, hinged second support beam of the other end of other two connection steel disc.The patent utilizes hydraulic biography Dynamic structure substantially increases it is advantageously ensured that the quality of Pipe installing, the investment for reducing human resources, reducing construction cost The effect of installation, but its structure is relative complex, component is more, and construction can generate certain difficulty in pipeline.
Summary of the invention
The first purpose of the invention is to provide drawing device in a kind of PCCP pipeline, which has structure simple, construction Efficient advantage.
The purpose of the present invention is what is be achieved by the following technical programs:
Drawing device in a kind of PCCP pipeline, including internal crossbeam, outer transverse beams and chain block, the internal crossbeam are arranged in phase The outermost end of PCCP pipeline to be installed, the chain block is arranged in seam crossing between adjacent PCCP pipeline, the outer transverse beams It is arranged between internal crossbeam and outer transverse beams.
Internal crossbeam is connected to phase when carrying out the docking of PCCP pipeline to be installed by using above-mentioned technical proposal Seam crossing between adjacent PCCP pipeline, outer transverse beams are connected to the outermost end of PCCP pipeline to be installed, are distinguished by chain block It is connect with internal crossbeam and outer transverse beams, tenses chain block, in outer transverse beams, outer transverse beams drive to be installed pulling force effect PCCP pipeline to be installed carries out installation accuracy that is assembled, and passing through the control easily controllable PCCP pipeline of chain block.The present invention Structure is simple, the high advantage of installation accuracy.The structure for avoiding hydraulic interior drawing installation equipment is relative complex, and component is more, in pipe Construction can lead to the problem of certain difficulty in road.
The present invention is further arranged to: the both ends fixed setting first of the internal crossbeam is picked up the ears, and described first picks up the ears to insert The seam crossing between adjacent PCCP pipeline is connect, the both ends of the outer transverse beams fix second and pick up the ears, and described second picks up the ears to abut In the outermost end of PCCP pipeline to be installed.
By using above-mentioned technical proposal, the seam crossing being connected between adjacent PCCP pipeline is picked up the ears to internal horizontal by first Beam is fixed, and makes internal crossbeam as stable load end, and second is picked up the ears the outermost end for being connected to PCCP pipeline to be installed, Make outer transverse beams as force side, to reach the installation by chain block to PCCP pipeline to be installed.
The present invention is further arranged to: first being fixedly installed respectively by the position of two close end on the side wall of the internal crossbeam The second hangers is fixedly installed by the position of two close end in hangers, the outer transverse beams respectively, and the chain block includes fixed hook It is linked up with lifting, the fixed hook is connect with the first hangers, and the lifting hook is connect with the second hangers.
By using above-mentioned technical proposal, fixed hook is connect with the first hangers, lifting hook is connect with the second hangers, Connect it is fairly simple, it is easy to operate.
The present invention is further arranged to: transmission rod, the transmission rod two being arranged between the fixed hook and the first hangers End fixed setting shackle, the shackle of described transmission rod one end are connect with fixed hook, and the other end is hung by bow shackle and first Ear connection.
By using above-mentioned technical proposal, sometimes due to the length of PCCP pipeline is long, the length of chain block is discontented The length requirement of foot PCCP pipeline to be installed, is arranged transmission rod between internal crossbeam and chain block, can lengthen and pull calabash The action length of reed, while meeting the transmitting to chain block power again, so that chain block is adapted to the length of different PCCP pipelines.
The present invention is further arranged to: transmission rod, the transmission rod two is arranged between the lifting hook and the first hangers End fixed setting shackle, the shackle of described transmission rod one end and lifting hook connect, and the other end is hung by bow shackle and second Ear connection.
By using above-mentioned technical proposal, sometimes due to the length of PCCP pipeline is long, the length of chain block is discontented The length requirement of sufficient PCCP pipeline, is arranged transmission rod between outer transverse beams and chain block, can lengthen the work of chain block With length, while meeting the transmitting to chain block power again, chain block is made to adapt to the length of different PCCP pipelines.
The present invention is further arranged to: the chain block includes hoisting chain, fixed hook, lifting hook and bearing Seat, the hoisting chain both ends are fixed on bearing block, and the hoisting chain is linked up with across lifting, and the fixed hook is solid Fixed to be arranged on bearing block, the side of the bearing block is rotatably connected to rotating disc.
By using above-mentioned technical proposal, the hoisting chain both ends of chain block are separately fixed on bearing block, lifting Chain is linked up with across lifting, and hoisting chain is tightened and loosened by the rotating disc on rolling bearing seat, makes chain block Operation it is simpler, it is convenient.
The present invention is further arranged to: the rotating disc is connect by rotation axis with bearing block, the hoisting chain winding On the rotating shaft.
On the rotating shaft by hoisting chain winding prevent hoisting chain from turning in rotating disc by using above-mentioned technical proposal It is intertwined when dynamic, convenient for the winding of hoisting chain.
The present invention is further arranged to: reinforcing rod, the reinforcing rod one being fixedly installed between the rotating disc and rotation axis On the rotating shaft, the other end is welded on rotating disc for end setting, and the reinforcing rod is arranged multiple along rotating disc circumferencial direction.
Reinforce rotating disc and rotation by reinforcing rod by rotating disc and rotation axis connection by using above-mentioned technical proposal Bonding strength between axis keeps rotating disc more stable in rotation.
The present invention is further arranged to: the rotating disc has been arranged radially multiple insertion pipes.
By using above-mentioned technical proposal, chain tightening is being pulled, when steering wheel rotation is relatively difficult, is being inserted in insertion pipe Enter steel pipe, using lever principle, steering wheel continues to rotate steering wheel by bigger power, easy to operate.
A second object of the present invention is to provide drawing device and its construction methods in a kind of PCCP pipeline, have high construction efficiency The advantages of.
The purpose of the present invention is what is be achieved by the following technical programs:
Drawing device and its construction method in a kind of PCCP pipeline, comprising the following steps:
S1: the seam crossing that the first of internal crossbeam both ends is picked up the ears between the adjacent PCCP pipeline that has been installed of insertion, will in Portion's crossbeam connects and fixes;
S2: the fixed hook hook of chain block is located on the first hangers, if the hoisting chain length of chain block is unsatisfactory for The length requirement of PCCP pipeline increases transmission rod between internal crossbeam and chain block.
S3: outer transverse beams are made to be connected to the outermost end of PCCP pipeline to be installed;
S4: lifting hook is hooked and is located on the second hangers;
S5: to the direction rotary motion disk of winding hoisting chain, hoisting chain being tensed, and carries out interior draw to PCCP pipeline to be installed Splicing is inserted into waddy in insertion pipe and carries out rotary motion disk when rotating disc spins difficulty;
S7: after PCCP pipeline to be installed splicing precision reaches design requirement, rotating disc is reversely rotated, hoisting chain is in Then relaxed state dismantles internal crossbeam and outer transverse beams;
S8: forming at new adjacent PCCP pipeline joint-seam in S5 and install internal crossbeam, then proceedes to above step and carries out next section The installation of PCCP pipeline.
In conclusion advantageous effects of the invention are as follows:
1. keeping interior drawing device structure simpler by the way that chain block is arranged between internal crossbeam and outer transverse beams, operation is more Add conveniently, while the moving distance of PCCP pipeline can be controlled by chain block at any time, installation accuracy is higher.
2. keeping the working efficiency of chain block higher by the way that bearing block and steering wheel are arranged on chain block, operation is more Add conveniently.
Detailed description of the invention
Fig. 1 is the front view of embodiment one;
Fig. 2 is the cross-sectional view of embodiment one;
Fig. 3 is the prominent internal beam structure schematic diagram of embodiment one;
Fig. 4 is the prominent outer transverse beams structural schematic diagram of embodiment one;
Fig. 5 is the structural schematic diagram of the chain block of embodiment one;
Fig. 6 is the structural schematic diagram of the protrusion chain block of embodiment two.
In figure, 1, PCCP pipeline;2, internal crossbeam;21, the first hangers;22, it first picks up the ears;3, outer transverse beams;31, second Hangers;33, it second picks up the ears;4, chain block;41, hoisting chain;42, lifting is linked up with;43, fixed hook;44, bearing block; 441, rotation axis;442, reinforcing rod;443, rotating disc;444, insertion pipe;45, support frame;451, upright bar;4511, outer tube; 4512, elevating lever;4513, limit hole;4514, fastening screw;452, cross bar;453, rotating wheel;5, transmission rod;51, shackle.
Specific embodiment
Below in conjunction with attached drawing, invention is further described in detail.
Embodiment one:
It referring to Figures 1 and 2, is drawing device in a kind of PCCP pipeline disclosed by the invention, including internal crossbeam, outer transverse beams and hand Cucurbit is drawn, the cross section of internal crossbeam is rectangle, and the seam crossing of adjacent PCCP pipeline is arranged in, and internal crossbeam is located at PCCP pipe The lower half in road.The outermost end of PCCP pipeline to be installed, the end abutment with PCCP pipeline, outer transverse beams are arranged in outer transverse beams It is located in same level with the top surface of internal crossbeam.Chain block setting is between outer transverse beams and internal crossbeam, for mentioning Active force when for being drawn in PCCP pipeline to be installed.When carrying out PCCP Pipe installing, the setting of internal crossbeam is being installed The lifting end of the seam crossing of adjacent PCCP pipeline, chain block is arranged in outer transverse beams, and fixing end is arranged on internal crossbeam, Outer transverse beams are connected to the outermost end of PCCP pipeline to be installed, tense chain block, the pulling force of chain block passes through outer lateral Beam effect docks PCCP pipeline to be installed on PCCP pipeline to be installed.
Referring to Fig. 2, chain block includes fixed hook and lifting hook, and fixed hook is hung for connecting supporting part, lifting Hook is for connecting stressed member.The first hangers is welded on the side wall of internal crossbeam, the first hangers is separately positioned on close to internal horizontal The position at beam both ends, the first hangers are arranged close to the direction of PCCP pipeline to be installed, and fixed hook is connected on the first hangers.Outside Portion's crossbeam is welded with the second hangers corresponding with the first hangers close to the side of internal crossbeam, and lifting hook connects with the second hangers It connects.The both ends of internal crossbeam are fixedly installed first respectively and pick up the ears, and first, which picks up the ears, is plugged on the adjacent PCCP pipe being installed The seam crossing in road.The both ends of outer transverse beams are fixedly installed second respectively and pick up the ears, and second, which picks up the ears, is connected to PCCP pipeline to be installed Outermost end.
When carrying out PCCP pipeline abutting joint, two first of internal crossbeam insertions of picking up the ears are installed adjacent The seam crossing of PCCP pipeline, it is then that internal crossbeam is mobile to the lower part of PCCP pipeline, until inside crossbeam be clamped on it is adjacent Until at PCCP pipeline joint-seam.The fixed hook of two chain blocks is articulated in respectively on the first hangers.By outer transverse beams Second, which picks up the ears, is connected to the outermost end of PCCP pipeline to be installed, by load-bearing be articulated in second pick up the ears on.Tension pulls calabash Reed, load-bearing hook pulling force is acted on PCCP pipeline to be installed by outer transverse beams, drive PCCP pipeline to be installed into Row is mobile assembled.
Referring to Fig. 2, when the length of PCCP pipeline is bigger, the length that the length of chain block is unsatisfactory for PCCP pipeline is wanted It asks, transmission rod is set between chain block and outer transverse beams, transmission rod is welded for round steel pipe, welds at the both ends of transmission rod Shackle is connect, the shackle of transmission rod one end picks up the ears to connect by bow shackle with second, and the shackle of the other end and lifting hook connect. With the setting of above-mentioned transmission rod, transmission rod is set between internal crossbeam and chain block.Transmission rod is able to extend chain block Action length, while transmission rod by bow shackle with inside crossbeam and outer transverse beams connect, it is easy to connect, securely.
Bearing block, chain block packet are fixedly installed on chain block for the ease of the operation of chain block referring to Fig. 5 It includes and pulls chain, fixed hook, lifting hook and bearing block, pull chain and linked up with across lifting, pull the both ends difference of chain It is fixed on bearing block.Rotation is provided with rotation axis on bearing block, and the end of rotation axis is connected with steering by reinforcing rod Disk, reinforcing rod are multiple along the evenly spaced setting of circumferencial direction of steering wheel.Fixed hook is fixed on bearing block.Work When, steering wheel is rotated, pulls chain winding on the rotating shaft, while pulling chain shortening, lifting hook is by towards bearing block Pulling force, by lifting link up with to bearing block direction pull, lifting hook on pulling force effect in outer transverse beams, outer transverse beams band PCCP pipeline to be installed is moved to be spliced.By the way that bearing block and steering wheel are arranged on chain block, accelerate chain block and pull The winding of chain improves the working efficiency of chain block, keeps PCCP Pipe installing quicker.
Referring to Fig. 5, multiple insertion pipes are uniformly set along the spaced radial of steering wheel, grafting tube opening towards outside steering wheel, Chain tightening is being pulled, when steering wheel rotation is relatively difficult, steel pipe or waddy etc. are inserted into insertion pipe, using lever principle, Steering wheel is conveniently steered disk and continues to rotate by bigger power at this time.
Further, one end setting sealing iron plate of insertion pipe, prevents waddy to be pierced by out of insertion pipe when being inserted into, improves behaviour Make efficiency.
Embodiment two:
Referring to Fig. 6, with embodiment one the difference is that, since the bearing block and rotating disc of chain block do not have at work Support, can be less smooth when rotating rotating disc, for the ease of supporting chain block, keeps the operation of rotating disc more smooth, Support frame is arranged in the lower section of bearing block, and bearing block is arranged on the support frame, and rotating steadying bar is set on the support frame, rotation axis one end Rotating disc stretches out support frame.When being worked, the support frame with chain block is placed in PCCP pipeline, calabash will be pulled The fixed hook hook of reed is located on internal crossbeam, and lifting hook is hooked and is located in outer transverse beams, directly rotation rotating disc, is tightened Heavy chain item, chain block pull PCCP pipeline to be installed to be spliced external beam effect pulling force.Due to by chain block by To the supporting role of support frame, stablize chain block position, when rotary motion disk is more smooth, increases the work of chain block Efficiency.
Referring to Fig. 6, in order to make support frame adapt to different height PCCP pipeline caliber, set liftable for support frame Structure, support frame includes four upright bars and the cross bars that are fixed between adjacent upright bar in rectangular arranged, and cross bar is along vertical Twice are arranged in the upper and lower ends of bar.Upright bar includes outer tube and elevating lever, and the appearance for accommodating elevating lever is offered on outer tube Receive chamber, accommodating chamber is adapted with elevating lever.Elevating lever is slidably arranged in the accommodating chamber in outer tube, on the side wall of elevating lever Evenly spaced to offer multiple limit holes, multiple limit holes are located on the same axis of elevating lever.It is inserted into limit hole Fastening screw, fastening screw are abutted with the upper end of outer tube, while the position of elevating lever being fixed.
Referring to Fig. 6, for the ease of movable supporting frame, rotating wheel is set in support frame bottom end, rotating wheel is four, is set respectively Set the four corners in support frame.When carrying out movable supporting frame, support frame need to be only pushed, movement is more convenient.
Embodiment three:
For drawing device and its construction method in a kind of PCCP pipeline disclosed by the invention, comprising the following steps:
S1: the seam crossing that the first of internal crossbeam both ends is picked up the ears between the adjacent PCCP pipeline that has been installed of insertion, will in Portion's crossbeam connects and fixes;
S2: the fixed hook hook of chain block is located on the first hangers, if the hoisting chain length of chain block is unsatisfactory for The length requirement of PCCP pipeline increases transmission rod between internal crossbeam and chain block;
S3: outer transverse beams are made to be connected to the outermost end of PCCP pipeline to be installed;
S4: lifting hook is hooked and is located on the second hangers;
S5: to the direction rotary motion disk of winding hoisting chain, hoisting chain being tensed, and carries out interior draw to PCCP pipeline to be installed Splicing is inserted into waddy in insertion pipe and carries out rotary motion disk when rotating disc spins difficulty;
S7: after PCCP pipeline to be installed splicing precision reaches design requirement, rotating disc is reversely rotated, hoisting chain is in Then relaxed state dismantles internal crossbeam and outer transverse beams,
S8: forming at new adjacent PCCP pipeline joint-seam in S5 and install internal crossbeam, then proceedes to above step and carries out next section The installation of PCCP pipeline.
The embodiment of present embodiment is presently preferred embodiments of the present invention, not limits protection of the invention according to this Range, therefore: the equivalence changes that all structures under this invention, shape, principle are done, should all be covered by protection scope of the present invention it It is interior.

Claims (10)

1. drawing device in a kind of PCCP pipeline, it is characterised in that: described interior including internal crossbeam, outer transverse beams and chain block The seam crossing between adjacent PCCP pipeline is arranged in portion's crossbeam, and the outermost of PCCP pipeline to be installed is arranged in the outer transverse beams End, the chain block are arranged between internal crossbeam and outer transverse beams.
2. drawing device in a kind of PCCP pipeline according to claim 1, it is characterised in that: the both ends of the internal crossbeam are solid Surely setting first is picked up the ears, and described first picks up the ears the seam crossing being plugged between adjacent PCCP pipeline, the both ends of the outer transverse beams It fixes second to pick up the ears, described second, which picks up the ears, is connected to the outermost end of PCCP pipeline to be installed.
3. drawing device in a kind of PCCP pipeline according to claim 1, it is characterised in that: on the side wall of the internal crossbeam The first hangers is fixedly installed respectively by the position of two close end, the outer transverse beams are fixedly installed second by the position of two close end respectively Hangers, the chain block include fixed hook and lifting hook, and the fixed hook is connect with the first hangers, and the lifting is hung Hook is connect with the second hangers.
4. drawing device in a kind of PCCP pipeline according to claim 1, it is characterised in that: the fixed hook and first is hung Transmission rod is set between ear, and shackle is fixedly installed in the transmission rod both ends, and the shackle and fixed hook of described transmission rod one end connect It connects, the other end is connect by bow shackle with the first hangers.
5. drawing device in a kind of PCCP pipeline according to claim 1, it is characterised in that: the lifting hook and first is hung Transmission rod is set between ear, and shackle is fixedly installed in the transmission rod both ends, and the shackle of described transmission rod one end and lifting hook connect It connects, the other end is connect by bow shackle with the second hangers.
6. drawing device in a kind of PCCP pipeline according to claim 1, it is characterised in that: the chain block includes lifting Chain, fixed hook, lifting hook and bearing block, the hoisting chain both ends are fixed on bearing block, the hoisting-chain Item is linked up with across lifting, and the fixed hook is fixed on bearing block, and the side of the bearing block is rotatably connected to rotation Disk.
7. drawing device in a kind of PCCP pipeline according to claim 6, it is characterised in that: the rotating disc passes through rotation axis It is connect with bearing block, the hoisting chain winding is on the rotating shaft.
8. drawing device in a kind of PCCP pipeline according to claim 7, it is characterised in that: the rotating disc and rotation axis it Between be fixedly installed reinforcing rod, on the rotating shaft, the other end is welded on rotating disc, the reinforcing rod for reinforcing rod one end setting It is arranged along rotating disc circumferencial direction multiple.
9. drawing device in a kind of PCCP pipeline according to claim 7, it is characterised in that: the rotating disc is arranged radially There are multiple insertion pipes.
10. drawing device and its construction method in a kind of PCCP pipeline, which comprises the following steps:
S1: the seam crossing that the first of internal crossbeam both ends is picked up the ears between the adjacent PCCP pipeline that has been installed of insertion, will in Portion's crossbeam connects and fixes;
S2: the fixed hook hook of chain block is located on the first hangers, if the hoisting chain length of chain block is unsatisfactory for The length requirement of PCCP pipeline increases transmission rod between internal crossbeam and chain block;
S3: outer transverse beams are made to be connected to the outermost end of PCCP pipeline to be installed;
S4: lifting hook is hooked and is located on the second hangers;
S5: to the direction rotary motion disk of winding hoisting chain, hoisting chain being tensed, and carries out interior draw to PCCP pipeline to be installed Splicing is inserted into waddy in insertion pipe and carries out rotary motion disk when rotating disc spins difficulty;
S7: after PCCP pipeline to be installed splicing precision reaches design requirement, rotating disc is reversely rotated, hoisting chain is in Then relaxed state dismantles internal crossbeam and outer transverse beams;
S8: forming at new adjacent PCCP pipeline joint-seam in S5 and install internal crossbeam, then proceedes to above step and carries out next section The installation of PCCP pipeline.
CN201811645062.2A 2018-12-29 2018-12-29 Drawing device and its construction method in a kind of PCCP pipeline Pending CN109442096A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811645062.2A CN109442096A (en) 2018-12-29 2018-12-29 Drawing device and its construction method in a kind of PCCP pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811645062.2A CN109442096A (en) 2018-12-29 2018-12-29 Drawing device and its construction method in a kind of PCCP pipeline

Publications (1)

Publication Number Publication Date
CN109442096A true CN109442096A (en) 2019-03-08

Family

ID=65539956

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811645062.2A Pending CN109442096A (en) 2018-12-29 2018-12-29 Drawing device and its construction method in a kind of PCCP pipeline

Country Status (1)

Country Link
CN (1) CN109442096A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110726005A (en) * 2019-10-28 2020-01-24 施展 System and method for installing field buried pipeline
CN112247899A (en) * 2020-09-29 2021-01-22 程永振 Automatic butt joint hydraulic machine for PCCP (prestressed concrete cylinder pipe) pipelines
CN113251211A (en) * 2021-04-22 2021-08-13 中国一冶集团有限公司 Pipeline socket butt joint device
CN114508643A (en) * 2020-11-17 2022-05-17 北京市水利规划设计研究院 Method for replacing pipeline

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010036166A (en) * 1999-10-06 2001-05-07 나남열 device for constructing fume pipe
CN202215871U (en) * 2011-08-29 2012-05-09 四川国统混凝土制品有限公司 Tensioning tool for installing prestressed concrete cylinder pipe (PCCP) finished tube
CN204711898U (en) * 2015-07-01 2015-10-21 宜都市供水总公司 A kind of pipeline butt joint auxiliary device
CN205740135U (en) * 2015-12-10 2016-11-30 中建安装工程有限公司 A kind of chain block
CN107178655A (en) * 2016-03-09 2017-09-19 中国水利水电第十工程局有限公司 The construction method of PCCP pipes under MODEL OVER COMPLEX TOPOGRAPHY
CN209654736U (en) * 2018-12-29 2019-11-19 北京京水建设集团有限公司 Drawing device in a kind of PCCP pipeline

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010036166A (en) * 1999-10-06 2001-05-07 나남열 device for constructing fume pipe
CN202215871U (en) * 2011-08-29 2012-05-09 四川国统混凝土制品有限公司 Tensioning tool for installing prestressed concrete cylinder pipe (PCCP) finished tube
CN204711898U (en) * 2015-07-01 2015-10-21 宜都市供水总公司 A kind of pipeline butt joint auxiliary device
CN205740135U (en) * 2015-12-10 2016-11-30 中建安装工程有限公司 A kind of chain block
CN107178655A (en) * 2016-03-09 2017-09-19 中国水利水电第十工程局有限公司 The construction method of PCCP pipes under MODEL OVER COMPLEX TOPOGRAPHY
CN209654736U (en) * 2018-12-29 2019-11-19 北京京水建设集团有限公司 Drawing device in a kind of PCCP pipeline

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110726005A (en) * 2019-10-28 2020-01-24 施展 System and method for installing field buried pipeline
CN110726005B (en) * 2019-10-28 2021-07-23 施展 System and method for installing field buried pipeline
CN112247899A (en) * 2020-09-29 2021-01-22 程永振 Automatic butt joint hydraulic machine for PCCP (prestressed concrete cylinder pipe) pipelines
CN114508643A (en) * 2020-11-17 2022-05-17 北京市水利规划设计研究院 Method for replacing pipeline
CN114508643B (en) * 2020-11-17 2024-05-07 北京市水利规划设计研究院 Pipeline replacement method
CN113251211A (en) * 2021-04-22 2021-08-13 中国一冶集团有限公司 Pipeline socket butt joint device
CN113251211B (en) * 2021-04-22 2022-08-19 中国一冶集团有限公司 Pipeline socket joint interfacing apparatus

Similar Documents

Publication Publication Date Title
CN109442096A (en) Drawing device and its construction method in a kind of PCCP pipeline
CN209654736U (en) Drawing device in a kind of PCCP pipeline
CN107558723B (en) Method for manufacturing and installing hanging bracket of hanging basket for inclined roof
CN108119164B (en) Prefabricated assembled composite support structure
CN201330136Y (en) Arc crane boom
CN211056577U (en) Pipe gallery tubular product hoisting accessory
CN113529979A (en) Exempt from welded rack node reinforced structure
CN207918257U (en) Prefabricated post hanger structure
CN103993739B (en) The construction method of granulation tower spraying layer stiff beam
CN210286469U (en) Prefabricated part hoist
CN207848588U (en) A kind of Diameter PC CP pipeline hydraulics are interior to draw installation equipment
CN206646836U (en) A kind of exterior wall, inner partition plate movement lifting frame
CN211899735U (en) Temporary support seat for adjusting balance degree of prefabricated bay window
CN201873949U (en) Bride prestress stretch-draw trolley
CN211775988U (en) Steel construction high-rise tower high altitude protector
CN204876620U (en) Peripheral hardware concrete frame reinforced structure
CN112178289A (en) Gallows of pipeline swift installation in tall and big space upper portion rack
CN114607171B (en) Reinforcing device and reinforcing method for concrete column
CN113235436A (en) Temporary inhaul cable construction method suitable for cable-first and beam-second construction of suspension bridge
CN207660296U (en) A kind of precast concrete hanging apparatus
CN105715045B (en) Column structure construction template
CN212609023U (en) Multi-functional hoist of assembly type structure
CN214941635U (en) Prefabricated assembled concrete beam component
CN216638684U (en) Lifting and hanging device
CN213685598U (en) Gallows of pipeline swift installation in tall and big space upper portion rack

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190308