CN109388902A - A kind of Ground arrangement construction method using BIM technology - Google Patents

A kind of Ground arrangement construction method using BIM technology Download PDF

Info

Publication number
CN109388902A
CN109388902A CN201811258365.9A CN201811258365A CN109388902A CN 109388902 A CN109388902 A CN 109388902A CN 201811258365 A CN201811258365 A CN 201811258365A CN 109388902 A CN109388902 A CN 109388902A
Authority
CN
China
Prior art keywords
construction
bim
arrangement
model
ground arrangement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811258365.9A
Other languages
Chinese (zh)
Inventor
许涛
邓利平
刘凌龙
殷立龙
冉华
张勇
刘小禾
雷杰
贺佳
张金奎
王波
甘鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fourth Engineering Co Ltd of China Railway No 8 Engineering Group Co Ltd
Original Assignee
Fourth Engineering Co Ltd of China Railway No 8 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fourth Engineering Co Ltd of China Railway No 8 Engineering Group Co Ltd filed Critical Fourth Engineering Co Ltd of China Railway No 8 Engineering Group Co Ltd
Priority to CN201811258365.9A priority Critical patent/CN109388902A/en
Publication of CN109388902A publication Critical patent/CN109388902A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads

Abstract

The invention discloses a kind of Ground arrangement construction methods using BIM technology, it is characterised in that: Ground arrangement is divided into 3 stages: design phase;Dummy run phase;Adjusting stage;Design phase: before construction, two-dimentional Ground arrangement is carried out;Arrangement is optimized with the construction site BIM deploying software;Using the construction site BIM deploying software, in conjunction with site contour rendering model;Construction overall process correlated variables is set;Dummy run phase: being simulated in three-dimensional place placement model, and by setting time variable, construction simulation overall process in advance, inspection applies the unreasonable place of group, adjusts construction organization design, formed and finalized a text;Adjusting stage: the critical circuits time limit modification in conjunction with caused by live force majeure factor, according to live actual progress, Optimized model, group is applied in adjustment, then is simulated, then adjust, and model is optimised with PDCA mode operation so that applying group.Horizontal layout is changed into image, intuitive three dimensional arrangement figure by BIM, and space is made to reach reasonable optimization aim.

Description

A kind of Ground arrangement construction method using BIM technology
Technical field
The present invention relates to a kind of Ground arrangement construction methods using BIM technology.
Background technique
BIM full name is " Building Information Model (Building Information Modeling) " concept from 20 generation Record U.S. in the 70's, and U.S. government carried out national level 3D -4D-BIM and plan from 2003;From 2007, it is specified that All big events carry out space planning by BIM;In May, 2011, Britain's Cabinet Office have issued " government building strategy (Government Construction Strategy) " file, wherein have entire chapters and sections about Building Information Model (BIM), It is distinctly claimed in this chapters and sections, is managed by 2016, the 3DBIM of administration request total synergy, and by whole files with informationization Reason.Globally, the application of BIM has become mainstream, many countries and regions the research of BIM is lasted it is longer, from basis Theoretical system has had systematicness to methodology, and being advocated in theory to run is guiding to realize construction project value maximization, people It is recognized more deep, more mature to the understanding of BIM, acceptance is high constantly to propose more perfect frame to realize reason One of important trend has been increasingly becoming by upper innovation, or even interdisciplinary, cross-cutting innovative research.
In China, BIM technology application is still in the budding stage, but BIM development trend is bright and clear.Compared to 2014, in State's BIM popularity rate is more than that 25%, BIM pilot improves nearly 16%.The current main application content of country BIM is (1) collision detection, Reduction is done over again (2) construction simulation, and (3) three-dimensional rendering, promotional display (4) three-dimensional rendering, promotional display are effectively cooperateed with.About BIM Technical application software is various, and each software emphasis is different, but the intelligence for being presented as modeling mostly and the difference on quantities calculation It is different;Integral planar arrangement and the software of site operation progress monitoring can be effectively combined still to lack.
Summary of the invention
It is an object of the invention to overcome the deficiencies of the prior art and provide a kind of BIM Ground arrangements of integral planar arrangement Construction method.
The purpose of the present invention is achieved through the following technical solutions: a kind of Ground arrangement construction using BIM technology Ground arrangement is divided into 3 stages: design phase by method;Dummy run phase;Adjusting stage;
Design phase:
Before construction, two-dimentional Ground arrangement is carried out according to range of relocating residents from locations to be used for construction of new buildings or factories;In conjunction with site contour and on-site actual situations, to synthesis Processing factory, living area and construction road of marching into the arena carry out reasonable Arrangement, and establishment, which is tentatively faced the scheme of setting and faced, sets cost budgeting;With wide Connection optimizes scheme up to the construction site BIM deploying software, by live Ground arrangement image, intuitively shows;
According to planning duration, and construction blueprint, Design of Construction Organization is worked out in conjunction with practical investigation is obtained to field condition, is drawn Gantt chart;According to group is applied, the construction site BIM deploying software is reached using wide connection, in conjunction with site contour rendering model;Setting construction is complete Process correlated variables;
Dummy run phase:
It is simulated in three-dimensional place placement model, group will be applied in the form of visible Virtual Construction by model and shown Come, by setting time variable, construction simulation overall process in advance, the unreasonable place of group is applied in inspection, and adjusts construction organization design, is formed It finalizes a text;
Adjusting stage:
The critical circuits time limit modification in conjunction with caused by live force majeure factor, according to live actual progress, Optimized model, Group is applied in adjustment, then is simulated, then adjust, and model is optimized with PDCA mode operation so that applying group;In the actual construction process Can lead to the adjustment of duration because of various factors such as weather, red-letter days can be applied by model modification correlated variables parameter, Optimized Simulated Work progress intuitively shows vivid progress.
It is preferred that for the design phase: establishing safety construction facility BIM component base, collect security civilization Construction material, models, and carry out the phases such as size, material by safety construction facility of the BIM technology to construction site The mark for closing information forms unified safety construction facility library.
It is preferred that for the design phase: two-dimensional surface layout design is carried out using CAD mapping software, place The classifying rationallies such as living area, Office Area, construction area;The reasonable cloth of carry out such as material area, road, interim water power arrangement in construction area It sets.
It is preferred that for the design phase: planning site machinery construction disengaging field road and sequence of construction, planning are mixed Solidifying navy barrow travelling route.
It is preferred that for the software dummy run phase:
Three-dimensional modeling is carried out up to the construction site BIM deploying software using wide connection, by the living area, Office Area, construction in place The classifying rationallies such as area;Material area, road, interim water power arrangement etc. carry out reasonable Arrangement in construction area.
It is preferred that for the software dummy run phase: department pattern component is excessively complicated, is compiled by Revit software System modeling, then field cloth software mutual conductance is reached with wide connection.
It is preferred that for the software dummy run phase:
The a variety of Ground arrangement schemes of fast construction are established by BIM component base, from economy, tissue, traffic, variant rank The feedback of the multi-party face data such as demand of section finds out more preferable scheme;
Machinery disengaging field is simulated on construction ground based on ready-portioned floor area, to mechanical equipment position It checks again for, guarantees that site location is best, Mechanical Moving route is reasonable.
It is preferred that for the software dummy run phase: utilizing the concrete mixer built in the deploying software of the construction site BIM And tank car, the supply line of status landform, reasonable Arrangement pump truck position and concrete tank is combined in three-dimensional place placement model Road, avoids in casting process pump truck position unreasonable and tank car feed route conflict causes concrete that can not continue supply phenomenon; Construction overall process simulation is carried out to find the deficiency and potential risk factor of Shi Zuzhong by three-dimensional display Virtual Construction, advise in advance Wind sheltering danger.
It is preferred that it further includes effect at this stage:
It is limited due to extensively joining up to BIM Ground arrangement software, model quality, precision and inner space arrangement cannot be in completely It is existing, therefore model quality promotion and inner space refinement will be carried out by SketchUp software and lumion software.
(1) after the final version sizing of place deploying software model, 3DMax format is exported, is imported by SU (SketchUp), Department pattern replacement is carried out, model quality is improved, model internal space layout is refined, so that model total quality is promoted;
(2) it after SU is modified, imported into LU (lumion) and carries out secondary in-depth, replace department pattern, change part Model material improves model quality, according to live actual survey, modifies landform, so that model scene reduction rate is reached 95%, setting Scene roaming animation.
It is preferred that it further includes effect at this stage:
By combining wide connection to reach the scalability of the construction site BIM deploying software, the innovative means such as cooperation VR, can be project Management level and site operation personnel offer are simple, quickly understand channel, and construction site is all at the moment, and stay indoors grasp project The overall situation can also carry out safety education true to nature, improve the awareness of safety of project entirety, reduce between different work posts, different majors Communication disorders.
The beneficial effects of the present invention are: the construction site BIM deploying software can make up the short slab of conventional two-dimensional drawing, will put down Face arrangement is changed into image, intuitive three dimensional arrangement figure, and space is made to reach reasonable optimization aim.By combining BIM construction existing The scalability of deploying software, the innovative means such as cooperation VR can provide simple, fast for project management layer and site operation personnel The understanding channel of speed, construction site are all at the moment, and the grasp project that stays indoors is global, can also carry out safety education true to nature, The awareness of safety of raising project entirety, reduces the communication disorders between different work posts, different majors.
Specific embodiment
Technical solution of the present invention is detailed further below, but protection scope of the present invention is not limited to following institute It states.
Ground arrangement is divided into 3 stages: design phase by a kind of Ground arrangement construction method using BIM technology;Mould The quasi- stage;Adjusting stage;
Design phase:
Before construction, two-dimentional Ground arrangement is carried out according to range of relocating residents from locations to be used for construction of new buildings or factories;In conjunction with site contour and on-site actual situations, to synthesis Processing factory, living area and construction road of marching into the arena carry out reasonable Arrangement, and establishment, which is tentatively faced the scheme of setting and faced, sets cost budgeting;With wide Connection optimizes scheme up to the construction site BIM deploying software, by live Ground arrangement image, intuitively shows;
According to planning duration, and construction blueprint, Design of Construction Organization is worked out in conjunction with practical investigation is obtained to field condition, is drawn Gantt chart;
According to group is applied, the construction site BIM deploying software is reached using wide connection, in conjunction with site contour rendering model;Setting construction Overall process correlated variables;
Dummy run phase:
It is simulated in three-dimensional place placement model, group will be applied in the form of visible Virtual Construction by model and shown Come, by setting time variable, construction simulation overall process in advance, the unreasonable place of group is applied in inspection, and adjusts construction organization design, is formed It finalizes a text;
Adjusting stage:
The critical circuits time limit modification in conjunction with caused by live force majeure factor, according to live actual progress, Optimized model, Group is applied in adjustment, then is simulated, then adjust, and model is optimized with PDCA mode operation so that applying group;In the actual construction process Can lead to the adjustment of duration because of the various non-artificial factors such as weather, red-letter day can be optimized by model modification correlated variables parameter Construction simulation progress intuitively shows vivid progress.
In a preferred embodiment,
Design phase:
(1) it establishes safety construction facility BIM component base, collects safety construction material, by BIM technology to applying The safety construction facility on workshop ground is modeled, and the mark for carrying out the relevant informations such as size, material forms unified peace Bright construction installation library in full;
(2) two-dimensional surface layout design is carried out using CAD mapping software, living area, Office Area, the construction area in place etc. are closed Reason divides;Material area, road, interim water power arrangement etc. carry out reasonable Arrangement in construction area;
(3) planning site machinery construction disengaging field road and sequence of construction, plan concrete placement vehicle travelling route.
In a preferred embodiment,
The software dummy run phase:
(1) three-dimensional modeling is carried out up to the construction site BIM deploying software using wide connection, by the living area in place, Office Area, applied The classifying rationallies such as work area;Material area, road, interim water power arrangement etc. carry out reasonable Arrangement in construction area;
(2) department pattern component is excessively complicated, carries out establishment modeling by Revit software, then mutual up to field cloth software with wide connection It leads;
(3) a variety of Ground arrangement schemes of fast construction are established by BIM component base, from economy, tissue, traffic, respectively not The feedback of the multi-party face data such as demand with the stage finds out more preferable scheme;
(4) machinery disengaging field is simulated on construction ground based on ready-portioned floor area, to mechanical equipment Position checks again for, and guarantees that site location is best, Mechanical Moving route is reasonable;
(5) using the concrete mixer and tank car built in the deploying software of the construction site BIM, in three-dimensional place placement model In conjunction with status landform, the feed route of reasonable Arrangement pump truck position and concrete tank avoids in casting process pump truck position not Rationally and tank car feed route conflict causes concrete that can not continue supply phenomenon;
(6) it carries out construction overall process simulation and the deficiency and potential risk of Shi Zuzhong is found by three-dimensional display Virtual Construction Factor is avoided risk in advance;
(7) three-dimensional display for carrying out corporate image, can more intuitively check Ground arrangement situation, improve communication efficiency;
(8) using the model built up, the project amount of Ground arrangement is accurately counted.
In a preferred embodiment, it further includes
Effect is at this stage:
It is limited due to extensively joining up to BIM Ground arrangement software, model quality, precision and inner space arrangement cannot be in completely It is existing, therefore model quality promotion and inner space refinement will be carried out by SketchUp software and lumion software.
(1) after the final version sizing of place deploying software model, 3DMax format is exported, is imported by SU (SketchUp), Department pattern replacement is carried out, model quality is improved, model internal space layout is refined, so that model total quality is promoted;
(2) it after SU is modified, imported into LU (lumion) and carries out secondary in-depth, replace department pattern, change part Model material improves model quality, according to live actual survey, modifies landform, so that model scene reduction rate is reached 95%, setting Scene roaming animation;
(3) by combining wide connection to reach the scalability of the construction site BIM deploying software, the innovative means such as cooperation VR, Ke Yiwei Project management layer and site operation personnel offer are simple, quickly understand channel, and construction site is all at the moment, grasp of staying indoors Project is global, can also carry out safety education true to nature, improves the awareness of safety of project entirety, reduces different work posts, difference specially Communication disorders between industry.
BIM arrange on construction ground in application be it is of great value, at present everybody also in Ground arrangement BIM application In trying to explore, it is believed that BIM can provide more scientific decision support for project management.Field portion technology can effectively facilitate peace Full civilized construction, is conducive to green construction and national standardization is checked and accepted;The execution that can ensure construction plan is avoided because of material unrest Stacking, mechanical equipment installation position interfere construction etc. to move material, machinery, influence being normally carried out for construction.It is provided for construction It is convenient;Live cost payout is effectively controlled, reduces the reasons rehandlings such as narrow field and the expense that generates.Ground arrangement is to apply Essential step before work, before construction is marched into the arena, good Ground arrangement can save many unnecessary fiber crops for practice of construction It is tired, and efficient BIM software is then the powerful mean for realizing scientific Ground arrangement.
Since the engineering scale of construction is big, the duration is shorter, the human and material resources that disposably put into, mechanical more, each work post need to intert into Row.In order to guarantee that site inside accesses are smooth and engineering safety, civilized construction, reducing live material, equipment rehandling and avoid Environmental pollution, should carry out scientific and rational arrangement to spot plane, carry out place with BIM according to engineering construction horizontal layout Horizontal layout, reasonable Arrangement machining area have planned construction road and place, reduce rehandling in freight and field.Cloth It sets and meets the requirement such as on-site sanitation, fire safety and environmental protection.
Compared to conventional planar picture technology, this project carries out entire projects before being marched into the arena using BIM application technology Three-dimensional simulation arrangement, scene CI standardized management, placing of material plant area, selection of construction machinery are equipped with level-one three-dimensional animation and show Deng, further improve scene in the construction process visualized management work, pass through scheme comparison.
The application of this BIM technology also has accumulated invaluable experience for group, in BIM technology using upper, has landing property, can The reference of duplication.The affirmative of company leader is obtained by BIM Ground arrangement, engineering construction provides from now on for our companies Reference, the company of basing on practicality of BIM technology bring good economic benefit and social benefit.
With BIM technology, reasonably optimizing Design of Construction Organization plans Ground arrangement, on solution working procedure and time Conflict reduces problem in work progress, shortens the construction period, carries out Whole Course Management completion owner and requires;Give full play to concentration The coordinative role of unified command, it is ensured that construction site management harmonious orderly.Duration is rationally reduced to 15 days to 30 days.(1) it can close Optimizing construction organization design is managed, is shortened the construction period.(2) influence factor easily ignored in work progress is calculated in advance.(3) distribution is waved The coordinative role of centralized and unified commander, it is ensured that construction site management harmonious orderly.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, it is noted that all Made any modifications, equivalent replacements, and improvements etc. within the spirit and principles in the present invention should be included in guarantor of the invention Within the scope of shield.

Claims (10)

1. a kind of Ground arrangement construction method using BIM technology, it is characterised in that: Ground arrangement is divided into 3 stages: being set The meter stage;Dummy run phase;Adjusting stage;
Design phase:
Before construction, two-dimentional Ground arrangement is carried out;Reasonable Arrangement is carried out to comprehensive process factory, living area and construction road of marching into the arena;Fortune Arrangement is optimized with the construction site BIM deploying software;
According to group is applied, using the construction site BIM deploying software, in conjunction with site contour rendering model;It is related that construction overall process is set Variable;
Dummy run phase:
It is simulated in three-dimensional place placement model, by setting time variable, construction simulation overall process in advance, inspection is applied The unreasonable place of group, adjusts construction organization design, is formed and is finalized a text;
Adjusting stage:
The critical circuits time limit modification in conjunction with caused by live force majeure factor, according to live actual progress, Optimized model, adjustment Group is applied, then is simulated, then is adjusted, model is optimised with PDCA mode operation so that applying group.
2. a kind of Ground arrangement construction method using BIM technology according to claim 1, it is characterised in that: for setting The meter stage: establishing safety construction facility BIM component base, collects safety construction material, by BIM technology to construction field The safety construction facility on ground is modeled, and the mark for carrying out the relevant informations such as size, material forms unified safety text Bright construction installation library.
3. a kind of Ground arrangement construction method using BIM technology according to claim 1, it is characterised in that: for setting The meter stage: two-dimensional surface layout design is carried out using CAD mapping software, living area, Office Area, the construction area in place etc. are rationally drawn Point;Material area, road, interim water power arrangement etc. carry out reasonable Arrangement in construction area.
4. a kind of Ground arrangement construction method using BIM technology according to claim 1, it is characterised in that: for setting The meter stage: planning site machinery construction disengaging field road and sequence of construction plan concrete placement vehicle travelling route.
5. a kind of Ground arrangement construction method using BIM technology according to claim 1, it is characterised in that: for soft The part dummy run phase:
Three-dimensional modeling is carried out using the construction site BIM deploying software, the living area, Office Area, construction area in place etc. are rationally drawn Point;Material area, road, interim water power arrangement etc. carry out reasonable Arrangement in construction area.
6. a kind of Ground arrangement construction method using BIM technology according to claim 1, it is characterised in that: for soft The part dummy run phase: department pattern component is excessively complicated, carries out establishment modeling by Revit software, then with BIM software mutual conductance.
7. a kind of Ground arrangement construction method using BIM technology according to claim 1, it is characterised in that: for soft The part dummy run phase:
By BIM component base a variety of Ground arrangement schemes of fast construction are established, from economy, tissue, traffic, variant stage The feedback of the multi-party face data such as demand finds out more preferable scheme;
Machinery disengaging field is simulated on construction ground based on ready-portioned floor area, again to mechanical equipment position It checks, guarantees that site location is best, Mechanical Moving route is reasonable.
8. a kind of Ground arrangement construction method using BIM technology according to claim 1, it is characterised in that: for soft The part dummy run phase: using the concrete mixer and tank car built in the deploying software of the construction site BIM, in three-dimensional place placement model In conjunction with status landform, the feed route of reasonable Arrangement pump truck position and concrete tank avoids in casting process pump truck position not Rationally and tank car feed route conflict causes concrete that can not continue supply phenomenon;Construction overall process simulation is carried out, three-dimensional is passed through It shows Virtual Construction, finds the deficiency and potential risk factor of Shi Zuzhong, avoid risk in advance.
9. a kind of Ground arrangement construction method using BIM technology according to claim 1, it is characterised in that: it is also wrapped Effect is included at this stage:
(1) after the final version sizing of place deploying software model, 3DMax format is exported, is imported by SU, department pattern is carried out and replaces It changes, improves model quality, model internal space layout is refined, so that model total quality is promoted;
(2) it after SU is modified, imported into LU and carries out secondary in-depth, replace department pattern, change department pattern material, improve Model quality modifies landform according to live actual survey, and model scene reduction rate is made to reach 95%, and scene roaming animation is arranged.
10. a kind of Ground arrangement construction method using BIM technology according to claim 1, it is characterised in that: it is also wrapped Effect is included at this stage:
By combining the scalability of the construction site BIM deploying software, the equipment such as cooperation VR can be applied for project management layer and scene Worker person provide it is simple, quickly understand channel, construction site is all at the moment, and the grasp project that stays indoors is global, can also be into Row safety education true to nature, improves the awareness of safety of project entirety, reduces the communication disorders between different work posts, different majors.
CN201811258365.9A 2018-10-26 2018-10-26 A kind of Ground arrangement construction method using BIM technology Pending CN109388902A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811258365.9A CN109388902A (en) 2018-10-26 2018-10-26 A kind of Ground arrangement construction method using BIM technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811258365.9A CN109388902A (en) 2018-10-26 2018-10-26 A kind of Ground arrangement construction method using BIM technology

Publications (1)

Publication Number Publication Date
CN109388902A true CN109388902A (en) 2019-02-26

Family

ID=65428157

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811258365.9A Pending CN109388902A (en) 2018-10-26 2018-10-26 A kind of Ground arrangement construction method using BIM technology

Country Status (1)

Country Link
CN (1) CN109388902A (en)

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109933900A (en) * 2019-03-13 2019-06-25 上海理工大学 A kind of construction three dimensional field cloth modeling method based on BIM technology
CN110414128A (en) * 2019-07-26 2019-11-05 上海宝冶集团有限公司 Method, apparatus, electronic equipment and the storage medium of transport simulation are carried out based on BIM
CN110489897A (en) * 2019-08-25 2019-11-22 中铁二局第一工程有限公司 A kind of three-dimensional construction field cloth VR panoramic sand table production method based on BIM and GIS
CN110750823A (en) * 2019-09-27 2020-02-04 贵州百胜工程建设咨询有限公司 BIM visual display method
CN110941867A (en) * 2019-11-07 2020-03-31 广东龙越建筑工程有限公司 Construction method of standardized site layout based on BIM
CN111079339A (en) * 2019-12-25 2020-04-28 三峡大学 Time-product element-based warehouse construction space-time conflict quantitative calculation method
CN111125820A (en) * 2019-12-16 2020-05-08 福建建工集团有限责任公司 BIM + GIS-based construction site space virtual construction method
CN111339601A (en) * 2020-03-25 2020-06-26 中国十七冶集团有限公司 BIM + VR construction site arrangement method
CN111443885A (en) * 2020-05-14 2020-07-24 河北建设集团股份有限公司 Interactive construction site plane arrangement system and arrangement method
CN111581818A (en) * 2020-05-06 2020-08-25 北方工业大学 BIM technology-based construction site layout optimization method
CN111898179A (en) * 2020-05-22 2020-11-06 甘肃久智建筑科技有限公司 Method for applying field cloth applied to underground stereo garage
CN112182710A (en) * 2020-09-28 2021-01-05 杭州品茗安控信息技术股份有限公司 Construction road arrangement method, device and equipment and readable storage medium
CN113343342A (en) * 2021-07-07 2021-09-03 贵州百胜工程建设咨询有限公司 BIM technology-based construction engineering quantity analysis management method and system and computer storage medium
CN113739071A (en) * 2021-09-06 2021-12-03 中国电建集团重庆工程有限公司 Instrument pipeline arrangement sample method and thermal control instrument pipeline
CN114595903A (en) * 2022-05-10 2022-06-07 安徽智享云科技有限公司 BIM-based construction site layout optimization system and method
CN114934504A (en) * 2022-04-24 2022-08-23 珠海华发人居生活研究院有限公司 One-column one-pile construction method for super-large cross section
CN115048688A (en) * 2022-04-01 2022-09-13 湖州电力设计院有限公司 GIS room plane optimization method based on movable roof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104808610A (en) * 2015-02-13 2015-07-29 上海同筑信息科技有限公司 Machinery control system and machinery control method based on a BIM (building information model)
CN106202723A (en) * 2016-07-10 2016-12-07 北京工业大学 A kind of BIM subway work method
CN108256213A (en) * 2018-01-16 2018-07-06 中铁局集团有限公司 Depot of urban railway transit vehicles modular construction analogy method based on VR and BIM
CN108268715A (en) * 2018-01-18 2018-07-10 东南大学 A kind of paving steel bridge deck Construction simulation analogy method based on BIM technology
CN108509653A (en) * 2018-04-18 2018-09-07 苏州智在云数据科技有限公司 A kind of BIM building WEB terminal visualization engine and its application method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104808610A (en) * 2015-02-13 2015-07-29 上海同筑信息科技有限公司 Machinery control system and machinery control method based on a BIM (building information model)
CN106202723A (en) * 2016-07-10 2016-12-07 北京工业大学 A kind of BIM subway work method
CN108256213A (en) * 2018-01-16 2018-07-06 中铁局集团有限公司 Depot of urban railway transit vehicles modular construction analogy method based on VR and BIM
CN108268715A (en) * 2018-01-18 2018-07-10 东南大学 A kind of paving steel bridge deck Construction simulation analogy method based on BIM technology
CN108509653A (en) * 2018-04-18 2018-09-07 苏州智在云数据科技有限公司 A kind of BIM building WEB terminal visualization engine and its application method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
李飞等: ""基于BIM技术的施工场地布置研究与应用"", 《土木建筑工程信息技术》 *
黄兰等: ""BIM应用"", 《BIM应用》 *

Cited By (23)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109933900A (en) * 2019-03-13 2019-06-25 上海理工大学 A kind of construction three dimensional field cloth modeling method based on BIM technology
CN110414128A (en) * 2019-07-26 2019-11-05 上海宝冶集团有限公司 Method, apparatus, electronic equipment and the storage medium of transport simulation are carried out based on BIM
CN110414128B (en) * 2019-07-26 2023-08-29 上海宝冶集团有限公司 BIM-based transportation simulation method and device, electronic equipment and storage medium
CN110489897A (en) * 2019-08-25 2019-11-22 中铁二局第一工程有限公司 A kind of three-dimensional construction field cloth VR panoramic sand table production method based on BIM and GIS
CN110489897B (en) * 2019-08-25 2022-09-23 中铁二局第一工程有限公司 BIM and GIS-based three-dimensional construction site cloth VR panoramic sand table manufacturing method
CN110750823A (en) * 2019-09-27 2020-02-04 贵州百胜工程建设咨询有限公司 BIM visual display method
CN110941867A (en) * 2019-11-07 2020-03-31 广东龙越建筑工程有限公司 Construction method of standardized site layout based on BIM
CN111125820A (en) * 2019-12-16 2020-05-08 福建建工集团有限责任公司 BIM + GIS-based construction site space virtual construction method
CN111125820B (en) * 2019-12-16 2023-06-02 福建建工集团有限责任公司 BIM+GIS-based construction site space virtual construction method
CN111079339B (en) * 2019-12-25 2023-10-27 三峡大学 Bin face construction space-time conflict quantitative calculation method based on time integral
CN111079339A (en) * 2019-12-25 2020-04-28 三峡大学 Time-product element-based warehouse construction space-time conflict quantitative calculation method
CN111339601A (en) * 2020-03-25 2020-06-26 中国十七冶集团有限公司 BIM + VR construction site arrangement method
CN111581818A (en) * 2020-05-06 2020-08-25 北方工业大学 BIM technology-based construction site layout optimization method
CN111443885A (en) * 2020-05-14 2020-07-24 河北建设集团股份有限公司 Interactive construction site plane arrangement system and arrangement method
CN111898179A (en) * 2020-05-22 2020-11-06 甘肃久智建筑科技有限公司 Method for applying field cloth applied to underground stereo garage
CN112182710A (en) * 2020-09-28 2021-01-05 杭州品茗安控信息技术股份有限公司 Construction road arrangement method, device and equipment and readable storage medium
CN113343342B (en) * 2021-07-07 2022-02-15 贵州百胜数源工程技术管理有限公司 BIM technology-based construction engineering quantity analysis management method and system and computer storage medium
CN113343342A (en) * 2021-07-07 2021-09-03 贵州百胜工程建设咨询有限公司 BIM technology-based construction engineering quantity analysis management method and system and computer storage medium
CN113739071A (en) * 2021-09-06 2021-12-03 中国电建集团重庆工程有限公司 Instrument pipeline arrangement sample method and thermal control instrument pipeline
CN113739071B (en) * 2021-09-06 2023-08-01 中国电建集团重庆工程有限公司 Instrument pipeline sample arranging method and thermal control instrument pipeline
CN115048688A (en) * 2022-04-01 2022-09-13 湖州电力设计院有限公司 GIS room plane optimization method based on movable roof
CN114934504A (en) * 2022-04-24 2022-08-23 珠海华发人居生活研究院有限公司 One-column one-pile construction method for super-large cross section
CN114595903A (en) * 2022-05-10 2022-06-07 安徽智享云科技有限公司 BIM-based construction site layout optimization system and method

Similar Documents

Publication Publication Date Title
CN109388902A (en) A kind of Ground arrangement construction method using BIM technology
US20220309202A1 (en) Artificial intelligence-based urban design multi-plan generation method for regulatory plot
CN111199066B (en) Construction site virtual construction restoration method based on BIM+GIS
CN106599332A (en) Three-dimensional digital scheme aided design and display method
CN115292789B (en) Building body quantity digital generation method based on morphological type in city design
CN109933900A (en) A kind of construction three dimensional field cloth modeling method based on BIM technology
Liu et al. Application analysis of BIM technology in metro rail transit
CN110046405A (en) A kind of electric power line pole tower three-dimensional collaborative planning design method and system
Wei et al. The case study of BIM in urban planning and design
Bi et al. Research on the construction of City information modelling basic platform based on multi-source data
Stanilov Bridging the gap between urban morphology and urban modelling K. Stanilov
CN113409462A (en) Municipal engineering construction safety control method and system based on 3DGIS and BIM technology
CN111125820A (en) BIM + GIS-based construction site space virtual construction method
Wei et al. The Application of BIM in the “China Beautiful Rural” Design Project–Yangyou Village River Ecological Landscape Reconstruction Design Project
Wang et al. Integration of GIS and BIM in Metro Construction
Lyu et al. Research on railway cooperative test platform and key technologies based on digital twin
Wang Integrated Urban Design Methodology of “Planning-Construction-Management” and Intelligent Management and Control Based on Teaching Reproduction Robot
Khalil et al. Advances in Urban Engineering and Management Science Volume 2: Proceedings of the 3rd International Conference on Urban Engineering and Management Science (ICUEMS 2022), Wuhan, China, 21-23 January 2022
Zhao et al. Research on the feasibility of solving problems in construction of sponge city based on gis, vr and bim combined technology
Zhao Application of BIM Technology in Data Collection of Large-Scale Engineering Intelligent Construction
Li et al. Research on BIM technology application in the construction of a subway station
Peng et al. Application of Building Information Modeling (BIM) technology in the quality management of prefabricated buildings
Su Digitalization and application research of BIM-based power plants lifecycle information
Bi Application Research of Building Information Model in the Construction Project Life Cycle
CHENG et al. Application Research of BIM in the Whole Life Cycle of Metro Station

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20190226