CN109386133A - PC component matches mould construction method with cast-in-place wall column aluminum alloy mould plate - Google Patents
PC component matches mould construction method with cast-in-place wall column aluminum alloy mould plate Download PDFInfo
- Publication number
- CN109386133A CN109386133A CN201710662337.2A CN201710662337A CN109386133A CN 109386133 A CN109386133 A CN 109386133A CN 201710662337 A CN201710662337 A CN 201710662337A CN 109386133 A CN109386133 A CN 109386133A
- Authority
- CN
- China
- Prior art keywords
- aluminum alloy
- component
- cast
- alloy mould
- mould plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G17/00—Connecting or other auxiliary members for forms, falsework structures, or shutterings
- E04G17/04—Connecting or fastening means for metallic forming or stiffening elements, e.g. for connecting metallic elements to non-metallic elements
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Retaining Walls (AREA)
Abstract
The invention discloses a kind of PC component with cast-in-place wall column aluminum alloy mould plate with mould construction method, this method is first depending on design detail, reserves indent in PC component setting aluminum alloy mould plate position;Apertured hole, pre-buried screw thread borehole jack in hole are in a row spaced apart along indent;Pressing plate is fixed by bolts in screw thread borehole jack, and angle steel passes through that pressing plate is fixed on PC component indent, aluminum alloy mould plate is bolted in another side on one side.The defect that this method effectively avoids PC component from constructing in conjunction with plank sheathing saves the duration, effectively improves construction efficiency and quality by considering PC component pre-processing the matching with aluminum alloy mould plate simultaneously.
Description
Technical field
The present invention relates to a kind of PC component with cast-in-place wall column aluminum alloy mould plate with mould construction method.
Background technique
PC(precast concrete) component be precast concrete, with the fast development of building trade, aluminium alloy
Template and PC component are widely promoted and applied.Wherein aluminum alloy mould plate has intensity height, the concrete perception matter poured out
The advantages that having measured, but aluminum alloy mould plate needs scene to carry out the operations such as template assembly, reinforcing bar binding, therefore speed of application is slower.PC
Component is concentrated to the prefabricated processing of building structural element, and scene is mounted directly construction, and construction efficiency is high.In construction operation
When, PC component is often combined with plank sheathing, and use process is easy to produce many mass defects, as plank sheathing deformation causes to leak
Slurry, faulting of slab ends, crackle, apparent size error, the problems such as plastering again;Meanwhile when site operation, the reduction amount of plank sheathing is larger,
Workload is significantly increased, the integrated engineering progress delayed to a certain extent reduces construction efficiency.
Summary of the invention
Technical problem to be solved by the invention is to provide applying with mould for a kind of PC component and cast-in-place wall column aluminum alloy mould plate
Work method, the defect that this method effectively avoids PC component from constructing in conjunction with plank sheathing, by being examined simultaneously PC component pre-processing
Consider the matching with aluminum alloy mould plate, saves the duration, effectively improve construction efficiency and quality.
In order to solve the above technical problems, the mould construction method of matching of PC component of the present invention and cast-in-place wall column aluminum alloy mould plate includes
Following steps:
Step 1: the aluminum alloy mould plate position of cast-in-place wall column is arranged in PC component according to PC component and cast-in-place wall post design detail drawing
Reserved indent;
Step 2: being in a row spaced apart apertured hole, pre-buried screw thread borehole jack in hole along indent;
Step 3: pressing plate is fixed by bolts in screw thread borehole jack, angle steel passes through pressing plate on one side and is fixed on PC component indent, another side
Aluminum alloy mould plate is bolted.
Further, the width of the indent is 80~100mm.
Further, there are enough safe distances away from PC Member Lip for described hole.
Since the mould construction method of matching of PC component of the present invention and cast-in-place wall column aluminum alloy mould plate uses above-mentioned technical proposal, i.e., originally
Method is first depending on design detail, reserves indent in the aluminum alloy mould plate position that cast-in-place wall column is arranged in PC component;It is in a row along indent
It is spaced apart apertured hole, pre-buried screw thread borehole jack in hole;Pressing plate is fixed by bolts in screw thread borehole jack, and angle steel is solid by pressing plate on one side
Aluminum alloy mould plate is bolted due to PC component indent, another side.This method effectively avoids PC component in conjunction with plank sheathing
The defect of construction saves the duration, effectively improves and apply by considering PC component pre-processing the matching with aluminum alloy mould plate simultaneously
Work efficiency rate and quality.
Detailed description of the invention
The present invention will be further described in detail below with reference to the accompanying drawings and embodiments:
Fig. 1 is for PC component of the present invention with cast-in-place wall column aluminum alloy mould plate with mould construction method schematic diagram;
Fig. 2 is the schematic diagram that PC component is connect with aluminum alloy mould plate vertical direction.
Specific embodiment
Embodiment is as shown in Figure 1, the mould construction method of matching of PC component of the present invention and cast-in-place wall column aluminum alloy mould plate includes such as
Lower step:
Step 1: the aluminum alloy mould plate 3 of cast-in-place wall column is arranged in PC component 1 according to 2 design detail of PC component 1 and cast-in-place wall column
Reserve indent 11 in position;
Step 2: being in a row spaced apart apertured hole, pre-buried screw thread borehole jack 4 in hole along indent 11;
Step 3: pressing plate 5 is fixed on screw thread borehole jack 4 by bolt 6, angle steel 7 is fixed on 1 indent of PC component by pressing plate 5 on one side
11, another side connects aluminum alloy mould plate 3 by bolt 8.
Preferably, the width of the indent 11 is 80~100mm, and 11 width of indent is for accommodating pressing plate 5 and angle steel 7.
Preferably, there are enough safe distances away from 1 edge of PC component for described hole, it is ensured that aluminum alloy mould plate 3 was arranged
Reliability.
Fig. 1 show the aluminum alloy mould plate 3 that PC component 1 is located at same facade with cast-in-place wall column 2 and matches modular form, such as Fig. 2 institute
Show, when PC component 1 is vertical with cast-in-place wall column 2, can be connected using transition angle steel 9 between pressing plate 5 and angle steel 7, transition angle steel 9
On one side use pressing plate to fix, another side compress angle steel 7 on one side, 7 another side of angle steel by bolt 8 connect aluminum alloy mould plate 3, realization
PC component 1 matches mould with aluminum alloy mould plate 3.
Since there are swellings for cast-in-place concrete to final set, in view of the factor of expansion, this method is in PC component
Aluminum alloy mould plate position is set and reserves indent, for adjusting, the later period can carry out plastering processing, guarantee PC component and cast-in-place wall column
It is generally aligned in the same plane, while securely connecting between aluminum alloy mould plate and PC component is effectively increased by angle steel and pressure plate structure
It connects.PC component and aluminum alloy mould plate reliable connection are effectively improved construction efficiency, save the duration, can solve simultaneously by this method
The mass defect problem of the cast-in-place concretes such as common spillage, crackle, faulting of slab ends.
Claims (3)
1. a kind of PC component matches mould construction method with cast-in-place wall column aluminum alloy mould plate, it is characterised in that this method includes following step
It is rapid:
Step 1: the aluminum alloy mould plate position of cast-in-place wall column is arranged in PC component according to PC component and cast-in-place wall post design detail drawing
Reserved indent;
Step 2: being in a row spaced apart apertured hole, pre-buried screw thread borehole jack in hole along indent;
Step 3: pressing plate is fixed by bolts in screw thread borehole jack, angle steel passes through pressing plate on one side and is fixed on PC component indent, another side
Aluminum alloy mould plate is bolted.
2. PC component according to claim 1 matches mould construction method with cast-in-place wall column aluminum alloy mould plate, it is characterised in that:
The width of the indent is 80~100mm, with a thickness of 2mm.
3. PC component according to claim 1 or 2 matches mould construction method with cast-in-place wall column aluminum alloy mould plate, feature exists
In: there are enough safe distances away from PC Member Lip for described hole.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710662337.2A CN109386133A (en) | 2017-08-04 | 2017-08-04 | PC component matches mould construction method with cast-in-place wall column aluminum alloy mould plate |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710662337.2A CN109386133A (en) | 2017-08-04 | 2017-08-04 | PC component matches mould construction method with cast-in-place wall column aluminum alloy mould plate |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109386133A true CN109386133A (en) | 2019-02-26 |
Family
ID=65412427
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710662337.2A Pending CN109386133A (en) | 2017-08-04 | 2017-08-04 | PC component matches mould construction method with cast-in-place wall column aluminum alloy mould plate |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109386133A (en) |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN205206324U (en) * | 2015-11-26 | 2016-05-04 | 广东合迪科技股份有限公司 | Precast concrete wallboard and wall form setting node |
CN205206308U (en) * | 2015-11-26 | 2016-05-04 | 广东合迪科技股份有限公司 | Stencil assembly and cast member installation node |
CN106088595A (en) * | 2016-08-10 | 2016-11-09 | 中民筑友科技投资有限公司 | Erecting device and mold method |
CN206267521U (en) * | 2016-10-27 | 2017-06-20 | 合迪科技江苏有限公司 | Precast concrete installs node with cast-in-place structural mortar leakage prevention |
-
2017
- 2017-08-04 CN CN201710662337.2A patent/CN109386133A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN205206324U (en) * | 2015-11-26 | 2016-05-04 | 广东合迪科技股份有限公司 | Precast concrete wallboard and wall form setting node |
CN205206308U (en) * | 2015-11-26 | 2016-05-04 | 广东合迪科技股份有限公司 | Stencil assembly and cast member installation node |
CN106088595A (en) * | 2016-08-10 | 2016-11-09 | 中民筑友科技投资有限公司 | Erecting device and mold method |
CN206267521U (en) * | 2016-10-27 | 2017-06-20 | 合迪科技江苏有限公司 | Precast concrete installs node with cast-in-place structural mortar leakage prevention |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107299699B (en) | Assembled cavity shear wall horizontal joint Alveolus type dry type connection structure | |
CN108797847B (en) | Assembled steel frame infilled wall structure system and construction method thereof | |
CN106638981A (en) | Steel bar connection structure of prefabricated parts | |
CN106013787A (en) | Cast-in-place concrete beam formwork tool type reinforcing system and construction technology thereof | |
CN106337561A (en) | Shear wall template reinforcing structure and reinforcing construction method thereof | |
CN112761307A (en) | Prefabricated reinforced concrete column node connecting device | |
CN206233579U (en) | Shear wall template is to drawing connecting piece and template reinforced structure thereof | |
CN204059661U (en) | A kind of ALC body of wall assembly | |
CN109386133A (en) | PC component matches mould construction method with cast-in-place wall column aluminum alloy mould plate | |
CN206091355U (en) | Post structure is taken out to concrete plant's pillars of a house | |
CN210013473U (en) | Inverted L-shaped side form reinforcing structure | |
CN218375201U (en) | Frame post and wall body crossing department constructional column unilateral template reinforcing apparatus | |
CN202990111U (en) | Embedded sleeve component | |
CN212224611U (en) | Shear force wall pouring template reinforcing apparatus | |
CN206667492U (en) | A kind of prefabricated composite wallboard and the laterally attached structure of precast stair | |
CN109403489A (en) | A kind of fabricated shear wall vertical abutment joint friction energy-dissipating attachment device | |
CN206503365U (en) | A kind of shear wall and filling wall junction aluminum alloy pattern plate erecting device | |
CN212641764U (en) | Curtain wall embedded part placed after beam side mold is closed | |
CN212957325U (en) | Device for improving installation precision of anchoring ribs at fixed end of prefabricated staircase | |
CN217204665U (en) | Upper and lower double-groove embedded part for curtain wall | |
CN218292276U (en) | Precast beam and floor connection structure | |
CN111305556A (en) | Embedded column formwork assembly of prefabricated building and construction method thereof | |
CN215484653U (en) | Building construction lintel shaping fixture | |
CN219568963U (en) | Auxiliary fixing structure and tool for embedded bolts in pouring process of comprehensive pipe rack | |
CN211691546U (en) | Mounting device of pre-buried spout |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190226 |