CN109372003B - Deep cup rim template of bearing platform foundation and construction method for removing cup rim template - Google Patents

Deep cup rim template of bearing platform foundation and construction method for removing cup rim template Download PDF

Info

Publication number
CN109372003B
CN109372003B CN201811496575.1A CN201811496575A CN109372003B CN 109372003 B CN109372003 B CN 109372003B CN 201811496575 A CN201811496575 A CN 201811496575A CN 109372003 B CN109372003 B CN 109372003B
Authority
CN
China
Prior art keywords
cup
bearing platform
wood box
template
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201811496575.1A
Other languages
Chinese (zh)
Other versions
CN109372003A (en
Inventor
王凤杰
焦更晓
蒋小强
布图格其
王雪韬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 22MCC Group Corp Ltd
Original Assignee
China 22MCC Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 22MCC Group Corp Ltd filed Critical China 22MCC Group Corp Ltd
Priority to CN201811496575.1A priority Critical patent/CN109372003B/en
Publication of CN109372003A publication Critical patent/CN109372003A/en
Application granted granted Critical
Publication of CN109372003B publication Critical patent/CN109372003B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • E02D27/14Pile framings, i.e. piles assembled to form the substructure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Manufacturing Of Tubular Articles Or Embedded Moulded Articles (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The invention relates to a building construction template, in particular to a deep cup mouth template of a bearing platform foundation and a construction method for dismantling the cup mouth template. The cup mouth wood box comprises a cup mouth wood box body, wherein the outer contour surface of the cup mouth wood box body is coated with a polyphenyl board, and the outer surface of the polyphenyl board is provided with a plurality of blind holes. The construction is simple, the degree of accuracy is high, convenient operation, and the rim of a cup template that takes out that can be quick for rim of a cup template turnover speed need not to chisel the rim of a cup before the secondary grout of rim of a cup, improves labor efficiency and reduces the cost of labor.

Description

Deep cup rim template of bearing platform foundation and construction method for removing cup rim template
Technical Field
The invention relates to a building construction template, in particular to a deep cup mouth template of a bearing platform foundation and a construction method for removing the cup mouth template, which are used for quickly removing the cup mouth without secondary roughening.
Background
The prefabricated reinforced concrete column and the steel column are installed in the rim of a cup basis and are more common factory building structural forms, the cross section size of the rim of a cup is smaller, and the problem that the formwork is difficult to dismantle due to the fact that the depth is large is frequently encountered in building construction. And after the steel column is installed, performing fine stone concrete grouting fixation on the cup opening. Before grouting, the wall of the cup mouth needs to be subjected to roughening treatment, the cup mouth is deep and small, and manual roughening is difficult.
The cup mouth template of the current bearing platform foundation comprises a steel mould and a wood mould, and the construction quality of the steel mould is poor and the mould is not easy to disassemble; and the universal wood pattern is adopted for construction, and the construction quality is better than that of a steel mould but is not easy to dismantle. A layer of polyphenyl board is stuck on the surface of the wood die, the polyphenyl board is directly destroyed when the die is disassembled, and polyphenyl board particles can fall in the cup opening and are difficult to clean.
Disclosure of Invention
The invention aims to solve the technical problem of providing a deep cup mouth template for a bearing platform foundation, which is capable of rapidly removing a die without secondary roughening.
The technical scheme adopted for solving the technical problems is as follows:
the utility model provides a deep rim of a cup template of cushion cap basis, includes rim of a cup wooden box, and the outside profile face cladding polyphenyl board of rim of a cup wooden box, the surface of polyphenyl board is equipped with a plurality of blind holes, waters alkyd diluent on polyphenyl board upper portion when the demolding, and polyphenyl board can melt completely, causes wooden box and concrete surface separation.
Compared with the prior art, the invention adopting the technology has the beneficial effects that:
The construction is simple, the degree of accuracy is high, convenient operation, and the rim of a cup template that takes out that can be quick for rim of a cup template turnover speed need not to chisel the rim of a cup before the secondary grout of rim of a cup, improves labor efficiency and reduces the cost of labor.
Further, the optimization scheme of the invention is as follows:
the cross section of the blind hole is irregularly shaped.
The blind holes are irregularly arranged.
Binding pieces are arranged around the polyphenyl board.
The ligature is an adhesive tape.
The section of the cup opening wood box is consistent with the section of the bearing platform foundation, the cup opening wood box comprises a bottom plate and a vertical plate, and the wood supporting piece is arranged around the inside of the cup opening wood box.
The batten support comprises a transverse support batten and a vertical support batten.
A construction method of a deep cup mouth template of a bearing platform foundation comprises the following steps:
A. Manufacturing a cup opening wood box according to the size of a cup opening of a bearing platform foundation, and installing a square support piece in the cup opening wood box;
B. wrapping the polystyrene board around the outside of the cup opening wood box, and firmly adhering the polystyrene board by using an adhesive tape;
C. Processing blind holes with irregular sections on the outer surface of the polystyrene board;
D. placing a cup opening wood box with a polyphenyl plate at the cup opening of the bearing platform, and fixing firmly;
E. Pouring foundation concrete;
F. after the concrete reaches the form removal strength, the alkyd diluent is dripped on the polyphenyl board, and the polyphenyl board is immediately melted when meeting the alkyd diluent, so that the template is quickly separated from the concrete surface, and the cup opening wood box is easily moved out of the cup opening of the bearing platform foundation;
G. The blind holes of the polyphenyl board can be filled during concrete pouring, and protruding concrete small pits can appear on the inner concrete surface of the cup rim of the bearing platform after the polyphenyl board is melted.
Drawings
FIG. 1 is a schematic diagram of the overall structure of a cup rim wooden box according to an embodiment of the invention
FIG. 2 is a schematic plan view of a casting structure according to an embodiment of the present invention;
FIG. 3 is a cross-sectional view A-A of FIG. 2;
FIG. 4 is a cross-sectional view of a concrete cup opening of an embodiment of the invention;
in the figure: a cup opening wood box 1; a timber support 2; 2-1 parts of vertical battens; 2-2 parts of transverse battens; polyphenyl board 3; a blind hole 3-1; an adhesive tape 4; concrete 5; protruding pits 5-1; and a split heads 6.
Detailed Description
The invention is described in detail below with reference to the drawings and examples.
Referring to fig. 1 and 2, a deep cup mouth template of a bearing platform foundation is composed of a cup mouth wood box 1, a wood square support piece 2, a polystyrene board 3 and an adhesive tape 4. The cross section of the cup opening wooden box 1 is the size of a concrete cup opening to be poured minus the thickness of the two polyphenyl plates 3, in the embodiment, the cup opening wooden box 1 is a box body with a square cross section, the upper end of the cup opening wooden box 1 is open, the cup opening wooden box 1 is composed of four vertical plates and a bottom plate, and the vertical plates and the bottom plate are made of multilayer plates.
The inside of rim of a cup wooden box 1 installs timber side support piece 2 all around, and timber side support piece 2 comprises four vertical timber sides 2-1 and a plurality of horizontal timber sides 2-2, and horizontal timber sides 2-2 layer number is confirmed according to rim of a cup degree of depth, installs horizontal timber side 2-2 between the adjacent vertical timber sides 2-1, and the up end of four vertical timber sides 2-1 is higher than the up end of rim of a cup wooden box 1.
The outer contour surface of the cup opening wood box 1 is coated with the polyphenyl board 3, the polyphenyl board 3 is coated on the outer surfaces of the bottom board of the cup opening wood box 1 and the four vertical boards, the upper end surface of the polyphenyl board 3 is guaranteed to be consistent with the surface of a concrete cup opening, the thickness of the polyphenyl board 3 is 50 mm, the periphery of the polyphenyl board 3 is fixed through transparent adhesive tapes 4 (shown in fig. 1), and the distance between two adjacent adhesive tapes 4 is 300-500 mm. The outer surface of the polystyrene board 3 is provided with a plurality of blind holes 3-1, the cross section of the blind holes 3-1 is in an irregular shape, the blind holes 3-1 are irregularly arranged, the depth of the blind holes 3-1 is 5-10 mm, and the diameter is about 15-20 mm.
A construction method of a deep cup mouth template of a bearing platform foundation comprises the following steps:
A. Manufacturing a cup opening wooden box 1 by using a multilayer board according to the size of a cup opening of a bearing platform foundation, installing a square support piece 2 in the cup opening wooden box 1, fixing the square support piece 2 and the cup opening wooden box 1 firmly, and erecting the cup opening wooden box 1 on two split heads 6;
B. the polystyrene board 3 is coated on the periphery of the cup opening wood box 1 and the lower surface of the bottom plate, the polystyrene board 3 is firmly adhered by the transparent adhesive tape 4, and the interval between the transparent adhesive tape 4 is controlled within 300 to 500 millimeters;
C. a plurality of blind holes 3-1 with irregular cross sections are processed on the outer surface of the polystyrene board 3 by using a small spoon or other tools, and the blind holes 3-1 are irregularly arranged;
D. The cup opening wood box 1 with the polyphenyl plate 3 is placed at the cup opening of the bearing platform and is fixed firmly;
E. Pouring foundation concrete 5;
F. after the concrete 5 reaches the form removal strength, the bottled alkyd diluent is dripped on the polyphenyl board 3, the polyphenyl board 3 is immediately melted when meeting the alkyd diluent, so that the polyphenyl board 3 is quickly separated from the concrete surface, and the cup opening wood box 1 is easily moved out of the cup opening of the bearing platform foundation;
G. because the blind holes 3-1 are arranged on the outer side of the polystyrene board 3, the blind holes 3-1 are filled up when concrete is poured, the raised pits 3-1 appear on the inner surface of the concrete at the cup opening of the bearing platform after the polystyrene board 3 is melted, and roughening is not needed when the steel column is installed for secondary grouting, so that the secondary roughening cost is saved, and the purpose of rapidly removing the mould is achieved.
The foregoing description is only of the preferred embodiments of the invention and is not intended to limit the scope of the claims, but rather the equivalent structural changes made by the application of the present description and drawings are intended to be included within the scope of the claims.

Claims (2)

1. A deep cup mouth template of a bearing platform foundation comprises a cup mouth wood box and is characterized in that an outer contour surface of the cup mouth wood box is coated with a polyphenyl board, the outer surface of the polyphenyl board is provided with a plurality of blind holes, the cross sections of the blind holes are in irregular shapes, the blind holes are irregularly arranged, the blind holes are filled with the polyphenyl board when concrete is poured, protruding concrete small pits can appear on the inner concrete surface of the cup mouth of the bearing platform after the polyphenyl board is melted, binding pieces are arranged on the periphery of the polyphenyl board, the cross sections of the cup mouth wood box are consistent with the cross sections of the cup mouth of the bearing platform foundation, the cup mouth wood box comprises a bottom plate and vertical plates, timber supports are arranged on the periphery of the inner side of the cup mouth wood box, and each timber support comprises a transverse supporting timber and a vertical supporting timber.
2. The construction method of the deep cup mouth template of the bearing platform foundation, which is characterized by comprising the following steps:
A. Manufacturing a cup opening wood box according to the size of a cup opening of a bearing platform foundation, and installing a square support piece in the cup opening wood box;
B. wrapping the polystyrene board around the cup opening wood box, and fixing the polystyrene board firmly by using a binding piece;
C. Processing blind holes with irregular sections on the outer surface of the polystyrene board;
D. placing a cup opening wood box with a polyphenyl plate at the cup opening of the bearing platform, and fixing firmly;
E. Pouring foundation concrete;
F. After the concrete reaches the form removal strength, the alkyd diluent is dripped on the polyphenyl board, and the polyphenyl board is immediately melted when meeting the alkyd diluent, so that the template is quickly separated from the concrete surface, and the cup opening wood box is easy to move out of the cup opening;
G. The blind holes of the polyphenyl board can be filled during concrete pouring, and protruding concrete small pits can appear on the inner concrete surface of the cup rim of the bearing platform after the polyphenyl board is melted.
CN201811496575.1A 2018-12-07 2018-12-07 Deep cup rim template of bearing platform foundation and construction method for removing cup rim template Active CN109372003B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811496575.1A CN109372003B (en) 2018-12-07 2018-12-07 Deep cup rim template of bearing platform foundation and construction method for removing cup rim template

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811496575.1A CN109372003B (en) 2018-12-07 2018-12-07 Deep cup rim template of bearing platform foundation and construction method for removing cup rim template

Publications (2)

Publication Number Publication Date
CN109372003A CN109372003A (en) 2019-02-22
CN109372003B true CN109372003B (en) 2024-04-26

Family

ID=65373847

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811496575.1A Active CN109372003B (en) 2018-12-07 2018-12-07 Deep cup rim template of bearing platform foundation and construction method for removing cup rim template

Country Status (1)

Country Link
CN (1) CN109372003B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109778900B (en) * 2019-03-25 2024-09-20 中国二十二冶集团有限公司 Quick-dismantling formwork supporting structure for foundation cup rim formwork and construction method thereof
CN112227399A (en) * 2020-10-27 2021-01-15 上海建工七建集团有限公司 Template mounting and dismounting device of large cup-shaped foundation and template supporting and dismounting method
CN116240915A (en) * 2023-02-27 2023-06-09 中国五冶集团有限公司 Cup-type foundation internal mold construction structure and construction method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102677689A (en) * 2012-03-28 2012-09-19 天津二十冶建设有限公司 Structure for pouring column foundation cup mouth and pouring method
CN203270595U (en) * 2013-04-10 2013-11-06 大连宜华建设集团有限公司 Independent foundation construction inner formwork device with cup rabbet smaller than 600mm*600mm
CN106193093A (en) * 2016-08-25 2016-12-07 中启胶建集团有限公司 Rim of a cup foundation forms is reinforced and hydraulic pressure construction process for removing
CN108625389A (en) * 2018-05-30 2018-10-09 五冶集团上海有限公司 A kind of rim of a cup basis internal model panel assembly
CN108842799A (en) * 2018-06-26 2018-11-20 五冶集团上海有限公司 A kind of large size rim of a cup basis internal model board setting method
CN209723008U (en) * 2018-12-07 2019-12-03 中国二十二冶集团有限公司 Cushion cap foundation depth rim of a cup template

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102677689A (en) * 2012-03-28 2012-09-19 天津二十冶建设有限公司 Structure for pouring column foundation cup mouth and pouring method
CN203270595U (en) * 2013-04-10 2013-11-06 大连宜华建设集团有限公司 Independent foundation construction inner formwork device with cup rabbet smaller than 600mm*600mm
CN106193093A (en) * 2016-08-25 2016-12-07 中启胶建集团有限公司 Rim of a cup foundation forms is reinforced and hydraulic pressure construction process for removing
CN108625389A (en) * 2018-05-30 2018-10-09 五冶集团上海有限公司 A kind of rim of a cup basis internal model panel assembly
CN108842799A (en) * 2018-06-26 2018-11-20 五冶集团上海有限公司 A kind of large size rim of a cup basis internal model board setting method
CN209723008U (en) * 2018-12-07 2019-12-03 中国二十二冶集团有限公司 Cushion cap foundation depth rim of a cup template

Also Published As

Publication number Publication date
CN109372003A (en) 2019-02-22

Similar Documents

Publication Publication Date Title
CN109372003B (en) Deep cup rim template of bearing platform foundation and construction method for removing cup rim template
CN108457421B (en) Manufacturing die and manufacturing method of assembled reinforced concrete U-shaped frame beam
CN103821366B (en) Clear water concrete metope grooved stereo wood pattern decoration construction method
CN106337391B (en) Maintenance construction method for large-area damage of bottom of high-pile wharf panel
CN204530742U (en) A kind of adjustable suspension column
CN110616838A (en) Assembled composite floor slab with height limiting device and production process thereof
CN104712086B (en) Assembled type concrete hollow composite floor slab and manufacturing method thereof
CN212561935U (en) Drilling-free embedded part for chemically planting steel bars of constructional column
CN111255157A (en) Concrete pouring device and construction method for building edge constructional column
CN105040973B (en) Construction method of external decorative layer template of conical column of comprehensive gymnasium
CN104675112A (en) Steel stair formwork and constructing method for once pouring forming of building staircase
CN209723008U (en) Cushion cap foundation depth rim of a cup template
CN106522544A (en) Root-rotting-preventing compensating device for formwork
CN109208799B (en) Construction method for early formwork removal in structure hole of waffle slab
CN107214819B (en) Building constructional column shaping moulding box
CN103774846B (en) The construction method of post is cut off between a kind of construction work window
CN205012621U (en) Template is pour to outside decorative layer of toper post
CN203097290U (en) Assembled type split bolt
CN204626965U (en) For the steel stair template of poured up at a time between architectural stair
CN111590731B (en) Prefabricated mold for regular polygon floor tile, application of prefabricated mold and paving method of floor tile
CN103469952B (en) A kind of reinforced concrete hollow floor and construction method
CN105951870B (en) Steel building concrete cup-shaped foundation inner bore die carrier
CN107447772A (en) The integrated core die combination and its construction method of base for post cushion cap rim of a cup
CN206110668U (en) Clear water concrete outseam strip
CN218985175U (en) Composite slab mould with adjustable combination

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant