CN213741468U - Prefabricated concrete assembled temporary drainage ditch capable of being recycled - Google Patents

Prefabricated concrete assembled temporary drainage ditch capable of being recycled Download PDF

Info

Publication number
CN213741468U
CN213741468U CN202022738604.XU CN202022738604U CN213741468U CN 213741468 U CN213741468 U CN 213741468U CN 202022738604 U CN202022738604 U CN 202022738604U CN 213741468 U CN213741468 U CN 213741468U
Authority
CN
China
Prior art keywords
ditch
brick
ditch brick
shaped
prefabricated concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202022738604.XU
Other languages
Chinese (zh)
Inventor
罗娟
刘华波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Tianken Construction Co ltd
Original Assignee
Wuhan Tianken Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Tianken Construction Co ltd filed Critical Wuhan Tianken Construction Co ltd
Priority to CN202022738604.XU priority Critical patent/CN213741468U/en
Application granted granted Critical
Publication of CN213741468U publication Critical patent/CN213741468U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Sewage (AREA)

Abstract

The utility model relates to a but interim escape canal is assembled to cyclic utilization's prefabricated concrete relates to municipal construction field to connect as an organic whole and difficult bump between the adjacent ditch brick, it includes multiunit ditch brick, bearing structure and U-shaped board, the guiding gutter has been seted up along its length direction to the ditch brick, the slide rail of two parallels of bottom fixedly connected with of ditch brick, the slide rail is the same with the length direction of ditch brick, the bottom of ditch brick is equipped with two bearing structure, bearing structure includes the supporting shoe, sliding connection between supporting shoe and the slide rail is used for adjusting ditch brick and bearing structure's relative position, U-shaped board symmetry fixed connection in the both sides of supporting shoe for the locating position of more accurate supporting shoe. This application has and to make adjacent ditch brick be convenient for connect as an organic wholely, and need not during the installation butt joint in the air, the effect of difficult emergence collision.

Description

Prefabricated concrete assembled temporary drainage ditch capable of being recycled
Technical Field
The application relates to the field of municipal construction, in particular to a recyclable prefabricated concrete assembled temporary drainage ditch.
Background
In order to deal with rainy seasons in the construction process, temporary drainage facilities are generally required to be arranged, drainage ditches are divided into open ditches and blind ditches in the prior art, the open ditches are generally used for drainage in construction sites, a traditional open ditch method comprises the steps of digging a groove by using a digging machine, pouring a cushion layer at the bottom of the groove, then building a brick moulding bed on the cushion layer, plastering on the brick moulding bed, placing a cover plate on the brick moulding bed, wasting materials for the drainage ditches, and being tedious in construction process, long in construction time, high in manufacturing cost and incapable of being reused.
Retrieving a china utility model that application number is 201920821972.5 now and assembling interim escape canal, hanging through the loop wheel machine and putting the ditch brick, the joint strip that makes the one end of ditch brick inlays the cooperation with the joint groove inlay card to connect two adjacent ditch bricks as an organic whole, the concatenation is firm, and the wholeness is stronger.
With respect to the related art among the above, the inventors consider that the following drawbacks exist: through connecting two adjacent ditch bricks as an organic whole, need aim at joint strip and joint groove on two ditch bricks when hanging the ditch brick, it is comparatively troublesome to connect, and probably bumps between the ditch brick and cause the damage.
SUMMERY OF THE UTILITY MODEL
In order to connect as an organic whole and difficult bump between the ditch brick of convenience adjacent, this application provides a but interim escape canal is assembled to cyclic utilization's prefabricated concrete.
The application provides a but interim escape canal is assembled to cyclic utilization's prefabricated concrete adopts following technical scheme:
the utility model provides a temporary drainage ditch is assembled to prefabricated concrete that can cyclic utilization, includes multiunit ditch brick, bearing structure and U-shaped board, the guiding gutter has been seted up along its length direction to the ditch brick, the bottom fixedly connected with two parallel slide rails of ditch brick, the slide rail is the same with the length direction of ditch brick, the bottom of ditch brick is located to the bearing structure symmetry, bearing structure includes the supporting shoe, sliding connection between supporting shoe and the slide rail is used for adjusting the relative position of ditch brick and bearing structure, U-shaped board symmetry fixed connection in the both sides of supporting shoe for the locating position of accurate supporting shoe.
By adopting the technical scheme, when the temporary drainage ditch is laid, a plurality of groups of ditch bricks are laid in a drainage ditch gully, and the ditch bricks slide with the supporting blocks by pushing the ditch bricks, so that the adjacent ditch bricks are spliced together, accumulated water can be discharged through the diversion trench, the ditch bricks are butted in the horizontal direction and are easily connected into a whole, and the temporary drainage ditch cannot be damaged due to collision.
Optionally, the two side walls of the diversion trench are inclined, the bottom groove width of the diversion trench is smaller than the top groove width, and the inner wall of the diversion trench is coated with waterproof paint.
Through adopting above-mentioned technical scheme, the inner wall of guiding gutter scribbles waterproof paint, and the ditch brick is when carrying out the drainage, and during water can not permeate the ditch brick, can prolong the life of ditch brick.
Optionally, the supporting block is in a cuboid shape, a sliding groove is formed in the upper surface of the supporting block, two connecting portions are symmetrically arranged at the sliding groove of the supporting block, the connecting portions are poured inside the supporting block, and a T-shaped sliding groove is formed inside the connecting portions.
Through adopting above-mentioned technical scheme, two supporting shoes can support the bottom both sides of ditch brick, and the ditch brick can slide on the supporting shoe, is convenient for make two adjacent supporting shoes dock, and convenient operation improves and assembles efficiency.
Optionally, the slide rail is T-shaped and made of stainless steel, and the slide rail is slidably connected with the T-shaped sliding groove of the connecting portion.
Through adopting above-mentioned technical scheme, the slide rail sets to the T shape, makes it can be connected with connecting portion to can make the supporting shoe connect on the ditch brick, and connect more stably, the ditch brick of being convenient for simultaneously slides on the supporting shoe.
Optionally, a U-shaped clamping groove is formed in one end of each ditch brick, a U-shaped clamping strip is fixedly connected to the other end of each ditch brick, and the clamping strips are matched with the clamping grooves and used for connecting adjacent ditch bricks.
Through adopting above-mentioned technical scheme, the U type joint strip of ditch brick one end can insert in the joint groove of another ditch brick one end to can be with two adjacent ditch brick connection more stable, reduce ponding simultaneously and flow into ground from the gap.
Optionally, the equal fixedly connected with rubber piece in both ends of ditch brick, set up the U-shaped through-hole with joint groove and joint strip looks adaptation on the rubber piece.
Through adopting above-mentioned technical scheme, when two adjacent ditch bricks splice, two sheet rubbers contact, rivers flow out from the gap when further reducing the drainage to can improve the leakproofness that the ditch brick is connected, make drainage effect better.
Optionally, two limiting structures which are symmetrically arranged and used for accurately positioning the supporting block are arranged below the supporting block, the distance between the two limiting structures is equal to the distance between the two U-shaped plates, each limiting structure comprises a limiting rod and two bases, two ends of each limiting rod are fixedly connected with the two bases respectively, the bases are fixedly connected to the ground, and the limiting rods are matched with the U-shaped plates.
Through adopting above-mentioned technical scheme, the base can fixed mounting in ground, and the gag lever post on the base can carry out the calibration to the supporting shoe, makes the position of placing of supporting shoe more accurate.
Optionally, the U-shaped plate is made of a steel plate, an opening of the U-shaped plate faces downward, one side of the U-shaped plate is fixedly connected with the supporting block, and the U-shaped plate can be sleeved outside the limiting rod.
Through adopting above-mentioned technical scheme, the outside of symmetrical arrangement's gag lever post is located to the U-shaped plate cover of backup pad both sides, can make the ditch brick can accurate location when falling, makes the supporting shoe keep at same axis to the ditch brick can prepare the butt joint when sliding.
Optionally, the mounting groove has all been seted up to the both sides of the upper surface of ditch brick, a plurality of apron that are used for covering the guiding gutter have been laid to the top of ditch brick, apron and mounting groove looks adaptation, the arc wall has all been seted up to the both sides of apron, and two are adjacent the arc wall combination is used for leaking.
Through adopting above-mentioned technical scheme, the apron can cover the top of ditch brick, avoids debris to cause the jam in falling into the ditch brick, and in the installation groove was located to the apron, and difficult removal, the arc wall combination on the apron can form the through-hole, makes the water on the apron flow to the guiding gutter in through the through-hole.
Optionally, two symmetrically-arranged grooves are formed in the two sides of each ditch brick, fixing rods are transversely and fixedly connected between the inner walls of the two sides of each groove, and lifting hooks for conveying the ditch bricks are sleeved outside the fixing rods.
Through adopting above-mentioned technical scheme, with the lifting hook roll-out, can use the loop wheel machine to hang the ditch brick and put to putting the ditch brick, the ditch brick is laid and is accomplished the back, and the lifting hook can rotate to the inside of recess, conveniently deposits.
In summary, the present application includes at least the following advantageous technical effects:
1. the sliding rails can slide at the connecting parts of the supporting blocks, so that the ditch bricks can be connected with the supporting blocks in a sliding manner, the adjacent ditch bricks can be connected by sliding of the ditch bricks, the ditch bricks can be conveniently spliced into a whole, the ditch bricks are not required to be directly contacted when being hung, and the condition that the ditch bricks are collided and damaged can not be caused;
2. the clamping strip at one end of each ditch brick is inserted into the clamping groove at one end of each ditch brick, so that the two adjacent ditch bricks are connected, accumulated water is reduced to flow out of a gap, and when the two ditch bricks are spliced, the two rubber sheets are contacted, so that the connection tightness can be further improved;
3. the limiting structure can position the supporting plate, and the U-shaped plate is sleeved on the limiting rod, so that the supporting block can be kept on the same axis, and the ditch brick can be accurately butted when sliding.
Drawings
Fig. 1 is a schematic view showing an overall structure of a connection bar according to an embodiment of the present application.
Fig. 2 is a schematic view showing an overall structure of a connecting groove according to an embodiment of the present application.
Fig. 3 is a schematic structural diagram of the display support structure according to an embodiment of the present application.
Reference numerals: 1. a gutter brick; 11. a diversion trench; 12. a clamping groove; 13. a clamping strip; 14. a rubber sheet; 15. mounting grooves; 2. a support structure; 21. a support block; 22. a connecting portion; 3. a U-shaped plate; 4. a slide rail; 5. a limiting structure; 51. a limiting rod; 52. a base; 6. a cover plate; 61. an arc-shaped slot; 7. fixing the rod; 8. and (4) a lifting hook.
Detailed Description
The present application is described in further detail below with reference to figures 1-3.
For coping with rainy season in the work progress, interim drainage facility generally need to be set up, the escape canal divide into open ditch and blind ditch two kinds among the prior art, job site drainage generally uses open ditch, traditional open ditch method is earlier to dig a groove with the excavator, at the bottom of the groove pouring bed course, then build by laying bricks bed film on the bed course, plaster on bricks bed film, above-mentioned apron 6 of putting, this kind of extravagant material in escape canal, the work progress is loaded down with trivial details, the engineering time is long, the cost is high, and can not used repeatedly, current ditch brick 1 can form interim escape canal through connecting as an organic whole, be used for the drainage, nevertheless ditch brick 1 need butt joint in the air when connecting, connect inconveniently, and easy the collision that takes place during the butt joint causes ditch brick 1 to damage.
The embodiment of the application discloses interim escape canal is assembled to prefabricated concrete that can cyclic utilization. Referring to fig. 1-3, the prefabricated concrete assembling temporary drainage ditch capable of being recycled comprises a plurality of groups of ditch bricks 1, a supporting structure 2 and U-shaped plates 3, wherein a diversion trench 11 is formed in each ditch brick 1 along the length direction of the ditch brick, the diversion trench 11 is used for draining water, the groove walls on two sides of each diversion trench 11 are inclined, the groove width of the bottom of each diversion trench 11 is smaller than that of the top of each diversion trench, and the inner wall of each diversion trench 11 is coated with waterproof paint to prevent water from permeating into cement and prolonging the service life of each ditch brick 1.
The bottom of the ditch brick 1 is connected with two parallel slide rails 4 through bolts, the slide rails 4 are the same as the ditch brick 1 in the length direction, the slide rails 4 are T-shaped and made of stainless steel, and the slide rails are used for enabling the ditch brick 1 to slide.
Joint groove 12 that is the U-shaped is seted up to ditch brick 1's one end, ditch brick 1's the other end be equipped with pour in ditch brick 1 inside and with joint strip 13 of joint groove 12 looks adaptation, joint strip 13 can be connected with joint groove 12 and be used for two adjacent ditch bricks 1, ditch brick 1's both ends all bond there is rubber piece 14, and set up the U-shaped through-hole with joint groove 12 and joint strip 13 looks adaptations on the rubber piece 14, it flows into the underground to reduce ponding from ditch brick 1's gap.
The bottom of ditch brick 1 is located to bearing structure 2 symmetry, bearing structure 2 includes supporting shoe 21, supporting shoe 21 is the cuboid form, the spout is seted up to the upper surface of supporting shoe 21, supporting shoe 21 has two connecting portion 22 at spout department symmetrical arrangement, connecting portion 22 are pour in the inside of supporting shoe 21, and the inside T shape recess of having seted up of connecting portion 22, slide rail 4 and connecting portion 22 looks adaptation, slide rail 4 can slide in T shape recess is inside, thereby make ditch brick 1 slide on supporting shoe 21.
U-shaped plate 3 symmetry sets up in the both sides of supporting shoe 21, and the material of U-shaped plate 3 is the steel sheet, and the opening of U-shaped plate 3 is down, and the inside in supporting shoe 21 is pour to one side of U-shaped plate 3, and the U-shaped piece is used for fixing a position supporting shoe 21 to make the supporting shoe 21 of adjacent ditch brick 1 bottom place at same axis.
The below of supporting shoe 21 is equipped with two symmetrical arrangement's limit structure 5, and limit structure 5 is used for the position of accurate positioning supporting shoe 21, and limit structure includes gag lever post 51 and two bases 52, and the inside in two bases 52 is pour respectively at gag lever post 51's both ends, and base 52 can be buried in the underground and fixed, and the U-shaped plate 3 cover of supporting shoe 21 both sides is located on two gag lever posts 51 to make the position of supporting shoe 21 can fix.
Mounting groove 15 has all been seted up to the both sides of 1 upper surface of ditch brick, and a plurality of apron 6 have been laid to the top of ditch brick 1, and in mounting groove 15 was all located at the both ends of apron 6, apron 6 was used for covering the guiding gutter 11 of ditch brick 1, and the arc 61 has all been seted up to the both sides of apron 6, and two adjacent apron 6 connect the back, and two arc 61 can make up into the through-hole that is used for leaking.
Two symmetrical arrangement's recess has all been seted up to ditch brick 1's both sides, transversely is provided with dead lever 7 between the both sides inner wall of recess, and the both ends of dead lever 7 are all pour in ditch brick 1's inside, and the outside cover of dead lever 7 is equipped with lifting hook 8, and lifting hook 8 is used for connecting the loop wheel machine, transports ditch brick 1.
The implementation principle of this application embodiment temporary drainage ditch is assembled to cyclic utilization's prefabricated concrete does: when the ditch brick 1 is laid, the two limit structures 5 are symmetrically arranged in the dug drainage gully, the base 52 is buried underground, the limit rod 51 is exposed on the ground, the lifting hook 8 of the ditch brick 1 is hooked up by a crane, transporting the gutter brick 1, placing the gutter brick 1 above the limiting structure 5, sleeving the U-shaped plates 3 on two sides of the supporting block 21 outside the limiting rod 51, then installing another gutter brick 1 above the limiting structure in the same way, by pushing the gutter brick 1, the slide rail 4 can slide in the supporting block 21, the clamping strip 13 on the gutter brick 1 enters the clamping groove 12 on the other gutter brick 1, thereby can connect two ditch bricks 1, the contact of the rubber piece 14 between ditch brick 1, reinforcing leakproofness, lay apron 6 on ditch brick 1 again at last for people and vehicle pass through, arc wall 61 between the apron 6 can be used for logical water.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (10)

1. The utility model provides a but interim escape canal is assembled to cyclic utilization's prefabricated concrete which characterized in that: including multiunit ditch brick (1), bearing structure (2) and U-shaped board (3), guiding gutter (11) have been seted up along its length direction in ditch brick (1), the bottom fixedly connected with two parallel slide rails (4) of ditch brick (1), slide rail (4) are the same with the length direction of ditch brick (1), the bottom of ditch brick (1) is located to bearing structure (2) symmetry, bearing structure (2) include supporting shoe (21), sliding connection between supporting shoe (21) and slide rail (4) is used for adjusting the relative position of ditch brick (1) and bearing structure (2), U-shaped board (3) symmetry fixed connection in the both sides of supporting shoe (21) are used for calibrating the locating position of supporting shoe (21).
2. The prefabricated concrete assembled temporary drainage ditch capable of being recycled according to claim 1, which is characterized in that: the both sides cell wall of guiding gutter (11) all is the slope form, and the bottom groove width of guiding gutter (11) is less than the top groove width, the inner wall of guiding gutter (11) scribbles waterproof paint.
3. The prefabricated concrete assembled temporary drainage ditch capable of being recycled according to claim 1, which is characterized in that: the supporting block (21) is cuboid, a sliding groove is formed in the upper surface of the supporting block (21), two connecting portions (22) are symmetrically arranged at the sliding groove of the supporting block (21), the connecting portions (22) are poured inside the supporting block (21), and a T-shaped sliding groove is formed inside the connecting portions (22).
4. The prefabricated concrete assembled temporary drainage ditch capable of being recycled according to claim 3, wherein: the sliding rail (4) is T-shaped and made of stainless steel, and the sliding rail (4) is connected with the T-shaped sliding groove of the connecting portion (22) in a sliding mode.
5. The prefabricated concrete assembled temporary drainage ditch capable of being recycled according to claim 1, which is characterized in that: joint groove (12) that are the U-shaped are seted up to the one end of ditch brick (1), the other end fixedly connected with of ditch brick (1) is joint strip (13) of U-shaped, joint strip (13) and joint groove (12) looks adaptation for connect adjacent ditch brick (1).
6. The prefabricated concrete assembled temporary drainage ditch capable of being recycled according to claim 5, is characterized in that: equal fixedly connected with sheet rubber (14) in both ends of ditch brick (1), set up the U-shaped through-hole with joint groove (12) and joint strip (13) looks adaptation on sheet rubber (14).
7. The prefabricated concrete assembled temporary drainage ditch capable of being recycled according to claim 1, which is characterized in that: the supporting structure is characterized in that two limiting structures (5) which are symmetrically arranged and used for accurately positioning the supporting block (21) are arranged below the supporting block (21), the distance between the limiting structures (5) is equal to the distance between the two U-shaped plates (3), each limiting structure (5) comprises a limiting rod (51) and two bases (52), two ends of each limiting rod (51) are fixedly connected with the two bases (52), the bases (52) are fixedly connected to the ground, and the limiting rods (51) are matched with the U-shaped plates (3).
8. The prefabricated concrete assembled temporary drainage ditch capable of being recycled according to claim 7, wherein: the U-shaped plate (3) is made of a steel plate, an opening of the U-shaped plate (3) faces downwards, one side of the U-shaped plate (3) is fixedly connected with the supporting block (21), and the U-shaped plate (3) can be sleeved outside the limiting rod (51).
9. The prefabricated concrete assembled temporary drainage ditch capable of being recycled according to claim 1, which is characterized in that: mounting groove (15) have all been seted up to the both sides of the upper surface of ditch brick (1), a plurality of apron (6) that are used for covering guiding gutter (11) have been laid to the top of ditch brick (1), apron (6) and mounting groove (15) looks adaptation, arc wall (61), two adjacent arc wall (61) combination is used for leaking has all been seted up to the both sides of apron (6).
10. The prefabricated concrete assembled temporary drainage ditch capable of being recycled according to claim 1, which is characterized in that: two symmetrically-arranged grooves are formed in two sides of each ditch brick (1), fixing rods (7) are transversely and fixedly connected between the inner walls of two sides of each groove, and lifting hooks (8) used for conveying the ditch bricks (1) are sleeved outside the fixing rods (7).
CN202022738604.XU 2020-11-24 2020-11-24 Prefabricated concrete assembled temporary drainage ditch capable of being recycled Active CN213741468U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022738604.XU CN213741468U (en) 2020-11-24 2020-11-24 Prefabricated concrete assembled temporary drainage ditch capable of being recycled

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022738604.XU CN213741468U (en) 2020-11-24 2020-11-24 Prefabricated concrete assembled temporary drainage ditch capable of being recycled

Publications (1)

Publication Number Publication Date
CN213741468U true CN213741468U (en) 2021-07-20

Family

ID=76828286

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022738604.XU Active CN213741468U (en) 2020-11-24 2020-11-24 Prefabricated concrete assembled temporary drainage ditch capable of being recycled

Country Status (1)

Country Link
CN (1) CN213741468U (en)

Similar Documents

Publication Publication Date Title
US3195312A (en) Method for erecting precast retaining wall
CN111691467B (en) Construction method for basement water prevention and drainage combination
CN114808776A (en) Prefabricated installation construction method for prefabricated box culvert pipe
CN109403363A (en) A kind of self balance combined water-retaining cofferdam and its construction method
CN111779028A (en) Finished prefabricated electric shallow trench and construction method thereof
CN103822017A (en) Construction method based on laying of cable duct bank
CN113700018A (en) Open caisson construction method for large-volume pump station
CN213741468U (en) Prefabricated concrete assembled temporary drainage ditch capable of being recycled
CN111424699A (en) Construction method of pile foundation bearing platform A L C plate forming die
CN114809000B (en) Rapid construction method of prefabricated plate brick moulding bed
CN114319545A (en) High-impermeability concrete drainage ditch system and construction method thereof
CN110863555B (en) Construction process for laying sewage collection pipeline in village and town areas
CN213086849U (en) U-shaped groove with side wall
CN210395594U (en) Prefabricated concrete assembled temporary drainage ditch
CN114703770A (en) Box culvert construction process
CN113089454A (en) Foundation pit trestle slope and construction method thereof
CN211172070U (en) Assembled type suspended wall retaining wall structure of reinforced concrete member
CN112681345A (en) Installation process of prefabricated block for framework slope protection
CN110685719A (en) Quick construction method for double-span simply-supported inverted arch trestle
KR20090095204A (en) Method of repairing and reinforcing submarine concrete constructions
CN215052711U (en) It leads to steel-concrete river course to span subway station foundation ditch guarantor
CN217204517U (en) High impervious concrete escape canal system
CN217537031U (en) Deep basal pit raft, sump pit, elevartor shaft integration construction structures
CN215289648U (en) Foundation pit trestle slope
CN213114712U (en) U type groove of being connected with road bed

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant