CN109403363A - A kind of self balance combined water-retaining cofferdam and its construction method - Google Patents

A kind of self balance combined water-retaining cofferdam and its construction method Download PDF

Info

Publication number
CN109403363A
CN109403363A CN201811529614.3A CN201811529614A CN109403363A CN 109403363 A CN109403363 A CN 109403363A CN 201811529614 A CN201811529614 A CN 201811529614A CN 109403363 A CN109403363 A CN 109403363A
Authority
CN
China
Prior art keywords
pedestal
water
bottom edge
column
cofferdam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811529614.3A
Other languages
Chinese (zh)
Other versions
CN109403363B (en
Inventor
左丽
南国喜
肖发光
冀荣贤
杜春林
樊梦洒
段俊法
李乔
吴国权
王伟
马雅琪
付军
李飞
赵海涛
陈育志
贾瑞明
王玉龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
YELLOW RIVER CONSTRUCTION ENGINEERING GROUP Co Ltd
Central Route Construction Management Bureau Of South To North Water Transfer Project
Hohai University HHU
Original Assignee
YELLOW RIVER CONSTRUCTION ENGINEERING GROUP Co Ltd
Central Route Construction Management Bureau Of South To North Water Transfer Project
Hohai University HHU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by YELLOW RIVER CONSTRUCTION ENGINEERING GROUP Co Ltd, Central Route Construction Management Bureau Of South To North Water Transfer Project, Hohai University HHU filed Critical YELLOW RIVER CONSTRUCTION ENGINEERING GROUP Co Ltd
Priority to CN201811529614.3A priority Critical patent/CN109403363B/en
Publication of CN109403363A publication Critical patent/CN109403363A/en
Application granted granted Critical
Publication of CN109403363B publication Critical patent/CN109403363B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/02Restraining of open water
    • E02D19/04Restraining of open water by coffer-dams, e.g. made of sheet piles
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/11Hard structures, e.g. dams, dykes or breakwaters

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)

Abstract

The invention discloses a kind of self balance combined water-retaining cofferdams, including enclosing structure, support construction as made of modular unit segmented assembly, counter-force balanced structure;Each modular unit includes pedestal, column, water retaining facing;Each pedestal includes the pedestal T shape socket joint slot and pedestal T shape socket joint head for being respectively arranged at both ends, it is provided on pedestal and is respectively used to vertical columns, the installation bayonet of water retaining facing, water retaining facing limiting slot, the bottom surface of pedestal is fixedly installed pedestal plate soft rubber plate, and the pedestal side that meets water is provided with pedestal rubber Water shielding curtain;Pedestal includes bottom edge pedestal, side pedestal, corner pedestals;The cross sectional shape of bottom edge pedestal is right-angled trapezium;The cross sectional shape of side pedestal is rectangle;Corner pedestals are formed by connecting by two sections identical with the section of side pedestal and bottom edge pedestal respectively.The invention also discloses the construction methods of said combination formula water-retaining cofferdam.The present invention has very strong operability and applicability, while all transfer efficients of device can be improved.

Description

A kind of self balance combined water-retaining cofferdam and its construction method
Technical field
The present invention relates to a kind of self balance combined water-retaining cofferdams, can implement fast enclosure to slope surface, to be channel (river) side slope lining cutting panel provides dry working space.
Background technique
General large water transportation water delivery engineering route is long, along the line complex geologic conditions, and changes in environmental conditions is big, and channel easily occurs Lining cutting panel crack, the defects of surface layer freeze-thaw damage, removing, collapsing.Currently, channel defect processing is typically all to drop both at home and abroad Low water level operation is implemented in the case of cutting off the water, however large water transportation water delivery engineering does not have drop low water level operation generally or cuts off the water Maintenance condition, the following canal lining panel of water surface curve is collapsed, swell and water surface curve above and below freeze-thaw damage the defects of can only use The interim measures such as ballast bring security risk for engineering.Current existing cofferdam facility or the generally existing underwater construction of technology are difficult The problems such as degree is big, waterstop sealing effect is poor, while general cofferdam underwater penetration limited (less than 1 meter), being only capable of every time to one piece etc. A small number of block panels are locally repaired, and large water transportation water delivery engineering normal maintenance and maintenance demand are much unable to satisfy.Therefore, it grinds Hair is safe and reliable, water-stagnating effect is good, disassembled combination, project cost are low, strong applicability novel combination type water blocking equipment has Important meaning and application value.
Summary of the invention
The technical problem to be solved by the present invention is to overcome the deficiencies of the prior art and to provide one kind can quickly in place and removal Combined type water-retaining cofferdam, can to channel (river) slope surface implement fast enclosure, dry working space be provided.
The present invention specifically uses following technical scheme to solve above-mentioned technical problem:
A kind of self balance combined water-retaining cofferdam, including the floor projection as made of modular unit segmented assembly are open eight words The enclosing structure of shape or open rectangle, one group of support knot for being supported respectively to each modular unit of enclosing structure Structure, and the counter-force balanced structure for enclosing structure integrally to be stablized and reinforced;Each module of the enclosing structure Changing unit includes pedestal, column, water retaining facing;The weight of each pedestal is not less than 1 ton comprising is respectively arranged at both ends Pedestal T shape socket joint slot and pedestal T shape socket joint head, be provided on pedestal be respectively used to vertical columns, water retaining facing installation bayonet, Water retaining facing limiting slot, the bottom surface of pedestal are fixedly installed pedestal plate soft rubber plate, and the pedestal side that meets water is provided with pedestal rubber Glue Water shielding curtain;The pedestal includes the bottom edge pedestal and side pedestal for being respectively used to the bottom edge and side of enclosing structure, Yi Jiyong In the corner pedestals of connection bottom edge pedestal and side pedestal;The cross sectional shape of bottom edge pedestal is right-angled trapezium, the right-angled trapezium four Sharp angle in a angle is equal to the angle between construction water channel lining cutting slope surface and horizontal plane;The cross sectional shape of side pedestal is square Shape;Corner pedestals are formed by connecting by two sections identical with the section of side pedestal and bottom edge pedestal respectively.
Preferably, the radially opposite sides of column are separately provided for the water retaining facing limiting slot of insertion water retaining facing, column At least one end be provided with and connect installation landing nipple with the female type that the installation bayonet of pedestal matches, be arranged on column useful In the connection structure of connected support structure.
Preferably, the support construction includes braced bar system, plate bearing;Braced bar system is adjustable triangular structure, Including upper links, lower link, it is set to four connection sleeves at upper links both ends and lower link both ends;Upper links It is the solid pole that both ends are respectively arranged with rectangle lead screw transmission tooth with lower link, the section for connecting sleeve is annulus, Inner ring is provided with rectangular inner meshing gear compatible with the rectangle lead screw transmission tooth.
Preferably, the pedestal rubber Water shielding curtain be combined by the thicker rubber slab in the upper layer rubber slab relatively thin with lower layer and At the free flexible combination rubber slab of bilayer.It is further preferred that the upper layer of the double-deck free flexible combination rubber slab for thickness not Rubber slab greater than 6mm, lower layer are the rubber slab that thickness is not more than 3mm.
Preferably, the main body of the water retaining facing is the plane steel facing for being provided with stiffener plate, the bottom of plane steel facing Water sealing structure is provided on side and two sides.
It is further preferred that the water sealing structure is made of the side waterstop of back side waterstop and two sides, the sealing Band is flexible flat rubber slab or expansion sealing strip.
Preferably, the counter-force balanced structure includes being fixedly installed on one group to construct in water channel lining cutting slope surface and can accommodating to match The reaction box of weight, each reaction box can be connect by connecting rod with pedestal respectively.
Further, the bottom surface of reaction box is provided with the friction for increasing coefficient of friction between reaction box and side slope surface Structure.
Further, installation positioning pipe is provided on column.
The construction method of combined type water-retaining cofferdam described in any technical solution as above, cofferdam installation process are specific as follows:
S1, bottom edge pedestal is successively lifted on side slope surface and connecting, then according to elder generation according to swimming over to the order of upstream under Two corner pedestals and first and the last one bottom edge pedestal are separately connected by the order in downstream behind upstream, finally according to upstream Side pedestal is installed with interlocking one section one section of along order with downstream;
S2, column is sequentially inserted into the installation bayonet of the column on mounted pedestal according to the sequence for being from upstream to downstream, Then support construction is installed;
S3, by the pedestal being connected and column Xiang Shuizhong synchronous push into water at predetermined depth;
S4, water retaining facing is sequentially inserted into each column limiting slot according to the sequence for being from upstream to downstream;
S5, setting counter-force balanced structure;
S6, the water on the inside of enclosing structure is discharged outward, until cofferdam good seal, without obvious percolating water;
Cofferdam disassembly process is specific as follows:
After the completion of S7, operation, according to first downstream side water retaining facing, then bottom edge water retaining facing, last upstream side water retaining facing Sequence successively hangs out water retaining facing;
S8, according to first downstream heel post, then bottom edge column, the sequence of last upstream heel post successively hangs out column;
S9, synchronization remove pedestal after pulling up pedestal to side slope top of the slope.
Compared with prior art, technical solution of the present invention has the advantages that
Combined type water-retaining cofferdam of the present invention blocks water curtain in the different free flexible combination rubber slab of bilayer of chassis side setting thickness, The feature that rubber slab using thickness no more than 3mm posts, lap gap is small forms water blocking layer, is not more than 6mm using thickness Rubber slab self-strength is big, limit fixing layer that feature that anti-flow performance is strong is as underlying rubber water blocking layer, base bottom is set Flexible water stop is set, lower automatic paste tightening canal slope is acted on by self weight, water pressure and water flow pressure, slope surface can be well adapted to not It is flat, reach the purpose that blocks water;Between pedestal and pedestal of the present invention use T-type bindiny mechanism, between T-type socket joint head and T-type socket joint slot according to Cooperate precision between component and is mutually twisted relationship, labyrinth sealing;Slot is used between water retaining facing and pedestal, column of the invention Type structure and plane cooperation, soft flat rubber is installed between plane, is realized between cofferdam column and water retaining facing and pedestal Sealing between water retaining facing.The above-mentioned Water stop mechanism combined plays good sealing effect.It installed in cofferdam of the present invention Journey does not need heavy construction equipment, can satisfy different length of slope, different underwater penetrations and different slope coefficient construction demands, And it is safe and reliable, water-stagnating effect is good, disassembled combination, project cost are low, overcome previous cofferdam sealing and form the operation of dry ground The technical problems such as equipment anti-floating, upper cunning, underwater penetration be small afterwards have very strong operability and applicability, while can shorten cofferdam In place, disassembly and assembly time, simplify operating procedure, saved the operating time, shorten the construction period, improve all transfer efficients of device.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of one preferred embodiment of combined type water-retaining cofferdam of the present invention;
Fig. 2 is schematic diagram of base structure;
Fig. 3 is pillar construction schematic diagram;
Fig. 4 is water retaining facing structural schematic diagram;
Fig. 5 is the structural schematic diagram of support construction;
Fig. 6 is the structural schematic diagram of counter-force balanced structure;
The meaning of each appended drawing reference is specific as follows in figure:
1, enclosing structure, 2, support construction, 3, counter-force balanced structure;11, pedestal, 12, column, 13, water retaining facing;21, it supports Leverage, 22, plate bearing;31, reaction box, 32, connecting rod, 33, mass, 34, plate soft rubber plate;111, pedestal T shape Socket joint slot, 112, pedestal T shape socket joint head, 113, column installation card, 114, water retaining facing limiting slot, 115, the soft rubber of pedestal plate Offset plate, 116, pedestal rubber Water shielding curtain, 117, hanging ring;121, water retaining facing limiting slot, 122, female type connection installation positioning connect Head, 123, support hole location, 124, installation positioning pipe;131, plane steel facing, 132, stiffener plate, 133, side waterstop, 134, back side waterstop;221, plate bearing, 211, upper links, 212, lower link, 213, connection sleeve.
Specific embodiment
In view of the shortcomings of the prior art, thinking of the invention is by the way of piecewise combination, by pedestal self weight while in fact Existing anti-floating, antiskid and good water-stagnating effect, and support construction and counter-force balanced structure is combined to realize the firm of cofferdam;Pass through The double-deck free flexible combination rubber slab of chassis side setting blocks water curtain, and flexible water stop is arranged in base bottom, by being self-possessed, water pressure And water flow pressure acts on lower automatic paste tightening canal slope, reaches the purpose that blocks water, is realized by the T-type bindiny mechanism between pedestal and pedestal Good sealing is cooperated by trench structure used between water retaining facing and pedestal, column and plane, is installed between plane soft Matter flat rubber, is realized between cofferdam column and water retaining facing and the sealing between pedestal and water retaining facing.
Specifically, self balance combined water-retaining cofferdam proposed by the invention, including by modular unit segmented assembly Made of floor projection be open splayed or open rectangle enclosing structure, for being carried out respectively to each segmentation of enclosing structure One group of support construction of support, and the counter-force balanced structure for enclosing structure integrally to be stablized and reinforced;It is described to enclose The each segmentation for keeping off structure includes pedestal, column, water retaining facing;The weight of each pedestal is not less than 1 ton comprising sets respectively It is placed in the pedestal T shape socket joint slot and pedestal T shape socket joint head at both ends, is provided on pedestal and is respectively used to vertical columns, water retaining facing Installation bayonet, water retaining facing limiting slot, the bottom surface of pedestal is fixedly installed pedestal plate soft rubber plate, and the pedestal side that meets water is set It is equipped with pedestal rubber Water shielding curtain;The pedestal includes the bottom edge pedestal and side edge bottom for being respectively used to the bottom edge and side of enclosing structure Seat, and the corner pedestals for connecting bottom edge pedestal and side pedestal;The cross sectional shape of bottom edge pedestal is right-angled trapezium, this is straight Sharp angle in trapezoidal four angles in angle is equal to the angle between construction water channel lining cutting slope surface and horizontal plane;The section shape of side pedestal Shape is rectangle;Corner pedestals are formed by connecting by two sections identical with the section of side pedestal and bottom edge pedestal respectively.
The construction method of the combined type water-retaining cofferdam, cofferdam installation process are specific as follows:
S1, bottom edge pedestal is successively lifted on side slope surface and connecting, then according to elder generation according to swimming over to the order of upstream under Two corner pedestals and first and the last one bottom edge pedestal are separately connected by the order in downstream behind upstream, finally according to upstream Side pedestal is installed with interlocking one section one section of along order with downstream;
S2, column is sequentially inserted into the installation bayonet of the column on mounted pedestal according to the sequence for being from upstream to downstream, Then support construction is installed;
S3, by the pedestal being connected and column Xiang Shuizhong synchronous push into water at predetermined depth;
S4, water retaining facing is sequentially inserted into each column limiting slot according to the sequence for being from upstream to downstream;
S5, setting counter-force balanced structure;
S6, the water on the inside of enclosing structure is discharged outward, until cofferdam good seal, without obvious percolating water;
Cofferdam disassembly process is specific as follows:
After the completion of S7, operation, according to first downstream side water retaining facing, then bottom edge water retaining facing, last upstream side water retaining facing Sequence successively hangs out water retaining facing;
S8, according to first downstream heel post, then bottom edge column, the sequence of last upstream heel post successively hangs out column;
S9, synchronization remove pedestal after pulling up pedestal to side slope top of the slope.
For convenient for public understanding, below with a preferred embodiment and in conjunction with attached drawing come to technical solution of the present invention carry out into One step is described in detail:
As shown in Figure 1, it is open eight words that the combined type water-retaining cofferdam in the present embodiment, which includes floor projection made of segmented assembly, The enclosing structure 1 of shape or open rectangle, one group of support knot for being supported respectively to each modular unit of enclosing structure 1 Structure 2, and for the whole counter-force balanced structure 3 stablized and reinforced of enclosing structure 1.The base width in cofferdam and enter water Depth can be adjusted flexibly by different modular unit quantity.
Each modular unit of enclosing structure 1 includes pedestal 11, column 12, water retaining facing 13.As shown in Figure 1, bottom 11 points of seat are three kinds, respectively the bottom edge pedestal and side pedestal for the bottom edge of enclosing structure 1 and side, and for connecting The corner pedestals of bottom edge pedestal and side pedestal;The cross sectional shape of bottom edge pedestal is right-angled trapezium, in four angles of the right-angled trapezium Sharp angle be equal to construction channel or river lining cutting slope surface and horizontal plane between angle;The cross sectional shape of side pedestal is square Shape;Corner pedestals are formed by connecting by two sections identical with the section of side pedestal and bottom edge pedestal respectively.
As shown in Fig. 2, not less than 1 ton of the weight of each pedestal 11 (single-base weight is 1800kg in the present embodiment), It includes the pedestal T shape socket joint slot 111 and pedestal T shape socket joint head 112 for being respectively arranged at both ends, is provided on pedestal 11 and uses respectively In vertical columns 12, the installation bayonet 113 of water retaining facing 13, water retaining facing limiting slot 114, the bottom surface of pedestal 11 is fixedly installed Pedestal plate soft rubber plate 115, the side that meets water of pedestal 11 are provided with pedestal rubber Water shielding curtain 116(in order to easy for construction, can also All it is arranged with the two sides in pedestal 11).In order to obtain better water-stagnating effect, it is preferred through many experiments discovery double-deck free Flexible combination rubber slab, i.e., the described pedestal rubber Water shielding curtain 116 by upper layer thicker (thickness is desirably no more than 6mm) rubber slab with The rubber slab of lower layer's relatively thin (thickness is desirably no more than 3mm) is freely combined, so as to be not more than the rubber of 3mm using thickness Plate posts, lap gap is small feature forms water blocking layer, and the rubber slab self-strength using thickness no more than 6mm is big, anti-current Limit fixing layer of the strong feature of performance as underlying rubber water blocking layer, and then obtain good water-stagnating effect.When specific processing, The pedestal that is fixed on one side of thick rubber slab and Thin rubber plate need to only be met water side bottom position.Pedestal rubber in the present embodiment Glue Water shielding curtain 116 uses the free flexible combination rubber slab of bilayer of lower layer 3mm+ upper layer 6mm.In addition, for the ease of lifting, pedestal One group of hanging ring 117 is additionally provided on 11.
As shown in figure 3, the radially opposite sides of column 12 are separately provided for the water retaining facing limit of insertion water retaining facing 13 Slot 121, at least one end of column 12 is provided with connect with the female type that the installation bayonet 113 of pedestal 11 matches installation positioning connect First 122, the support hole location 123 for connected support structure 2 is provided on column 12.Positioning when for the ease of cofferdam installation, Installation positioning pipe 124 is additionally provided on column 12 in the present embodiment.The section of column 12 can use round, rectangular or rectangle It is easy to form limit in base holes Deng, rectangular or rectangle steel, guarantees relatively accurate installation site, but need to pass through circle Steel mill out four planes, need very big processing capacity.And circular steel is directlyed adopt as column and only needs to install in pedestal Position locally mills out limit plane, and processes limiting slot in side, it is possible to reduce processing capacity, therefore column 12 is preferably using circle Section.
As shown in figure 4, the main body of water retaining facing 13 is the plane steel facing 131 for being provided with stiffener plate 132, flat steel face It is provided with water sealing structure in the bottom edge of plate 131, two sides and dorsal edge, water sealing structure is by the back side described in the present embodiment Waterstop 134 and two sides side and bottom surface waterstop 133 form, and the waterstop preferably uses flexible flat rubber slab or swollen Swollen sealing rod.
As shown in figure 5, the support construction 2 includes braced bar system 21, plate bearing 22;Braced bar system 21 is adjustable three Corner structure comprising upper links 211, lower link 212, and it is set to 211 both ends of upper links and 212 liang of lower link Four connection sleeves 213 at end;Upper links 211 and lower link 212 are that both ends are respectively arranged with rectangle lead screw transmission tooth Solid cylinder, the section of connection sleeve 213 is annulus, and inner ring is provided with square compatible with the rectangle lead screw transmission tooth Shape internal tooth.
The support construction 2 can guarantee the stability of column and water fender, but when pedestal and side slope contact condition are poor, May be too small because of frictional force, the whole passage upwards in cofferdam, or since local slope sedimentation is difficult to support, asked to solve this Topic, the present invention are devised for the whole counter-force balanced structure 3 stablized and reinforced of enclosing structure 1.As shown in fig. 6, this Counter-force balanced structure 3 includes the reaction box 31 that one group be fixedly installed on side slope surface can accommodate mass 33 in embodiment, Each reaction box 31 can be connect by connecting rod 32 with pedestal 11 respectively.It is ingenious in the present embodiment to use reaction box along side slope surface Partical gravity obliquely resists the bottom edge pedestal suffered thrust upward along side slope under water, in order to further such that whole knot Structure is stablized, and the friction knot for increasing coefficient of friction between reaction box 31 and side slope surface can be arranged in the bottom surface of reaction box 31 Structure, such as the bottom surface of reaction box 31 can be made to decorative pattern, it is soft using the plate for being fixed on 31 bottom surface of reaction box in the present embodiment Rubber slab 34 rubs to increase.
The concrete construction method in above-mentioned cofferdam includes:
Step 1 pops up a bottom edge pedestal installation base directrix at adjoined water surface line position using horizontal tube and tape measure surely, simultaneously Divide every section bottom edge base mounting orientation line;
First segment bottom edge pedestal lifting in downstream is transported near installation site by step 2 with crane, is hung using horizontal ruler and every Flower basket bolt on rope accurately adjusts pedestal posture, then hangs on canal slope panel in place bottom edge pedestal, uses angle measurement Tool carries out longitudinal and transverse direction angle of bank measurement to manned bottom edge pedestal and records deviation scale, then is lifted by crane in advance by crane Tight lifting rope readjusts each lifting rope length using flower basket bolt according to each lifting rope tightness, and keep it is elastic it is consistent after by hook The suspension hook hung on pedestal hanging ring is removed, and the second section of socket joint bottom edge pedestal is then lifted;
Step 3 repeats step 2, installs bottom edge pedestal one by one;
Step 4 lifts upstream corner pedestals, and connect with upstream first segment bottom edge pedestal socket joint;
Step 5 lifts downstream corner pedestals, and connect with downstream final section bottom edge pedestal socket joint;
Upstream first segment right edge pedestal is lifted, and connect with upstream corner pedestals socket joint by step 6;
Downstream first segment left side pedestal is lifted, and connect with downstream corner pedestals socket joint by step 7;
Step 8 repeats step 6 ~ 7, installs side pedestal one by one;
Column is sequentially inserted into mounted pedestal upright post installation bayonet by step 9 according to the sequence in downstream behind first upstream;
Step 10, installation supporting bar structure;
Step 11, diving operation, by cofferdam below water surface curve surround mudcake giant that canal slope panel in range adheres to or Spatula is removed;
Step 12, with the jack and mandril synchronous push upstream first segment and downstream final section pedestal for being fixed on canal top, will The pedestal and column Xiang Shuizhong pushing tow being connected, pushing tow measure pushing tow stroke in the process, and control two sides pushing tow is synchronous;
Step 13 repeats step 12, will be in place at whole pedestals and column pushing tow to predetermined depth;
Step 14, assembled floating drum, the water surface in cofferdam are all paved with and installs railing form operating platform waterborne;
Step 15 is opposed to the column in water according to design size on operating platform on the water and measures correction, and uses water It is positioned in flushconnection bar insertion column side positioning pipe;
Step 16, by water retaining facing since being sequentially inserted into from top to bottom the panel of upstream side in each column limiting slot;
Reaction box connect with upstream and downstream side pedestal, and loads mass by step 17;
The water on the inside of enclosing structure is discharged outward for step 18, unlatching water pump, until cofferdam good seal, without obvious leakage Water;
After the completion of step 19, operation, water pump is hung out, assembles Overwater floating platform;
Step 20, according to first downstream side water retaining facing, then bottom edge water retaining facing, the sequence of last upstream side water retaining facing is successively Water retaining facing is hung out;
Step 21, according to first downstream heel post, then bottom edge column, the sequence of last upstream heel post successively ties column and support Structure is hung out together;
Step 22 removes operating platform waterborne;
Two step 23, starting hoist engine synchronizations pull up pedestal, and pedestal is removed;
Each component of combined type water-retaining cofferdam is transported to next construction location by step 24.
Combined type water-retaining cofferdam installation process of the invention does not need heavy construction equipment, and it is long to can satisfy different side slopes Degree, different underwater penetration and different slope coefficients are constructed demand, and it is safe and reliable, water-stagnating effect is good, disassembled combination, engineering are made Valence is low, overcomes previous cofferdam sealing and forms the technical problems such as equipment anti-floating after dry ground operation, antiskid, underwater penetration be small, tool There are very strong operability and applicability, while in place, the disassembly and assembly time in cofferdam can be shortened, simplifies operating procedure, saved behaviour Make the time, shorten the construction period, improves all transfer efficients of device.The composite can be widely applied to similar water channel, dykes and dams has lining in this way The hydraulic engineering for building slope surface, has a good application prospect.

Claims (10)

1. a kind of self balance combined water-retaining cofferdam, which is characterized in that including the level as made of modular unit segmented assembly Be projected as the enclosing structure (1) of open splayed or open rectangle, for enclosing structure (1) each modular unit respectively into One group of support construction (2) of row support, and the counter-force balanced structure for enclosing structure (1) integrally to be stablized and reinforced (3);Each modular unit of the enclosing structure (1) includes pedestal (11), column (12), water retaining facing (13);Each The weight of pedestal (11) is not less than 1 ton comprising is respectively arranged at the pedestal T shape socket joint slot (111) and pedestal T shape socket joint at both ends Head (112) is provided with installation bayonet (113), the water blocking for being respectively used to vertical columns (12), water retaining facing (13) on pedestal (11) Panel limiting slot (114), the bottom surface of pedestal (11) are fixedly installed pedestal plate soft rubber plate (115), and pedestal (11) are met Water side is provided with pedestal rubber Water shielding curtain (116);The pedestal (11) includes the bottom edge and side for being respectively used to enclosing structure (1) Bottom edge pedestal and side pedestal, and corner pedestals for connecting bottom edge pedestal and side pedestal;The section of bottom edge pedestal Shape is right-angled trapezium, and the sharp angle in four angles of the right-angled trapezium is equal to the folder between construction water channel lining cutting slope surface and horizontal plane Angle;The cross sectional shape of side pedestal is rectangle;Corner pedestals are by respectively identical with the section of side pedestal and bottom edge pedestal two Section is formed by connecting.
2. self balance combined water-retaining cofferdam as described in claim 1, which is characterized in that the radially opposite sides of column (12) are set respectively It is equipped with the water retaining facing limiting slot (121) for being inserted into water retaining facing (13), at least one end of column (12) is provided with and pedestal (11) female type connection installation landing nipple (122) that installation bayonet (113) matches, column are provided on (12) for connecting The connection structure of structure for welding and supporting (2).
3. self balance combined water-retaining cofferdam as described in claim 1, which is characterized in that the support construction (2) includes support Leverage (21), plate bearing (22);Braced bar system (21) is adjustable triangular structure comprising upper links (211), lower part connect Bar (212), and it is set to four connection sleeves (213) at upper links (211) both ends and lower link (212) both ends;On Portion's connecting rod (211) and lower link (212) are the solid cylinder that both ends are respectively arranged with rectangle lead screw transmission tooth, connect sleeve (213) section is annulus, and inner ring is provided with rectangular inner meshing gear compatible with the rectangle lead screw transmission tooth.
4. self balance combined water-retaining cofferdam as described in claim 1, which is characterized in that the pedestal rubber Water shielding curtain (116) For the free flexible combination rubber slab of bilayer being composed of the thicker rubber slab in upper layer and the relatively thin rubber slab of lower layer.
5. self balance combined water-retaining cofferdam as described in claim 1, which is characterized in that the main body of the water retaining facing (13) is It is provided with the plane steel facing (131) of stiffener plate (132), is respectively provided on the bottom edge of plane steel facing (131) and two sides There is water sealing structure.
6. self balance combined water-retaining cofferdam as claimed in claim 5, which is characterized in that the water sealing structure is by back side waterstop (134) and the side waterstop (133) of two sides composition, the waterstop are flexible flat rubber slab or expansion sealing strip.
7. self balance combined water-retaining cofferdam as described in claim 1, which is characterized in that the counter-force balanced structure (3) includes One group be fixedly installed on side slope surface can accommodate the reaction box (31) of mass, and each reaction box (31) can pass through company respectively Extension bar (32) is connect with pedestal (11).
8. self balance combined water-retaining cofferdam as claimed in claim 7, which is characterized in that the bottom surface setting of reaction box (31) is useful In the friction structure for increasing coefficient of friction between reaction box (31) and side slope surface.
9. self balance combined water-retaining cofferdam as described in claim 1, which is characterized in that be provided with installation positioning on column (12) It manages (124).
10. such as the construction method of any one of the claim 1 ~ 9 combined type water-retaining cofferdam, which is characterized in that installed in cofferdam Journey is specific as follows:
S1, bottom edge pedestal is successively lifted on side slope surface and connecting, then according to elder generation according to swimming over to the order of upstream under Two corner pedestals and first and the last one bottom edge pedestal are separately connected by the order in downstream behind upstream, finally according to upstream Side pedestal is installed with interlocking one section one section of along order with downstream;
S2, column is sequentially inserted into the installation bayonet of the column on mounted pedestal according to the sequence for being from upstream to downstream, Then support construction is installed;
S3, by the pedestal being connected and column Xiang Shuizhong synchronous push into water at predetermined depth;
S4, water retaining facing is sequentially inserted into each column limiting slot according to the sequence for being from upstream to downstream;
S5, setting counter-force balanced structure;
S6, the water on the inside of enclosing structure is discharged outward, until cofferdam good seal, without obvious percolating water;
Cofferdam disassembly process is specific as follows:
After the completion of S7, operation, according to first downstream side water retaining facing, then bottom edge water retaining facing, last upstream side water retaining facing Sequence successively hangs out water retaining facing;
S8, according to first downstream heel post, then bottom edge column, the sequence of last upstream heel post successively hangs out column;
S9, synchronization remove pedestal after pulling up pedestal to side slope top of the slope.
CN201811529614.3A 2018-12-14 2018-12-14 Self-balancing combined water retaining cofferdam and construction method thereof Active CN109403363B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811529614.3A CN109403363B (en) 2018-12-14 2018-12-14 Self-balancing combined water retaining cofferdam and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811529614.3A CN109403363B (en) 2018-12-14 2018-12-14 Self-balancing combined water retaining cofferdam and construction method thereof

Publications (2)

Publication Number Publication Date
CN109403363A true CN109403363A (en) 2019-03-01
CN109403363B CN109403363B (en) 2023-09-05

Family

ID=65459075

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811529614.3A Active CN109403363B (en) 2018-12-14 2018-12-14 Self-balancing combined water retaining cofferdam and construction method thereof

Country Status (1)

Country Link
CN (1) CN109403363B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111851542A (en) * 2020-07-31 2020-10-30 华北水利水电大学 Self-sinking combined steel cofferdam for channel side slope maintenance
CN111997074A (en) * 2020-08-20 2020-11-27 山西四建集团有限公司 Interim assembled concrete retaining platform subassembly
CN112459012A (en) * 2020-11-16 2021-03-09 河北省水利工程局 Canal lining plate repairing method
CN114839357A (en) * 2022-03-25 2022-08-02 河海大学 Device and method for testing frost heaving stress and frost heaving strain of porous asphalt mixture

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011208389A (en) * 2010-03-29 2011-10-20 Nippon Steel & Sumikin Metal Products Co Ltd Self-standing cofferdam structure and self-standing cofferdam method
CN106193074A (en) * 2016-07-14 2016-12-07 长江勘测规划设计研究有限责任公司 The steel cofferdam repaired for channel
CN107780423A (en) * 2017-11-24 2018-03-09 河南水建集团有限公司 Adjustable water cofferdam
CN108166515A (en) * 2017-12-29 2018-06-15 华北水利水电大学 A kind of waterpower self-stabilization type underwater construction cofferdam

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011208389A (en) * 2010-03-29 2011-10-20 Nippon Steel & Sumikin Metal Products Co Ltd Self-standing cofferdam structure and self-standing cofferdam method
CN106193074A (en) * 2016-07-14 2016-12-07 长江勘测规划设计研究有限责任公司 The steel cofferdam repaired for channel
CN107780423A (en) * 2017-11-24 2018-03-09 河南水建集团有限公司 Adjustable water cofferdam
CN108166515A (en) * 2017-12-29 2018-06-15 华北水利水电大学 A kind of waterpower self-stabilization type underwater construction cofferdam

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111851542A (en) * 2020-07-31 2020-10-30 华北水利水电大学 Self-sinking combined steel cofferdam for channel side slope maintenance
CN111997074A (en) * 2020-08-20 2020-11-27 山西四建集团有限公司 Interim assembled concrete retaining platform subassembly
CN112459012A (en) * 2020-11-16 2021-03-09 河北省水利工程局 Canal lining plate repairing method
CN114839357A (en) * 2022-03-25 2022-08-02 河海大学 Device and method for testing frost heaving stress and frost heaving strain of porous asphalt mixture
CN114839357B (en) * 2022-03-25 2023-05-16 河海大学 Device and method for testing frost heaving stress and frost heaving strain of porous asphalt mixture

Also Published As

Publication number Publication date
CN109403363B (en) 2023-09-05

Similar Documents

Publication Publication Date Title
CN109403363A (en) A kind of self balance combined water-retaining cofferdam and its construction method
CN104631512B (en) Hang modulus method after-pouring band beam-slab construction method
CN209412843U (en) A kind of self balance combined water-retaining cofferdam
CN103741657B (en) The construction method of large-sized multifunction waterborne traffic accident
CN209011138U (en) A kind of slope retaining device for excavation of foundation pit
CN206538788U (en) Prefabricated piping lane
CN105350581A (en) Advanced sealing structure for basement top slab settlement post-cast strips
CN111828013B (en) Ground shield tunnel experiment entity model and construction method thereof
CN106245678A (en) Outer wall of basement single side formwork construction method based on steel pipe truss
CN111188648A (en) Tunnel water-proof and drainage system and construction method thereof
CN207143746U (en) Support beam template system under concrete support trestle plate
CN110117959A (en) One kind closing on rivers base pit stand construction
CN207717504U (en) A kind of support construction for ultra-large type bifurcated pipe group's water pressure test
CN209585117U (en) A kind of prefabricated piping lane of hydraulic engineering
CN209211487U (en) A kind of breast boards structure
CN208886124U (en) A kind of fixation device of equipment installation
CN110258528B (en) Assembled and inserted self-clamping type prefabricated hollow underground continuous wall and construction method thereof
CN206591633U (en) A kind of cushion cap raft plate connecting node of concrete partition both sides different level
CN208167743U (en) A kind of concrete sealing bottom magazine attachment
CN112502746A (en) Shallow-buried underground excavation tunnel excavation supporting system and construction method
CN208010365U (en) A kind of gateway opening type light section lining shuttering support system
CN109681239A (en) A kind of unearthed tunnel mould bases construction method of shield
CN109577373A (en) A kind of prefabricated piping lane of hydraulic engineering
CN213741468U (en) Prefabricated concrete assembled temporary drainage ditch capable of being recycled
CN217630116U (en) Front-mounted assembly type water-stop post-pouring belt

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant