CN109403339A - The deep basal pit composite supporting construction and its method for protecting support of double-row pile combination method of center island - Google Patents

The deep basal pit composite supporting construction and its method for protecting support of double-row pile combination method of center island Download PDF

Info

Publication number
CN109403339A
CN109403339A CN201811203470.2A CN201811203470A CN109403339A CN 109403339 A CN109403339 A CN 109403339A CN 201811203470 A CN201811203470 A CN 201811203470A CN 109403339 A CN109403339 A CN 109403339A
Authority
CN
China
Prior art keywords
double
bracing members
earthen platform
campshed
row pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811203470.2A
Other languages
Chinese (zh)
Other versions
CN109403339B (en
Inventor
刘卫未
周予启
马丽丽
聂艳侠
刘广济
马书杰
郭恒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction First Group Corp Ltd
Original Assignee
China Construction First Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction First Group Corp Ltd filed Critical China Construction First Group Corp Ltd
Priority to CN201811203470.2A priority Critical patent/CN109403339B/en
Publication of CN109403339A publication Critical patent/CN109403339A/en
Application granted granted Critical
Publication of CN109403339B publication Critical patent/CN109403339B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/18Restraining of underground water by damming or interrupting the passage of underground water by making use of sealing aprons, e.g. diaphragms made from bituminous or clay material

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Foundations (AREA)

Abstract

A kind of the deep basal pit composite supporting construction and its method for protecting support of double-row pile combination method of center island, supporting construction includes double-row pile, crown beam, coupling beam and water-stop curtain, it further include back-pressure earthen platform, waist rail, main structure bottom plate, buttress and bracing members, back-pressure earthen platform is to reserve after carrying out central island excavation along the soil body in the middle part of foundation pit in the earthen platform on foundation pit side-wall periphery, one end of bracing members is fixedly connected with waist rail, the other end of bracing members is fixedly connected with buttress, and bracing members cross over back-pressure earthen platform or the top for being embedded to back-pressure earthen platform.The method for protecting support of reserved back-pressure soil in bracing members and hole is excavated and be aided with to double-row pile combination central island of the invention, effectively control Foundation Pit, that the pre- allowance, later period that can effectively save back-pressure soil are excavated in conjunction with central island excavates workload, save the construction cost of a large amount of inner supports, lattice column and stand column pile etc., realize accessible effective of large area in cheating excavate and and building rapid construction, shorten the construction period.

Description

The deep basal pit composite supporting construction and its method for protecting support of double-row pile combination method of center island
Technical field
The present invention relates to a kind of deep foundation pit supporting structure, especially a kind of double-row pile composite supporting construction and its supporting side Method.
Background technique
In foundation pit supporting project, the door type structure that double-row pile is formed plus top crown beam and coupling beam has biggish side To rigidity and overall stability, it can favorably control foundation pit deformation, shorten the construction period and reduce cost.Cantilevered double-row pile theory branch Depth is protected generally in 10m or so, in conjunction with large area inner support or draws anchor that can increase supporting depth, but anchor support is to surrounding enviroment requirement Harsh, large area inner support needs to occupy part construction space, extends the construction period.
Summary of the invention
The object of the present invention is to provide a kind of deep basal pit composite supporting construction of double-row pile combination method of center island and its supportings Method, to solve existing Double-row Piles Support there are depth limits it is larger, surrounding enviroment are required it is harsh, occupy part construct it is empty Between, construction period longer technical problem.
To achieve the above object, the present invention adopts the following technical scheme:
A kind of deep basal pit composite supporting construction of double-row pile combination method of center island, including double-row pile, crown beam, coupling beam and sealing curtain Curtain, the double-row pile includes preceding campshed and rear campshed, and preceding campshed and rear campshed are along vertical foundation pit side wall soil body direction time interval Setting, together with the crown beam is respectively fixedly connected with along the stake top of preceding campshed with the stake top of rear campshed, before the coupling beam is fixedly connected Twice crown beam afterwards, the rear side setting of campshed before the water-stop curtain is close to,
The deep basal pit composite supporting construction of the double-row pile combination method of center island further includes back-pressure earthen platform, waist rail, main structure bottom Plate, main structure, buttress and bracing members,
The back-pressure earthen platform is to reserve after carrying out central island excavation along the soil body in the middle part of foundation pit in the earthen platform on foundation pit side-wall periphery, described The front side of the immediately preceding campshed in back-pressure earthen platform,
The top of the front side of campshed, the top positioned at back-pressure earthen platform or embedment back-pressure earthen platform before the waist rail is fixedly connected on,
The main structure bottom plate is located in the substrate reserved after central island is excavated, and the buttress is fixedly connected on main structure bottom The end of plate, the end are located at close to the side of foundation pit side-wall,
The bracing members are arranged along foundation pit interval, and one end of bracing members is fixedly connected with waist rail, the face that waist rail is connect with bracing members It is vertical with bracing members,
The other end of bracing members is fixedly connected with buttress, and the bracing members are across back-pressure earthen platform and are positioned above or are partly embedded into The top of back-pressure earthen platform.
The downside of coupling beam is fixedly connected at the top of the water-stop curtain, the elevation of bottom of the water-stop curtain is lower than front row The elevation of bottom of stake and the elevation of bottom of rear campshed.
The cross-sectional shape of the back-pressure earthen platform is right-angled trapezium, and bevel edge tilts down.
The gradient of the bevel edge is 1:1.5-1:2.0.
The width at least 20m on the bottom edge of the back-pressure earthen platform, the back-pressure earthen platform are single-stage step or two stage steps or three The step width of grade step, two stage steps or three-level step is from top to bottom successively decreased.
The buttress reinforced concrete block or fashioned iron block, the face that buttress is connect with bracing members is vertical with bracing members, the branch The number of pier and the number of bracing members are identical, are arranged in a one-to-one correspondence with it.
The depth of the foundation pit is greater than 15m.
A kind of method for protecting support of the deep basal pit composite supporting construction using double-row pile combination method of center island, construction procedure is such as Under:
Step 1 determines the diameter of double-row pile, the pilespacing of every campshed, the pilespacing of front and back campshed and anti-according to design and force analysis The base width of firming platform, the length of the gradient of bevel edge and bracing members, tilt angle, prestress and construction location;
Step 2, successively construct in order preceding campshed, rear campshed, crown beam, coupling beam and water-stop curtain;
Step 3, foundation pit middle part carry out central island-type excavation, reserve back-pressure earthen platform on foundation pit periphery;
Step 4, when central island-type is excavated to substrate, in base upper portion construction main structure bottom plate;
Step 5, waist rail of constructing on preceding campshed, buttress of constructing on main structure bottom plate;
Step 6 sets up bracing members, while the main structure on main structure bottom plate in the middle part of construction foundation pit between waist rail and buttress;
Step 7, to main structure construction after, excavate back-pressure earthen platform;
Step 8, the construction foundation pit surrounding structure between preceding campshed and main structure exterior wall remove bracing members after completing support replacement.
Compared with prior art the invention has the characteristics that and the utility model has the advantages that
The present invention solves the Double-row Piles Support technical problem larger there are depth limit, and double-row pile combination central island excavation is simultaneously auxiliary With the method for protecting support of reserved back-pressure soil in bracing members and hole, can be applied to soft clay area, high water level and cutting depth is more than 15m's In super-sized foundation pit engineering.
Double-row pile combination bracing members and reserved back-pressure soil the central island digging mode phase in conjunction with simple double-row pile of the invention Than supporting depth can be deepened, effectively control Foundation Pit;The reserved of back-pressure soil can effectively be saved by excavating in conjunction with central island Amount, later period excavate workload, save the construction cost of a large amount of inner supports, lattice column and stand column pile etc..Present invention solution simultaneously Having determined, it is harsh to require surrounding enviroment, occupies part construction space, and construction period longer technical problem realizes large area in cheating It is accessible it is effective excavate and and building rapid construction, shorten the construction period.The present invention combines sealing curtain in high water level area The use of curtain is effectively truncated or increases the percolation path of underground water inside and outside foundation pit, reduces underground water to the shadow of base pit engineering It rings.
Detailed description of the invention
The present invention will be further described in detail with reference to the accompanying drawing.
Schematic diagram after the completion of the step of Fig. 1 is structural schematic diagram of the invention, construction method of the present invention six.
Schematic diagram after the completion of the step of Fig. 2 is construction method of the present invention three.
Schematic diagram after the completion of the step of Fig. 3 is construction method of the present invention five.
Schematic diagram after the completion of the step of Fig. 4 is construction method of the present invention seven.
Appended drawing reference: campshed after campshed, 2- before 1-, 3- crown beam, 4- coupling beam, 5- water-stop curtain, 6- bracing members, 7- back-pressure earthen platform, 71- bevel edge, the bottom edge 72-, 8- waist rail, 9- buttress, 10- main structure, 11- main structure bottom plate, 12- substrate.
Specific embodiment
Embodiment is shown in Figure 1, a kind of deep basal pit composite supporting construction of double-row pile combination method of center island, including double Stake, crown beam 3, coupling beam 4 and water-stop curtain 5, the double-row pile include preceding campshed 1 and rear campshed 2, and preceding campshed 1 and rear campshed 2 are along vertical Straight foundation pit side-wall soil body direction time interval setting, the crown beam 3 are solid respectively along the stake top of preceding campshed 1 and the stake top of rear campshed 2 Together, the coupling beam 4 is fixedly connected with front and back twice crown beam 3 for fixed connection, the rear side setting of campshed before the water-stop curtain 5 is close to.
The deep basal pit composite supporting construction of the double-row pile combination method of center island further includes back-pressure earthen platform 7, waist rail 8, main body Structure base slab 11, main structure 10, buttress 9 and bracing members 6.
The back-pressure earthen platform 7 is to reserve after carrying out central island excavation along the soil body in the middle part of foundation pit in the soil on foundation pit side-wall periphery Platform, the front side of the immediately preceding campshed 1 in the back-pressure earthen platform 7.
The front side of campshed 1, the top positioned at back-pressure earthen platform 7 or embedment back-pressure earthen platform before the waist rail 8 is fixedly connected on Top.
The main structure bottom plate 11 is located in the substrate 12 reserved after central island is excavated, and the buttress 9 is fixedly connected on The end of main structure bottom plate 11, the end are located at close to the side of foundation pit side-wall.
The bracing members 6 are arranged along foundation pit interval, and one end of bracing members 6 is fixedly connected with waist rail 8, waist rail 8 and bracing members 6 The face of connection is vertical with bracing members 6.
The other end of bracing members 6 is fixedly connected with buttress 9, the bracing members 6 across back-pressure earthen platform 7 and be positioned above or It is partly embedded into the top of back-pressure earthen platform 7.
The top of the water-stop curtain 5 is fixedly connected on the downside of coupling beam 4, and the elevation of bottom of the water-stop curtain 5 is lower than The elevation of bottom of preceding campshed 1 and the elevation of bottom of rear campshed 2.
The cross-sectional shape of the back-pressure earthen platform 7 is right-angled trapezium, and bevel edge 71 tilts down.
The gradient of the bevel edge 71 is 1:1.5-1:2.0.
The width at least 20m on the bottom edge 72 of the back-pressure earthen platform 7, the back-pressure earthen platform be single-stage step or two stage steps or The step width of three-level step, two stage steps or three-level step is from top to bottom successively decreased.
9 reinforced concrete block of buttress or fashioned iron block, the face that buttress 9 is connect with bracing members 6 is vertical with bracing members 6, institute The number for stating buttress 9 is identical as the number of bracing members 6, is arranged in a one-to-one correspondence with it.
The depth of the foundation pit is greater than 15m.
The method for protecting support of this deep basal pit composite supporting construction using double-row pile combination method of center island, construction procedure is such as Under:
Step 1 determines the diameter of double-row pile, the pilespacing of every campshed, the pilespacing of front and back campshed and anti-according to design and force analysis 72 width of bottom edge of firming platform 7, the length of the gradient of bevel edge 71 and bracing members 6, tilt angle, prestress and construction position It sets.
Step 2, successively construct in order preceding campshed 1, rear campshed 2, crown beam 3, coupling beam 4 and water-stop curtain 5.
Step 3, foundation pit middle part carry out central island-type excavation, reserve back-pressure earthen platform 7 on foundation pit periphery, shown in Figure 2.
Step 4, when central island-type is excavated to substrate 12, on the base 12 portion construct main structure bottom plate 11.
Step 5, waist rail 8 of constructing on preceding campshed, construct on main structure bottom plate 11 buttress 9, in practice of construction, waist Beam 8 may be arranged at the top of back-pressure earthen platform 7, can also slightly shallow embedding can will be native around inside the upper surface of back-pressure earthen platform 7, when construction Body is constructed waist rail after digging out.It is shown in Figure 3, it is the case where waist rail 8 may be arranged at the top of back-pressure earthen platform 7.
Step 6 sets up bracing members 6 between waist rail 8 and buttress 9, while on main structure bottom plate 11 in the middle part of construction foundation pit Main structure 10, in practice of construction, bracing members 6 may be arranged at the top of back-pressure earthen platform 7, can also slightly shallow embedding in back-pressure earthen platform 7 Upper surface inside, construction steel support 6 after slotting can be carried out when construction to the soil body.It is shown in Figure 1, it is the slightly shallow embedding of bracing members 6 Situation inside the upper surface of back-pressure earthen platform 7.
Step 7 excavates back-pressure earthen platform 7 after constructing to main structure 10, shown in Figure 4.
Step 8, the construction foundation pit surrounding structure between 10 exterior wall of preceding campshed 1 and main structure are completed bracing members after support replacement 6 remove.

Claims (8)

1. a kind of deep basal pit composite supporting construction of double-row pile combination method of center island, including double-row pile, crown beam (3), coupling beam (4) and Water-stop curtain (5), the double-row pile include preceding campshed (1) and rear campshed (2), and preceding campshed (1) and rear campshed (2) are along vertical foundation pit The setting of side wall soil body direction time interval, the crown beam (3) are solid respectively along the stake top of preceding campshed (1) and the stake top of rear campshed (2) Together, the coupling beam (4) is fixedly connected with front and back twice crown beam (3) for fixed connection, the rear side of campshed before the water-stop curtain (5) is close to Setting, it is characterised in that:
The deep basal pit composite supporting construction of the double-row pile combination method of center island further includes back-pressure earthen platform (7), waist rail (8), main body Structure base slab (11), main structure (10), buttress (9) and bracing members (6),
The back-pressure earthen platform (7) is to reserve after carrying out central island excavation along the soil body in the middle part of foundation pit in the earthen platform on foundation pit side-wall periphery, The front side of the immediately preceding campshed of the back-pressure earthen platform (7) (1),
The waist rail (8) is fixedly connected on the front side of preceding campshed (1), the top for being located at back-pressure earthen platform (7) or embedment back-pressure earthen platform (7) top,
The main structure bottom plate (11) is located in the substrate (12) reserved after central island is excavated, and the buttress (9) is fixedly connected In the end of main structure bottom plate (11), which is located at close to the side of foundation pit side-wall,
The bracing members (6) are arranged along foundation pit interval, and one end of bracing members (6) is fixedly connected with waist rail (8), waist rail (8) and steel Support the face of (6) connection vertical with bracing members,
The other end of bracing members (6) is fixedly connected with buttress (9), and the bracing members (6) are crossed over back-pressure earthen platform (7) and disposed thereon Side or the top for being partly embedded into back-pressure earthen platform (7).
2. the deep basal pit composite supporting construction of double-row pile combination method of center island according to claim 1, it is characterised in that: institute The downside that coupling beam (4) are fixedly connected at the top of water-stop curtain (5) is stated, the elevation of bottom of the water-stop curtain (5) is lower than front row The stake elevation of bottom of (1) and the elevation of bottom of rear campshed (2).
3. the deep basal pit composite supporting construction of double-row pile combination method of center island according to claim 1, it is characterised in that: institute The cross-sectional shape for stating back-pressure earthen platform (7) is right-angled trapezium, and bevel edge (71) tilts down.
4. the deep basal pit composite supporting construction of double-row pile combination method of center island according to claim 1, it is characterised in that: institute The gradient for stating bevel edge (71) is 1:1.5-1:2.0.
5. the deep basal pit composite supporting construction of double-row pile combination method of center island according to claim 4, it is characterised in that: institute The width at least 20m on the bottom edge (72) of back-pressure earthen platform (7) is stated, the back-pressure earthen platform is single-stage step or two stage steps or three-level platform The step width of rank, two stage steps or three-level step is from top to bottom successively decreased.
6. the deep basal pit composite supporting construction of double-row pile combination method of center island according to claim 1, it is characterised in that: institute Buttress (9) reinforced concrete block or fashioned iron block are stated, the face that buttress (9) is connect with bracing members (6) is vertical with bracing members, the buttress (9) number is identical as the number of bracing members (6), is arranged in a one-to-one correspondence with it.
7. the deep basal pit composite supporting construction of double-row pile combination method of center island according to claim 1, it is characterised in that: institute The depth for stating foundation pit is greater than 15m.
8. a kind of deep basal pit composite supporting construction using double-row pile combination method of center island described in claim 1-7 any one Method for protecting support, which is characterized in that construction procedure is as follows:
Step 1 determines the diameter of double-row pile, the pilespacing of every campshed, the pilespacing of front and back campshed and anti-according to design and force analysis Bottom edge (72) width of firming platform (7), the gradient of bevel edge (71) and length, the tilt angle, prestress of bracing members (6) And construction location;
Step 2, successively construct in order preceding campshed (1), rear campshed (2), crown beam (3), coupling beam (4) and water-stop curtain (5);
Step 3, foundation pit middle part carry out central island-type excavation, reserve back-pressure earthen platform (7) on foundation pit periphery;
Step 4 when central island-type is excavated to substrate (12), constructs main structure bottom plate (11) on substrate (12) top;
Step 5 is constructed waist rail (8) on preceding campshed, constructs buttress (9) on main structure bottom plate (11);
Step 6 sets up bracing members (6) between waist rail (8) and buttress (9), while on main structure bottom plate (11) in construction foundation pit The main structure (10) in portion;
Step 7 excavates back-pressure earthen platform (7) after constructing to main structure (10);
Step 8, the construction foundation pit surrounding structure between preceding campshed (1) and main structure (10) exterior wall are completed bracing members after support replacement (6) it removes.
CN201811203470.2A 2018-10-16 2018-10-16 Deep foundation pit composite supporting structure combining double-row piles with center island method and supporting method thereof Active CN109403339B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811203470.2A CN109403339B (en) 2018-10-16 2018-10-16 Deep foundation pit composite supporting structure combining double-row piles with center island method and supporting method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811203470.2A CN109403339B (en) 2018-10-16 2018-10-16 Deep foundation pit composite supporting structure combining double-row piles with center island method and supporting method thereof

Publications (2)

Publication Number Publication Date
CN109403339A true CN109403339A (en) 2019-03-01
CN109403339B CN109403339B (en) 2024-01-23

Family

ID=65468186

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811203470.2A Active CN109403339B (en) 2018-10-16 2018-10-16 Deep foundation pit composite supporting structure combining double-row piles with center island method and supporting method thereof

Country Status (1)

Country Link
CN (1) CN109403339B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110318402A (en) * 2019-07-01 2019-10-11 广东建星建造集团有限公司 A kind of deep basal pit back-pressure soil adds diagonal brace form construction method for supporting
CN112921987A (en) * 2021-04-19 2021-06-08 湖南大学 Deep foundation pit supporting structure and deep foundation pit construction method
CN113356230A (en) * 2021-06-24 2021-09-07 中国建筑第二工程局有限公司 Foundation pit support construction method based on combination of back pressure soil and prestressed steel support

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2254417C1 (en) * 2003-12-15 2005-06-20 Басиев Асхар Николаевич Method and anchor system for securing pit bordering
CN103469798A (en) * 2013-08-28 2013-12-25 中国建筑第七工程局有限公司 Pit support structure and construction method thereof
CN103510525A (en) * 2013-10-22 2014-01-15 天津大学 Cascade support method of foundation trench of gravity type cement cob wall combined single-row piles
CN103510526A (en) * 2013-10-22 2014-01-15 天津大学 Foundation pit stepped supporting method with double-row piles combined with single-row piles
CN108643190A (en) * 2018-04-12 2018-10-12 中铁上海工程局集团有限公司 A kind of construction method suitable for the larger deep foundation pit supporting structure of excavation area
CN209227546U (en) * 2018-10-16 2019-08-09 中建一局集团建设发展有限公司 The deep basal pit composite supporting construction of double-row pile combination method of center island

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2254417C1 (en) * 2003-12-15 2005-06-20 Басиев Асхар Николаевич Method and anchor system for securing pit bordering
CN103469798A (en) * 2013-08-28 2013-12-25 中国建筑第七工程局有限公司 Pit support structure and construction method thereof
CN103510525A (en) * 2013-10-22 2014-01-15 天津大学 Cascade support method of foundation trench of gravity type cement cob wall combined single-row piles
CN103510526A (en) * 2013-10-22 2014-01-15 天津大学 Foundation pit stepped supporting method with double-row piles combined with single-row piles
CN108643190A (en) * 2018-04-12 2018-10-12 中铁上海工程局集团有限公司 A kind of construction method suitable for the larger deep foundation pit supporting structure of excavation area
CN209227546U (en) * 2018-10-16 2019-08-09 中建一局集团建设发展有限公司 The deep basal pit composite supporting construction of double-row pile combination method of center island

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110318402A (en) * 2019-07-01 2019-10-11 广东建星建造集团有限公司 A kind of deep basal pit back-pressure soil adds diagonal brace form construction method for supporting
CN112921987A (en) * 2021-04-19 2021-06-08 湖南大学 Deep foundation pit supporting structure and deep foundation pit construction method
CN113356230A (en) * 2021-06-24 2021-09-07 中国建筑第二工程局有限公司 Foundation pit support construction method based on combination of back pressure soil and prestressed steel support

Also Published As

Publication number Publication date
CN109403339B (en) 2024-01-23

Similar Documents

Publication Publication Date Title
CN104264688B (en) Manually digging hole non-uniform pile support construction process
CN106677189B (en) A kind of taper pile wall supporting type foundation pit supporting construction and its construction method
CN105951843B (en) A kind of construction method of deep foundation ditch
CN205134331U (en) Foundation ditch excavation bearing structure
CN103290849B (en) Pit-in-pit supporting structure of half topdown construction method and construction method thereof
CN106013171B (en) A kind of semi-rigid supporting construction semi-flexible and method of deep-foundation side wall
CN104563130B (en) A kind of cross fender post and the double construction method doing agent structure of space enclosing structure
CN203905018U (en) Supporting and protecting system with combined double-row piles in combination with oblique anchors
CN109797755B (en) Steel pipe Larsen steel sheet pile enclosure structure supported by steel mesh frame and construction method thereof
CN210598987U (en) Subway station based on single-layer four-guide-hole and middle-guide-hole inner pile foundation
CN110106919A (en) A kind of lid digs the building enclosure and its construction method at station
CN204590038U (en) A kind of permanent foundation pit supporting construction
CN205013013U (en) Secretly dig station supporting construction suitable for last soft hard formation down
CN109403339A (en) The deep basal pit composite supporting construction and its method for protecting support of double-row pile combination method of center island
CN104947681A (en) Super large super deep basement ground pit construction method
CN104594361A (en) Construction method of H-shaped enclosure pile and enclosure structure as main structure
CN109457709A (en) A kind of supporting construction and construction method of double-row pile combination wide-angle anchor cable
CN105155548A (en) Cable double-row pile (wall) supporting structure
CN209227546U (en) The deep basal pit composite supporting construction of double-row pile combination method of center island
CN106120804B (en) A kind of super-giant foundation pit double-row pile second level support system and its construction method
CN107700519A (en) One kind lifting tower crane installation method
CN101498133B (en) Method and supporting construction for enlarging basement top-down method earth excavation space
CN203213131U (en) Open caisson combining water drainage sinking and water-drainage-free sinking
CN203729309U (en) Support system with combined double-row piles combined with vertical prestressed anchor bolts
CN105040707A (en) Combined densely-arrayed pile deep foundation pit supporting and enclosure structure used as basement external wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant